Sie sind auf Seite 1von 4

Activity

ID

Activity
Description

Location
LOCN
QTY
Orig PROJ
Dur

RESP

Early
Start

Early
Finish

14-151337

VISCOMI

01JUL15

29AUG15

Demo of 722 S. Main - Project on Hold

14-151335

VISCOMI

01JUL15

29AUG15

Demo of 738 S. Main -Project on Hold

15-157743

HUDICK

15JUN15

08AUG15

Cadaver lab renovations -

15-2059-00

HUDICK

26MAY15

03JUL15

Specimen room -in design -for summer 2015

14-138164

THAYER

11MAY15

31JUL15

Replace roof & Soffett

14-146234
15-2000-18

HUDICK
J.COMBS

26MAY15
26MAY15

31JUL15
07AUG15

Upgrade Fire Alarms

HUDICK

20JUL15

08AUG15

Fire Alarm Panel change out

15-2067-00

SHANTZ

01JUN15

08AUG15

Starbucks refresh Awaiting drawings

14-2000-33

DERROW

26MAY15

15AUG15

Raised crosswalks Carrier Drive

15-2065-00
15-2055-00

THAYER
THAYER

11MAY15
11MAY15

06AUG15
18JUL15

Speed Bunps

15-2043-00
15-2069-00
14-149303

THAYER
DERROW
VISCOMI

26MAY15
01JUN15
15JUN15

10JUL15
01AUG15
26JUN15

Re-grout all brick joints (Shops)

15-2037-0
15-2047-00

J.COMBS
DERROW

12MAY15
12MAY15

18JUL15
11JUL15

Replace Ceiling

SHANTZ

27JUL15

01AUG15

refinish floor

DERROW

12MAY15

22AUG15

room 100 build wall in all wings

Weeks

722 S.MAIN
EN1368 Demo of 722 S. Main - Project on Hold

738 S.MAIN
EN1288 Demo of 738 S. Main -Project on Hold

A-2 Building
EN1498 Cadaver lab renovations -

Bio Science
EN1528 Specimen room -in design -for summer 2015

Alumnae Hall
EN1298 Replace roof & Soffett

Anthony-Seeger Hall
EN1318 Upgrade Fire Alarms
EN1338 Renovations

Renovations

Burruss Hall
EN1248 Fire Alarm Panel change out

Carrier Library
EN1268 Starbucks refresh Awaiting drawings

CARRIER DR
EN090

Raised crosswalks Carrier Drive

CHAMPION
EN310
EN320

Structural IssuesSpeed Bunps

Structural Issues-

Chandler Hall
EN998 Re-grout all brick joints (Shops)
EN1918 Lakeside express renovations
EN1008 Replace carpet in 8 rooms

Lakeside express renovations


Replace carpet in 8 rooms

Chappelear Hall
EN1728 Replace Ceiling
EN1788 room 100 build wall in all wings

room 100 build wall in all wings

Convocation Center
EN237

refinish floor

Dingledine Hall
EN1818 room 100 build wall in all wings

Start Date
Finish Date
Data Date
Run Date

05JAN15
05JAN15
22JUN15 13:15

15-2047-00

Early Bar
Float Bar
Progress Bar
Critical Activity

PLAN

Sheet 1 of 4

JMU - Facilities Management


JMU FM Master Project Schedule
Classic Schedule Layout

Primavera Systems, Inc.

Date

Revision

Checked

Approved

Activity
ID

Activity
Description

Location
LOCN
QTY
Orig PROJ
Dur

RESP

Early
Start

Early
Finish

09-2003-00
14-2002-00

THAYER
VISCOMI

16DEC13
01JAN14

06SEP14
29DEC14

15-2060-00
15-2018-00

DERROW
THAYER

11MAY15
15JUN15

22JUN15
11JUL15

Replace all vanitieis

15-2000-13

HUDICK

11MAY15

08AUG15

Renovations to JMU Farm

15-156039

THAYER

11MAY15

18JUL15

Canopy at Board of Visitors entrance

14-128603
14-137529

THAYER
HUDICK

11MAY15
11MAY15

01AUG15
31JUL15

Covered walkway

DERROW

11MAY15

05JUN15

room 100 build wall in all wings

SHANTZ
SHANTZ

11MAY15
11MAY15

18JUL15
29MAY15

repairs to Volleyball court

SHANTZ
SHANTZ

11MAY15
12MAY15

11JUL15
18JUL15

Water intrusion project

13-2008-04

SHORT

06MAY13

01JUL15

Grace Street Student Housing

15-2047-00

DERROW

12MAY15

18JUL15

room 100 build wall in all wings

15-2046-00

12MAY15
12MAY15
12MAY15

11JUL15
31JUL15
01AUG15

Replace floor Tile

15-2046-00

VISCOMI
JENKINS
VISCOMI

15-2037-00

J.COMBS

12MAY15

18JUL15

Replace ceiling

15-2036-00

J.COMBS

12MAY15

11JUL15

Install Hand Dryers

14-146200

THAYER

18MAY15

10JUL15

Repair water intrusion into basement

14-143592

J.COMBS

03NOV14

13JUN15

Renovations to Lakeview

14-146204

THAYER
BAKER

26MAY15
22JUN15

30JUN15
26JUN15

Repair roof

Weeks

E&G
EN198
EN238

On going side walk repairs as needed


Mis small asbestos projects as needed

On going side walk repairs as needed


Mis small asbestos projects as needed

Eagle Hall
EN728
EN688

Replace all vanitieis


Replace Roof

Replace Roof

FARM
EN1678 Renovations to JMU Farm

Festival
EN220

Canopy at Board of Visitors entrance

Forbes Center
EN200
EN230

Covered walkway
Paint booth

Paint booth

Frederikson Hall
EN1798 room 100 build wall in all wings

Godwin Hall
EN1638 Repair Pool
EN1698 repairs to Volleyball court

15-258-00

Repair Pool

GR ROW
EN1118 Water intrusion project
EN1108 Floor Tile Lake A,

Floor Tile Lake A,

Grace Street Student Housing


EN888

Grace Street Student Housing

Hanson Hall
EN1808 room 100 build wall in all wings

Hillside Hall
EN1418 Replace floor Tile
EN1478 Total Paint
EN1488 Replace boiler & Coils

Total Paint
Replace boiler & Coils

Huffman Hall
EN1738 Replace ceiling

Ikenberry Hall
EN1748 Install Hand Dryers

Johnston Hall
EN1648 Repair water intrusion into basement

LAKEVIEW
EN1658 Renovations to Lakeview

Memorial Hall
EN1168 Repair roof
EN1178 Cover stages at amphtheater

Sheet 2 of 4

Cover stages at amphtheater

Activity
ID

Activity
Description

EN1278 refinish Gym floor

Location
LOCN
QTY
Orig PROJ
Dur

RESP

Early
Start

Early
Finish

15-158786

SHANTZ

25JUN15

03JUL15

refinish Gym floor

1272

THAYER

26MAY15

30JUN15

Replace roof

NANCY C

17NOV14

15AUG15

Steam line connection -

15-2008-06
15-2061-00

THAYER
VISCOMI

11MAY15
11MAY15

15AUG15
13JUN15

Rockingham parking lot


Rockingham demo

15-2062-00

SHANTZ

26MAY15

30JUN15

room 2300 renovate

15-2019-00

11MAY15
11MAY15
12MAY15
01JUN15

25JUL15
25JUL15
31JUL15
17JUL15

Replace fire Alarms

14-2049-00

HUDICK
HART
J.COMBS
THAYER

replace windows-

15-2068-00

HUDICK

26MAY15

02AUG15

Auntie Annes

14-153283

HUDICK

04MAY15

01OCT15

Renovations to Farm

12-2081-00
15-161324
14-137164
15-2026-00

G.WAY
SHANTZ
SHANTZ
J.COMBS

05MAY14
11MAY15
11MAY15
11MAY15

16JUL16
05JUN15
05JUN15
20JUN15

14-2047-00
15-2049-00

DERROW
HUDICK

11MAY15
11MAY15

01AUG15
18JUL15

renovate 4 HD appts

216-17949

R.MILLER

16DEC13

04AUG15

New Student Housing

TELECOM

11MAY15

05JUN15

Network Install

15-2001-02

J.COMBS

15JAN15

15AUG15

Post office/bank Renovations

15-2035-00
15-2047-00

VISCOMI
DERROW

11MAY15
12MAY15

03JUL15
24JUL15

Replace ceiling

14-144880
15-158866
15-2036-00

VISCOMI
J.COMBS
J.COMBS

07MAR15
11MAY15
12MAY15

14MAR15
08AUG15
18JUL15

C302/C303 Bathroom ceiling

Weeks

Music Building
EN698

Replace roof

NORTH CAMP
EN898

Steam line connection -

Rockingham Hall
EN1878 Rockingham parking lot
EN1888 Rockingham demo

Rose Library
EN1958 room 2300 renovate

Spotswood Hall
EN1708
EN1948
EN1778
EN1688

Replace fire Alarms


Upgrade steam radiators
Install wi-fi
replace windows-

Upgrade steam radiators


Install wi-fi

Taylor Hall
EN908

Auntie Annes

University Farm
EN1668 Renovations to Farm

University Recreation Center


EN868
EN918
EN928
EN938

UREC Expansion -phase I -in planning


Dock Lift
3rd Floor Lift
Office renovations

UREC Expansion -phase I -in planning


Dock Lift
3rd Floor Lift
Office renovations

Village Halls
EN1458 Village Quad rooms
EN1468 renovate 4 HD appts

Village Quad rooms

Walnut Lane
EN1378 New Student Housing

Wampler Hall
EN1408 Network Install

Warren Hall
EN1238 Post office/bank Renovations

Weaver Hall
EN1438 Replace ceiling
EN1828 room 100 build wall in all wings

room 100 build wall in all wings

White Hall
EN1428 C302/C303 Bathroom ceiling
EN1928 Network Install
EN1758 Install Hand Dryers

Sheet 3 of 4

Network Install
Install Hand Dryers

Activity
ID

Activity
Description

Location
LOCN
QTY
Orig PROJ
Dur

RESP

Early
Start

Early
Finish

BAKER

08JUL15

09JUL15

Weeks

Wine-Price Hall
EN1388 Install carpet in basement

Sheet 4 of 4

Install carpet in basement