PMP

Sample
Questions

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has
not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no
warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP
International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP
certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used
only as a reference and not as a replacement for officially published material. Using the information from this document does not
guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP
International LLC.

This presentation will showcase free


sample PMP questions that will help
and guide you in studying for your
PMP exam
Find more free sample
questions when you visit
www.free-pm-exam-questions.com
and free.pm-exam-simulator.com

Sample PMP Exam Question


Which of the following elements constitute the scope baseline?
a.Scope Statement, WBS, and Project Schedule
b.Scope Statement, Project Schedule, and WBS Dictionary
c.WBS Dictionary, Resource Calendars, and Project Schedule
d.Scope Statement, WBS, and WBS Dictionary

HINT: The Scope Baseline should contain the scope and related
work information.

Answer and Explanation


The correct answer is D
The Scope Baseline contains the Scope
Statement, the WBS, and the WBS Dictionary.

Sample PMP Exam Question


Which of the following buffers are placed at the end of the critical chain to protect
the target finish date from slippage?
a.Feeding Buffer
b.Project Buffer
c.Free Buffer
d.Activity Buffer

HINT: This buffer protects the target finish date from moving
and is intended to protect the project end date.

Answer and Explanation


The correct answer is B
A Project Buffer is placed at the end of the
critical chain to protect the target finish from
slippage along the critical chain. On the other
hand, Feeding Buffers are placed at those
points in the chain where tasks that are not on
the critical path feed into the critical path. Free
buffers and Activity buffers are not used in
critical chain.

Sample PMP Exam Question


According to the PMBOK Guide, which of the following is not a valid activity
dependency?
a.Mandatory Dependency
b.Internal Dependency
c.External Dependency
d.Discretional Dependency

HINT: This question references the Sequence Activities


process.

Answer and Explanation


The correct answer is B
The PMBOK Guide recognizes three types of dependencies;
Mandatory, Discretionary and External. The PMBOK Guide
doesn't recognize "Internal Dependencies" as a type of
dependency. Did it confuse you that one of the answers used
the term "Discretional Dependencies" instead of
"Discretionary Dependencies"? Expect that even on the
actual PMP exam you will come across questions where
terminology does not exactly match the PMBOK Guide. Even
considering that "Discretional Dependencies" is not the exact
same term as Discretionary Dependencies, "Internal
Dependencies" is even less correct and therefore the correct
answer.

Sample PMP Exam Question


According to the PMBOK Guide, a WBS is not directly involved in which of the
following processes?
a.Develop Project Management Plan
b.Define Activities
c.Create WBS
d.Define Scope

HINT: Develop Project Management Plan process creates the


Scope Management Plan.

Answer and Explanation


The correct answer is D
The Develop Project Management Plan
process carries out scope planning, which
documents how the WBS will be created and
defined. Define Activities takes the WBS as an
input and decomposes it to define activities.
Create WBS creates the WBS itself. The
Define Scope process must be completed
before the Create WBS process can be
started.

Sample PMP Exam Question


Information in the WBS dictionary does not include?
a.Contract Information
b.Quality Requirements
c.Responsible Organization
d.Project Activities

HINT: WBS dictionary contains a lot of items and explains each


work package in great detail.

Answer and Explanation


The correct answer is D
The WBS Dictionary contains a lot of items
and explains each work package in great
detail. This information includes Contract
Information regarding the work packages,
Quality Requirements, and the Responsible
Organization. However, the WBS Dictionary
does not included the specific project activities.