LABOUR ESTIMATE FOR VARIOUS ITEMS OF WORKS

SN
.

ITEM DESCRIPTION

QUANTITY

LABOUR ( 8 hours per day)

1.

Concrete in Foundation.

10 m3

Head Mason 1/4, Mason 2, Labour


20

2.

R.C.C. M - 15 grade.

10 m3

Head Mason 1/2, Mason 3, Labour


23

Note: For each additional storey, the strength should be increased by 6 nos. for
volume of 10 cu.m to lift the materials.
3.

Supplying, fitting, fixing


and removing shuttering &
staging.

7 m2

Carpenter 1, Labour 2

4.

Reinforcement for R.C.C.


work including cutting,
bending and placing in
position.

100 kg.

Bar binder (Black- smith/fitter) 1,


Labour 1

5.

Damp proof course.

100 m2

Head Mason 1/2, Mason 5, Labour 6

6.

First class brickwork in 1:6


in super structure.

10 m3

Head Mason 1/2, Mason 9, Labour


18, Bhisti 2

7.

Brick on edge flooring with 100 m2


cement Mortar (1:3).

Head Mason 1/2, Mason 10, Labour


14, Bhisti 1

8.

Ironite flooring (40mm


thk).

100 m2

Head Mason 1, Mason 24, Labour


27, Labour for Scrubbing 3

9.

C.G.I sheeting on roof

10 m2

Carpenter 1, Fitter (Blacksmith)


1/2, Labour 2

10. C.I. rain water pipe fixing.

9m

Mason 1/2, Labour 2.5

11. 12mm thk cement plaster


on brickwork in 1:6.

100 m2

Head Mason 1, Mason 10, Labour


14, Bhisti 1

12. Ruled pointing (1:3).

100 m2

Head mason 1/2, Mason 10, Labour


9, Bhisti 1

13. White washing primer coat


and 2 finished coats to
new plaster.

100 m2

Painter 1/2, Labour 2

14. Dry Distemper

100 m2

Painter 8.5, Labour 5.5

15. Plastic Emulsion paint on


new work.

100 m2

Painter 5.5, Labour (Helper) 5.5

16. Primer coat on wood


work/ steel work.

100 m2

Painter 2.5, Labour (Helper) 2.5

17. Panting two coats over


priming coat for new wood
work/steel work.

100 m2

Painter 5.5, Labour (Helper) 5.5

18. Demolishing cement


concrete (1:2:4/1:3:6)
including lead upto 50m.

10 m3

Labour 23

19. Demolishing R.C.C. work


including lead upto 50m.

10 m3

Labour 33.5

20. Demolishing Brickwork in


cement mortar including
stacking of serviceable
material and disposal of
unserviceable materials
within a lead of 50m.

10 m3

Labour 19.5

21. Removing mortar and


cleaning bricks and
stacking cleaned bricks.

10 m3

Mason 6, Labour 25

22. Dismantling doors &


windows including
framing, stacking of
material.

1 no.

Mason 1, Labour 0.20

23. Supplying and fixing


12mn/15mm dia G.I. pipe
with G.I. fittings and M.S.
clamps including cutting
holes in walls and making
good the same

100 r.m.

Fitter 7, Labour (Beldar) 6

24. Supplying, fitting and


laying 25mm G.I pipes
with G.I. fittings including
trenching and refilling of
external work

100 r.m.

Fitter 1, Labour 8

25. Laying, fitting and fixing


100 mm dia G.I. pipes
including testing of joint,
trench cutting for pipe
laying upto a depth of 90
cm. and refilling, dressing
etc.

20 r.m.

Fitter 1.5, Labour 13

26. Supplying, laying, joining


100 dia stoneware pipes
with cement mortar 1:1
(excluding earthwork
etc.).

15 r.m..

Mason 1, Labour 2

27. Wash Basin with C.I.


brackets, brass taps, brass
plug with brass chain,
waste pipe Including
cutting walls and making
good the same.

1 no.

Plumber 1, Mason 1/2, Labour 1

28. Sink.

1 no.

Plumber 1/2, Mason 1/2, Labour 1

29. 9" thick brick flat soling


filled with local sand.

10 m2

Labour 1

30. Earth work for roads


including cutting, loading,
unloading, carrying &
dressing.

10 m2

Labour 4

31. Stone soling for roads


including packing with
smaller stones manually.

10 m3

Labour 7

32. Stone soling for roads


including packing with
smaller stones With steam
roller.

20 m3

Labour 7

33. Surface
dressing/Bituminous
carpeting on roads

100 m2

Labour (for one layer) 10, Labour


(for two layers) 15