Sie sind auf Seite 1von 1

71462 Federal Register / Vol. 70, No.

228 / Tuesday, November 29, 2005 / Notices

techniques or other forms of information McClellanville Government Services McClellanville Branch Library, 222
technology. All responses to this notice Building, located at 405 Pinckney Baker St., McClellanville, SC 29458,
will become a matter of public record Street, McClellanville, SC 29458 Phone: (843) 889–3300.
and be summarized in the request for (843) 887–3712. The purpose of the Government agencies, private
OMB approval. meeting is to provide information and organizations, and the public are invited
Signed at Washington, DC, November 14, solicit comments for the preparation of to participate in the planning and
2005. an EA. analysis of the proposed project.
Joe Reilly, FOR FURTHER INFORMATION CONTACT: Representatives from RUS and CEPCI
Associate Administrator. Stephanie Strength, Environmental will be available at the scoping meeting
[FR Doc. E5–6675 Filed 11–28–05; 8:45 am] Protection Specialist, USDA, Rural to discuss RUS’ environmental review
BILLING CODE 3410–20–P Development, Utilities Programs, process, describe the project, the need
Engineering and Environmental Staff, for the project, the macro corridors
Stop 1571, 1400 Independence Avenue, under consideration, and discuss the
DEPARTMENT OF AGRICULTURE SW., Washington, DC 20250–1571, scope of environmental issues to be
telephone (202) 720–0468. Mrs. considered, answer questions, and
Rural Utilities Service Strength’s e-mail address is accept oral and written comments.
stephanie.strength@wdc.usda.gov. Written comments will be accepted for
Central Electric Power Cooperative, 30 days after the public scoping
Inc.; Notice of Intent to Hold Public SUPPLEMENTARY INFORMATION: CEPCI meeting. Written comments should be
Scoping Meetings and Prepare an proposes to construct a 115 kilovolt sent to RUS at the address provided in
Environmental Assessment transmission line between a source this notice.
AGENCY: Rural Utilities Service, USDA. substation and a proposed substation From information provided in the
located in McClellanville. alternative evaluation and site selection
ACTION:Notice of intent to hold public
scoping meetings and prepare an Single pole structures ranging in study, input that may be provided by
environmental assessment (EA). height from 80- to 150-feet would government agencies, private
support the conductors and would organizations, and the public, Central
SUMMARY: The Rural Utilities Service require a right-of-way of 70 feet. One Electric Power Cooperative will prepare
(RUS) intends to hold public scoping alternative route includes an an environmental analysis to be
meetings and prepare an environmental approximately 2-mile subsurface submitted to RUS for review. RUS will
assessment in connection with possible directionally-drilled section below the use the environmental analysis to
impacts related to a project proposed by Santee River delta. Depending on which determine the significance of the
Central Electric Power Cooperative, Inc. route is chosen the approximate length impacts of the project and may adopt it
(CEPCI) of South Carolina. The proposal of the transmission line would be from as its environmental assessment of the
consists of the construction of 16 to 26 miles. It is anticipated that this project. RUS’ environmental assessment
approximately 20 miles of 115 kilovolt transmission line would be in service in of the project would be available for
transmission line to provide more the Spring of 2008. review and comment for 30 days.
reliable transmission power to Alternatives considered by RUS and Should RUS determine, based on the
McClellanville, SC. The proposed 115- CEPCI include: (a) No action, (b) EA of the project, that the project would
kilovolt transmission line project would alternative transmission improvements, not have a significant environmental
be constructed within one of several and (c) alternative transmission line impact, it will prepare a finding of no
alternative corridors under corridors. An Electric Alternative significant impact. Public notification of
consideration. The alternative Evaluation and Macro Corridor Study a finding of no significant impact would
transmission line corridors originate at Report, prepared by CEPCI will be be published in the Federal Register
existing power delivery points near presented at the public scoping meeting. and in newspapers with a circulation in
Jamestown and Charity, Berkeley The Report is available for public the project area.
County and Winyah and Belle Isle south review at the USDA/Rural Development Any final action by RUS related to the
of the city of Georgetown in Georgetown address provided in this notice, at proposed project will be subject to, and
County, SC and at a potential new Central Electric Power Cooperative, Inc., contingent upon, compliance with
substation that would be built in the 121 Greystone Blvd., Columbia, SC environmental review requirements as
vicinity of the town of Honey Hill, 29210 and at: prescribed by the Council on
Berkeley County, SC. The corridors Environmental Quality and RUS
terminate at the proposed location of a Berkeley County Library, PO Box 1239, environmental policies and procedures.
substation in McClellanville from which 1003 Hwy. 52, Moncks Corner, SC
29461, (843) 719–4223, (843) 719– Benjamin Shuman,
electric power distribution lines would
service the community. Portions of the 4226 (Fax), Director: Colleen L. Acting Director, Engineering and
Carney, Web Site: http:// Environmental Staff, USDA/Rural
alternative corridors include Federal Development/Utilities Programs.
lands of the Francis Marion National www.berkeley.lib.sc.us/.
Charleston County Library, 68 Calhoun [FR Doc. 05–23381 Filed 11–28–05; 8:45 am]
Forest therefore the United States
Street, Charleston, SC 29401, (843) BILLING CODE 3410–15–P
Department of Agriculture (USDA)
Forest Service (FS) is a cooperating 805–6801, (843) 727–3741 (Fax),
agency in the National Environmental Director: Jan Buvinger, Web Site:
Policy Act (NEPA) analysis. CEPCI is http://www.ccpl.org. DEPARTMENT OF COMMERCE
requesting RUS to provide financing for Georgetown County Library, 405 Submission for OMB Review;
the proposed project. Cleland Street, Georgetown, SC Comment Request
DATES: RUS will conduct a scoping 29440, (843) 546–2521, (843) 527–
meeting in an open house format from 3251 (Fax), Director: Dwight The Department of Commerce has
4 p.m. until 8 p.m. on Thursday, McInvaill, Web Site: http:// submitted to the Office of Management
December 14, 2005, at the www.gcpl.lib.sc.us/. and Budget (OMB) for clearance the

VerDate Aug<31>2005 20:13 Nov 28, 2005 Jkt 208001 PO 00000 Frm 00004 Fmt 4703 Sfmt 4703 E:\FR\FM\29NON1.SGM 29NON1