Sie sind auf Seite 1von 11

LATERAL LOAD BEHAVIOR OF A POSTTENSIONED COUPLED CORE WALL

Steven Barbachyn,1 Yahya C. Kurama,2 Michael J. McGinnis,3 Richard


Sause,4 and Kristen A. Peterson5
ABSTRACT
A 40%-scale multi-story reinforced concrete (RC) coupled core wall structure with unbonded
post-tensioned coupling beams was recently tested under quasi-static reversed-cyclic lateral
loading. This paper provides an overview of the structural design and experimental results from
this test. Conventional RC coupling beams in seismic regions are often designed with two
intersecting groups of diagonal reinforcing bars crossing the beam-to-wall joints. The placement
of these reinforcing bars is a major challenge during construction. The new system eliminates the
diagonal reinforcement by using a combination of high-strength unbonded post-tensioning (PT)
steel and top and bottom horizontal energy-dissipating (ED) mild steel bars crossing the beamto-wall joints to develop the coupling forces. The coupled wall specimen that was tested
represented the most critical bottom three stories of an eight story prototype structure, consisting
of two C-shaped wall piers, six post-tensioned coupling beams (two beams at each floor because
of the C-shaped piers), tributary post-tensioned slabs at each floor, and the foundation. The less
critical upper stories of the prototype structure were simulated analytically to obtain the axial
forces and overturning moments imposed at the top of the three-story test sub-structure. In
addition to a dense array of conventional sensors, the deformations of the specimen were
monitored using 14 two and three-dimensional digital image correlation (DIC) sensors, providing
near-full-field response data of the most critical regions of the structure in the wall piers, floor
slabs, and coupling beams. Ultimately, the high-fidelity measured data from the test will be used
to validate seismic design procedures and modeling/prediction tools for post-tensioned coupled
shear wall structures. These procedures and tools may form the basis for the future
implementation of this novel structural system as special RC shear walls in medium and high
seismic regions of the U.S.

Graduate Student, Dept. of Civil & Envir. Engin. & Earth Sciences, U. of Notre Dame, Notre Dame, IN 46556
Professor, Dept. of Civil & Envir. Engin. & Earth Sciences, U. of Notre Dame, Notre Dame, IN 46556
3
Associate Professor, Dept. of Civil Engin., U. of Texas at Tyler, Tyler, TX 75799
4
Professor, Dept. of Civil & Environmental Engin., Lehigh U., Bethlehem, PA 18015
5
Staff I-Structures, Simpson Gumpertz & Heger, Boston, MA 02453
2

Barbachyn S., Kurama Y., McGinnis M., Sause R., and Peterson K. Lateral Load Behavior of a Post-Tensioned
Coupled Core Wall. Proceedings of the 10th National Conference in Earthquake Engineering, Earthquake
Engineering Research Institute, Anchorage, AK, 2014.

Lateral Load Behavior of a Post-Tensioned Coupled Core Wall


Steven Barbachyn,1 Yahya C. Kurama,2 Michael J. McGinnis,3 Richard Sause,4 and Kristen A.
Peterson5
ABSTRACT
A 40%-scale multi-story reinforced concrete (RC) coupled core wall structure with unbonded
post-tensioned coupling beams was recently tested under quasi-static reversed-cyclic lateral
loading. This paper provides an overview of the structural design and experimental results from
this test. Conventional RC coupling beams in seismic regions are often designed with two
intersecting groups of diagonal reinforcing bars crossing the beam-to-wall joints. The placement
of these reinforcing bars is a major challenge during construction. The new system eliminates the
diagonal reinforcement by using a combination of high-strength unbonded post-tensioning (PT)
steel and top and bottom horizontal energy-dissipating (ED) mild steel bars crossing the beam-towall joints to develop the coupling forces. The coupled wall specimen that was tested represented
the most critical bottom three stories of an eight story prototype structure, consisting of two Cshaped wall piers, six post-tensioned coupling beams (two beams at each floor because of the Cshaped piers), tributary post-tensioned slabs at each floor, and the foundation. The less critical
upper stories of the prototype structure were simulated analytically to obtain the axial forces and
overturning moments imposed at the top of the three-story test sub-structure. In addition to a dense
array of conventional sensors, the deformations of the specimen were monitored using 14 two and
three-dimensional digital image correlation (DIC) sensors, providing near-full-field response data
of the most critical regions of the structure in the wall piers, floor slabs, and coupling beams.
Ultimately, the high-fidelity measured data from the test will be used to validate seismic design
procedures and modeling/prediction tools for post-tensioned coupled shear wall structures. These
procedures and tools may form the basis for the future implementation of this novel structural
system as special RC shear walls in medium and high seismic regions of the U.S.

Introduction
Reinforced concrete (RC) coupled shear wall structures are commonly used for primary lateral
load resistance in medium and high-rise buildings in regions of moderate and high seismicity.
The typical coupled wall system consists of two or more vertical shear wall piers connected by
relatively short, deep beams called coupling (or link) beams at the floor and roof levels. Properly
designed and detailed coupled walls can provide large strength, stiffness, and energy dissipation
under lateral loads; however, the design and construction of the coupling beams remain
1

Graduate Student, Dept. of Civil & Envir. Engin. & Earth Sciences, U. of Notre Dame, Notre Dame, IN 46556
Professor, Dept. of Civil & Envir. Engin. & Earth Sciences, U. of Notre Dame, Notre Dame, IN 46556
3
Associate Professor, Dept. of Civil Engin., U. of Texas at Tyler, Tyler, TX 75799
4
Professor, Dept. of Civil & Environmental Engin., Lehigh U., Bethlehem, PA 18015
5
Staff I-Structures, Simpson Gumpertz & Heger, Boston, MA 02453
2

Barbachyn S., Kurama Y., McGinnis M., Sause R., and Peterson K. Lateral Load Behavior of a Post-Tensioned
Coupled Core Wall. Proceedings of the 10th National Conference in Earthquake Engineering, Earthquake
Engineering Research Institute, Anchorage, AK, 2014.

challenging due to the presence of large reversed-cyclic nonlinear rotation demands combined
with large shear forces, resulting in complex reinforcement details.
To meet the significant shear and rotation demands, the primary reinforcement for typical
RC coupling beams in seismic regions consists of two intersecting groups of large diagonal
reinforcing bars passing through the beam and anchored into the wall piers ([1-5]). This
conventional system is difficult to construct [as shown in Fig. 1(a)] and can experience
considerable damage under seismic loading. In comparison, the primary reinforcement in the
coupling beams of the wall system described herein consists of unbonded post-tensioning (PT)
strands placed in one or two tendons at the beam centroid, greatly simplifying construction [see
Fig. 1(b)]. This new system represents a significant innovation and transformation, but one that
can be realistically achieved by adapting the existing and widely-used post-tensioned slab
technology. The deformations in the coupling beams occur primarily in the form of concentrated
cracking at the ends, resulting in little damage to the rest of the beam as the structure displaces
laterally during a large earthquake. Additionally, energy dissipating (ED) top and bottom
horizontal mild steel bars (ASTM A615, Grade 60) are designed to yield in tension and
compression as the beams rotate under reversed-cyclic lateral displacements. After the
earthquake, the PT tendons provide a restoring (self-centering) force that closes the cracks and
pulls the structure back toward its undeformed, plumb position. The combination of PT steel and
mild steel reinforcement to develop the design coupling forces with self-centering capability and
energy dissipation results in an efficient structure for seismic loading conditions.

(a)

(b)

Figure 1. RC coupling beams: (a) diagonally reinforced beam (courtesy, Magnusson


Klemencic Associates); (b) proposed post-tensioned beam
The single major barrier to the use of post-tensioned coupling beams in seismic regions is
the lack of experimentally-validated design methods, construction procedures, and numerical
simulation models for multi-story structures. Previous experiments on the use of the proposed
technology are limited to isolated floor level subassembly studies ([6-8]). To fill this knowledge
gap, a 40%-scale physical laboratory experiment integrated with the analytical model of a multistory coupled wall structure was recently conducted at the Network for Earthquake Engineering
Simulation (NEES) laboratory site operated by Lehigh University. The laboratory specimen
included the first three floors, tributary slabs, and foundation of an 8-story prototype system,
representing the most critical regions of the structure. The other (less critical) regions of the
structure were simulated in the computer to obtain the forces and overturning moments acting at
the top of the 3-story laboratory specimen. Fig. 2(a) shows a three-dimensional rendering of the
40%-scale experimental setup in the laboratory, while Fig. 2(b) shows the completed test
specimen. In addition to a dense array of conventional sensors (load cells, strain gauges,

displacement/rotation transducers), the deformations of the laboratory structure were monitored


using a total of 14 two and three-dimensional digital image correlation (DIC) sensors ([9])
providing near-full-field response data of the most critical regions of the structure in the wall
piers, floor slabs, and coupling beams. Ultimately, the high-fidelity measured data from this test,
as well as from a subsequent second specimen to be tested in 2014, is expected to lead the
development of validated design procedures and modeling/prediction tools for the new system.
The primary focus of the current paper is on an overview of the structural design and
experimental results from the first 40%-scale laboratory test specimen.

(a)

(b)

Figure 2. 40%-scale experimental setup: (a) 3D rendering; (b) completed structure


Full-Scale Prototype Structure
A full-scale 8-story prototype building was designed to form the basis for the 40%-scale posttensioned coupled shear wall test specimen. An overview of the design and detailing of this
prototype structure is given in this section.
Design Approach
The prototype structure was designed for a site in Los Angeles, California with a seismic
response coefficient of Cs = 0.136g. The plan and elevation views of the structure are shown in
Figs. 3(a) and 3(b), respectively. The primary lateral load resistance was provided by a coupled
core wall system at the center of the building, consisting of two C-shaped shear walls connected
by post-tensioned coupling beams at each floor. This core included two slab openings to simulate
the elevator shafts and stairwells in an office building. These slab openings were centered inside
the core to prevent any significant asymmetric behavior during testing. The configuration,
dimensions, and detailing of the prototype building were chosen with the assistance of
Magnusson Klemencic Associates (MKA) in Seattle, Washington. The design strengths of
concrete, mild steel, and PT steel were fc=6 ksi, fy=60 ksi, and fpu=270 ksi, respectively.
To determine the design forces for the prototype structure, the Equivalent Lateral Force
(ELF) procedure from ASCE 7 ([10]) was used with a response modification factor of R=6.0.
The structure had a calculated fundamental period of T=0.74 s. The ELF procedure resulted in a

design total base moment and total base shear force, which were distributed to the components of
the coupled wall structure by making a number of design selections. First, a coupling degree of
30% was chosen, meaning that 30% of the design total base moment was to be carried by the
coupling action between the two wall piers. This coupling moment was distributed to the posttensioned coupling beams as a design shear force and corresponding moment at the beam ends,
with the remaining base moment distributed evenly between the two wall piers. The
reinforcement details of the wall piers and coupling beams were then selected to satisfy these
design forces and achieve ductile behavior up to a maximum roof drift ratio of 3% for the 8-story
structure. The specimen was intentionally designed not to have any significant over-capacity in
force or displacement (e.g., no capacity reduction factor was used for axial-flexural design).

Figure 3. Full-scale prototype structure: (a) building plan (b) coupled wall elevation;
(c) wall pier base details; (d) 1st floor coupling beam end details
Structure Detailing
Fig. 3(c) shows the wall pier details at the base of the structure, which were symmetric in the NS direction for each pier and symmetric in the E-W direction between the two piers. The pier

reinforcement plan was selected to be similar to typical reinforcement details used in


conventional coupled shear walls. The 1st floor post-tensioned coupling beam end details are
given in Fig. 3(d). Sixteen 0.5 in. diameter PT strands (ASTM A416) anchored at the outsides of
the wall piers provided the total post-tensioning force for this beam. The strands were placed
inside two ungrouted ducts to prevent bonding to the concrete, resulting in uniformly distributed
strand strains over the entire length of the structure, thus, delaying the yielding of the strands and
maintaining the initial post-tensioning force. Energy dissipation in the 1st floor coupling beams
was provided by three No. 6 ASTM A615, Grade 60 ED reinforcing bars at the top and bottom
of the beam, crossing the beam-to-wall interface at each end. A predetermined length of this
reinforcement was unbonded from the concrete by wrapping each ED bar in a plastic sleeve to
limit the maximum steel strains and delay low-cycle fatigue fracture. The beams were designed
as T-beams considering an effective flange width from the slab, resulting in unequal amounts of
unbonded length for the ED reinforcement as well as unequal amounts of confinement hoop
reinforcement at the top and bottom of the cross-section. The coupling beams in the upper stories
were designed similarly, but with smaller amounts of reinforcement due to the reduced beam
shear and moment demands over the height of the structure. Preliminary analytical models of the
structure were used to determine an estimate of the coupling beam design forces, resulting in
three different beam designs over the height (1st floor, 2nd-4th floors, and 5th-8th floors).
The deliberate lack of bond (i.e., debonding) between the steel and surrounding concrete
was intended to result in the development of concentrated cracks at the beam ends rather than
distributed cracks developing into the span. The post-tensioning steel was designed to create a
large diagonal compression strut over the beam length, essentially eliminating cracking in the
mid-span. This compression strut also resulted in large compression stresses at the beam ends;
and thus, closely spaced transverse hoops were placed for concrete confinement in these regions.
However, the transverse shear reinforcement away from the beam ends was significantly reduced
compared with conventionally reinforced coupling beams. The simplified rectilinear orientation
of the beam reinforcement and localization of damage under lateral loading represent significant
improvements over diagonally-reinforced coupling beams.
The widely-used unbonded post-tensioned slab technology was used for the floor slabs.
These slabs were designed by MKA following typical methods for coupled core wall structures,
but with slight modifications to account for the new post-tensioned coupling beam details. The
final reinforcement layout consisted of a top and bottom mat of mild steel bars (continuous into
and through the wall piers) and unbonded PT steel in both the N-S and E-W directions of the
slab. The slab PT tendons were banded in the N-S direction and distributed evenly along the slab
length in the E-W direction. The main deviation from a typical post-tensioned slab design was in
the termination of the E-W mild steel bars running parallel to the coupling beams. In order to
prevent these slab bars from interfering with the intended behavior at the beam ends, the bars
placed within the effective slab width were terminated at the beam-to-wall interfaces (i.e., the
slab bars were not continuous across the beam-to-wall interfaces).
Experimental Program
The construction and testing of the 40%-scale post-tensioned coupled core wall specimen took
place at the Lehigh University NEES Equipment Site. All dimensions, reinforcement, and

structure demands for the test specimen were reduced from the full-scale prototype building
using the 40% length scale factor. In some cases, the full-scale detailing did not scale exactly to a
nominal reinforcement area or a regular dimension, requiring slight deviations from a perfectlyscaled structure. Despite these small deviations, the specimen still satisfied the scaled design
demands very closely. The measured material strengths ranged between fc=6.7-7.6 ksi, and
fy=61-69 ksi for the concrete and steel, respectively, in the different parts of the structure.
The laboratory test specimen represented the most critical bottom three stories of the 8story prototype structure. The upper five stories of the structure were simulated analytically
using the DRAIN-2DX ([11]) software. Since the post-tensioning of the coupled core wall was
an integral part of the floor construction, the test sub-structure included a tributary portion of the
slab at each of the three floors. In the analytical simulation, a 40%-scale model of the 8-story
structure was subjected to a reversed-cyclic lateral displacement history under the ELF profile
from ASCE 7, combined with tributary gravity loads. The foundations of the structure were
modeled as fixed. The analytical models for the wall piers and coupling beams consisted of
nonlinear beam-column elements discretized into fibers with areas and material properties that
accurately depicted the measured concrete and steel properties in the structure. The PT steel and
unbonded lengths of the ED mild steel bars in the coupling beams were modeled using truss
elements. An initial load was applied to the PT steel elements to accurately represent the
measured prestress force in the tendons near the test date. This accounted for any prestress losses
that occurred between the initial post-tensioning phase and the test date.
The wall pier forces determined from this reversed-cyclic analysis were then applied to
the top of the 3-story test specimen using a total of 7 servo-controlled actuators and 4 hydraulic
gravity jacks, simulating the behavior of the upper 5 stories of the 8-story building. Fig. 4(a)
shows a schematic of the test setup, including the steel reaction frame surrounding the structure.
The forces from the actuators and gravity jacks were transferred to the specimen through a load
block fixed to the top of each wall pier. Combinations of these forces were used to impose the
prescribed shear force, axial force, and overturning moment from the upper 5 stories at the top of
each wall pier [see Fig. 4(b)], resulting in equilibrium between the physical and analytical substructures at the interface. In the E-W horizontal direction (i.e., direction of the coupling beams),
one servo-controlled hydraulic actuator was connected to the west loading block (at the top of
the west wall pier, see Fig. 4) to simulate the lateral forces acting on the 3-story sub-structure
from all of the stories above (i.e., 4th through the 8th stories). The ELF forces on the 1st, 2nd, and
3rd floors were also lumped at the west loading block level in a manner to result in the
appropriate overturning moment at the base of the structure. Two additional horizontal actuators
were placed between the east and west loading blocks (one on each of the north and south sides
of the loading blocks) to appropriately distribute the applied shear force between the east and
west wall piers. In the vertical direction, two servo-controlled hydraulic actuators were
connected to the loading block at the top of each wall pier to control the axial force and bending
moment boundary conditions at the top of the 3-story sub-structure, representing the forces
transferred from the upper 4th through 8th stories. Additional hydraulic jacks placed on top of
each wall pier simulated the tributary gravity loads on the structure, including the gravity loads
from the upper stories (i.e., 4th through 8th stories). The load blocks were designed to perform as
a rigid body with small deformations under the large forces applied during testing. The
connections between the load blocks and the wall piers were also designed to have very little
deformations, thus allowing the applied forces and displacements to be controlled accurately.

The specimen was tested under a pseudo-static reversed-cyclic lateral displacement


history applied in the direction of the coupling beams. The lateral displacement history was
similar to the validation testing requirements specified by ACI ITG-5.1 ([12]) for the
classification of unbonded post-tensioned precast concrete structural walls as special RC shear
walls in moderate and high seismic regions of the U.S. While pseudo-dynamic tests may be more
representative of the inertial loads from an earthquake, including higher mode effects, pseudostatic reversed-cyclic tests are typically more demanding and allow for better observation of the
structure performance under a well-defined loading scheme. Furthermore, the structure behavior
during a conventional reversed-cyclic test is not dependent on any particular earthquake record
and can be more readily compared with other test data available in the literature.

(a)

(b)

Figure 4. Specimen test setup: (a) schematic; (b) interface forces


Experimental Results
The measured total base shear force (Vb) versus average 3rd floor drift (3) behavior of the
specimen is shown in Fig. 5. Although minimal, the effects of foundation slip and rotation were
removed from the drift calculation. The testing started in the negative drift direction with the
specimen displaced towards the east. The structure demonstrated ductile behavior up to -2.70%
and +2.53% drift at the 3rd floor level, reaching a maximum base shear of -432 kips and +416
kips in the negative and positive directions of loading, respectively. Note that the corresponding
drifts at the roof of the 8-story structure would be greater than -2.70% and +2.53% due to the
nonlinear displaced shape of the building under lateral loads. According to the analytical model,
at large lateral displacements, the 8th floor drift is about 20% greater than the 3rd floor drift,
implying that the 8-story coupled core wall likely obtained a roof drift ratio greater than 3.00% at
the end of the test, which was the maximum roof drift used in the design of the 8-story structure.

The strength loss from the overall ultimate strength to


the peak load during the last cycle of the test was 22.2% and
20.7% in the negative and positive directions, respectively.
Fig. 6 depicts the damage state of various components of the
structure at the completion of the test. Most of the lateral
strength loss during the last two drift cycles was largely
caused by low-cycle fatigue fracture (preceded by buckling)
of the vertical mild steel bars at the extreme edges of all four
wall pier toes at the base. Audio evidence of these bar
fractures throughout the last two cycles and post-test
excavation of the wall pier toe regions led to this conclusion. Figure 5.rdMeasured base shear
For example, Fig. 6(a) shows the excavated north toe of the versus 3 floor drift behavior
west wall pier base and Fig. 6(b) shows the north toe of the east wall pier base prior to
excavation, each depicting two buckled and fractured vertical bars above the foundation.
Improved detailing to prevent the buckling and fracture of these bars will be investigated in a
second specimen to be tested by the project. Spalling of the cover concrete and subsequent
buckling (with no fracture) of the vertical mild steel bars at the wall pier outer corners [i.e.,
intersection of flange and web of pier; see Figs. 3(a) and (c)] were also noted [e.g., see Fig. 6(c)
for the damage at the outer south corner of the west wall pier base]. The damage in the wall piers
was significantly reduced away from the corners and toes of the C-shaped piers.

(a)

(b)

(c)

(d)
(e)
(f)
Figure 6. Specimen damage at completion of test: (a) north toe of west wall pier base; (b) north toe
of east wall pier base; (c) south corner of west wall pier base; (d) 1st floor south coupling beam; (e)
ED bar buckling in 3rd floor north coupling beam; (f) bottom of 1st floor slab
Overall, the post-tensioned coupling beams performed well during the test. The observed
damage included localized crushing of the concrete at the beam ends [Fig. 6(d)], which was
mostly limited to cover spalling, confirming the design of the confinement reinforcement. The
damage pattern in Fig. 6(d) was generally representative of all of the six coupling beams in the
structure. The beams underwent significant deformations at the ends where large concentrated

cracks formed. Minimal cracking was found in the rest of the span, validating the design
philosophy for the post-tensioned system. Additionally, the large compression stresses at the
beam ends resulted in concrete spalling in the adjacent wall pier regions. In the 3rd floor north
beam, buckling within the unbonded length of one of the bottom ED bars was also observed,
which caused additional concrete spalling and splitting in this region [Fig. 6(e)]. This was the
only ED bar in the structure that exhibited buckling. The ED bar buckling occurred immediately
outside of the closely-spaced hoop region [see Fig. 3(d)], which may indicate the need for
extending the closely spaced hoops along the entire unbonded length of the ED bars.
As shown for the bottom of the 1st floor slab in Fig. 6(f), significant concrete cracking
and spalling was observed in the post-tensioned slabs. These cracks (and the corresponding
spalling regions) propagated outward from the beam ends due to the termination of the mild steel
slab reinforcement to allow for the intended behavior with concentrated cracks at the beam ends.
The presence of cold construction joints in the slabs (perpendicular to the beam length and near
each beam end) may have also contributed to the observed spalling of the concrete in these
regions. The cold joints could be moved further away from the beam ends and a small amount of
mild steel could be added within the effective slab width to help reduce this spalling.
Ongoing and Future Work
Construction of the second post-tensioned coupled core wall test specimen is currently underway.
The design of this structure includes improvements to the first specimen, particularly addressing
the buckling and fracture of the vertical bars at the wall pier toes. Other specimen changes
include the use of fully post-tensioned coupling beams (i.e., with no ED bars), reduced coupling
beam length-to-depth aspect ratio, and modified slab reinforcement details to reduce the amount
of concrete damage in the slabs. More information can be found at http://ptcoupledwalls.nd.edu.
Summary
Large-scale testing of a novel post-tensioned coupled core wall structure under lateral loads
combined with tributary gravity loads was recently completed. Overall, the specimen performed
as predicted, and validated the design approach. The behavior of the structure was ductile up to a
3rd floor drift of -2.70% and +2.53% in the negative and positive directions, respectively.
Analytical models indicate that these results translate to drift levels greater than 3.00% at the
roof of the 8-story structure, which was the maximum drift used in design. Strength loss near the
end of the test was largely caused by the low-cycle fatigue fracture (preceded by buckling) of the
vertical reinforcing bars in the wall pier toes at the base. Additional damage was observed in the
form of localized concrete crushing and cracking at the coupling beam ends, buckling of one ED
bar in the 3rd floor north beam, and cover concrete spalling and subsequent buckling of the
vertical mild steel bars at the outer corners of the wall pier bases. The post-tensioned coupling
beams performed well during the test, demonstrating the advantages of the new system. These
results may ultimately form the basis for the implementation of post-tensioned coupled wall
systems as special RC shear walls in medium and high seismic regions of the U.S.
Acknowledgments
This project is a collaborative effort that includes the University of Notre Dame, the University
of Texas at Tyler, and Lehigh University. The research is funded by the National Science

Foundation (NSF) under Grant No. CMMI 1041598 as a part of the George E. Brown, Jr.
Network for Earthquake Engineering Simulation (NEES) Research (NEESR). This award is a
part of the National Earthquake Hazards Reduction Program (NEHRP). Support of the NSF
Program Director Dr. J. Pauschke is gratefully acknowledged. At the University of Texas at
Tyler, students M. Lisk and M. Holloman worked on the development of the multiple DIC sensor
protocol. At the Lehigh University NEES equipment site, laboratory staff (C. Bowman, P. Bryan,
D. Fritchman, T. Maurullo, G. Novak, and E. Tomlinson), faculty members (S. Pakzad and J.
Ricles), graduate students (M. Tillotson and K. Kazemibidokhti), and undergraduate students (A.
Breden, M. Davis, F. Tao, E. Salazar, C. Fallon, and K. Brinkhoff) worked on the construction,
instrumentation, and testing of the coupled wall specimen. The design of the test specimen was
conducted in collaboration with practicing engineers from Magnusson Klemencic Associates (D.
Fields, A. Haaland, and J. Mouras). The contributions of K. Bondy, Consulting Structural
Engineer, to the project are also acknowledged. The concrete used to construct the test specimen
was donated by Essroc Italcementi Group, the PT anchors were donated by Hayes Industries,
Ltd., the PT strand was donated by Sumiden Wire Products Corporation (SWPC), and the
formwork was donated by A.H. Harris & Sons, Inc. Additional material donations were made by
Dayton Superior and Casilio Concrete. The findings, conclusions, and/or recommendations
expressed in this paper are those of the authors and do not necessarily represent the views of the
individuals or organizations noted above.
References
1.

Barney, G., Shiu, K., Rabbat, B., Fiorato, A., Russell, H., and Corley, W., Earthquake Resistant Structural
Walls Tests of Coupling Beams, Construction Tech. Lab. Report, Portland Cement Assoc., January 1978.

2.

Tassios, T., Moretti, M., and Bezas, A., On the Behavior and Ductility of Reinforced Concrete Coupling
Beams of Shear Walls, ACI Structural J., 93(6), 1996, 711-720.

3.

Bristowe, S., Seismic Response of Normal and High Strength Concrete Members, Ph.D. Dissertation. Civil
Engineering and Applied Mechanics, McGill U., Montreal, Canada, 2000.

4.

Galano, L. and Vignoli, A., Seismic Behavior of Short Coupling Beams with Different Reinforcement
Layouts, ACI Structural J., 97(6), 2000, 876-885.

5.

Canbolat, B., Parra-Montesinos, G., and Wight, J., Experimental Study on Seismic Behavior of HighPerformance Fiber-Reinforced Cement Composite Coupling Beams, ACI Structural J., 102(1), 2005, 159-166.

6.

Weldon, B. and Kurama, Y., Nonlinear Behavior of Precast Concrete Coupling Beams, J. of Structural
Engineering, 133(11), 2007, 1571-1581.

7.

Weldon, B. and Kurama, Y., Experimental Evaluation of Post-Tensioned Precast Concrete Coupling Beams,
J. of Structural Engineering, 136(9), 2010, 1066-1077.

8.

Weldon, B. and Kurama, Y., Analytical Modeling and Design Validation of Posttensioned Precast Concrete
Coupling Beams for Seismic Regions, J. of Structural Engineering, 138(2), 2012, 224-234.

9.

McGinnis, M., Barbachyn, S., and Kurama, Y., Application of Multiple Digital Image Correlation Sensors in
Earthquake Engineering, 10th National Conference in Earthquake Engineering, Anchorage, AK, 2014.

10. ASCE/SEI 7-10, Minimum Design Loads for Buildings and Other Structures, American Society of Civil
Engineers, Reston, Virginia, 2010.
11. Prakash, V., G.A. Powell, and Campbell, S., DRAIN-2DX Base Program Description and User Guide,
Department of Civil Engineering, University of California, Berkeley, California, 1993.
12. ACI, ACI ITG-5.1-07 Acceptance Criteria for Special Unbonded Post-Tensioned Precast Structural Walls
Based on Validation Testing and Commentary, ACI Innovation Task Group 5, 2007.

Das könnte Ihnen auch gefallen