Sie sind auf Seite 1von 14

Federal Register / Vol. 70, No.

184 / Friday, September 23, 2005 / Notices 55821

DEPARTMENT OF ENERGY and Ancillary Service rates on August 1, Voltage Control from Generation
1998, in Rate Order No. WAPA–79. The Sources Service (Reactive Service) is
Western Area Power Administration Commission confirmed and approved $0.06/kWmonth. The provisional rate
the rate schedules on November 25, for Reactive Service is $0.07/kWmonth.
Pick-Sloan Missouri Basin Program— 1998, in FERC Docket No. EF98–5031– Under Rate Schedule UGP–AS3, the
Eastern Division Transmission and 000. These rate schedules were then provisional rate calculated for
Ancillary Services-Rate Order No. extended through September 30, 2005, Regulation and Frequency Response
WAPA–122 by Rate Order No. WAPA–100, which Service is unchanged from the existing
AGENCY: Western Area Power was confirmed and approved by the rate of $0.04/kWmonth. Under Rate
Administration, DOE. Commission on December 16, 2003, Schedule UGP–AS4, there is no change
under FERC Docket No. EF03–5032– in the rate for Energy Imbalance Service
ACTION: Notice of Order Concerning
000. The rate schedules for Rate Order between the existing and the proposed
Transmission and Ancillary Services No. WAPA–79 and Rate Order No. rates. Under Rate Schedules UGP–AS5
Rates. WAPA–100 contained formulary rates and UGP–AS6, the rate for Spinning and
SUMMARY: The Deputy Secretary of that were recalculated yearly using the Supplemental Reserves is $0.11/
Energy confirmed and approved Rate fixed charge rate methodology. The kWmonth. The provisional rate
Order No. WAPA–122 and Rate provisional formula rates will continue calculated for Spinning and
Schedules UGP–FPT1, UGP–NFPT1, to use the fixed charge rate methodology Supplemental Reserves is $0.12/
UGP–NT1, UGP–AS1, UGP–AS2, UGP– and will continue to be recalculated kWmonth.
AS3, UGP–AS4, UGP–AS5, and UGP– yearly from updated financial and load By Delegation Order No. 00–037.00,
AS6 placing the Integrated System (IS) data. However, the Generator Step Up effective December 6, 2001, the
Transmission and Ancillary Services Transformers are to be removed from Secretary of Energy delegated: (1) The
rate into effect on an interim basis. The the annual revenue requirement for IS. authority to develop power and
provisional rates will be in effect until After the approval of the original transmission rates to Western’s
the Federal Energy Regulatory Transmission and Ancillary Service Administrator, (2) the authority to
Commission (Commission) confirms, rates for the IS, the Commission decided confirm, approve, and place such rates
that Generator Step Up Transformers into effect on an interim basis to the
approves, and places them into effect on
should not be included in transmission Deputy Secretary of Energy, and (3) the
a final basis or until they are replaced
rates for jurisdictional utilities. authority to confirm, approve, and place
by other rates. The provisional rates will
Consistent with Western’s goal to into effect on a final basis, to remand or
provide sufficient revenue to pay all
observe Commission precedent to the to disapprove such rates to the
annual costs, including interest
extent consistent with its mission and Commission. Existing DOE procedures
expense, and repayment of required
permitted by law and regulation, the IS for public participation in power rate
investment, within the allowable
Transmission and Ancillary Service adjustments (10 CFR part 903) were
periods.
rates are being modified. published on September 18, 1985.
DATES: Rate Schedules UGP–FPT1, The existing IS Long-Term Firm and Under Delegation Order Nos. 00–
UGP–NFPT1, UGP–NT1, UGP–AS1, Short-Term Firm Point-to-Point 037.00 and 00–001.00A, 10 CFR part
UGP–AS2, UGP–AS3, UGP–AS4, UGP– Transmission Service Rate Schedule is 903, and 18 CFR part 300, I hereby
AS5, and UGP–AS6 will be placed into superseded by Rate Schedule UGP– confirm, approve, and place Rate Order
effect on an interim basis on the first FPT1, dated October 2005. The 2004– No. WAPA–122, the proposed IS Firm
day of the first full billing period 2005 existing rate for IS Long-Term and Non-Firm Transmission and
beginning on or after October 1, 2005, Firm and Short-Term Firm Point-to- Ancillary Service rates into effect on an
and will be in effect until the Point Transmission Service is $2.72 per interim basis. The new Rate Schedules
Commission confirms, approves, and kilowattmonth (kWmonth). The UGP–FPT1, UGP–NFPT1, UGP–NT1,
places the rate schedules in effect on a provisional rate for IS Long-Term Firm UGP–AS1, UGP–AS2, UGP–AS3, UGP–
final basis through September 30, 2010, and Short-Term Firm Point-to-Point AS4, UGP–AS5, and UGP–AS6 for IS
or until the rate schedules are Transmission Service is $2.69/ Transmission and Ancillary Service
superseded. These new rate schedules KWmonth. Under Rate Schedule UGP– rates will be promptly submitted to the
dated October 2005, supersede the NFPT1, the existing rate calculation for Commission for confirmation and
similarly titled rate schedules dated IS Non-Firm Point-to-Point approval on a final basis.
1998. Transmission Service is 3.73 mills per
kilowatthour (mills/kWh). The Dated: September 13, 2005.
FOR FURTHER INFORMATION CONTACT: Mr. provisional rate for IS Non-Firm Point- Clay Sell,
Robert J. Harris, Upper Great Plains to Point Transmission Service is 3.68 Deputy Secretary.
Regional Manager, Western Area Power mills/kWh. Under Rate Schedule UGP– [Rate Order No. WAPA–122]
Administration, 2900 4th Avenue North, NT1 the existing annual revenue
Billings, MT 59101–1266, telephone In the matter of: Western Area Power
requirement for IS Network Integration Administration Rate Adjustment for the Pick-
(406) 247–7405, or Mr. Jon R. Horst, Transmission Service is $128,017,923. Sloan Missouri Basin Program—Eastern
Rates Manager, Upper Great Plains The provisional annual revenue Division Transmission and Ancillary
Region, Western Area Power requirement for IS Network Integration Services; Order Confirming, Approving, and
Administration, 2900 4th Avenue North, Transmission Service is $126,741,576. Placing the Pick-Sloan Missouri Basin
Billings, MT 59101–1266, telephone Under Rate Schedule UGP–AS1, the Program—Eastern Division Transmission and
(406) 247–7444, e-mail horst@wapa.gov. existing rate for Scheduling System Ancillary Services Formula Rates Into Effect
SUPPLEMENTARY INFORMATION: The Control and Dispatch (Scheduling and on an Interim Basis
Deputy Secretary of Energy approved Dispatch) Service is $49.29/schedule/ This rate was established in
existing Rate Schedules UGP–FPT1, day. The provisional rate for Scheduling accordance with section 302 of the
UGP–NFPT1, UGP–NT1, UGP–AS1, and Dispatch is $49.77/schedule/day. Department of Energy (DOE)
UGP–AS2, UGP–AS3, UGP–AS4, UGP– Under Rate Schedule UGP–AS2, the Organization Act (42 U.S.C. 7152). This
AS5, and UGP–AS6 for IS Transmission existing rate for Reactive Supply and Act transferred to and vested in the

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00007 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
55822 Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices

Secretary of Energy the power marketing Commission: Federal Energy hourly load (including its designated
functions of the Secretary of the Regulatory Commission. network load not physically
Department of the Interior and the Corps of Engineers: U.S. Army Corps interconnected with the Transmission
Bureau of Reclamation under the of Engineers. Provider) to the Transmission Provider’s
Reclamation Act of 1902 (ch. 1093, 32 Customer: An entity with a contract monthly Transmission System peak,
Stat. 388), as amended and that is receiving service from Western’s calculated on a rolling 12-month basis.
supplemented by subsequent laws, UGPR. Long-Term Firm Point-to-Point: Firm
particularly section 9(c) of the DOE: United States Department of Point-to-Point Transmission Service
Reclamation Project Act of 1939 (43 Energy. reservation with at least 12 consecutive
U.S.C. 485h(c)), section 5 of the Flood DOE Order RA 6120.2: An order equal monthly amounts.
Control Act of 1944 (16 U.S.C. 825s), outlining power marketing MAPP: Mid-Continent Area Power
and other Acts that specifically apply to administration financial reporting and Pool.
the project involved. ratemaking procedures. MBMPA: Missouri Basin Municipal
By Delegation Order No. 00–037.00, Energy: Measured in terms of the Power Agency.
effective December 6, 2001, the work capacity over a period of time. It Mill: A monetary denomination of the
Secretary of Energy delegated: (1) The is expressed in kilowatthours. United States that equals one tenth of a
authority to develop power and Emergency Energy: Electric energy cent or one thousandth of a dollar.
transmission rates to Western’s purchased by an electric utility Mills/kWh: Mills per kilowatthour—
Administrator, (2) the authority to whenever an event on the system causes the unit of charge for energy.
confirm, approve, and place such rates insufficient operating capability to cover MVAR: Megavar, equal to 1,000,000
into effect on an interim basis to the its own demand requirement. VARs.
Deputy Secretary of Energy, and (3) the Energy Imbalance Service: A service MW: Megawatt—the electrical unit of
authority to confirm, approve, and place which provides energy correction for capacity that equals 1 million watts or
into effect on a final basis, to remand or any hourly mismatch between a 1,000 kilowatts.
to disapprove such rates to the Transmission Customer’s energy supply NERC: North American Electric
Commission. Existing DOE procedures and the demand served. Reliability Council.
for public participation in power rate Energy Rate: The rate which sets forth Net Revenue: Revenue remaining after
adjustments (10 CFR part 903) were the charges for energy. It is expressed in paying all annual expenses.
published on September 18, 1985. mills per kilowatthour and applied to Network Customer: An entity
each kilowatthour delivered to each receiving Transmission Service under
Acronyms and Definitions customer. the terms of the Transmission Provider’s
As used in this Rate Order, the FERC: The Commission (to be used Network Integration Transmission
following acronyms and definitions when referencing Commission Orders). Service of the Tariff.
apply: FERC Order No. 888: FERC Order Non-Firm Point-to-Point: Point-to-
$/kWmonth: Monthly charge for Nos. 888, 888–A, 888–B and 888–C Point Transmission Service under the
capacity (i.e., $ per kilowatt (kW) per unless otherwise noted. Tariff that is reserved and scheduled on
month). Firm: A type of product and/or service an as-available basis and is subject to
available at the time requested by the interruption for economic reasons.
12-cp: 12-month coincident peak
customer. O&M: Operation and maintenance.
average.
Firm Point-to-Point: Service that is OASIS: Open Access Same-Time
Administrator: The Administrator of Information System—provides access to
the Western Area Power reserved and/or scheduled between
Points of Receipt and Delivery. information on transmission pricing and
Administration. availability for potential transmission
FRN: Federal Register notice.
Ancillary Services: Those services customers.
FY: Fiscal year; October 1 to
necessary to support the transfer of OM&R: Operation, Maintenance &
September 30.
electricity while maintaining reliable GSU: Generator Step Up Transformer. Replacement.
operation of the transmission system in GWh: Gigawatthour—the electrical P–SMBP: Pick-Sloan Missouri Basin
accordance with standard utility unit of energy that equals 1 billion Program.
practice. watthours or 1 million kWh. P–SMBP—ED: Pick-Sloan Missouri
A&GE: Administrative and general Heartland: Heartland Consumers Basin Program—Eastern Division.
expense. Power District. Point-to-Point: The reservation and
Balancing Authority: An electric IS: Integrated System. transmission of capacity and energy on
system or systems, bounded by ISO: Independent System Operator. either a firm or non-firm basis from
interconnection metering and telemetry, JTS: Joint Transmission System. designated Point(s) of Receipt to
capable of controlling generation to kW: Kilowatt—the electrical unit of designated Point(s) of Delivery.
maintain its interchange schedule with capacity that equals 1,000 watts. Power: Capacity and energy.
other Balancing Authorities and kWh: Kilowatthour—the electrical Provisional Rate: A rate which has
contributing to frequency regulation of unit of energy that equals 1,000 watts in been confirmed, approved, and placed
the Interconnection. Formerly known as 1 hour. into effect on an interim basis by the
control area. kWmonth: Kilowattmonth—the Deputy Secretary.
Basin Electric: Basin Electric Power electrical unit of the monthly amount of Rate Brochure: An April 2005
Cooperative. capacity. document explaining the rationale and
Capacity: The electric capability of a kWyear: Kilowattyear—the electrical background for the rate proposal
generator, transformer, transmission unit of the yearly amount of capacity. contained in this Rate Order.
circuit, or other equipment. It is Load: The amount of electric power or Reclamation: United States
expressed in kilowatts. energy delivered or required at any Department of the Interior, Bureau of
Capacity Rate: The rate which sets specified point(s) on a system. Reclamation.
forth the charges for capacity. It is Load-ratio share: Ratio of the Network Reclamation Law: A series of Federal
expressed in $/kWmonth. Transmission Customer’s coincident laws. Viewed as a whole, these laws

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00008 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices 55823

create the framework under which Supplemental Reserve Service: Plains Customer Service Region,
Western markets power. Generation capacity needed to serve Operations Office, 1330 41st Street SE.,
Reactive Supply and Voltage Control load in the event of a system Watertown, South Dakota.
from Generating Sources Service: A contingency; however, it is not available Western: United States Department of
service which provides reactive supply immediately to serve load but rather Energy, Western Area Power
through changes to generator reactive within a short period of time. Administration.
output to maintain transmission line Supplemental Reserve Service may be Western Regions: Customer service
voltage and facilitate electricity provided by generation units that are regions of the Western Area Power
transfers. on-line but unloaded, by quick start Administration.
Regulation and Frequency Response generation or by interruptible load. The Western’s Tariff: Western’s Open
Service: A service which provides for Transmission Provider must offer this Access Transmission Service Tariff.
following the moment-to-moment service when the transmission service is Effective Date
variations in the demand or supply in used to serve load within its Balancing
a Balancing Authority and maintaining Authority. The Transmission Customer The new interim rates will take effect
scheduled interconnection frequency. must either purchase this service from on the first day of the first full billing
Reserve Services: Spinning Reserve the Transmission Provider or make period beginning on or after October 1,
Service and Supplemental Reserve alternative comparable arrangements to 2005, and will remain in effect until
Service. satisfy its Supplemental Reserve Service September 30, 2010, pending approval
Revenue Requirement: The revenue obligation. by the Commission on a final basis.
required to recover annual expenses Supporting Documentation: A Public Notice and Comment
(such as O&M, purchase power, compilation of data and documents that
transmission service expenses, interest, support the Rate Brochure and the rate Western followed the Procedures for
and deferred expenses) and repay proposal. Public Participation in Power and
Federal investments, and other assigned System: An interconnected Transmission Rate Adjustments and
costs. combination of generation, transmission Extensions, 10 CFR part 903, for a minor
SCADA: Supervisory Control and Data and/or distribution components rate adjustment in developing these
Acquisition. comprising an electric utility, rates. The steps Western took to involve
Schedule: An agreed-upon transaction independent power producer(s) (IPP), or interested parties in the rate process
size (megawatts), beginning and ending group of utilities and IPP(s). were:
ramp times and rate, and type of service Tariff: Western Area Power 1. The proposed rate adjustment
required for delivery and receipt of Administration Open Access process began February 9, 2005, when
power between the contracting parties Transmission Service Tariff, originally Western mailed a notice announcing an
and the Balancing Authority(ies) approved in Docket No. NJ98–1–000, 99 informal customer meeting to all IS
involved in the transaction. FERC ¶ 61,062 (2002) and amended in Transmission Customers and interested
Scheduling, System Control and Docket No. NJ05–1–000, 112 FERC parties. The meeting was held on March
Dispatch Service: A service which ¶ 61,044 (2005). 22, 2005, in Sioux Falls, South Dakota.
provides for (a) scheduling, (b) Transmission Customer: Any eligible At this informal meeting, Western
confirming and implementing an customer (or its designated agent) that explained the rationale for the rate
interchange schedule with other receives transmission service under the adjustment, presented rate designs and
balancing authorities, including Tariff. methodologies, and answered questions.
intermediary balancing authorities Transmission Provider: Any utility 2. A Federal Register notice
providing transmission service, and (c) that owns, operates, or controls facilities published on April 18, 2005, (70 FR
ensuring operational security during the used to transmit electric energy in 20119), announced the proposed rates
interchange transaction. interstate commerce. The UGPR, as for P–SMBP—ED Transmission and
Service Agreement: The initial operator of the IS, is the Transmission Ancillary Service rates, and began a
agreement and any amendments or Provider for the purposes of this Federal public consultation and comment
supplements entered into by the Register notice. period.
Transmission Customer and Western for Transmission System: The facilities 3. On April 28, 2005, Western mailed
service under the Tariff. owned, controlled, or operated by the letters to all IS Transmission Customers
Short-Term Firm Point-to-Point: Firm Transmission Provider that are used to and interested parties transmitting the
Point-to-Point Transmission Service provide transmission service. Federal Register notice published on
with service duration of less than one Transmission System Total Load: The April 18, 2005, and directing them to
year. 12-cp peak for Network Transmission the rate brochure on Western’s Web site.
Spinning Reserve Service: Generation Service plus reserved capacity for all 4. Western received no comment
capacity needed to serve load Firm Point-to-Point Transmission letters during the consultation and
immediately in the event of a system Service. comment period, which ended May 18,
contingency. Spinning Reserve Service UGPR: The Upper Great Plains 2005.
may be provided by generating units Customer Service Region of the Western
that are on-line and loaded at less than Project Description
Area Power Administration. In some
maximum output. The Transmission places in this order, UGPR maybe The initial stages of the Missouri
Provider must offer this service when referenced generically as Western. River Basin Project were authorized by
the transmission service is used to serve VAR: A unit of reactive power. section 9 of the Flood Control Act of
load within its Balancing Authority. The WAUGP: The NERC acronym for the 1944 (58 Stat. 887, 890, Pub. L. 78–534).
Transmission Customer must either Western Area Upper Great Plains It was later renamed the P–SMBP. The
purchase this service from the Balancing Authority. This balancing P–SMBP is a comprehensive program,
Transmission Provider or make authority is also known as the with the following authorized functions:
alternative comparable arrangements to Watertown Balancing Authority. flood control, navigation improvement,
satisfy its Spinning Reserve Service Watertown Operation Office: Western irrigation, municipal and industrial
obligation. Area Power Administration Upper Great water development, and hydroelectric

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00009 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
55824 Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices

production for the entire Missouri River facilities interconnect with utilities in These revenue requirements are offset
Basin. Multipurpose projects have been the states of Montana, North Dakota, by appropriate IS revenues.
developed on the Missouri River and its South Dakota, Iowa, Minnesota,
Integrated System Transmission
tributaries in Colorado, Montana, Missouri, and in addition include
Service
Nebraska, North Dakota, South Dakota, facilities which interconnect with
and Wyoming. Canada. Western will offer Network, Firm
The UGPR markets significant The approach for formation of the IS Point-to-Point, and Non-Firm Point-to-
quantities of Federally-generated was to include facilities which followed Point Transmission Service on the IS.
hydroelectric power from the P– the spirit and intent of the FERC Order The service offered is the transmission
SMBP—ED. Western owns and operates No. 888 and to make the system the of energy and capacity from Points of
an extensive system of high-voltage most useful to all transmission Receipt to Points of Delivery on the IS.
transmission facilities which the UGPR requesters. The ‘‘seven-factor test’’ The IS Transmission Service Rates
uses to market approximately 2,400 MW defined in FERC Order No. 888 was include the cost of Scheduling, System
of capacity from Federal projects within used to determine the distribution Control and Dispatch Service.
the Missouri River Basin. This capacity facilities that were excluded from the IS Therefore, an additional charge for this
is generated by eight powerplants Transmission System. Several major ancillary service is not required for
located in Montana, North Dakota, and facilities are included in the IS. The transmission users.
South Dakota. The UGPR uses the second 345-kV transmission line Western, Basin Electric, and
transmission facilities of Western and between the Antelope Valley and Heartland will take IS Transmission
others to market this power and energy Leland Olds generation stations, which Service. Transmission Service to
to customers located within the P– meets the standards for acceptable Western’s Customers continues to be
SMBP—ED. This marketing area transmission facilities set in the bundled in the firm electric power
includes Montana, east of the Commission rulings on filings by other service rate under existing contracts that
Continental Divide, all of North and transmission entities, is included. The expire in 2020.
South Dakota, eastern Nebraska, western 230-kV transmission line between
Iowa, and western Minnesota. The UGPR prepared a transmission
Tioga, North Dakota, and Boundary
service study to ensure that the formula
Integrated System Description Dam, which provides access to
IS Transmission and Ancillary Service
generation and loads in Canada, is
Using a single system, joint-planning rates are based on the cost of service to
included in the IS. The IS also includes
concept, the UGPR, Basin Electric, and the IS. The UGPR seeks approval of
the Miles City DC tie, which opens the
Heartland combined their transmission formula rates for calculating Point-to-
markets between the east-west electrical
facilities to form the IS and developed Point IS Transmission Rates, the
separation of the United States and
Transmission and Ancillary Service Network Annual Revenue Requirement
increases access to other utilities.
rates for transmission over the IS. This for IS Transmission Service, and
action was necessary because the UGPR, P–SMBP—ED Transmission and ancillary service rates. Western requests
Basin Electric, and Heartland, whose Ancillary Service Rates Study the Commission confirm that these rates
facilities are fully integrated, did not Western prepared a Transmission and are not arbitrary, capricious, or in
have rates suitable for long-term open Ancillary Service rates study to ensure violation of the law. The rates will be
access transmission service. The that Transmission and Ancillary Service recalculated every year, effective May 1,
transmission facilities included in the IS rates are based on the cost of service of based on the approved formula rates
are transmission lines, substations, the IS Transmission System. This study and updated financial and load data.
communication equipment and facilities includes all IS Transmission and The UGPR will provide customers
related to operation, maintenance, and Ancillary Service expenses and notice of changes in the Transmission
support of the IS Transmission System. associated offsetting revenues. Western and Ancillary Service rates no later than
The UGPR is designated as the operator charges IS Transmission Service rates April 1 of each year.
of the other participants’ transmission separately to entities receiving IS Transmission System Total Load
facilities and as such contracts for transmission-only services over the IS
service, determines and posts the Transmission System. The IS Transmission System Total
available transmission capacity on the The UGPR is proposing to continue Load is the 12-cp system peak for IS
OASIS, bills for service, collects using an annual fixed charge formula Network Transmission Service plus the
payments, and distributes revenues to that will determine how much revenue reserved capacity for all IS Long-Term
each IS participant. The IS consists of must be recovered from the IS Firm Point-to-Point Transmission
the transmission facilities owned by Transmission and Ancillary Service Service.
Basin Electric and Heartland east of the rates. The annual revenue requirements The IS Transmission System Total
east-west electrical separation in the include O&M expenses, administrative Load is calculated as follows based
United States, the transmission facilities and general expenses, interest expense, upon the most recent historical data
owned by Western in the P–SMBP—ED, and depreciation expense. This available at the time of the initial rate
and the Miles City DC Tie owned by methodology is applied annually using proposal. This included both 2003 and
Western and Basin Electric. These the most recent historical test year. 2004 data:

IS Network Transmission Load ................................................................................................................................................. 3,185,000 kW


Long-Term Firm Point-to-Point Reserved Capacity .................................................................................................................. 743,000 kW

IS Transmission System Total Load .......................................................................................................................................... 3,928,000 kW

Annual Costs and Ancillary Services using a charge rates for various cost
Western calculated the annual costs of Commission-recognized methodology components. The cost components
providing the various IS Transmission for annual cost calculation with fixed applicable to Western include O&M,

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00010 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices 55825

A&GE, depreciation, and the cost of fixed charge rates are then summed to fixed charge rate calculation for the
capital. These components are arrive at a total fixed charge rate various IS Transmission and Ancillary
displayed as fixed charge rates or associated with the particular service for Services can be summarized with the
percentages of net investment. These which a rate is being calculated. The following formula:

O&M ÷ Net investment


+ A&GE ÷ Net investment
+ Depreciation expense ÷ Net investment
+Annual interest expense ÷ Unpaid investment balance

Total fixed charge rate

To arrive at the annual cost of providing data are Basin Electric’s Consolidated providing the IS Transmission Service
the IS Transmission Service or one of Financial Statement, Rural Utility plus any facility credit paid to the IS
the Ancillary Services, the total fixed Service Form 12, and other accounting Transmission Customers. The annual
charge rate is applied to the net records. revenue requirement for IS
investment allocated to the service: Annual Revenue Requirement for IS Transmission Service includes the cost
Total fixed charge rate × Net Transmission Service for Scheduling, System Control, and
investment = Annual cost of providing Dispatch Service needed to provide
The annual revenue requirement for
service. transmission service. Therefore, an
IS Transmission Service is based upon
The source for the UGPR’s annual the most recent historical data available additional charge for this ancillary
O&M, A&GE, depreciation expense, at the time of the initial rate proposal. service is not required for transmission
interest expense, and investment is the This data is used in a test year and uses users. The annual transmission costs are
Results of Operations for the Upper an annual fixed charge methodology. offset by appropriate Transmission
Great Plains Customer Service Region- The rates for IS Transmission Service Revenue Credits to avoid over-recovery
Pick Sloan Missouri Basin. The source (Network and Point-to-Point) are based of costs. The annual revenue
for Heartland’s data is Heartland on a revenue requirement that recovers requirement for IS Transmission Service
Consumers Power District Annual the annual costs of Western, Basin can be summarized with the following
Report. The sources for Basin Electric’s Electric, and Heartland associated with formula:

Annual IS Transmission Costs of UGPR


+ Annual IS Transmission Costs Basin Electric and Heartland
+ Transmission Customer Facility Credits
¥ Transmission Revenue Credits

Annual Revenue Requirement for IS Transmission Service

Transmission Customer Facility Commission’s guidance in the FERC IS Network Transmission Service
Credits are credits paid to IS Order No. 888, other relevant
Transmission Customers for facilities Commission policy, and the terms of the The proposed rate for IS Network
that are integrated with the IS and Tariff. Transmission Service is a formula
increase both the capability and the Transmission Revenue Credits calculation based upon the annual
reliability of the IS. The credits are include revenue from sales of Non-Firm, revenue requirement for IS
addressed in individual agreements and discounted IS Firm and Short-Term Transmission Service then in effect, as
appropriate adjustments are made in Firm Point-to-Point Transmission determined by the annual fixed charge
Service; revenue from existing methodology. The monthly charge for IS
subsequent rate calculations. The IS
transmission agreements; and revenue Network Transmission Service is as
participants will evaluate requests for
from Scheduling, System Control and follows:
facility credits consistent with the Dispatch Services.

Network Customer’s Load-ratio share


× Annual Revenue Requirement for IS Transmission
÷ 12 months

Monthly IS Network Transmission Service Charge

The load ratio-share is the ratio of the on a rolling 12-cp basis. The proposed revenue requirement for IS
Network Customer’s coincident hourly rate formula would be effective October Transmission Service divided by the IS
load to the monthly IS Transmission 1, 2005, through September 30, 2010. Transmission System Total Load in kW,
System peak minus the coincident peak to derive a cost per kilowattyear
IS Firm Point-to-Point Transmission
for all IS Firm Point-to-Point (kWyear). The formula for the monthly
Service
Transmission Service plus the IS Firm rate is as follows:
Point-to-Point reservations, calculated The rate for IS Firm Point-to-Point
Transmission Service is the annual

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00011 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
55826 Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices

Annual Revenue Requirement for IS Transmission


÷ IS Transmission System Total Load
÷ 12 months

Monthly IS Firm Point-to-Point Transmission Rate

The rate formula is applied annually IS Non-Firm Point-to-Point mills/kWh rate, based upon the current
by using the most current historical data Transmission Service firm point-to-point rate and may be
available. The proposed rate formula discounted. The formula rate is as
would be effective October 1, 2005, The proposed rate for IS Non-Firm follows:
through September 30, 2010. Point-to-Point Transmission Service is a

Monthly IS Firm Point-to-Point Transmission Rate


÷ 730 hours/month
× 1000 mills per dollar

IS Non-Firm Point-to-Point Transmission Rate

This rate will remain in effect for the remaining four ancillary services are: (3) unable to provide these services from its
same period as the IS Firm Point-to- Regulation and Frequency Response own resources, an offer will be made to
Point Transmission Service rate and Service, (4) Energy Imbalance Service, purchase the services and pass through
will also be reviewed annually. The IS (5) Spinning Reserve Service, and (6) these costs, including an administrative
Non-Firm Point-to-Point Transmission Supplemental Reserve Service. The charge to the customer.
Service will be offered at hourly, daily, open access ancillary service formula
and monthly rates. The IS Transmission Scheduling, System Control, and
rates are designed to recover only the
Service availability will be posted on Dispatch Service
costs incurred for providing the
the UGPR OASIS. service(s). The charges for ancillary Western’s annual revenue
Ancillary Services services are based on the cost of requirement for Scheduling, System
resources used to provide these services. Control, and Dispatch Service is
In accordance with the Tariff, Western
will offer to all customers the six Sales of Regulation and Frequency determined by multiplying the portion
ancillary services defined by the Response Service, Energy Imbalance of the Watertown Operations Office net
Commission, two of which IS Service, Spinning Reserve Service, and plant and communications facilities net
Transmission Customers are required to Supplemental Reserve Service may be plant associated with Scheduling,
purchase: (1) Scheduling, System limited since Western has allocated its System Control, and Dispatch Service
Control, and Dispatch Service, and (2) power resources to preference entities by the transmission fixed charge rate.
Reactive Supply and Voltage Control under long-term commitments. In The formula rate for Scheduling, System
from Generation Sources Service. The accordance with the Tariff, if Western is Control, and Dispatch Service is:

Annual Revenue Requirement for


Scheduling, System Control and Dispatch Service
÷ Annual Number of Daily Schedules

Scheduling, System Control and Dispatch Rate

This rate and rate design only recovers generation fixed charge rate. The annual the total revenue requirement for this
Western’s revenue requirement for cost is multiplied by the capability used service. The Reactive Supply and
Scheduling, System Control, and for reactive support to determine Voltage Control Service from Generation
Dispatch Service. Western’s reactive service revenue Sources Service rate is then derived by
Reactive Supply and Voltage Control requirement. Basin Electric’s and dividing the total annual revenue
from Generation Sources Service Heartland’s annual revenue requirement requirement by the load requiring
is based on the annual cost of reactive service. The annual rate is then
Western’s annual cost of providing
equipment installed on its generators to divided by 12 months to obtain a
Reactive Supply and Voltage Control
from Generation Sources Service is provide this service. Western’s, Basin monthly rate. The Reactive Supply and
determined by multiplying the total P– Electric’s, and Heartland’s annual Voltage Control rate calculation is
SMBP—ED generation net plant by the revenue requirements are summed for summarized in the following formula:

Annual Reactive Revenue Requirement


+ Load Requiring Reactive Service
÷ 12 months

Monthly Reactive Rate

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00012 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices 55827

Regulation and Frequency Response Peck powerplants’ installed capacity. Service. Basin Electric’s and Heartland’s
Service This dollar per kilowatt amount is then annual revenue requirement is based on
applied to the capacity of Oahe the annual cost of equipment installed
Regulation and Frequency Response generation and Fort Peck generation on its generators to provide this service.
Service in the east side of the balancing reserved for Regulation and Frequency Western’s, Basin Electric’s, and
authority is provided primarily by Oahe Response Service in the balancing Heartland’s annual revenue
generation and in the west side of the authority. The capacity reserved for requirements are summed for the total
balancing authority by Fort Peck Regulation and Frequency Response revenue requirement for this service.
generation, both of which are Corps of Service has been determined to be 2 Annual rate for Regulation and
Engineer facilities. To calculate the percent of the annual peak load. The 2 Frequency Response Service is then
annual cost of providing Regulation and percent value was derived by averaging determined by dividing the total
Frequency Response Service, the Corps yearly peak condensing as percentage of revenue requirement by the total load in
of Engineers’ generation fixed charge load for five years. Western’s annual the Balancing Authority. The annual
rate is applied to Oahe generation and revenue requirement for Regulation and rate is then divided by 12 months to
Fort Peck generation net plant Frequency Response Service is obtain a monthly rate. The Regulation
investment. This cost is divided by the determined by applying the dollar per and Frequency Response Service rate
capacity at the plants to derive a dollar kilowatt amount to the capacity used for calculation is summarized in the
per kilowatt amount for Oahe and Fort Regulation and Frequency Response following formula:

Annual Revenue Requirement for Regulation


+ Load in the Balancing Authority Requiring Regulation
÷ 12 months

Monthly Regulation and Frequency Response Rate

Energy Imbalance Service Reserve Services requirement for Reserve Services. The
annual revenue requirement for Reserve
This service is not intended to Western’s annual cost of generation Services is divided by Western’s peak
provide backup for generation supply. for Reserve Services is determined by transmission load to calculate the
Energy shall be returned in like time multiplying the generation fixed charge annual rate. The annual rate is then
frames (on-peak, off-peak, etc.) and rate by the P–SMBP—ED generation net divided by 12 months to obtain a
accounts zeroed out monthly. Western plant investment. The cost/kW year is monthly rate. This rate and rate design
reserves the right to apply a penalty to determined by dividing the annual cost recovers only Western’s revenue
energy imbalances outside a 3-percent of generation by the plant capacity. The requirement associated with Reserve
bandwidth (±1.5 percent deviation). The capacity used for Reserve Services is Services. If energy is taken under these
penalty for under deliveries outside the determined by multiplying Western’s services, the energy charge will be the
3-percent bandwidth is 100 mills/kWh. peak IS load by the MAPP operating MAPP or its successors rate for
Over deliveries outside the bandwidth reserve requirement of 5 percent. The emergency energy. The Regulation and
will be forfeited to the balancing cost/kW year is multiplied by the Frequency Response Service rate
authority. capacity used for Reserve Services to calculation is summarized in the
determine the annual revenue following formula:

Annual Revenue Requirement for Reserves


÷ Load Requiring Reserves
÷ 12 months

Monthly Reserve Service Rate

Existing and Provisional Rates values are outlined in the following Requirement based upon the most
table. These rates are calculated recent historical data available at the
The revenue requirements for the comparing the Existing Revenue time of the initial rate proposal.
individual services and comparison Requirement to the Revenue

TABLE 1
Provisional
Existing revenue Percentage
Service revenue
requirement change
requirement

Transmission ............................................................................................................................ $128,017,923 $126,741,576 ¥0.997


Scheduling, System Control and Dispatch .............................................................................. 3,373,281 3,406,102 ¥0.973
Reactive Supply and Voltage Control from Generation Sources ............................................ 2,736,253 3,065,568 12.035
Regulation and Frequency Control .......................................................................................... 1,065,771 1,075,623 0.924
Reserves .................................................................................................................................. 1,895,268 2,009,276 6.015

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00013 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
55828 Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices

Certification of Rates the reserved capacity for all IS Long- share will be based on the network
Western’s Administrator certifies that Term Firm Point-to-Point Transmission customer’s hourly load (including its
the IS Transmission and Ancillary Service. For the provisional rate, the IS designated network load not physically
Service rates placed into effect on an Transmission System Total Load will be interconnected with Western),
interim basis are the lowest possible unchanged at 3,968,000 kW. coincident with the IS monthly
rates consistent with sound business transmission system peak, which will be
Annual Costs
principles. The provisional formula calculated on a rolling 12-cp basis.
Western will continue to use a Western’s transmission system peak
rates were developed following
Commission-recognized methodology includes the sum of capacity reserved
administrative policies and applicable
laws. for annual cost calculation with fixed for IS Point-to-Point Transmission
charge rates for various cost components Service, 12-cp monthly entitlements for
IS Transmission Service Discussion approved by the Commission in WAPA– firm power customers, and the average
Western proposes continuing the 79 and WAPA–100. The change in the 12-cp monthly system peak for IS
annual fixed charge formula to provisional rate is that the costs Network Transmission Service. The
determine the Annual Revenue associated with the GSUs are no longer provisional rate formula is to be
Requirement for IS Transmission included in the net plant investment for effective beginning October 1, 2005,
Service. The annual revenue transmission or the various expenses. through September 30, 2010.
requirement for IS Transmission Service The investment and costs for GSUs are
now in the generation fixed charge Firm Point-to-Point
includes O&M expense, A&GE, interest
expense, and depreciation expense from calculation in support of ancillary The current IS Firm Point-to-Point
the most recent historical test year. This services. The proposed methodology Transmission Service rate for 2004–
annual revenue requirement for IS will continue to be an annual fixed 2005 is $2.72 and expires September 30,
Transmission Service is offset by charge formula that will determine the 2005. The provisional formula rate will
appropriate revenue credits. annual revenue requirement to be continue to be the Annual Revenue
The IS Transmission System includes recovered from transmission services. Requirement for IS Transmission
the transmission facilities owned by Annual Revenue Requirement for IS Service divided by the IS Transmission
Western, Basin Electric, Heartland and Transmission System Total Load. The provisional rate
others in which the IS has contractual for IS Firm Point-to-Point Transmission
rights. The costs paid to others for A change in the costs that comprise
Service is $2.69 per kWmonth for 2004–
contractual rights on their transmission the annual revenue requirement for IS
2005.
lines are included in the costs recovered Transmission is being proposed. The
by the annual revenue requirement for proposed transmission rate Non-Firm Point-to-Point
IS Transmission Service. methodology is different from the
current transmission rate methodology The current IS Non-Firm
Western will continue to offer
in one area. The GSU investments are Transmission Service rate expires
Network, Firm Point-to-Point, and Non-
removed from the transmission September 30, 2005. The provisional
Firm Point-to-Point Transmission
investments and placed in the rate for IS Non-Firm Transmission
Service on the IS Transmission System.
generation investments. This also moves Service is expressed in mills/kWh and
The service offered is the transmission
the corresponding costs of GSUs from is based on the current IS Firm Point-
of energy and capacity from Points of
transmission costs to generation costs. to-Point Transmission Service rate and
Receipt to Points of Delivery on the IS.
The existing annual revenue may be discounted. The provisional IS
The IS Transmission Service rates
requirement for IS Transmission Service Non-Firm Point-to-Point Transmission
include the cost of Scheduling, System
is $128,017,923. The provisional Service rate will be the IS Firm Point-
Control, and Dispatch Service.
Annual Revenue Requirement for IS to-Point Transmission Service rate
Therefore an additional charge for this
Transmission Service is $126,741,576. divided by 730 hours per month and
ancillary service is not required for
multiplied by 1000 mills per dollar. The
transmission users. Network
The provisional IS Transmission provisional IS Non-Firm Transmission
Service rates will be applied to The current IS Network Transmission Service rate for 2004–2005 is 3.68 mills/
customers who purchase transmission Service schedule expires on September kWh.
services. Western, Basin Electric, and 30, 2005. The provisional annual The following table summarizes the
Heartland will take IS Transmission revenue requirement for IS difference in calculations between the
Service. The IS Transmission Service to Transmission Service will be used in current IS Transmission Service rates
the UGPR’s Customers will continue to the provisional rate formula for IS and the provisional IS Transmission
be bundled in the firm electric service Network Transmission Service. The Service rates. It compares the change in
rate under existing contracts that expire provisional charge for the monthly the average annual projections used in
in 2020. demand for IS Network Transmission the 2004–2005 transmission and
Service will be the product of the ancillary services study and the
IS Transmission System Total Load network customer’s load ratio share provisional IS Transmission Service
The IS Transmission System Total times one-twelfth (1/12) of the annual rates for this rate adjustment based upon
Load is the 12-cp system peak for revenue requirement for IS the most recent historical data available
Network IS Transmission Service plus Transmission Service. The load ratio at the time of the initial rate proposal.

COMPARISON OF ANNUAL REVENUES


Percent
Item Existing rate Provisional rate change

Annual IS Costs ....................................................................................................................... $137,088,496 $136,289,145 ¥0.577


Transmission Customer Facility Credits .................................................................................. 2,482,447 2,482,647 0.000

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00014 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices 55829

COMPARISON OF ANNUAL REVENUES—Continued


Percent
Item Existing rate Provisional rate change

Transmission Revenue Credits ............................................................................................... 9,454,494 9,454,494 0.000


Annual Revenue Requirement for IS Transmission Service ................................................... 128,017,923 126,741,576 ¥0.997

The change in annual revenue remain in effect through September 30, and (2) reactive supply and voltage
requirement for IS Transmission Service 2010, or until replaced. control service. All these ancillary
is primarily a result of a revision in the The proposed rates for IS services are listed in Western’s Tariff.
allocation of expenses and investments. Transmission Service include a The provisional rates for ancillary
The revenue change between the provision to pass through electric services are designed to recover only the
existing rate and the provisional rate is industry restructuring costs associated costs associated with providing the
<1 percent and, therefore, this is a with providing transmission service. service(s). The formula for calculating
minor rate adjustment. These costs will be passed through to the rates will remain the same but the
each appropriate IS Transmission GSUs will be included in the
Basis for Rate Development Customer. investment and costs for the generation
fixed charge in support of ancillary
The existing rates for IS Network, Comments services. The costs for providing
Firm and Non-Firm Transmission Scheduling, System Control, and
Western did not receive any
Service in Rate Schedules UGP–NT1, Dispatch Service are included in the
comments or responses regarding the IS
UGP–FPT1, and UGP–NFPT1, expire Transmission Service rate adjustment. provisional IS Transmission Service
September 30, 2005. This rate rates.
adjustment contains rates that replace Ancillary Services Discussion
The following table summarizes the
existing rates. The adjusted rates reflect The IS will continue to offer six difference in calculations between the
changes in costs. The provisional rates ancillary services. These are (1) current IS Ancillary Service rates and
will provide sufficient revenue to pay Scheduling, system control, and the provisional IS Ancillary Service
all annual costs, including interest dispatch service, (2) reactive supply and rates. It compares the change in the
expense, and repay investment within voltage control service, (3) regulation average annual projections used in the
the allowable period. The provisional IS and frequency response service, (4) 2004–2005 transmission and ancillary
Transmission Service rates, detailed in energy imbalance service, (5) spinning services study and the provisional IS
Rate Schedules UGP–NT1, UGP–FPT1, reserve service, and (6) supplemental Transmission and Ancillary Service
and UGP–NFPT1, will take effect on reserve service. The first two are rates for this rate adjustment based upon
October 1, 2005 to correspond with the required services: (1) Scheduling, the most recent historical data available
start of the Federal fiscal year and system control, and dispatch service at the time of the initial rate proposal.

COMPARISON OF ANCILLARY SERVICE RATES


Provisional Percent
Item Unit Existing rate rate change

Scheduling, System Control and Dispatch Service ................................. schedule/day ......... $49.29 $49.77 0.974
Reactive Supply and Voltage Control ...................................................... kWmonth ............... 0.06 0.07 16.667
Regulation and Frequency Response ...................................................... kWmonth ............... 0.04 0.04 0.000
Energy Imbalance .................................................................................... n/a ......................... n/a n/a n/a
Reserves .................................................................................................. kWmonth ............... 0.11 0.12 9.091

Basis for Rate Development Comments Regulatory Procedure Requirements


The existing rates for IS Ancillary Western did not receive any Regulatory Flexibility Analysis
Services in Rate Schedules UGP–AS1, comments or responses regarding the IS
UGP–AS2, UGP–AS3, UGP–AS4, UGP– The Regulatory Flexibility Act of 1980
Ancillary Services rate adjustment. (5 U.S.C. 601, et seq.) requires Federal
AS5, and UGP–AS6, expire September
30, 2005. The rate adjustment contains Availability of Information agencies to perform a regulatory
rates that replace existing rates. The flexibility analysis if a final rule is likely
adjusted rates reflect a revised Information about this rate to have a significant economic impact
methodology and changes in costs. The adjustment, including studies, on a substantial number of small entities
provisional rates will provide sufficient brochures, comments, letters, and there is a legal requirement to issue
revenue to pay all annual costs, memorandums, and other supporting a general notice of proposed
including interest expense, and material made or kept by Western, used rulemaking. Western has determined
repayment of required power to develop the provisional rates, is that this action does not require a
investment within the allowable period. available for public review in the Upper regulatory flexibility analysis since it is
The provisional rates will take effect on Great Plains Regional Office, 2900 4th a rulemaking of particular applicability
October 1, 2005, to correspond with the Avenue North, Billings, Montana. involving rates or services applicable to
start of the Federal fiscal year and public property.
remain in effect through September 30,
2010.

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00015 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
55830 Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices

Environmental Compliance Order Great Plains Balancing Authority


In compliance with the National In view of the foregoing and under the (WAUGP). The charges for Scheduling,
Environmental Policy Act (NEPA) of authority delegated to me, I confirm and System Control, and Dispatch Service
1969 (42 U.S.C. 4321, et seq.); Council approve on an interim basis, effective are to be based on the rate outlined
on Environmental Quality Regulations October 1, 2005, formula rates for the IS below. The formula rate used to
(40 CFR parts 1500–1508); and DOE Transmission and Ancillary Services calculate the charges for service under
NEPA Regulations (10 CFR part 1021), under Rate Schedules UGP–FPT1, UGP– this schedule was developed and may
Western has determined that this action NFPT1, UGP–NT1, UGP–AS1, UGP– be modified under applicable Federal
is categorically excluded from preparing AS2, UGP–AS3, UGP–AS4, UGP–AS5, laws, regulations, and policies.
an environmental assessment or an and UGP–AS6. The rate schedules shall The rate will be applied to all
environmental impact statement. remain in effect on an interim basis, schedules for WAUGP non-
Determination Under Executive Order pending the Commission’s confirmation Transmission Customers. The WAUGP
12866 and approval of them or substitute rates will accept any reasonable number of
on a final basis through September 30, schedule changes over the course of the
Western has an exemption from 2010.
centralized regulatory review under day without any additional charge.
Executive Order 12866; accordingly, no Dated: September 13, 2005.
The charges for Scheduling, System
clearance of this notice by the Office of Clay Sell,
Control, and Dispatch Service may be
Management and Budget is required. Deputy Secretary. modified upon written notice to the
Small Business Regulatory Enforcement Rate Schedule UGP–AS1; October 1, 2005; customer. Any change to the charges for
Fairness Act Supersedes 1998 Schedule the Scheduling, System Control, and
Western has determined that this rule Upper Great Plains Region Integrated Dispatch Service shall be as set forth in
is exempt from congressional System: Scheduling, System Control, a revision to this rate schedule
notification requirements under 5 U.S.C. and Dispatch Service developed under applicable Federal
801 because the action is a rulemaking laws, regulations, and policies and
Effective made part of the applicable
of particular applicability relating to
rates or services and involves matters of The first day of the first full billing Transmission Customer’s Service
procedure. period beginning on or after October 1, Agreement.
2005, through September 30, 2010, or The Upper Great Plains Region
Submission to the Federal Energy until superseded by another rate
Regulatory Commission (UGPR) shall charge the non-
schedule. Transmission Customer under the rate
The interim rates herein confirmed,
Applicable then in effect.
approved, and placed into effect,
together with supporting documents, This service is required to schedule Formula Rate
will be submitted to the Commission for the movement of power through, out of,
confirmation and final approval. within, or into the Western Area Upper

Rate per Annual Revenue Requirement for Scheduling, System Control, and Dispatch Service
Schedule per Day = Number of Daily Schedules per Year

Rate Applicable Transmission Provider. The charges for


To maintain transmission voltages on such service will be based upon the rate
A recalculated rate will go into effect outlined below. The formula rate used
every May 1 based on the above formula all transmission facilities within
acceptable limits, generation facilities to calculate the charges for service
and data. The UGPR will notify the under this schedule was developed and
under the control of the Western Area
customer annually of the recalculated Upper Great Plains balancing authority may be modified under applicable
rate on or before April 1. (WAUGP) are operated to produce or Federal laws, regulations, and policies.
Rate Schedule UGP–AS2; October 1, 2005; absorb reactive power. Thus, Reactive The charges for Reactive Service may
Supersedes 1998 Schedule Supply and Voltage Control from be modified upon written notice to the
Generation Sources Service (Reactive Transmission Customer. Any change to
Upper Great Plains Region Integrated Service) must be provided for each the charges for Reactive Service shall be
System: Reactive Supply and Voltage transaction on the transmission as set forth in a revision to this rate
Control From Generation Sources facilities. The amount of Reactive schedule developed under applicable
Service Service that must be supplied with Federal laws, regulations, and policies
respect to the Transmission Customer’s and made part of the applicable
Effective
transaction will be determined based on Transmission Customer’s Service
The first day of the first full billing the Reactive Service necessary to Agreement. The Upper Great Plains
period beginning on or after October 1, maintain transmission voltages within Region (UGPR) shall charge the
2005, through September 30, 2010, or limits that are generally accepted in the Transmission Customer under the rate
until superseded by another rate region and consistently adhered to by then in effect.
schedule. WAUGP. Those Transmission Customers with
The Transmission Customer must generators in the balancing authority
purchase this service from the providing WAUGP with adequate
EN23SE05.060</MATH>

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices 55831

Reactive Service will not be charged for Reactive Service must be documented in Formula Rate
this service. Any waiver of this charge the Transmission Customer’s Service
or any crediting arrangements for Agreement.
Formula Rate

WAUGP Annual Revenue Requirement for Reactive Service


Reactive Service =
Rate Load Requiring Reactive Service

Rate resources, generation, and interchange was developed and may be modified
with load and for maintaining under applicable Federal laws,
A recalculated rate will go into effect
scheduled interconnection frequency at regulations, and policies.
every May 1 based on the above formula
60 cycles per second (60 Hz). Regulation Charges for Regulation may be
and updated financial and load data.
is accomplished by committing on-line modified upon written notice to the
The UGPR will notify the Transmission
generation whose output is raised or Transmission Customer. Any change to
Customer annually of the recalculated
lowered, predominantly through the use the Regulation charges shall be as set
rate on or before April 1.
of automatic generating control forth in a revision to this rate schedule
Rate Schedule UGP–AS3; October 1, 2005; equipment, as necessary to follow the developed under applicable Federal
Supersedes 1998 Schedule moment-by-moment changes in load. laws, regulations, and policies and
Upper Great Plains Region Integrated The obligation to maintain this balance made part of the applicable
System: Regulation and Frequency between resources and load lies with Transmission Customer’s Service
Response Service the Western Area Upper Great Plains Agreement. The Upper Great Plains
balancing authority (WAUGP) operator. Region (UGPR) shall charge the
Effective The Transmission Customer must either Transmission Customer under the rate
purchase this service from WAUGP or then in effect.
The first day of the first full billing
make alternative comparable Transmission Customers will not be
period beginning on or after October 1,
arrangements to satisfy its Regulation charged for this service if they receive
2005, through September 30, 2010, or
obligation. The charges for Regulation Regulation from another source, or self-
until superseded by another rate
are outlined below. The amount of supply it for their own load. Any waiver
schedule.
Regulation will be set forth in the of this charge or any crediting
Applicable applicable Transmission Customer’s arrangement for Regulation must be
Service Agreement. documented in the Transmission
Regulation and Frequency Response
Customer’s Service Agreement.
Service (Regulation) is necessary to The formula rate used to calculate the
provide for the continuous balancing of charges for service under this schedule Formula Rate

WAUGP Annual Revenue Requirement for Regulation


Regulation =
Rate Load in the Balancing Authority Requiring Regulation

Rate Applicable under applicable Federal laws,


A recalculated rate will go into effect Energy Imbalance Service is provided regulations, and policies.
every May 1 based on the above formula when a difference occurs between The Energy Imbalance Service
and updated financial and load data. scheduled and actual delivery of energy compensation may be modified upon
The UGPR will notify the Transmission to a load located within the Western written notice to the Transmission
Customer annually of the recalculated Area Upper Great Plains Balancing Customer. Any change to the
rate on or before April 1. Authority (WAUGP) over a single hour. Transmission Customer compensation
If resources are not available from a The Transmission Customer must either for Energy Imbalance Service shall be as
WAUGP resource, the UGPR will offer obtain this service from WAUGP or set forth in a revision to this schedule
to purchase the Regulation and pass make alternative comparable developed under applicable Federal
through the costs, plus an amount for arrangements to satisfy its Energy laws, regulations, and policies and
administration, to the Transmission Imbalance Service obligation. made part of the applicable
Customer. The WAUGP shall establish a
Rate Schedule UGP–AS4; October 1, 2005; Transmission Customer’s Service
deviation band of +/¥1.5 percent (with Agreement. The Upper Great Plains
Supersedes 1998 Schedule a minimum of 2 MW) of the scheduled Region (UGPR) shall charge the
Upper Great Plains Region Integrated transaction to be applied hourly to any
Transmission Customer under the rate
System: Energy Imbalance Service energy imbalance that occurs as a result
then in effect.
of the Transmission Customer’s
Effective
EN23SE05.062</MATH>

scheduled transaction(s). Deviation Formula Rate


The first day of the first full billing accounting will be completed monthly
period beginning on or after October 1, on an hour-to-hour basis. The UGPR reserves the right to
2005, through September 30, 2010, or The formula rate used to calculate the implement the following upon
until superseded by another rate charges for service under this schedule providing notice to the Transmission
EN23SE05.061</MATH>

schedule. was developed and may be modified Customer.

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
55832 Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices

For negative excursions (under 2005, through September 30, 2010, or was promulgated and may be modified
deliveries) outside the bandwidth, the until superseded by another rate under applicable Federal laws,
WAUGP will assess a penalty charge of schedule. regulations, and policies.
100 mills/kWh. The charges for Reserves may be
For positive excursions (over Applicable
deliveries) outside the bandwidth, over modified upon written notice to the
Spinning Reserve Service (Reserves)
deliveries of energy will be forfeited to Transmission Customer. Any change to
is needed to serve load immediately in
the balancing authority. the charges for Reserves shall be as set
the event of a system contingency.
Reserves may be provided by generating forth in a revision to this rate schedule
Rate developed pursuant to applicable
units that are on-line and loaded at less
The bandwidth in effect October 1, than maximum output. The Federal laws, regulations, and policies
2005, through September 30, 2006, is 3 Transmission Customer must either and made part of the applicable
percent (+/¥1.5 percent hourly purchase this service from the Western Transmission Customer’s Service
deviation). Area Upper Great Plains balancing Agreement. The Upper Great Plains
Rate Schedule UGP–AS5; October 1, 2005; authority (WAUGP) or make alternative Region (UGPR) shall charge the
Supersedes 1998 Schedule comparable arrangements to satisfy its Transmission Customer under the rate
Upper Great Plains Region Integrated Reserves obligation. The charges for then in effect.
System: Operating Reserve—Spinning Reserves are outlined below. The
Formula Rate
Reserve Service amount of Reserves will be set forth in
the applicable Transmission Customer’s
Effective Service Agreement.
The first day of the first full billing The formula rate used to calculate the
period beginning on or after October 1, charges for service under this schedule

WAUGP Annual Revenue Requirement for Regulation


Regulation =
Rate Load in the Balancing Authority Requiring Regulation

Rate Rate Schedule UGP–AS6; October 1, 2005; (WAUGP) or make alternative


Supersedes 1998 Schedule comparable arrangements to satisfy its
A recalculated rate will go into effect Reserves obligation. The charges for
Upper Great Plains Region Integrated
every May 1 based on the above formula Reserves are outlined below. The
System: Operating Reserve—
and updated financial and load data. amount of Reserves will be set forth in
Supplemental Reserve Service
The UGPR will notify the Transmission the applicable Transmission Customer’s
Customer annually of the recalculated Effective Service Agreement.
rate on or before April 1. The first day of the first full billing The formula rate used to calculate the
If resources are not available from a period beginning on or after October 1, charges for service under this schedule
WAUGP resource, the UGPR will offer 2005, through September 30, 2010, or was developed and may be modified
to purchase the Reserves and pass until superseded by another rate under applicable Federal laws,
through the costs, plus an amount for schedule. regulations, and policies.
administration, to the Transmission Applicable The charges for Reserves may be
Customer. modified upon written notice to the
Supplemental Reserve Service Transmission Customer. Any change to
In the event that Reserves are called (Reserves) is needed to serve load in the
upon for emergency use, the UGPR will the charges for Reserves shall be as set
event of a system contingency, however, forth in a revision to this rate schedule
assess a charge for energy used at the it is not available immediately to serve
Mid-Continent Area Power Pool Rate for developed under applicable Federal
load but rather within a short period of laws, regulations, and policies and
emergency energy, presently the greater time. Reserves may be provided by
of 30 mills/kWh or the prevailing made part of the applicable Service
generating units that are on-line but
Agreement. The Upper Great Plains
market energy rate in the region. The unloaded, by quick-start generation or
Region (UGPR) shall charge the
Transmission Customer would be by interruptible load. The Transmission
Transmission Customer under the rate
responsible for providing transmission Customer must either purchase this
then in effect.
service to get the Reserves to its service from the Western Area Upper
destination. Great Plains Balancing Authority Formula Rate

WAUGP Annual Revenue Requirement for Reserves


Reserves =
Rate Load Requiring Reserves
EN23SE05.064</MATH>

Rate Customer annually of the recalculated through the costs, plus an amount for
rate on or before April 1. administration, to the Transmission
A recalculated rate will go into effect Customer.
every May 1 based on the above formula If resources are not available from a
and updated financial and load data. WAUGP resource, the UGPR will offer In the event Reserves are called upon
to purchase the Reserves and pass for Emergency Energy, the UGPR will
EN23SE05.063</MATH>

The UGPR will notify the Transmission

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1
Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices 55833

assess a charge for energy used at the Region (UGPR) each month for Reserved follows: (1) Any offer of a discount
Mid-Continent Area Power Pool Rate for Capacity under the applicable Firm made by the UGPR must be announced
Emergency Energy, presently the greater Point-to-Point Transmission Service to all eligible Transmission Customers
of 30 mills/kWh or the prevailing Agreement and rates outlined below. solely by posting on the Open Access
market energy rate in the region. The The formula rates used to calculate the Same-Time Information System
Transmission Customer would be charges for service under this schedule (OASIS), (2) any Transmission
responsible for providing transmission were developed and may be modified Customer-initiated requests for
service to get the Reserves to its under applicable Federal laws, discounts, including requests for use by
destination. regulations, and policies. one’s wholesale merchant or an
The UGPR may modify the rate for
Rate Schedule UGP–FPT1; October 1, 2005; affiliate’s use, must occur solely by
Supersedes 1998 Schedule Firm Point-to-Point Transmission
Service upon written notice to the posting on the OASIS, and (3) once a
Upper Great Plains Region Integrated Transmission Customer. Any change to discount is negotiated, details must be
System: Long-Term Firm and Short- the rate for Firm Point-to-Point immediately posted on the OASIS. For
Term Firm Point-to-Point Transmission Transmission Service shall be as set any discount agreed upon for service on
Service forth in a revision to this rate schedule a path, from Point(s) of Receipt to
developed under applicable Federal Point(s) of Delivery, the UGPR must
Effective offer the same discounted transmission
laws, regulations, and policies and
The first day of the first full billing made part of the applicable service rate for the same time period to
period beginning on or after October 1, Transmission Customer’s Service all eligible Transmission Customers on
2005, through September 30, 2010, or Agreement. The UGPR shall charge the all unconstrained transmission paths
until superseded by another rate Transmission Customer under the rate that go to the same point(s) of delivery
schedule. then in effect. on the Transmission System.
Applicable Discounts Formula Rate
The Transmission Customer shall Three principal requirements apply to
compensate the Upper Great Plains discounts for transmission service as

Firm Point-to-Point = Annual IS Transmissiion Service Revenue Requirement


Transmission Rate IS Transmission System Totaal Load

Rate Point Transmission Service under the follows: (1) Any offer of a discount
applicable Non-Firm Point-to-Point made by the UGPR must be announced
A recalculated rate will go into effect Transmission Service Agreement and to all eligible Transmission Customers
every May 1 based on the above formula rate outlined below. The formula rates
and updated financial and load data. solely by posting on the Open Access
used to calculate the charges for service Same-Time Information System
The UGPR will notify the Transmission under this schedule were developed and
Customer annually of the recalculated (OASIS), (2) any Transmission
may be modified under applicable Customer-initiated requests for
rate on or before April 1. Federal laws, regulations, and policies. discounts, including requests for use by
Rate Schedule UGP–NFPT1; October 1, The UGPR may modify the rate for
2005; Supersedes 1998 Schedule
one’s wholesale merchant or an
Non-Firm Point-to-Point Transmission
affiliate’s use, must occur solely by
Service upon written notice to the
Upper Great Plains Region Integrated Transmission Customer. Any change to posting on the OASIS, and (3) once a
System: Non-Firm Point-to-Point the rate for Non-Firm Point-to-Point discount is negotiated, details must be
Transmission Service Transmission Service shall be as set immediately posted on the OASIS. For
Effective forth in a revision to this rate schedule any discount agreed upon for service on
developed under applicable Federal a path, from Point(s) of Receipt to
The first day of the first full billing laws, regulations, and policies and Point(s) of Delivery, the UGPR must
period beginning on or after October 1, made part of the applicable offer the same discounted transmission
2005, through September 30, 2010, or Transmission Customer’s Service service rate for the same time period to
until superseded by another rate Agreement. The UGPR shall charge the all eligible Transmission Customers on
schedule. Transmission Customer under the rate all unconstrained transmission paths
Applicable then in effect. that go to the same point(s) of delivery
Discounts on the Transmission System.
The Transmission Customer shall
compensate the Upper Great Plains Three principal requirements apply to Formula Rate
Region (UGPR) for Non-Firm Point-to- discounts for transmission service as

Maximum Non-Firm
Point-to-Point = Firm Point-to-Point 730 hours 1000 mills
Transmission Rate ÷ per month × per dollar
EN23SE05.066</MATH>

Transmission Rate
EN23SE05.065</MATH>

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00019 Fmt 4703 Sfmt 4725 E:\FR\FM\23SEN1.SGM 23SEN1
55834 Federal Register / Vol. 70, No. 184 / Friday, September 23, 2005 / Notices

Rate 2005, through September 30, 2010, or The UGPR may modify the charges for
A recalculated rate will go into effect until superseded by another rate Network Integration Transmission
every May 1 based on the above formula schedule. Service upon written notice to the
and updated financial and load data. Applicable Transmission Customer. Any change to
The UGPR will notify the Transmission the charges to the Transmission
The Transmission Customer shall Customer for Network Integration
Customer annually of the recalculated
compensate the Upper Great Plains Transmission Service shall be as set
rate on or before April 1.
Region (UGPR) each month for Network forth in a revision to this rate schedule
Rate Schedule UGP–NT1; October 1, 2005; Transmission Service under the
Supersedes 1998 Schedule promulgated developed under
applicable Network Integration applicable Federal laws, regulations,
Upper Great Plains Region Integrated Transmission Service Agreement and and policies and made part of the
System: Annual Transmission Revenue annual revenue requirement outlined applicable Transmission Customer’s
Requirement for Network Integration below. The formula for the annual Service Agreement. The UGPR shall
Transmission Service revenue requirement used to calculate charge the Transmission Customer
the charges for this service under this under the revenue requirement then in
Effective schedule was developed and may be effect.
The first day of the first full billing modified under applicable Federal laws,
period beginning on or after October 1, regulations, and policies. Formula Rate

(Transmission Customer’s Load-Ratio Share × Annual Revenue Requirment for IS Transmission Service)
Monthly Charge =
12 months

Annual Revenue Requirement how the plan will be integrated with the Allotment Management Project,
A recalculated annual revenue Upper Mississippi River Navigation Proposing to Authorize Cattle Grazing
requirement will go into effect every Ecosystem Sustainability Program. on Four Allotment, Six Rivers
May 1 based on updated financial data. Rating LO. National Forest, Mad River Ranger
The UGPR will notify the Transmission EIS No. 20050209, ERP No. D–NPS– District, North Fork Eel River and
Customer annually of the recalculated J65442–WY, Grand Teton National Upper Mad River, Trinity County, CA.
annual revenue requirement on or Park Transportation Plan, Summary: EPA has no objection to the
before April 1. Implementation, Grand Teton proposed action. Rating LO.
[FR Doc. 05–19039 Filed 9–22–05; 8:45 am] National Park, Teton County, WY. EIS No. 20050306, ERP No. D–FHW–
Summart: EPA expressed concerns H40185–00, U.S. Highway 34,
BILLING CODE 6450–01–P
about wetland mitigation and storm Plattsmouth Bridge Study, over the
water impacts. Rating EC2. Missouri River between U.S. 75 and I–
EIS No. 20050259, ERP No. D–FHW– 29, Funding, Coast Guard Permit, U.S.
ENVIRONMENTAL PROTECTION Army COE 10 and 404 Permits, Cass
AGENCY C40166–NY, Southtowns Connector/
Buffalo Outer Harbor Project, County, NE and Mills County, IA.
[ER–FRL–6667–7] Improvements on the NYS Route 5 Summary: EPA expressed concerns
Corridor from Buffalo Skyway Bridge about potential wetland, floodplain,
Environmental Impact Statements and to NYS Route 179, in the City of stream, and cumulative impacts. Rating
Regulations; Availability of EPA Buffalo, City of Lackawanna and EC2.
Comments Town of Hamburg, Erie County, NY. EIS No. 20050311, ERP No. D–NPS–
Availability of EPA comments Summary: EPA expressed concerns H65025–NE, Niobrara National Scenic
prepared pursuant to the Environmental about assessment of cumulative River General Management Plan,
Review Process (ERP), under section impacts. Rating EC2. Implementation, Brown, Cherry, Keya
309 of the Clean Air Act and Section EIS No. 20050274, ERP No. D–AFS– Paha and Rock Counties, NE.
102(2)(c) of the National Environmental J61107–ND, NE McKenzie Allotment Summary: EPA has no objection to the
Policy Act as amended. Requests for Management Plan Revisions, Proposes proposed action. Rating LO.
copies of EPA comments can be directed to Continue Livestock Grazing on 28 EIS No. 20050294, ERP No. DR–COE–
to the Office of Federal Activities at Allotments, Dakota Prairie Grasslands K11114–CA, Mare Island Reuse of
202–564–7167. An explanation of the Land and Resource Management Plan, Dredged Material Disposal Ponds as a
ratings assigned to draft environmental Dakota Prairie Grasslands, McKenzie Confirmed Updated Dredged Material
impact statements (EISs) was published Ranger District, McKenzie County, Disposal Facility, Issuing Section 404
in the Federal Register dated April 1, ND. Permit Clean Water Act and Section
2005 (70 FR 16815). Summary: EPA expressed concerns 10 Permit Rivers and Harbor Act, San
about potential water quality impacts Francisco Bay Area, City of Vallejo,
Draft EISs from sediment, fecal coliform and Solando County, CA.
EIS No. 20050187, ERP No. D–SFW– temperature modification in streams Summary: Many of EPA’s objections
F64005–00, Upper Mississippi and other surface waters, and to the original Draft EIS were addressed
National Wildlife and Fish Refuge recommended reducing water quality in this revised document. However, EPA
Comprehensive Conservation Plan impacts near aquatic/riparian resources continues to have concerns about the
(CCP) Implementation, MN, WI, IL by working with permittees and other delegation of responsibility for site
and IA. stakeholders, and develop adaptive operations and associated
Summary: EPA has no objections to management monitoring. Rating EC2. environmental safeguards, as well as
the Preferred Alternative, and EIS No. 20050281, ERP No. D–AFS– implementation of wetlands restoration
EN23SE05.067</MATH>

recommends that the Final EIS address K65287–CA, North Fork Eel Grazing measures. Rating EC2.FINAL EISs.

VerDate Aug<31>2005 15:21 Sep 22, 2005 Jkt 205001 PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 E:\FR\FM\23SEN1.SGM 23SEN1

Das könnte Ihnen auch gefallen