Beruflich Dokumente
Kultur Dokumente
Before . . .
... after.
Construction
Construction began in October of 1975.
This is the point that is most important in
terms of the combined roles. The architect
must now proceed to get the job done with
his plans and the contractor in the best
possible way. The developer, on the other
hand, must see that the total project moves
forward not only economically but also in a
timely manner, and he must ensure that the
final product is rentable in support of the
costs required to achieve the finished space.
The interchange between the two roles is
crucial. To the degree the architect can
apply his imagination to solutions within
developer constraints, the project as conceived is supported. On the other hand, to
the degree the developer can be responsive
to changing opportunities that allow upgrading of the finished project, rentability
should be maximized and the project's
success enhanced.
For example, the major hole connecting
the lower level to the main level of AMTRAK space required maximum visibility
with a minimum expenditure. After much
thought of glass and wood railings, a final
solution was achieved by the architect using
simple wall construction which repeated
the motif of the existing wainscotting,
which strengthened the integration of the
two spaces without additional cost. In
another case, when a potential tenant suddenly appeared in early April of 1976 with
the requirement to move in on the first of
May, decisions were required by the developer within one week's time which enlarged the scope of the project, evaluated
the increased rental required, and confirmed the time factors to assure a cost
effective decision that encompassed all of
the major aspects of this complicated decision. These two instances illustrate an
acceptance of responsibility by both the
architect and the developer for their own
areas of expertise and an understanding
of the interaction between these two areas.
This is the basis for the shared responsiveness so crucial to final success.
On July 29, 1976, AMTRAK formally
opened its new space. Construction was
completed in October 1976, and final tenanting should be achieved by the first of
the year. The New London Day, the local
newspaper, took a full page in a supplement
published for the opening to say "We were
wrong! But we changed our mind" and
referred to their editorial of May, 1971,
advocating the demolition of the station
and their editorial of June, 1975, supporting
our plans for renovation-a key support in
our struggle for designation. They conclude
by saying, "The Day congratulates Ander10n Notter and the Union Railroad Station
Trust for their foresight in saving this
venerable building which becomes more
attractive with each passing day. It joins all
of those who use Union Station in saying
thanks for giving us a railroad station we
can be proud of."
Developer Designation
That period, from April 3, 1974, when our
proposal was first submitted, to October 3,
1975, when final agreements were signed,
was hell. Even by developer standards, this
time period seems excessive. Every aspect
of the development process was challenged:
economics, tenants, preservation, financing.
But the process itself was classic; it was
truly a period of persuasion.
Before . . .
... after.