GENERAL REQUIREMENTS
Generally
General requirements shall include :
Item
- mobilisation and demobilisation
- field engineering (survey)
- site management
- temporary utilities (electrical and lighting)
- temporary controls (dewatering and sand bags)
- coordinations and approvals from local concerned authority
- shop drawings and as-built drawing
- reporting and documentation
- construction tools and equipments
- site cleaning
- any coordination required with concerned institution during implementation of contract (from Purchase
Order issued to closing Purchase Order)

For project located at busway track, toll way, highway, railway, Harbour area.

Total project cost :


Less than 50.000.000

15

50.000.000 - 100.000.000

13

100.000.000 - 200.000.000

11

200.000.000 - 400.000.000

10

More than 400.000.000

For project located in Divisi Utara

Total project cost :


Less than 50.000.000

14

50.000.000 - 100.000.000

11

100.000.000 - 200.000.000

10

200.000.000 - 400.000.000

More than 400.000.000

For project located in Divisi Tengah or Divisi Selatan

Total project cost :


Less than 50.000.000

11

50.000.000 - 100.000.000

100.000.000 - 200.000.000

200.000.000 - 400.000.000

More than 400.000.000

1 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

For all projects (percentage to total project cost)

traffic management (road sign, barrier, banner)

Unit

Rate - 2014

Less than 50.000.000


50.000.000 - 100.000.000
100.000.000 - 200.000.000
200.000.000 - 400.000.000
More than 400.000.000
2

temporary site office and stockyard

Less than 50.000.000


50.000.000 - 100.000.000
100.000.000 - 200.000.000
200.000.000 - 400.000.000
More than 400.000.000
3

health and safety equipments

Less than 50.000.000


50.000.000 - 100.000.000
100.000.000 - 200.000.000
200.000.000 - 400.000.000
More than 400.000.000

2 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

Unit

Rate - 2014

REMEASUREMENT
The Contractor shall note that all items and quantities stated below will
subject to remeasure based on site implementation and condition
II

SITE WORKS
Test Pits / Trial Holes as specified
Price shall include :
- Mobilisation and Demobilisation
- Road sign, Barriers, Banners, and all necessary Safety Provision
- Standard Tools and Safety Equipments
- Heavy equipment such as excavator, steel padding, crane,
asphalt/concrete breaker, sheet pile, etc shall be included in unit rate
- Site Cleaning
- All necessary Coordinations with related Institutions

Excavation as specified (maximum depth 2.00 meter)

excavation in asphalt pavement (1.0mx0.6mx1.3m, 1 pit)

m3

120,700

excavation in concrete rigid pavement (1.0mx0.6mx1.3m, 1 pit)

m3

140,300

excavation in concrete floor (1.0mx0.6mx1.3m, 1 pit)

m3

111,300

excavation in interblock (1.0mx0.6mx1.3m, 1 pit)

m3

61,900

excavation in berm (1.0mx0.6mx1.3m, 1 pit)

m3

60,300

Demolition of existing concrete rigid pavement

1 layer pavement, thickness 30cm

m3

220,000

2 layers pavement, thickness 60cm

m3

220,000

Removing as specified

removing and reinstalling concrete paving block

m2

31,500

transport and disposal of demolished material / soil

m3

31,500

Bedding and backfilling as specified

to pits in asphalt pavement

m3

223,600

to pits in concrete rigid pavement

m3

167,500

to pits in concrete floor

m3

132,300

to pits in interblock (conblock) including reinstatement

m3

174,200

to pits in berm including reinstatement

m3

67,800

Pavement reinstatement as specified

macadam layer 250-300mm average thickness

m2

49,800

asphalt pavement 50-70mm average thickness

m2

99,000

Asphalt Treatment Base (ATB) pavement

m2

87,800

concrete rigid pavement 200-300mm average thickness


(including rebar dowel if required)

m2

325,100

concrete floor 70-100mm average thickness

m2

63,400

3 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No
III

Item Description

Unit

Rate - 2014

PIPE WORKS
Pipelaying work including:
transportation of as specified, Employer's supplied material from Employer's
storage to the Site
internal cleaning
all necessary cutting, trimming & connecting
installation of as specified, in-line accessories
construction tools and equipments such as pumps, lighting, etc
water charge for testing, flushing, chlorinating, etc : Rp.12.500,- per m3
testing and commissioning
Clean water pipe installation as specified

HDPE - Pipe WJ

< 63mm

21,400

63mm

21,400

90mm

21,400

110mm

36,700

160mm

42,100

200mm

46,400

250mm

62,000

Clean water pipe fittings installation as specified


B

HDPE - Mitter Bend 90 WJ

< 63mm

no

15,700

63mm

no

18,100

90mm

no

27,500

110mm

no

34,300

160mm

no

49,300

200mm

no

62,800

250mm

no

89,200

HDPE - Mitter Bend 90 with single flange FJ/WJ

< 63mm

no

14,700

63mm

no

18,200

90mm

no

27,500

110mm

no

34,300

4 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

III

PIPE WORKS

HDPE - Mitter Bend 90 with single flange FJ/WJ

Unit

Rate - 2014

160mm

no

47,200

200mm

no

61,400

250mm

no

88,200

HDPE - Mitter Bend 90 all flange FJ

< 63mm

no

14,100

63mm

no

18,100

90mm

no

25,000

110mm

no

31,300

160mm

no

44,400

200mm

no

58,100

250mm

no

80,500

HDPE - Mitter Bend 45 WJ

< 63mm

no

15,700

63mm

no

18,100

90mm

no

27,500

110mm

no

34,300

160mm

no

49,300

200mm

no

62,800

250mm

no

89,200

HDPE - Mitter Bend 45 with single flange FJ/WJ

< 63mm

no

14,700

63mm

no

18,100

90mm

no

27,500

110mm

no

34,300

160mm

no

47,200

200mm

no

61,400

250mm

no

88,200

HDPE - Mitter Bend 45 all flange FJ

< 63mm

no

14,100

63mm

no

18,100

90mm

no

25,000

5 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

III

PIPE WORKS

HDPE - Mitter Bend 45 all flange FJ

Unit

Rate - 2014

110mm

no

31,300

160mm

no

44,400

200mm

no

56,700

250mm

no

80,500

DCI - Flange Adaptor for PE FJ/MJ

50mm

no

23,600

75mm

no

26,400

100mm

no

34,200

150mm

no

41,000

200mm

no

57,700

250mm

no

74,100

DCI - Flange Adaptor for DIP FJ/MJ

50mm

no

23,600

75mm

no

26,400

100mm

no

34,200

150mm

no

41,000

200mm

no

57,700

250mm

no

74,100

DCI - Blank Flange FJ

50mm

no

18,900

75mm

no

21,200

100mm

no

28,600

150mm

no

34,100

200mm

no

41,200

250mm

no

49,300

DCI - Dismantling Joint FJ

50mm

no

30,700

75mm

no

34,100

100mm

no

41,000

150mm

no

44,400

200mm

no

52,500

250mm

no

65,500

6 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

III

PIPE WORKS

DCI - Gate valve with straatpot/street box


Price shall include :
installation of gate valve and related accessories
installation of thrust block
installation of precast concrete cover measured separately
rental of GPS equipment to identify valve position in international coordinate

Unit

Rate - 2014

50mm

no

292,100

75mm

no

326,500

100mm

no

415,100

150mm

no

565,400

200mm

no

645,200

250mm

no

777,000

HDPE - Mitter Tee WJ

63mm

no

19,000

90mm

no

40,900

110mm

no

49,600

160mm

no

72,400

200mm

no

81,900

250mm

no

100,100

HDPE - Stub Flange WJ/FJ

63mm

no

21,600

90mm

no

31,000

110mm

no

42,200

160mm

no

62,200

200mm

no

74,200

250mm

no

83,700

PIPE DECOMMISSIONING
Price shall include :
disconnection to existing pipe branching (taking out existing tee, pipe cutting, etc to ensure no flow)
installation of temporary valve (if required to ensure no connection to existing customers)

63mm

unit

290,000

90mm

unit

380,000

110mm

unit

420,000

160mm

unit

571,000

200mm

unit

647,000

250mm

unit

760,000

7 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No
III

Item Description

Unit

Rate - 2014

PIPEWORKS
Connection to Existing Network as specified
Price shall include :
demolition and reinstatement of existing pavement including excavation,
bedding, backfilling and removal
transportation of as specified, Employer's supplied material from Employer's
storage to the Site
internal cleaning
disconnecting to existing pipe
all necessary cutting and connecting
installation of thrust block

removing of unused pipe and fittings to Employer's warehouse

all necessary construction tools and equipments


testing and commissioning
site cleaning
installation of fittings measured separately
coordinations with related institutions

Connection to PVC / Asbestos Cement Existing Pipe as specified

to 50mm diameter existing networks

no

218,900

to 75mm diameter existing networks

no

328,900

to 100mm diameter existing networks

no

498,000

to 150mm diameter existing networks

no

692,600

to 200mm diameter existing networks

no

841,500

to 250mm diameter existing networks

no

956,100

to 300mm diameter existing networks

no

1,237,500

to 350mm diameter existing networks

no

1,553,500

Connection to GIP / Ductile Iron / Steel Existing Pipe as specified

to 50mm diameter existing networks

no

313,800

to 75mm diameter existing networks

no

423,700

to 100mm diameter existing networks

no

524,800

to 150mm diameter existing networks

no

784,300

to 200mm diameter existing networks

no

888,800

to 250mm diameter existing networks

no

1,045,000

to 300mm diameter existing networks

no

1,306,800

to 400mm diameter existing networks

no

1,742,400

to 600mm diameter existing networks

no

2,612,500

8 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

III

PIPEWORKS

Connection to HDPE Existing Pipe as specified

Unit

Rate - 2014

to 63mm diameter existing networks

no

229,900

to 90mm diameter existing networks

no

345,300

to 110mm diameter existing networks

no

522,900

to 160mm diameter existing networks

no

727,200

to 200mm diameter existing networks

no

884,000

to 250mm diameter existing networks

no

956,100

to 315mm diameter existing networks

no

1,375,000

to 350mm diameter existing networks

no

1,553,500

to 400mm diameter existing networks

no

1,627,600

10

to 630mm diameter existing networks

no

2,441,400

11

to 800mm diameter existing networks

no

3,662,100

unit

176,000

no

302,500

no

342,000

Transfer of Regular Service Connection as specified


Price shall include :
demolition and reinstatement of existing pavement including excavation,
bedding, backfilling and removal
transportation of as specified, Employer's supplied material from Employer's
storage to the Site
internal cleaning

disconnecting to existing pipe including taking out existing clamp saddle


all necessary cutting and connecting

removing of unused pipe and fittings to Employer's warehouse


all necessary construction tools and equipments
testing and commissioning
coordinations with related institutions

1
IV

Generally
CONCRETE WORKS
Precast Concrete Cover

Precast concrete for straatpot cover

Installing new precast surface box size 600x600x200mm (install only),


including :
- Transportation and equipment
- Excavation, backfilling and compaction
- Concrete support, lean concrete, crushed stone, sand bed
- Vertical sleeve installation
- Demolish and remove unapproved soil/material
Installing new precast concrete cover and shaft (install only), including transportation, grouting,
waterproofing, rubber ring and equipment :

RC Cover 125mm + RC Surround 190mm

9 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No
IV

Item Description

Unit

Rate - 2014

CONCRETE WORKS
Pipework Support

Thrustblock Concrete as specified

unreinforced concrete thrustblock K-175

m3

554,600

reinforced concrete thrustblock K-175

m3

1,773,600

reinforced concrete thrustblock K-225

m3

1,861,000

reinforced concrete thrustblock K-250

m3

2,008,000

reinforced concrete thrustblock K-350

m3

2,251,200

reinforced concrete thrustblock K-500

m3

3,350,500

Reinforced Concrete Chamber


C

Reinforced Concrete and Thrustblock (concrete support)

Lean concrete 50mm thick

m2

27,700

sand bed 100mm thick

m2

18,800

cast in situ poured concrete K-225 to concrete post including Formwok

m3

781,000

Reinforcement bar 8mm diameter

kg

16,000

cast in situ poured concrete K-350 to concrete post including Formwok

m3

957,000

Reinforcement bar 19mm diameter

kg

17,200

cast in situ poured concrete K-500 to concrete post including Formwok

m3

1,210,000

Reinforcement bar 22mm diameter

kg

19,800

Foundation

wooden pilling (cerucuk dolken) dia.10mm

8,800

wooden pilling (cerucuk dolken) dia.8mm

7,100

bore piling 400mm (manual)

566,200

bore piling 300mm (manual)

424,700

10 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No
V

Item Description

Unit

Rate - 2014

PIPE BRIDGE WORKS


Price shall include :
mobilisation & demobilisation, site management, tools & equipment
(scaffolding, steel plate bordes or wooden beams & piles, health & safety
tools, barriers, etc)
Notification :
approval of painting material specification (color, painting layer & coating
thickness, type of painting, etc) from PT. Aetra

Preparation / Surface Cleaning

mechanical brushing

m2

37,300

sand blasting

m2

65,200

cement mortar plastering and trowell smooth finishing

m2

26,900

Painting Work

air sprayed steel painting (primary coating, intermediate and top surface finishing)

m2

124,600

brushed steel painting (primary coating, intermediate and top surface finishing)

m2

104,200

rolling or brushing concrete/wall painting (acrylic emulsion paint for exterior wall)

m2

22,400

WF Work

WF

kg

21,000

Channel

kg

18,300

Angle Steel

kg

16,400

Anchor Bolt 13 L=700mm

no

15,300

no

137,500

Install Clamp and Support for steel pipe

Install Clamp Plate l =100mm, t =2mm with bolt 12mm =2 bolt and Baja L
200x200x2.5mm P =150mm with dynabolt 16 L =100mm distance @ 1500mm

Install stiffener

Stiffener

kg

21,000

Base Plate

kg

20,000

11 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

VI

NEW CONNECTION WORKS

Standard of Service Connection Large Meter Connection ( Type-I ) as


specified

for 3/4" Meter size

Unit

Rate - 2014

unit

787,500

unit

840,000

PE - Clamp saddle & Frle ( Stfs ) Push Fit x 1" =1nos


PE - Service pipe 1" =6m
GIP - Pipe Sleeve TJ 11/2"
BRASS - Lockable valve MCF/TJ 1''x3/4" =1nos
BRASS - Water meter including joint adaptor TJ 3/4" =1nos
BRASS - Check or Non Return valve ( Female & Male ) TJ 3/4" =1nos
BRASS - Double Nipple TJ 3/4" =1nos
BRASS - Ball valve TJ 3/4" =1nos
STEEL - Seal wire =1nos
Concrete - Meter box =1nos
2

for 1" Meter size


PE - Clamp saddle & Frle ( Stfs ) Push Fit x 11/2" =1nos
PE - Service pipe 11/2" =6m
GIP - Pipe Sleeve TJ 2"
BRASS - Lockable valve MCF/TJ 11/2''x1" =1nos
BRASS - Water meter including joint adaptor TJ 1" =1nos
BRASS - Check or Non Return valve ( Female & Male ) TJ 1" =1nos
BRASS - Double Nipple TJ 1" =1nos
BRASS - Ball valve TJ 1" =1nos
STEEL - Seal wire =1nos
Concrete - Meter box =1nos

12 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

VI

NEW CONNECTION WORKS

Standard of Service Connection Large Meter Connection ( Type-I ) as


specified

for 11/2" Meter size

Unit

Rate - 2014

unit

892,500

unit

840,000

PE - Clamp saddle & Frle ( Stfs ) Push Fit x 2" =1nos


PE - Service pipe 2" =6m
GIP - Pipe Sleeve TJ 21/2"
BRASS - Lockable valve MCF/TJ 2''x11/2" =1nos
BRASS - Water meter including joint adaptor TJ 11/2" =1nos
BRASS - Check or Non Return valve ( Female & Male ) TJ 11/2" =1nos
BRASS - Double Nipple TJ 11/2" =1nos
BRASS - Ball valve TJ 11/2" =1nos
STEEL - Seal wire =1nos
Concrete - Meter box =1nos

Standard of Service Connection Large Meter Connection ( Type-II ) as


specified
for 3/4" Meter size
PE - Clamp saddle & Frle ( Stfs ) Push Fit x 1" =1nos
PE - Service pipe 1" =6m
GIP - Pipe Sleeve TJ 11/2"
PE - Adaptor Coupling with Male Thread TJ 1''x3/4" =1nos
BRASS - Plug Valve TJ 3/4" =1nos
BRASS - Water meter including joint adaptor TJ 3/4" =1nos
BRASS - Check or Non Return valve ( Female & Male ) TJ 3/4" =1nos
BRASS - Double Nipple TJ 3/4" =1nos
BRASS - Ball valve TJ 3/4" =1nos
STEEL - Seal wire =1nos
Concrete - Meter box =1nos

13 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

VI

NEW CONNECTION WORKS

Standard of Service Connection Large Meter Connection ( Type-II ) as


specified

for 1" Meter size

Unit

Rate - 2014

unit

892,500

unit

945,000

PE - Clamp saddle & Frle ( Stfs ) Push Fit x 11/2" =1nos


PE - Service pipe 11/2" =6m
GIP - Pipe Sleeve TJ 2"
PE - Adaptor Coupling with Male Thread TJ 11/2''x1" =1nos
BRASS - Plug Valve TJ 1" =1nos
BRASS - Water meter including joint adaptor TJ 1" =1nos
BRASS - Check or Non Return valve ( Female & Male ) TJ 1" =1nos
BRASS - Double Nipple TJ 1" =1nos
BRASS - Ball valve TJ 1" =1nos
STEEL - Seal wire =1nos
Concrete - Meter box =1nos
3

for 11/2" Meter size


PE - Clamp saddle & Frle ( Stfs ) Push Fit x 2" =1nos
PE - Service pipe 2" =6m
GIP - Pipe Sleeve TJ 21/2"
PE - Adaptor Coupling with Male Thread TJ 2''x11/2" =1nos
BRASS - Plug Valve TJ 1" =11/2nos
BRASS - Water meter including joint adaptor TJ 11/2" =1nos
BRASS - Check or Non Return valve ( Female & Male ) TJ 11/2" =1nos
BRASS - Double Nipple TJ 11/2" =1nos
BRASS - Ball valve TJ 1" =11/2nos
STEEL - Seal wire =1nos
Concrete - Meter box =1nos

14 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

VI

NEW CONNECTION WORKS

Standard of service connection communal meter Type I installation as speified

for 1/2" meter size


HDPE - Clamp saddle & ferule (Stfs) TJ 00x2" =1 nos
HDPE - Service pipe WJ 2" = 7.5 m
BRASS - Lockable valve MCF/TJ 3/4"x1/2" = 5 nos
BRASS - Water Meter TJ 1/2" = 5 nos
BRASS - Ball Valve TJ 1/2" =5 nos
STEEL - Seal Wire = 5 nos
BRASS - Check or Non return Valve TJ 1/2" = 5 nos
GIP - Pipe Sleve TJ 21/2" =3 m
HDPE - Bend 90 CJ 2" = 2 nos
HDPE - Tee Equal CJ 2"x2" =1 nos
HDPE - Reducer CJ 2"x1" = 2 nos
HDPE - Tee CJ 2x1" = 3 nos
HDPE - Service Pipe 3/4" = 1 m
HDPE - Reducer CJ 1"x3/4" = 5 nos
HDPE - Service Pipe 1" = 1 m
BRASS - Double Nipple TJ 1/2" = 5 nos

Unit

Rate - 2014

no

1,421,000

Box Meter Works


2

cast in situ poured concrete K-175 to concrete post


including formworks

m3

529,300

Reinforcement bar 8mm diameter

kg

15,700

Install Cover Plate L =1.5m, W = 0.70m, T = 3mm including frames ;hinge;


padlock; all necessary cutting and welded

no

854,300

no

1,995,000

D
1

Standard of service connection communal meter Type II installation as speified


for 1/2" meter size
HDPE - Clamp saddle & ferule (Stfs) TJ 00x2" =1 nos
HDPE - Service pipe WJ 2" = 9 m
BRASS - Lockable valve MCF/TJ 3/4"x1/2" = 10 nos
BRASS - Water Meter TJ 1/2" = 10 nos
BRASS - Ball Valve TJ 1/2" = 10 nos
STEEL - Seal Wire = 10 nos
BRASS - Check or Non return Valve TJ 1/2" = 10 nos
GIP - Pipe Sleve TJ 21/2" =3 m
HDPE - Bend 90 CJ 2" = 2 nos
HDPE - Tee Equal CJ 2"x2" =1 nos
HDPE - Reducer CJ 2"x1" = 2 nos
HDPE - Tee CJ 2x1" = 8 nos
HDPE - Service Pipe 3/4" = 2.2 m
HDPE - Reducer CJ 1"x3/4" = 10 nos
HDPE - Service Pipe 1" = 1 m
BRASS - Double Nipple TJ 1/2" = 10 nos
Box Meter Works

cast in situ poured concrete K-175 to concrete post


including formworks

m3

529,300

Reinforcement bar 8mm diameter

kg

15,700

Install Cover Plate L =3.1m, W = 0.70m, T = 3mm including frames ;hinge;


padlock; all necessary cutting and welded

no

1,522,800

15 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

VI

NEW CONNECTION WORKS

Standard of service connection communal meter Type III installation as speified

for 1/2" meter size


HDPE - Clamp saddle & ferule (Stfs) TJ 00x2" =1 nos
HDPE - Service pipe WJ 2" = 10.5 m
BRASS - Lockable valve MCF/TJ 3/4"x1/2" = 15 nos
BRASS - Water Meter TJ 1/2" = 15 nos
BRASS - Ball Valve TJ 1/2" = 15 nos
STEEL - Seal Wire = 15 nos
BRASS - Check or Non return Valve TJ 1/2" = 15 nos
GIP - Pipe Sleve TJ 21/2" =3 m
HDPE - Bend 90 CJ 2" = 2 nos
HDPE - Tee Equal CJ 2"x2" =1 nos
HDPE - Reducer CJ 2"x1" = 2 nos
HDPE - Tee CJ 2x1" = 13 nos
HDPE - Service Pipe 3/4" = 4.5 m
HDPE - Reducer CJ 1"x3/4" = 15 nos
HDPE - Service Pipe 1" = 1 m
BRASS - Double Nipple TJ 1/2" = 15 nos

Unit

Rate - 2014

no

3,150,000

Box Meter Works


2

cast in situ poured concrete K-175 to concrete post


including formworks

m3

529,300

Reinforcement bar 8mm diameter

kg

15,700

Install Cover Plate L =3.1m, W = 0.70m, T = 3mm including frames ;hinge;


padlock; all necessary cutting and welded

no

1,522,800

Standard of Service Connection installation as specified

for 50mm mains

set

450,700

for 75mm mains

set

532,400

for 100mm mains

set

645,200

for 150mm mains

set

1,162,800

for 200mm mains

set

1,320,000

for 250mm mains

set

1,884,000

for 300mm mains

set

2,070,600

DCI - Flange Adaptor For HDPE FJ/MJ =1 nos


DCI - Wall Pipe All Flange FJ = 2 nos
DCI - Gate Valve FJ = 2 nos
DCI - T.Strainer FJ = 1 nos
SS - Flow Stabilizer FJ = 1 nos
DCI - Water Meter FJ = 1 nos
HDPE - Stub Flange + Spool Pipe WJ/FJ = 1 nos
DCI - Check Valve FJ = 1 nos
Tapping Clamp w ...x3/4" tap =1nos
Coupler 1/2" =1nos
Bushing 3/4"x1/2" =1nos
Seal Wire =1nos
Bolt with hole for seal wire =8nos
Tin seal =1nos
HDPE - Pipe WJ = 0.5 m

16 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

VI

NEW CONNECTION WORKS

Standard of Service Connection installation as specified

Installing new precast surface box size 600x600x200mm (install only),


including :
- Transportation and equipment
- Excavation, backfilling and compaction
- Concrete support, lean concrete, crushed stone, sand bed
- Vertical sleeve installation
- Demolish and remove unapproved soil/material

Unit

Rate - 2014

no

302,500

Pipeworks Support
Reinforced concrete Chamber and thrustblock (concrete support)
G

Reinforced concrete thrustblock (concrete support)

Lean concrete 50mm thick

m2

26,500

sand bed 100mm thick

m2

18,000

cast in situ poured concrete K-225 to concrete post including Formwok

m3

745,500

Reinforcement bar 8mm diameter

kg

15,700

no

715,000

Cover Plate Work


5

Install Cover Plate L =1.731m, W =0 .8m, T = 2mm including frames L 50 x 50 x


5; hinge; padlock; all necessary cutting and welded as speified
Service Pipe Connecion Non Standard
Additional Pipelaying Work
Price shall include :
- cutting and breaking of the existing pavement
- all necessary sheeting and bracing
- disposal of material arising from excavations
- sand bedding, filling materials, surface pavement
- compaction and finishing
- transportation of as specified, Employer's supplied material from Employer's
storage to the Site
- internal cleaning
- all necessary cutting, trimming & connecting
- installation of as specified, in-line accessories
- construction tools and equipments such as pumps, lighting, etc
- testing and commissioning
Excavation, bedding, backfilling, pavement reinstatement and pipelaying work as specified

for HDPE 32mm service pipe

in asphalt pavement

177,300

in concrete floor

107,600

in concrete rigid pavement

216,700

in paving block (conblock)

77,600

in berm

59,000

17 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No
VI

Item Description

Unit

Rate - 2014

NEW CONNECTION WORKS


Service Connecion Non Standard
Additional Pipelaying Work
Excavation, bedding, backfilling, pavement reinstatement and pipelaying work as specified

for HDPE 40mm service pipe

in asphalt pavement

198,600

in concrete floor

120,500

in concrete rigid pavement

244,800

in paving block (conblock)

84,700

in berm

679,800

for HDPE 50mm service pipe

in asphalt pavement

228,400

in concrete floor

141,000

in concrete rigid pavement

281,600

in paving block (conblock)

101,600

in berm

81,400

for HDPE 63mm service pipe

in asphalt pavement

190,600

in concrete floor

149,100

in concrete rigid pavement

246,600

in paving block (conblock)

124,200

in berm

90,600

for HDPE 90mm service pipe

in asphalt pavement

276,400

in concrete floor

183,200

in concrete rigid pavement

330,700

in paving block (conblock)

113,100

in berm

111,900

for HDPE 110mm service pipe

in asphalt pavement

286,600

in concrete floor

207,000

in concrete rigid pavement

343,200

in paving block (conblock)

134,500

in berm

133,700

18 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No
VI

Item Description

Unit

Rate - 2014

NEW CONNECTION WORKS


Service Connecion Non Standard
Additional Pipelaying Work
Excavation, bedding, backfilling, pavement reinstatement and pipelaying work as specified

for HDPE 160mm service pipe

in asphalt pavement

306,100

in concrete floor

231,900

in concrete rigid pavement

391,600

in paving block (conblock)

154,300

in berm

152,500

for HDPE 200mm service pipe

in asphalt pavement

332,600

in concrete floor

269,000

in concrete rigid pavement

413,400

in paving block (conblock)

170,400

in berm

154,300

for HDPE 250mm service pipe

in asphalt pavement

397,500

in concrete floor

309,300

in concrete rigid pavement

451,900

in paving block (conblock)

186,300

in berm

204,400

for HDPE 300mm service pipe

in asphalt pavement

406,100

in concrete floor

352,600

in concrete rigid pavement

469,700

in paving block (conblock)

206,800

in berm

159,500

19 of 20

FRAMEWORK AGREEMENT 2014


Schedule of Rate - Division Network Improvement and Key Account Works
Item
No

Item Description

Unit

Rate - 2014

VII

HEAVY EQUIPMENTS

Equipment (All-inclusive Rate)

drain pump portable; 3 inch

day

183,700

drain pump portable; 6 inch

day

367,500

drain pump portable; 8 inch

day

493,500

generator set 60KVA

day

1,113,000