Dr Khairuddin Abdul Rashid

Session 3
PWD Form DB/T (2002)
Conditions of Contract
Clause 16 – 30

1
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 16 Site boundaries and
setting out

 PD to define boundaries of the


site, determine levels, etc and
furnish information to the
contractor. The contractor
interprets the Government’s
information at his own risk
 The contractor is responsible
for setting out and for errors
arising from his own
inaccuracy.

2
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 17 Inspection of site

 The contractor is deemed to


have visited the site and make
the necessary allowances in
the Contract Sum

Clause 18 Employment of
Workmen

 Malaysians only, to reflect the


racial composition, shall abide
with all Acts, etc, localized

3
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 19 Compliance with
Employment Act 1955, etc

 The contractor, his sub-


contractors to comply with the
relevant Acts

Clause 20 Epidemics and Medical


Attendance
 The contractor to comply with
all regulations, orders , etc and
provide medical attendance
for his employees

4
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 21 Days and hours of
working

 As defined in Cl. 21.1 (a) – (c)


and Cl. 21.2

Clause 22 Contractor’s PM

 Competent, fluent in BM and


English. Instructions to PM is
deemed to have been given to
the contractor

5
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 23 Wages books and time
sheets
 To keep proper wages books
and time sheets and to make
available for inspection by the
PD

Clause 24 Default in payment of


wages (by the contractor)
 PD can make payments from
monies due or to become due
or from the Performance Bond

6
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 25 Discharge of Workmen

 PD may instruct the contractor


to discharge any person the
latter employed due to
misconduct, incompetent, etc…
Person discharged must be
replaced by the contractor asap.
The contractor is not entitled to
any claim.

7
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 26 Access for PD to the
Works

 PD / his representative shall


have access to the site and the
works and to the workshops,
etc at all reasonable times

8
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 27 Variations

Cl. 27.1 (a) The term refers to:


 Addition, omission or
substitution of any work
 The alteration of the kind or
standard of materials…
 The removal from site … that
are in accordance with the
contract

9
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 27 Variations

Cl. 27.1(b) The addition, alteration


or omission … imposed by the
PD on

 Access to the site…


 Limitation of working space
 Limitation of working hours
 Specific order of works

10
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 27 Variations

 Cl. 27.2 PD may issue


instructions effecting a change
in the government’s
requirements or the
contractor’s proposal … adjust
CS accordingly (unless due to
Contractor’s fault)
… requires the consent of the
contractor

11
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 27 Variations

 Cl. 27.3 The contractor may


effect variations for the
purposes of suitability and
safety … with the consent of
the PD

12
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 27 Variations

 Cl. 27.4 Variation under 27.3


Leading to additional costs:
The extra cost to be borne by
the contractor unless … the
variation is necessary…subject
to Cl. 28.5

 Leading to cost saving


Adjust the CS accordingly

13
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 28 Valuation of Variations

 Additional or substituted
works: Consistent with the
contract sum analysis or
schedule of rate … with
allowance for changes in
conditions, quantities

 Omission: follow contract sum


analysis

14
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 28 Valuation of Variations

 Fair valuation if none of the


above is applicable
 Fair valuation using Daywork
plus 15%
 Make allowance for any
necessary addition to or
reduction of site
administration, site facilities,
temporary works

15
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 29 Provisional Sums

 A sum for work to be executed


… which cannot be foreseen…
 Requires PD instruction
 Valuation as Cl. 28
 Adjust the Contract Sum
accordingly

16
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 30 Contract Sum

 Shall not be adjusted or altered


… except with express
provisions

 Amount added/omitted in the


adjustment of the contract sum
shall be accounted for the next
interim payment

17
Dr Khairuddin Abdul Rashid

End of Session 3