Beruflich Dokumente
Kultur Dokumente
Part 3: Construction
Second Edition
Version 2.3
WSA 022002-2.3
148
CONTENTS
11 GENERAL
153
11.1 SCOPE
11.2 INTERPRETATION
153
153
12 QUALITY
155
155
155
155
155
155
155
156
156
156
156
156
13 GENERAL CONSTRUCTION
158
13.1 GENERAL
13.2 ORDER OF CONSTRUCTION, TESTING AND COMMISSIONING
13.3 CONTRACT INTERFACES
13.4 CUSTOMER FOCUS
13.4.1 General
13.4.2 Resolution of complaints
13.5 PROTECTION OF PEOPLE, PROPERTY AND ENVIRONMENT
13.5.1 Safety of people
13.5.2 Protection of other services
13.5.3 Disused / Redundant sewers
13.5.4 Road reserves or other thoroughfares
13.5.4.1 Treatment of pavements and other surfaces
13.5.4.2 Traffic management
13.5.4.3 Cleanliness of roads, paths, accesses and drainage paths
13.5.4.4 Storage of products, materials and equipment
13.5.4.5 Obstruction of street drainage
13.5.5 Private and public properties
13.5.6 Protection of the environment and heritage areas
13.5.6.1 General
13.5.6.2 Collection and disposal of wastes
13.5.6.3 Protection of adjacent lands and vegetation
13.5.6.4 Control of water pollution
13.5.6.5 Acid sulphate and contaminated soils
13.5.6.6 Control of noise and atmospheric pollution
13.6 AFFECTED PARTY NOTIFICATIONS
13.7 ALTERATION OF EXISTING SERVICES
13.8 SURVEY MARKS
13.9 CONSTRUCTION TOLERANCES
13.10 LATENT CONDITIONS
158
158
158
158
158
158
159
159
159
160
160
160
160
161
161
161
161
161
161
161
162
162
162
163
163
163
163
163
163
164
149
14.5.1 Delivery
14.5.2 Transportation of concrete
14.5.3 Formwork
14.5.3.1 General
14.5.3.2 Formwork for plastics-lined concrete
14.5.4 Reinforcement
14.5.5 Placement
14.5.5.1 General
14.5.5.2 Placement in water
14.5.6 Slump
14.5.7 Compaction
14.5.8 Stripping
14.5.9 Curing
14.5.10 Repair of blemishes
14.6 SUPPLY OF WATER TO THE WORKS
14.7 ON-SITE STOCKPILES
15 EXCAVATION
WSA 022002-2.3
165
165
166
166
166
166
166
166
166
167
167
167
167
167
167
168
169
15.1 SAFETY
15.2 LIMITS OF EXCAVATION
15.3 EXCAVATION ACROSS IMPROVED SURFACES
15.4 EXCAVATION IN ROOT ZONES
15.5 BLASTING
15.6 SUPPORT OF EXCAVATIONS
15.7 DRAINAGE AND DEWATERING
15.8 FOUNDATIONS AND FOUNDATION STABILISATION
15.9 SURPLUS EXCAVATED MATERIAL
169
169
169
169
169
170
170
170
170
171
171
171
171
171
171
171
172
172
172
172
172
172
172
172
173
174
174
174
174
174
175
175
175
175
175
175
176
176
176
WSA 022002-2.3
150
176
176
176
176
176
177
177
177
177
177
177
177
177
177
179
18.1 GENERAL
18.2 MH BASE
18.3 TRENCH DRAINAGE AROUND MHS
18.4 PRECAST CONCRETE MH SYSTEMS
18.5 CAST IN-SITU CONCRETE MH
18.6 BENCHING AND CHANNELS
18.7 CONCRETING FOR PLASTICS-LINED WORK
18.7.1 Concrete work planning
18.7.2 Fixing of plastics lining for concrete work
18.7.3 Concrete placement and formwork removal
18.8 INTERNAL COATING OF CONCRETE MHS
18.9 COVERS
18.10 CONNECTIONS TO MHS
18.11 MH DROPS
179
179
179
179
179
180
180
180
180
180
180
180
181
181
182
182
182
182
182
183
20.1 GENERAL
183
20.2 EMBEDMENT MATERIALS
183
20.3 COMPACTION OF EMBEDMENT
183
20.3.1 Methods
183
20.3.2 Compaction trials / Pre-qualification of embedment compaction method
184
20.3.2.1 General
184
20.3.2.2 Test method
184
20.3.2.3 Interpretation and applicability
184
20.3.3 Compaction control
184
20.4 SPECIAL BEDDING AND EMBEDMENTS / GEOTEXTILE SURROUND AND PILLOW184
20.5 REMOVAL OF TRENCH SUPPORTS
184
20.6 CONCRETE EMBEDMENT AND ENCASEMENT
184
21 FILL
186
186
186
186
186
187
187
COPYRIGHT
151
22 ACCEPTANCE TESTING
WSA 022002-2.3
188
22.1 GENERAL
188
22.2 VISUAL INSPECTIONABOVE-GROUND
188
22.3 COMPACTION TESTING
188
22.3.1 General
188
22.3.2 Minimum compaction
189
22.3.3 Embedment compaction testing
189
22.3.3.1 Applicable pipe sizes
189
22.3.3.2 Frequency and location of embedment tests
189
22.3.3.3 Retesting
189
22.3.4 Trench fill compaction testing
190
22.3.4.1 Trafficable Test Zone
190
22.3.4.2 Non-trafficable test zone
190
22.3.4.3 Test method
190
22.3.4.4 Frequency and location of tests
190
22.3.4.5 Retesting
190
22.3.5 Other fill compaction testing
191
22.3.5.1 General
191
22.3.5.2 Trafficable test zone
191
22.3.5.3 Non-trafficable test zone
191
22.3.5.4 Frequency and location of tests
191
22.3.5.5 Retesting
192
22.4 AIR PRESSURE AND VACUUM TESTING OF SEWERS
192
22.4.1 General
192
22.4.2 Air testing methods for sewers
192
22.4.2.1 Vacuum testing
192
22.4.2.2 Low pressure air testing
193
22.4.3 Testing of sewers >DN 1500
194
22.4.3.1 General
194
22.4.3.2 Method of test
194
22.4.4 Testing of concrete MHs
194
22.4.4.1 General
194
22.4.4.2 Test method
194
22.5 INFILTRATION TESTING
195
22.6 DEFLECTION (OVALITY) TESTING OF FLEXIBLE SEWERS
196
22.6.1 General
196
22.6.2 Ovality proving tools
196
22.6.3 Flexible sewers DN 300
196
22.6.4 Flexible sewers >DN 300
196
22.6.4.1 General
196
22.6.4.2 Flexible sewers >DN 300 and <DN 750
197
22.6.4.3 Flexible sewers DN 750
197
22.7 CCTV INSPECTION
197
22.8 INSPECTION AND TESTING OF PLASTIC LINED CONCRETE SEWERS AND MHS 198
22.8.1 Visual inspection
198
22.8.2 Spark testing
198
22.8.3 Locking key pull-out tests
199
22.9 PRESSURE TESTING OF INVERTED SYPHONS
199
22.9.1 General
199
22.9.2 System test pressure
199
22.9.3 Maximum allowable loss
199
22.9.4 Test procedure
199
22.9.5 Satisfactory pressure test
200
22.9.6 Failure of test
200
COPYRIGHT
WSA 022002-2.3
152
202
202
202
202
202
202
202
202
203
203
203
204
25 RESTORATION
205
25.1 GENERAL
25.2 PAVEMENTS
25.3 LAWNS
25.4 GRASSED AREAS
25.5 BUSHLAND
25.6 PROVISION FOR SETTLEMENT
25.7 MAINTENANCE OF RESTORED SURFACES
205
205
205
205
206
206
206
207
208
208
TABLES
TABLE 17.1
TABLE 20.1
TABLE 22.1
TABLE 22.2
TABLE 22.3
TABLE 22.4
TABLE 22.5
TABLE 22.6
TABLE 22.7
TABLE 23.1
TABLE 23.2
TABLE G1
COPYRIGHT
173
183
189
190
190
193
194
195
197
203
203
208
153
WSA 022002-2.3
11 GENERAL
11.1 SCOPE
This Part of the Code details default requirements for the construction of gravity sewers
including maintenance and inspection structures.
This document should be read in conjunction with relevant Water Agency supplementary
manuals, development agreements, specific project contract documents, general
conditions of contract e.g. AS 2124 and other documents nominated by the Water Agency.
11.2 INTERPRETATION
Unless specifically stated otherwise, construction of the sewers includes all functions
described in this Part and the provision of any minor materials and services that are not
described but are reasonably necessary to produce a fully functional sewerage system.
For the purposes of this Part, except where otherwise shown:
"Authorised" means acceptable to, authorised by or approved by the Water Agency
or Owner or Regulator.
Constructor means the individual, corporation or legal entity including any
contractors and sub-contractors that is accountable at law for delivery of Works under
a specific contract or development agreement.
Design Drawings means plans, elevations and drawings required for the
construction of the sewerage systems and showing the locality including roads and
sewer details, the site plan including lots, boundaries, roads, proposed and existing
sewers, proposed property connection sewers, pumping stations, pressure mains,
water mains, drains, watercourses, site contours, proposed aqueducts, proposed
boreholes, a longitudinal section, construction details and a connection to existing
sewer schedule. Supplementary information may include proposed buildings, existing
services, and groundwater and watercourse levels.
The Designer may nominate Standard Drawings or parts thereof as Design Drawings
for the purposes of the project.
Improvements are deemed to include but not be limited to pavements, shrubs,
gardens, retaining walls, fences and all other structures.
"Owner means the Agency, Authority, Board, Company, Controlling Authority,
Corporation, Council, Department, Individual, Regulator, Utility or other legal entity
who is the owner of the asset and/or who has responsibility for the asset.
Part means the Sewerage Code of Australia, Part 3: Construction.
Purchase Specification means the WSAA Purchase Specification detailing the
requirements for the supply of a product or material.
Regulator means a Regulator who has the power to enforce Regulations related to
the activities and responsibilities of a Commonwealth, State, Territory or Local
government. It applies to environmental management and protection, occupational
health and safety and the like.
"Specification" means the Specification detailing the work involved in the particular
project in hand.
Specified means as specified in the Specification, Design Drawings, Purchase
Specifications and/or by the Superintendent.
Standard Drawings means the Sewerage Code of Australia, Part 4: Standard
Drawings.
COPYRIGHT
WSA 022002-2.3
154
COPYRIGHT
155
WSA 022002-2.3
12 QUALITY
12.1 QUALITY ASSURANCE
The Water Agency is responsible for specifying quality assurance of construction activities
and personnel qualifications. Unless otherwise specified, the requirements of this section
apply.
12.1.1 General
The Constructor shall comply with all requirements of the Civil Contractors Federation
(CCF) Civil Construction Management Code or Water Agency authorised equivalent
system. The quality management system shall address the more pertinent elements of
quality assurance (ISO 9001), health and safety issues (AS/NZS 4801) and environmental
requirements (ISO 14001). These elements are incorporated within the Civil Construction
Management Code and shall be addressed within the management system documentation.
The Constructor shall provide evidence of its certification to the CCF Code (or equivalent)
prior to the commencement of any work.
12.1.2 Quality system
The Constructor shall plan, establish, document and maintain a quality system that
conforms to the requirements of the contract and shall provide the Superintendent with
access to the Constructor's quality systems for monitoring and quality auditing. The quality
system proposed by the Constructor shall be used as an aid to achieve compliance with
the requirements of the contract and to document such compliance.
If the Constructor discovers material or work that is not in accordance with the contract, the
Constructor shall promptly initiate the non-conformance procedure required by the quality
system. If the Constructor proposes a disposition of any non-conforming materials or work
which is at variance with the requirements of the contract, the proposal shall be submitted
in writing to the Superintendent whose decision on the proposal shall be obtained in writing
before the non-conforming material or work is covered up and/or incorporated into the
Works, or is the subject of any other disposition.
12.1.3 Project management plan
The Constructor shall conform to the policies and procedures stated in the project
management plan submitted with the Constructor's tender.
12.1.4 Inspection and test plans
The Constructor shall submit inspection and test plans (ITPs) to the Superintendent for
verification before commencing work on activities covered by the project quality plan. The
ITPs shall include where applicable, observations, measurements or tests at the
Constructor's facilities.
Model ITPs for construction of reticulation sewers will be available at www.wsaa.asn.au.
12.1.5 Quality tests
The Constructor shall be responsible for the quality of all products, processes and services
under the contract, and unless otherwise specified, shall provide all tests required to
demonstrate conformance of all products, processes and services to the technical
requirements of the contract.
Unless otherwise agreed by the Superintendent, all laboratory tests and field tests
undertaken by the Constructor shall be performed by a Tester currently registered with the
National Association of Testing Authorities (NATA) or equivalent authority for the class of
tests being undertaken.
COPYRIGHT
WSA 022002-2.3
156
(b)
reviewing and verifying of the Constructor's quality procedures and work instructions
and documentary evidence of compliance with technical requirements of the contract.
12.1.7 Traceability
The Constructor shall maintain records clearly identifying the source of materials and
equipment, the suppliers declaration of conformity, the design drawings used for the
construction of the works and all test results. These shall be stored and maintained in
accordance with Clause 12.1.8.
12.1.8 Quality records
Quality records shall be stored and maintained such that they are readily retrievable in
facilities that provide a suitable environment to minimise deterioration or damage, and to
prevent loss. Quality records shall be available for evaluation by the Superintendent during
the period of the Contract and shall include all pertinent Constructor and third party
records.
The Constructor shall retain quality records for seven (7) years from the date of practical
completion of the Works.
The Constructor shall maintain records in two categories:
(a)
Test records, which shall comprise all working sheets and summaries associated with
testing in accordance with the Inspection and Test Plans.
(b)
Project quality records, which shall include, but not be limited to site meeting
minutes, technical reviews, minutes of meetings between Superintendent and
Constructor and other relevant documentation.
The Constructor shall submit to the Superintendent quality records as evidence that the
work has complied with the specified quality requirements. If unsatisfactory, the records
shall be submitted within twenty-four (24) hours of creation or receipt, and within seven (7)
days of creation or receipt if satisfactory.
Within three (3) months of the date of practical completion the Constructor shall make
available a register of all quality records required to be held under the contract. The
Constructor shall supply copies of all quality records or parts thereof as required by the
Superintendent.
12.1.9 Inspection
The Superintendent shall be given access in conjunction with or through the Constructor to
all laboratories and other facilities used for quality control tests to verify that specified
requirements are being met.
12.2 PERSONNEL QUALIFICATIONS
The handling, laying, jointing, trench filling and testing of all sewers, construction and
testing of associated structures and installation of appurtenances shall be carried out, and
supervised by, acceptably qualified and/or accredited personnel.
COPYRIGHT
157
WSA 022002-2.3
Personnel shall hold minimum qualifications or specialist accreditation appropriate for the
work undertaken.
Minimum qualifications shall mean Statements of Attainment for all those Units of
Competence, nominated by the Water Agency, from the Water Industry National Training
Package NWP01 or Local Government Training Package LGA00 or the Civil Construction
Training Package BCC98 or other relevant Training or a combination of one or more of the
aforementioned.
Specialist accreditation shall mean a qualification achieved through specialised training
and assessment for a specific product and/or situation that is not covered by relevant
Training Packages.
Qualifications from Training Packages shall be awarded by a registered training
organisation.
Training and assessment for specialist accreditation shall be provided by registered
training organisations or recognised organisations with appropriately qualified and
experienced trainers and assessors.
Registered training organisations shall be those listed by the National Training Information
Service for the provision of training or assessment services as required.
Training packages, together with relevant short training courses and training/assessment
service providers are provided by the National Training Information Service at
www.ntis.gov.au.
COPYRIGHT
WSA 022002-2.3
158
13 GENERAL CONSTRUCTION
13.1 GENERAL
Construct the sewerage works to the lines, levels, grades and in the locations using the
materials and methods as specified.
If insufficient detail or instruction is provided in the Design Drawings or Specification,
obtain instruction from the Superintendent prior to commencement.
Use only the types, materials, sizes, lengths, classes, jointing methods and corrosion
protection systems for the pipes, fittings and maintenance structures as specified. Use only
manufacturers products and product range authorised by the Water Agency.
Keep on site at all times a copy of the Specification, all relevant Design Drawings,
Standard Drawings and the Water Agencys manual or catalogue or listing of authorised
products and materials.
13.2 ORDER OF CONSTRUCTION, TESTING AND COMMISSIONING
Undertake and complete all Works in accordance with the following process:
(a)
Except where connection to a live sewer is required, start construction from the
furthest downstream point. Otherwise, start construction at a point clear of the live
sewer as specified by the Water Agency.
(b)
Install all Works in accordance with the Design Drawings and the Specification,
progressively working upstream.
(c)
(d)
(e)
Connect to the live sewer after all other Works have been constructed as specified.
159
WSA 022002-2.3
Keep the Superintendent informed and fully briefed of any contentious issues raised about
the Works.
13.5 PROTECTION OF PEOPLE, PROPERTY AND ENVIRONMENT
13.5.1 Safety of people
Protect the safety of all employees and people on or adjacent to the Works in accordance
with the relevant legislation, statutory requirements, regulations and codes of practice.
All people on the site shall have completed the relevant site induction program and wear
the certified safety apparel including helmets, vests, boots, ear and eye protection.
Conduct a hazard survey to identify potential hazards during construction in accordance
with the requirements designated by the Water Agency.
Comply with the relevant power authority requirements when operating near overhead
power lines. Provide an observer when working below or within 6 m of power lines to
advise on proximity. Maintain a clearance of at least 3 m at all times between plant and
power lines.
Store or leave unattended equipment, tools and materials in a condition that minimises
hazards.
Adhere at all times to the OH&S requirements of the Water Agency.
Ensure all employees are suitably trained in OH&S compliance.
13.5.2 Protection of other services
Prior to excavation, contact Dial Before You Dig by telephone 1100 or facsimile
1300 652 077 to determine or reconfirm the location of underground services.
Implement special precautions where excavations are to be undertaken near any other
services including petroleum pipelines, gas pipelines, overhead and buried electricity and
communication cables, drains, sewers and water mains. For these assets and any other
services:
(a)
(b)
(c)
As appropriate for critical services, arrange for a representative from the service
Owner to be present, unless the service Owner directs otherwise.
(d)
Adopt an appropriate method for exposing and protecting the service from damage if
the service is to be exposed.
Industry practice is generally to hand dig and locate underground services prior to
machine digging. Alternatively, location by vacuum potholing may provide a more
efficient and safer means in congested pipe corridors.
(e)
(f)
Take special care to ensure that other services are protected in accordance with the
conditions specified by the service Owner.
(g)
Arrange for isolation and subsequent restoration of any service that needs to be
removed from service while the Works are in progress.
(h)
COPYRIGHT
WSA 022002-2.3
160
If the Owner cannot be located within a reasonable time, report the damage to the
Superintendent, and arrange or perform repair to an approved standard. Do not
backfill, cover up or make the repair inaccessible prior to obtaining authorisation from
the Superintendent.
(i)
(b)
Restored to its original surface and material condition and to the satisfaction of the
Owner.
Restore the surface of unpaved streets before they are reopened to traffic.
Restore the surface of any excavation in a sealed road, footway or other pavement or
provide a temporary bituminous seal before being reopening it to the public.
13.5.4.2 Traffic management
Where required by the Water Agency, prepare a traffic management plan detailing the
proposals for traffic diversion and control. The plan shall detail the access requirements for
all developed properties, and outline specific proposals for continued access to these
properties. Traffic management plans shall be designed and supervised by persons
accredited to an approved national course. The plan shall include names and accreditation
details of the Designer and supervisor.
Construction within any public road will generally not be permitted until the traffic
management plan has been authorised by the relevant road Owner.
Ensure all personnel working on or adjacent to roadways wear safety vests and are
suitably trained and certified.
Follow traffic management practices:
(a)
(b)
(c)
As appropriate, notify the relevant road Owner, traffic authority, police, fire services,
ambulance services, bus companies, and any other service whose operations may be
affected by the change to the regular traffic flow pattern in the vicinity of the Works.
(d)
Provide an alternative means of access to all rights of way, buildings and property
where the Works disrupt access.
(e)
Ensure that pedestrians are kept clear of the work area and are provided with safe
alternative means of passing the Works.
(f)
Complete any work involving the opening of street pavements without delay.
COPYRIGHT
161
WSA 022002-2.3
(b)
Comply with the Water Agency requirements for resolution of any dispute associated
with access or entry rights to the Works.
(c)
(d)
(e)
Replace damaged conduits with the same, or agreed equivalent, material and
authorised connectors. Repair and/or replace all property and environmental damage
caused by the Works.
(f)
Remove all facilities for the Works from the site within the time frame specified or
agreed.
(g)
Restore all services, drains, fences, structures, surfaces and improvements affected
by the Works to the original surface and condition to the satisfaction of the Owner,
and within the time frame specified or agreed.
COPYRIGHT
WSA 022002-2.3
162
Measures to be taken to minimise erosion and to trap sediment in any water leaving
the site.
(b)
(c)
(d)
(e)
Procedures for monitoring, maintaining and removing erosion and sediment control
measures.
(f)
Procedures to trap and dispose of excess water during testing, disinfection and
swabbing of the completed Works.
Implement the requirements of the approved plan and comply with all applicable
Commonwealth, State, Territory and Local Government laws and regulations.
13.5.6.5 Acid sulphate and contaminated soils
Determine from the Design Drawings and mark out prior to work commencing the sites of
acid sulphate (or potential acid sulphate) soil and other contaminated sites to be
excavated. Where such sites exist, take appropriate measures during excavation, storage,
transport and disposal of soil and filling of the trench, to ensure that excavated material is
treated on-site or at an authorised remote location.
COPYRIGHT
163
WSA 022002-2.3
Refer to the Product and Material Information and Guidance for pipeline suitability in acid
sulphate and contaminated soils
13.5.6.6 Control of noise and atmospheric pollution
Comply with relevant Regulator requirements for mitigating noise and atmospheric
pollution.
Operate all plant and construction equipment such that it does not cause undue noise and
atmospheric pollution.
Fit compressors, air tools, generators and other plant as necessary with appropriate
silencers.
Take all necessary measures to prevent dust generation on the site and in particular its
spread to adjacent areas. Preventative measures shall include, but not be limited to,
regular watering of the Works area and the access tracks and roads.
13.6 AFFECTED PARTY NOTIFICATIONS
Ensure that all owners and residents of property directly and indirectly affected by the
Works are notified in writing of the proposed Works before their commencement.
Notify commencement of Works to the Superintendent. The period of notice shall comply
with the relevant notification requirements specified in the contract or by the Water Agency.
Comply with the notification requirements of all affected municipal, services and other
Owners having care, management or control over streets, services and/or property affected
by the Works.
Retain copies of all notices for audit purposes.
13.7 ALTERATION OF EXISTING SERVICES
Carry out alterations to other services in accordance with the policies, practices and
procedures specified by the responsible service Owner.
13.8 SURVEY MARKS
Maintain all State and Territory survey marks in their correct position.
When such survey marks are disturbed, re-establish or reinstate the marks to the
requirements of the relevant Regulator.
13.9 CONSTRUCTION TOLERANCES
Adhere to tolerances specified in Section 23.
13.10 LATENT CONDITIONS
Obtain instruction from the Superintendent regarding latent site conditions and obstacles
that impact on the project, such as:
(a)
Where sewers cannot be laid to achieve the minimum specified cover over the top of
the pipe barrel.
(b)
(c)
A building approval that has been given to construct a structure over the sewer.
(d)
Disused pipelines.
(e)
COPYRIGHT
WSA 022002-2.3
164
Use only lifting and transportation equipment that does not contact plastics linings
and plastics accessories, except where appropriate padding or protective systems
are used.
COPYRIGHT
165
WSA 022002-2.3
(b)
Provide special protection for unsecured plastics linings and PVC sheet flaps and
accessories during handling, storage and construction operations until secured in the
completed installation.
(c)
Prevent exposure to sunlight of plastics lining sheets and accessories for the duration
of the project.
(d)
Provide a secure, clean and dry storage area for plastics linings work materials and
tools.
(e)
(ii)
(iii)
(A)
(B)
(C)
PE pipes and fittings scored deeper than 10% of the wall thickness.
(b)
Faded / discoloured PVC, PE, ABS, GRP and plastic coated pipes and fittings.
(c)
PVC and ABS pipes and fittings scored deeper than 0.5 mm.
(d)
GRP pipes and fittings scored deeper than 1 mm or with impact damage.
Remove rejected products and materials and store separately from useable products to
prevent inadvertent use.
14.5 CONCRETE WORKS
14.5.1 Delivery
Concrete shall be delivered to site for placement within 90 minutes of commencement of
mixing at the plant or within the time limitations for the mix and ambient temperature.
14.5.2 Transportation of concrete
Use pneumatic and pumping or other methods for conveying and placing concrete when
nominated in the Specification or when authorised by the Superintendent. Where concrete
is conveyed by wheeled vehicles or barrows, the equipment used and the distance
travelled shall be authorised by the Superintendent.
If concrete is conveyed by chute, the equipment shall be of such size, slope and type as to
ensure the continuous flow of concrete without segregation of materials. The delivery end
of the chute shall be as near as possible to the final position of the concrete and it shall be
provided with an effective baffle. If the chuting operation is not continuous, the chute shall
discharge the concrete into a hopper.
COPYRIGHT
WSA 022002-2.3
166
14.5.3 Formwork
14.5.3.1 General
Formwork, including all temporary supporting structures and precast members, shall
comply with the requirements of AS 3610 and the additional requirements of this Code,
including Standard Drawings.
Forms shall be sufficiently tight to prevent loss of mortar from the concrete. Form surfaces
shall be smooth and free from holes or irregularities detrimental to the finished concrete
surface.
Before placing the concrete, coat the forms with a suitable, non-staining coating, which will
facilitate their release.
Finish surfaces as specified.
14.5.3.2 Formwork for plastics-lined concrete
Set out and install formwork for in-situ concrete structures to be plastic lined so as to
facilitate fixing of plastic lining materials to internal formwork faces and in a manner that
will:
(a)
(b)
Position fixing holes within areas of lining that will be subsequently covered by
jointing or welding strips.
(c)
Avoid the securing of lining materials by means of bands or straps otherwise than as
provided for in the lining material manufacturer's printed instructions.
14.5.4 Reinforcement
Supply, fix and place reinforcement in accordance with AS 3600. Ensure the specified
minimum cover is achievable between ends of members and / or construction joints.
Continuously monitor placement.
14.5.5 Placement
14.5.5.1 General
Place concrete within the time limitations for the mix and ambient temperature. Place in
discrete layers in one continuous operation between ends of members and/or construction
joints.
Continuously monitor placement.
Surfaces upon or against which concrete is to be placed shall be free of standing water,
mud and debris.
Prior to placing concrete on concrete that has set, prepare the surface of the set concrete
by scabbling to expose aggregate, clean off loose material and dampen and apply a
bonding agent recommended by the concrete supplier.
In the placement of vertical elements, do not allow free fall of concrete to exceed 1.6 m.
14.5.5.2 Placement in water
Deposit concrete in water only where specified or authorised by the Superintendent.
Place concrete in water under the direct supervision of the Superintendent.
Take precautions to prevent significant mortar loss where concrete is to be placed in
running water.
Place concrete in water continuously in a compact mass, with the top surface kept as level
as practicable, by:
(a)
167
WSA 022002-2.3
(b)
(c)
Placing in suitably tied jute bags, each containing not less than 15 litres of concrete.
Where concrete is provided in bags, place the bags in header and stretcher courses so
that the entire mass in interlocked.
14.5.6 Slump
Slump shall be appropriate to the project specified by the Constructor on advice from the
concrete supplier.
There is no default value for slump in the Purchase Specifications because slump is
dependent on the method of placement.
The slump at the point of acceptance shall be in the range 80120 mm. Under no
circumstances is additional water to be added onsite unless approved by the concrete
supplier.
Higher slumps can result in an increase in bleed water requiring additional precautions
when finishing concrete. The constructor should liaise with the concrete supplier in
determining the slump.
The addition of excess water onsite can adversely affect the strength and durability of the
concrete.
14.5.7 Compaction
Immediately compact concrete after placing. Use internal and/or external vibration in a
systematic manner to ensure that all concrete is thoroughly compacted. Vibrate to the full
depth of each layer and extend into the top 100 mm of the underlying layer. Do not vibrate
to the point where segregation of the ingredients occurs.
Use rotary out of balance vibrators.
Where internal vibrators are used, insert them vertically at successive locations and at
spacings not exceeding the manufacturers stated zone of influence. Do not allow vibrators
to contact partially hardened concrete or reinforcement embedded in it.
In regions of closely spaced horizontal reinforcement, ensure full compaction directly
beneath the closely spaced horizontal reinforcement prior to encasing the reinforcement
with concrete.
14.5.8 Stripping
Ensure that concrete has adequate strength before stripping formwork.
Remove forms in a manner that will not injure the concrete. Provide temporary support to
the concrete structure so as to protect freshly stripped concrete from construction loads.
14.5.9 Curing
Cure concrete as specified.
14.5.10 Repair of blemishes
Fill surface holes and damage exceeding specified limits by filling with cementitious mortar
bonded to the concrete.
14.6 SUPPLY OF WATER TO THE WORKS
Obtain an authorisation from the Superintendent for the supply of water for construction
purposes.
Do not take water from any metered or private trunk service without the Owner's
permission.
Maintain all hydrants to protect the quality of water supplied.
COPYRIGHT
WSA 022002-2.3
168
Fit an authorised backflow prevention device in accordance with AS/NZS 3500.1.2 to any
equipment drawing water from the Water Agency supply system.
Introduction of water supply restrictions over the designated Works area may prohibit the
supply of water to the site. The Water Agency should be consulted to confirm the
availability of water supply during the construction period. Alternative sources of supply
may need to be sought in the case of restrictions.
14.7 ON-SITE STOCKPILES
Store only sufficient materials on-site as are necessary to allow timely and efficient
progress of the work. Locate stockpiles of excavated or imported material where they
cause no interference to the public, drainage routes or vehicular or pedestrian traffic.
Do not obstruct clear lines of sight for drivers.
Do not stack materials against structures, fences, trees or other property improvements.
Leave a clear path between the edge of any excavation and the inner toe of any stockpile
or spoil banks such that no loading is imposed on the trench wall.
Do not stack or stockpile materials under overhead electrical conductors.
Obtain written permission of the Owner for storage of materials, equipment and/or
excavated material for the Works on the Owner's land.
COPYRIGHT
169
WSA 022002-2.3
15 EXCAVATION
15.1 SAFETY
Do not commence any excavation until all equipment and materials necessary to make the
excavation safe are on site and available for use. This includes any necessary fencing and
barriers, as well as trench support systems.
Assess site for prior excavations and consider their impact on the new excavation.
Conduct a site hazard and safety assessment prior to commencement of any excavation to
identify all potential hazards.
15.2 LIMITS OF EXCAVATION
Keep the extent of excavation to the minimum possible to allow efficient construction of the
Works while meeting the requirements shown on relevant Design Drawings.
Unless specified otherwise, keep the sides of excavations vertical to at least 150 mm
above the sewer.
Ensure that the minimum cover requirements shown on relevant Design Drawings are
satisfied following any earthworks that may occur in the area of the sewer. This is
particularly relevant in new subdivisions or developments where earthworks are expected
to form roads, driveways, footways and for general shaping of the surfaces. If minimum
cover requirements cannot be achieved, submit a proposal to the Superintendent to
overcome the problem.
15.3 EXCAVATION ACROSS IMPROVED SURFACES
Obtain written permission of the Owner prior to commencing any excavation across
improved surfaces.
If excavation is required across improved surfaces such as pavements, driveways, kerbs
and gutters, where the surfaces cannot be satisfactorily reinstated, use boring in
accordance with Clause 17.12.
For open excavations across improved surfaces, keep the trench width to the minimum
allowed. Saw cut neat straight lines at least 150 mm beyond the outer limits of the
excavation through bitumen, asphalt and concrete. Remove pavers, blocks or brick
pavements by hand, clean them and set them aside for later replacement. Ensure trench
fill is compacted to requirements of Clause 21.1.3.
15.4 EXCAVATION IN ROOT ZONES
Take every precaution to ensure that no undue damage is caused to a tree root system as
a result of excavation for the Works. Excavation for sewer construction by hand or by
boring may be required to protect the root zone.
Cleanly cut all roots 60 mm diameter encountered during excavation.
Do not cut tree roots larger than 60 mm diameter without authorisation of the
Superintendent.
15.5 BLASTING
Use alternative methods of excavation to blasting wherever achievable.
Obtain prior authorisation from the Superintendent, relevant Regulator and affected
Owners of assets within the vicinity before undertaking blasting.
Where authorisation is granted, prepare a blasting plan that includes management of the
blasting and means to be used to satisfy the requirements of AS 2187 and the authorising
parties.
COPYRIGHT
WSA 022002-2.3
170
COPYRIGHT
171
WSA 022002-2.3
COPYRIGHT
WSA 022002-2.3
172
(b)
the Design Drawings have been revised to show the bend or curve details, including
location, angle and methods of achieving deflection.
Ensure that actual details of deflections are accurately recorded on the Work as
Constructed drawings.
COPYRIGHT
WSA 022002-2.3
173
(b)
Manually (not mechanically) cold bending flexible pipes in circular arcs of uniform
radius to exceed the minium prescribed radii specified in Table 17.1. Limit cold
bending to DN 150 and DN 225 pipe sizes only. Do not cold bend SCJ PVC pipe
where branch sewers or property connection branches are to be installed along the
curve. Curves formed by cold bending the pipes should be designed.
(c)
Curve type
Cumulative
deflection at
joints
Manual cold
bending
Manufactured
bends
Material and
joint
Pipe size
Pipe length
DN
Deflection
at joint
Minimum horizontal
and vertical curve
radius
m
VC
Socket - Spigot
Yes
100 1400
Up to 2.5
varies with DN
Note 1
VC
polypropylene
coupling
Yes
100 300
Up to 2.5
varies with DN
Note 1
PVC
elastomeric seal
jointed (RRJ)
Yes
100 375
3.0 6.0
Note 1
Profiled wall PE
Socket - Spigot
Yes
375 2100
2.4 6.0
Note 1
PVC
solvent cement
jointed
No
100 300
PE
welded joints
SDR 21
No
160 355
Not dependent
Not dependent
0.3 X DN
o
0.02 X DN at T 20 C
0.05 X DN at 0 o C
Note 2
PVC
Yes
RRJ only
100 375
Not dependent
Note 3
GRP
Yes
300 1200
Not dependent
Note 3
Profiled wall PE
Yes
Up to 1500
Not dependent
Note 3
PVC variable
bend
No
150 225
Not dependent
0.9
NOTES:
1
The minimum radius for solvent cement welded PVC pipes and welded PE pipes is based upon:
(a)
the deflection that may be achieved without overstressing the pipe or pipe joint; and
(b)
ensuring that the necessary restraint of the pipe and joints around the curve is readily
achievable based on manually cold bending the pipe in the field.
Refer to Water Agency for minium acceptable radii for manufactured bends.
COPYRIGHT
WSA 022002-2.3
174
(b)
175
(c)
(d)
WSA 022002-2.3
Where trench de-watering is necessary, fully place and compact embedment and fill
material in accordance with Sections 20 and 21 while dewatering systems are operating.
Some materials such as PE have a density less than that of water and sewers can float
even when full of water.
17.5 TRENCH STOPS
Construct trench stops with trench drainage as specified.
Reference: Standard Drawings SEW1206 and SEW1207.
17.6 BULKHEADS
Construct concrete bulkheads with trench drainage as specified. Do not position the
bulkhead directly beneath a kerb.
Reference: Standard Drawings SEW1206 and SEW1207.
17.7 PROPERTY CONNECTION SEWERS
Install property connection sewers as specified.
Ensure tolerances for position, level and plumb are within the limits specified in Section 23.
Fill and compact as specified for the reticulation sewer.
Where concrete surround or encasement of a riser is specified, allow a minimum of 16 h
for the concrete to set before constructing a property connection sewer.
Locate vertical drops or risers to prevent damage to the sewer and provide support to
maintain their position during encasement or backfilling.
Mark locations of property connection points by placing a marking tape from the connection
point to a hardwood surface peg or by using detectable marking tape similarly placed.
Reference: Standard Drawings SEW1105, SEW1106, SEW1107, SEW1108, SEW
1109, SEW1314 and SEW1316.
17.8 DEAD ENDS
Terminate sewer lines as specified.
Reference: Standard Drawings SEW1109 and SEW1316.
17.9 MARKING OF PROPERTY CONNECTION SEWERS AND DEAD ENDS
Mark the position of each dead end and location of each property connection point using
identification tape and hardwood peg or by using a detectable tape.
Reference: Standard Drawings SEW1107 and SEW1109.
17.10 CORROSION PROTECTION OF CAST IRON
Sleeve uncoated buried cast iron items with polyethylene, fixed with PVC tape complying
with AS 3680. Install sleeving to AS 3681. Do not allow sleeved items to be exposed to
sunlight for more than seven (7) days.
Sleeving may be omitted for items that have a thermal-bonded polymeric external coating
complying with specified requirements in Part 2 of the Code.
Cast iron includes grey cast iron and ductile (cast) iron.
COPYRIGHT
WSA 022002-2.3
176
(b)
(c)
(d)
(e)
Lay the tape over the embedment to form a continuous connection between access cover
frames. Strip the ends of the tape to expose its conducting wires. Connect bare wires to a
nut or bolt of the access cover frame to form an electrical connection.
Reference: Standard Drawing SEW1201.
17.12 BORED PIPES UNDER ROADS, DRIVEWAYS AND ELSEWHERE
Construct bored sewers under roads, railways, driveways, footways and elsewhere of the
type, size and locations shown in the Design Drawings.
Construct encasing pipe as detailed in the Design Drawings. Where grouting of the annulus
between the encasing pipe and sewer is specified, commence grouting from the downhill
end of the bore. Check that the applied pressure will not cause buckling of the main.
Achieve full penetration and complete filling of the void.
Insert plastic slippers between the sewer and the bored hole in accordance with the
manufacturers directions.
Place buffer rings between VC and reinforced concrete pipes that are pushed into bores.
Reference: Standard Drawings SEW1400, SEW1401, SEW1402 and SEW1403.
17.13 AQUEDUCTS
Construct aqueducts of the type, size and locations shown in the Design Drawings.
Install protection grills and apply corrosion protection as specified.
Reference: Standard Drawings SEW1404 and SEW1405.
17.14 BRIDGE CROSSINGS
Construct bridge crossings of the type, size and locations shown in the Design Drawings.
Reference: Standard Drawing SEW1406.
17.15 PLASTICS-LINED RC PIPE JOINTING
17.15.1 General
Protect the protruding plastic lining flaps of precast pipes from sharp changes in flap
direction due to contact with adjoining pipes or due to poor pipe handling or installation
practice.
COPYRIGHT
177
WSA 022002-2.3
Install pipes that have been plastics-lined over less than 360 of internal pipe
circumference so that unlined pipe inverts are aligned continuously along the invert of the
installed sewer.
17.15.2 Plastics lining work protection
Protect from damage all plastics linings, PVC sheets and accessories to be field jointed
and maintain in a clean dry condition free of mortar and other foreign materials for the
duration of the jointing process. Do not allow the discharge of sewage or site water into or
through plastics-lined components to be field jointed prior to completion and acceptance of
the joint work by the Superintendent.
17.15.3 Field jointing
Conduct plastics lining, rigid PVC sheet and accessory field jointing following the
installation of precast plastics-lined concrete products.
Joint the plastics flap at the spigot end to the plastic lining of the previously laid pipe by
welding.
Complete jointing work prior to hydrostatic testing and backfilling of plastics-lined pipeline
components.
17.15.4 Plastics lining ancillary work
17.15.4.1 Alignment of lining keys
In order to facilitate drainage of fluid accumulations between structure and lining, vertically
align plastics-lining keys for embedment of lining into in-situ vertical concrete structural
components.
17.15.4.2 Provision of seepage channels
Provide vertical seepage channels between plastics lining and precast or in-situ concrete
components, which do not have vertically disposed keys, as specified.
17.15.4.3 Use of jointing accessories and adhesives
In accordance with the plastics lining manufacturers printed specification, provide for
continuity of plastics lining, including accessories, adhesives and jointing compounds, at
changes of direction, lining returns and jointing of lined components.
17.16 WELDING OF STEEL PIPELINES
17.16.1 General
Weld steel pipe in accordance with Category SP of AS/NZS 1554.1 employing welders
qualified in accordance with AS/NZS 1554.1.
Pre-qualify all weld preparations in accordance with AS/NZS 1554.1.
Inspect all welding in accordance with AS/NZS 1554.1, Section 7.
Apply corrosion protection to welded joints, internal and/or external, where specified.
Reinstate cement mortar linings as specified.
Reference: Standard Drawings WAT1400 to WAT1404 inclusive and WAT1408 of
WSA 03.
17.16.2 Field welding of flanges
Weld flanges either directly to the pipe or fitting after machining or to a coaming piece that
can be subsequently butt welded to the pipe or fitting.
Align flanges at right angles to the axis of the pipe or to the relevant leg of the fitting.
Attach flanges by one of the following procedures depending on steel plate thickness:
COPYRIGHT
WSA 022002-2.3
178
(a)
Where the pipe or fitting is 10 mm thick, weld the flange in accordance with AS 4041
Figure 3.24.4.8(H)(a) Type 6 slip-on weld.
(b)
Where the pipe or fitting is >10 mm thick, weld the flange in accordance AS 4041
Figure 3.24.4.8(B) Type 2 face and back or Figure 3.24.4.8(D) Type 3A bore and
back.
COPYRIGHT
179
WSA 022002-2.3
WSA 022002-2.3
180
Complies with the plastics lining material manufacturer's printed instructions for
incorporation of lining into in-situ concrete.
(b)
Facilitates embedment of plastics lining keys and of rigid PVC or PE invert channel
ribbing into the plastic concrete.
(c)
Facilitates compaction of and entrained air release from plastics lined concrete in the
plastic state by means of suitable concrete compaction equipment.
(d)
Ensures removal of all concrete mortar from lining areas to be jointed or welded while
the concrete is in the plastic state.
COPYRIGHT
181
WSA 022002-2.3
COPYRIGHT
WSA 022002-2.3
182
COPYRIGHT
WSA 022002-2.3
183
(b)
Comply with the Purchase Specification for embedment materials as nominated in the
Design Drawings or Specification.
TABLE 20.1
MAXIMUM PARTICLE SIZE
Pipe size
DN
mm
100
10
>100 to 160
14
>160
20
only use in situations where embedment material is non-cohesive (i.e. no clays) and
the surrounding native soil and the embedment material are completely free draining;
(b)
only use beneath non-trafficable areas where compaction trials have been
undertaken and proven successful; and
COPYRIGHT
WSA 022002-2.3
(c)
184
the diameter of the pipe being the same as that used in the pre-qualification test;
(b)
the actual embedment material used in construction being the same as used in the
pre-qualification test;
(c)
(d)
COPYRIGHT
185
WSA 022002-2.3
Provide rubber-ring jointed pipe "shorts" 6001000 mm long immediately upstream and
downstream of the concrete embedment or encasement to allow for differential movement.
Reference: Standard Drawings SEW1204, SEW1205, SEW1208, SEW1400, SEW
1401 and SEW1402.
COPYRIGHT
WSA 022002-2.3
186
21 FILL
21.1 TRENCH FILL
21.1.1 General
Place trench fill as specified. Use appropriate methods of compaction to achieve the
compaction requirements of the Design Drawings and Specification.
Avoid impact loading of the sewer during placement of trench fill material.
Do not place trench fill material within 24 h of placing embedment or encasement concrete,
or longer period if shown in the Design Drawings or Specification.
Fill voids behind timber ground support in close-timbered tunnels, drives and shafts by
pressure grouting or other authorised means.
Raise the fill evenly around MH and MS risers and compact in shallow layers to avoid
unbalanced lateral loading.
Take special care to prevent displacement of access cover assemblies or supports.
Correct any deficiencies of trench filling exposed by settlement.
Reference: Standard Drawings SEW1201, SEW1202, SEW1203, SEW1204 and
SEW1205.
21.1.2 Material requirements
The trench fill material shall comply with the Specification and relevant Design Drawings.
Where the filled trench will be subjected to traffic loading, the fill material shall comply with
the requirements of the road Owner. In the absence of a directive, use one of the following:
(a)
Compaction sand; or
(b)
(c)
75 mm crushed rock.
COPYRIGHT
187
WSA 022002-2.3
Prepare the foundation for the fill by cleaning away all debris, vegetation, organic
material and topsoil for the full width of the fill area.
(b)
Compact the cleared soil surface to not less than 95% of its standard maximum dry
density (AS 1289.5.1.1).
(c)
Place the fill in layers not exceeding 200 mm thickness and compact each layer to
not less than 95% of its standard maximum dry density (AS 1289.5.1.1). Bring the
compacted fill level up to a height of at least 300 mm above the design level of the
top of the pipe.
(d)
Place the remainder of the fill in layers not exceeding 300 mm thickness and compact
each layer to not less than 95% of its standard maximum dry density (AS 1289.5.1.1).
(b)
(c)
COPYRIGHT
WSA 022002-2.3
188
22 ACCEPTANCE TESTING
22.1 GENERAL
Acceptance testing is required to test the capability of the sewer assembly to satisfy design
requirements as specified. It is not intended to test the material capability. Testing is
intended to:
(a)
(b)
(c)
Confirm the success of placement and compaction of pipe embedment and trench fill,
design and placement of thrust and anchor blocks and installation of pipeline
components.
Undertake acceptance testing of all sewers and structures in accordance with the
Specification and in the following order:
1
Visual inspectionabove-ground.
Compaction testing.
Infiltration testing.
Deflection testing.
CCTV inspection.
WSA 022002-2.3
189
the allowable bearing pressure of the native ground is 50 kPa when assessed in
accordance with SEW1200;
(b)
pipe laying and embedment compaction was carried in accordance with this Code;
and
(c)
Test method
Trafficable areas
Non-trafficable areas
Non-cohesive
(Note)
70
70
Cohesive (Note)
95
95
NOTE: Type 3 support of SEW1202 requires non-cohesive embedment material. Cohesive graded
sands and gravels may be authorised by the Water Agency.
COPYRIGHT
WSA 022002-2.3
190
TABLE 22.2
EMBEDMENT OF RIGID PIPES
MINIMUM COMPACTION
Embedment type
Test method
Minimum value
Trafficable areas
Non-trafficable areas
Non-cohesive
Density Index (I D )
AS 1289.5.6.1
60
60
Cohesive
(Notes 1, 2)
Density Ratio (R D )
AS 1289.5.4.1 and
AS 1289.5.1.1
90
90
NOTES:
1
Graded gravels or sands having fines (silts and clays) greater than 5% have their compaction
determined by dry density ratio.
Type 1 and 2 supports on SEW1202 permit cohesive material at the side of the pipe above the
support material.
COPYRIGHT
WSA 022002-2.3
191
TABLE 22.3
TRENCH / EMBANKMENT FILL OF RIGID AND FLEXIBLE PIPES AND MAINTENANCE
STRUCTURESMIMIMUM COMPACTION
Minimum value
Fill type
Test method
Trafficable areas
(Note 2)
Non-trafficable areas
Non-cohesive
Density Index (I D )
AS 1289.5.6.1
70
60
Cohesive
Density Ratio (R D )
AS 1289.5.4.1 and
AS 1289.5.1.1
(Note 1)
95
90
(Notes 3, 4, 5)
NOTES:
1
Graded gravels and sands having fines (silts and clays) greater than 5% shall have their
compaction determined by dry density ratio.
the backfill zone higher degrees of compaction is required in the zones closer to the
surface; and
(ii)
the road type freeways and arterial roads carrying greater loads require higher
degrees of compaction.
The value given is a default where excessive initial surface settlement is not permitted.
Specification of alternative degrees of compaction of the trench fill in non-trafficable areas
depends on the site requirements.
Compaction shall be to the degree specified in the project Specification or the default value in
Table 22.3 if not specified.
COPYRIGHT
WSA 022002-2.3
192
For trenches located in a non-trafficable zone, conduct one test in each 900 mm layer of fill
and each 1200 m2 or part thereof.
The Superintendent may carry out random confirmatory tests.
22.3.5.5 Retesting
If one or more of the initial test results do not comply with Table 22.3, conduct two
additional tests in the area of that layer of fill represented by the initial test. If one or more
of the repeat tests does not comply, recompact the full zone and continue repeat testing.
Continue this cycle until the trench fill compaction test results comply with Table 22.3.
22.4 AIR PRESSURE AND VACUUM TESTING OF SEWERS
22.4.1 General
Pressure testing, either low pressure air testing or vacuum testing, is only qualitative as
pressure losses do not directly reflect water leakage rates. It is used to identify points of
leakage and potential pipeline infiltration and exfiltration due to damaged pipe seals and
joints.
Vacuum or air pressure test all sewers DN 1500 in accordance with Clauses 22.4.2.1 or
22.4.2.2. Include external MH drops, property connection sewers, vertical risers, MSs and
inspection shafts and fittings.
Undertake vacuum tests where the Specification does not specify the test method.
Test after placement and compaction of pipe embedment, including overlay.
Make calibration certificates for all air pressure and vacuum testing equipment available to
the Superintendent on request.
Sewers DN 750 should be inspected and tested during construction and before the
construction of MHs. The test may be conducted after trench filling but repair / rectification
costs would almost certainly be greater.
22.4.2 Air testing methods for sewers
22.4.2.1 Vacuum testing
Plug all sewer inlets and outlets and cap and seal all MS risers in the test length of sewer.
Apply an initial test vacuum pressure (negative pressure) of approximately 27 kPa. Close
the valve on the vacuum line and shut off the vacuum pump. Allow the air pressure to
stabilise for at least 3 minutes to identify any initial leakage.
When the pressure has stabilised and is at or below the starting test vacuum of 23.6 kPa,
commence the test by allowing the gauge pressure to drop to 23.6 kPa, at which point
initiate time recording. Record the drop in vacuum over the test period.
Accept the length of sewer under test if the test vacuum loss is 7 kPa for the relevant time
interval specified in Table 22.4.
If the sewer fails the test, re-apply the vacuum to identify any leaks.
Rectify all defects prior to conducting any further testing.
Rectify any visible or audible faults even if the vacuum testing is satisfactory.
This test method is based on ASTM test method C1214M, which may be downloaded from
www.astm.org/cgi-bin
COPYRIGHT
WSA 022002-2.3
193
TABLE 22.4
PRESSURE AND VACUUM AIR TESTING
ACCEPTANCE TIMES FOR 7 KPA PRESSURE CHANGE
Test length
m
Pipe size
DN
50
100
150
200
250
300
2
3
2
3
2
3
2
5
3
6
3
6
225
300
375
4
6
7
5
9
14
8
14
22
10
18
29
13
23
36
15
29
43
450
525
600
10
14
18
21
28
37
31
42
55
41
56
73
52
70
92
66
86
106
675
750
900
23
29
41
46
57
83
70
86
124
93
115
165
116
143
207
144
168
243
1000
1050
1200
51
56
73
102
112
147
153
169
220
204
225
294
255
281
367
300
319
460
1500
115
230
344
459
574
700
NOTES:
1
Timing of the test duration shall commence after the 3 minutes initial
period.
Test duration times for other combinations of pipe size and test length
may be interpolated.
COPYRIGHT
WSA 022002-2.3
194
COPYRIGHT
WSA 022002-2.3
195
TABLE 22.5
CONCRETE MH TESTING FREQUENCY
Number of each type
of MHs in the project
Pre-cast concrete
100%
6 to 10
50%
20%
11 to 20
33%
>20
25%
TABLE 22.6
MINIMUM TEST TIMES FOR CONCRETE MHs
MH Depth
MH Diameter
mm
900
1050
1200
1500
1800
Time*
m
2.4
14
17
20
26
33
3.0
18
21
25
33
41
3.7
21
25
30
39
49
4.3
25
30
35
46
57
4.9
29
34
40
52
65
5.5
32
38
45
59
73
6.1
35
42
50
65
81
6.7
39
46
55
72
89
7.3
42
51
59
78
97
7.9
46
55
64
85
105
8.5
49
59
69
91
113
9.1
53
63
74
98
121
COPYRIGHT
WSA 022002-2.3
196
(b)
(c)
di
Some product standards do not accurately specify internal diameters. Appendix G lists
default prover diameters for common sewer pipe materials.
22.6.3 Flexible sewers DN 300
Test all flexible gravity sewers DN 300 except where single size granular embedment
(Type 3 support of SEW1202) has been used or where a pre-qualified embedment
compaction method was used in accordance with Clause 20.3.2.
22.6.4 Flexible sewers >DN 300
22.6.4.1 General
Test all flexible gravity sewers >DN300 to determine any excessive pipe deflection.
Measure the actual short-term vertical deflection in accordance with Clause 22.6.4.2 or
Clause 22.6.4.3 as appropriate. Accept sewers with deflection values less than those given
in Table 22.7.
Record locations where the measured or calculated deflection exceeds the maximum
allowable deflection stated in Table 22.7.
Repair all sections of pipe that exhibit excessive deflection. Retest each repaired section in
accordance with Section 22.
COPYRIGHT
WSA 022002-2.3
197
TABLE 22.7
MAXIMUM ALLOWABLE SHORT-TERM PIPE DEFLECTIONS
Maximum allowable short term vertical pipe deflection
Pipe material
%
3 d*
7 d*
14 d
30 d
3 months
1 yr
3.8
4.3
4.8
5.0
5.5
GRP
3.0
3.4
3.8
4.0
4.4
4.8
0.8
0.9
1.0
1.0
1.1
1.2
No cement mortar
lining
2.3
2.6
2.9
3.0
3.3
3.6
1.5
1.7
1.9
2.0
2.2
2.4
Elastometric joint
0.8
0.9
1.0
1.0
1.1
1.2
Plastics
Metallic
Ductile iron
Steel
Welded joint with:
immediately after the pipe embedment has been placed and compacted; and
(b)
not less than 14 days after placement and compaction of the trench fill.
(c)
WSA 022002-2.3
198
(b)
Only accept CCTV videotapes of such quality that an accurate assessment of the
internal condition of the sewer can be made.
(c)
COPYRIGHT
199
WSA 022002-2.3
WSA 022002-2.3
200
5% of the test head and 5% of each other. Use the gauge recording the lower of the two
readings. Before testing, clean the syphon and then slowly fill it with water, ensuring that
air has been completely expelled.
With the exception of polyethylene, which is to be tested in accordance with WSA 01
2001, test all syphons as follows:
(a)
Install blank flanges or caps at each end of the test section. Do not test against
closed valves unless they are fully restrained and it is possible to check for leakage
past the valve seat. Temporarily strut or anchor mechanical ends that are not end
load resistant to withstand the test pressures without movement.
(b)
Clearly inform all personnel of the loading limits on temporary fittings and supports.
(c)
Pressurise the line to 75% of the test pressure and leave for a minimum of 12 hours.
The preliminary pressurisation is intended to:
(i)
(ii)
(iii)
(d)
Provided there is no obvious leak in the syphon, steadily raise the pressure in the
syphon until the specified test pressure is reached.
(e)
Maintain the test pressure for four (4) hours. Measure and record, at half hour
intervals, the quantity of water added in order to maintain the pressure during the
period of testing.
(f)
Visually inspect the line for leaks if practicable. If a leak is suspected but is not
visible, use aural or electronic assistance.
(g)
Do not remove temporary supports until the syphon has been depressurised.
(h)
Dispose of test water in accordance with the relevant environmental Regulator and
Water Agency requirements.
There is no failure of any thrust block, anchor block, pipe, fitting, valve, joint or any
other pipeline component;
(b)
(c)
The measured loss rate for the relevant test period of the pressure testing does not
exceed the maximum allowable loss rate as determined in accordance with Clause
22.9.3; and
(d)
(b)
201
WSA 022002-2.3
If both additional tests pass, accept the syphon. If one or both of the additional tests fail,
rectify the work.
Within two weeks of the completion of any rectification work, perform another test on the
syphon. If the test fails, rectify the work and retest. Rework until all test results are
satisfactory.
COPYRIGHT
WSA 022002-2.3
202
Structures 100 mm lateral displacement from the design sewer alignment; and
200 mm displacement (from the design position) along the sewer axis.
Junctions
100 mm displacement (from the design position) along the sewer axis.
COPYRIGHT
WSA 022002-2.3
203
TABLE 23.1
SEWER GRADE TOLERANCES
Category
Design grade
Flat grades
1.0%
(less than or equal to 1 in 100)
Flat to
moderate
grades
>1.0% 5.0%
(greater than 1 in 100 and)
(less than or equal to 1 in 20)
Moderate to
steep grades
>5.0%
(greater than 1 in 20)
TABLE 23.2
PROPERTY CONNECTION SEWER GRADE TOLERANCES
Category
Design grade
DN 100
1.65%
(1 in 60)
DN 150
1.2%
(1 in 83)
(b)
(b)
COPYRIGHT
WSA 022002-2.3
204
Exposure of the existing MH inlet or sewer to allow ready access for the connection
to be made or, where specified, inserting a junction or construction of a new
maintenance structure over the existing sewer.
(b)
(c)
(d)
Supply of authorised trench fill material in the case of road works or where additional
compaction is required.
(e)
Traffic control to allow safe passage of pedestrians, vehicular traffic and various
plant.
(f)
COPYRIGHT
205
WSA 022002-2.3
25 RESTORATION
25.1 GENERAL
The requirement to restore surfaces shall apply to construction by means of trenching,
tunnelling or boring.
Restore to pre-existing condition, all surfaces, services and/or improvements disturbed,
destroyed, removed or damaged during construction of the Works and/or during installation
of temporary Works such as access roads to the requirements of the Water Agency and
the Owner(s).
The Water Agencys relationship with its customers may be significantly enhanced by
providing excellent service, particularly in the area of site restoration. Consequently, there
is an expectation that restoration should be to the highest standards.
The site shall be:
(a)
Kept in a safe, clean and tidy manner during construction; unsightly items such as
spoil stockpiles and barricades shall be kept to a minimum; site debris and excess
materials shall be regularly cleaned up, removed and properly disposed.
(b)
(c)
25.2 PAVEMENTS
Immediately the filling of a trench excavation through a pavement has been completed,
restore the pavement to a trafficable condition. Where the initial restoration is of a
temporary nature, use a pre-mixed asphaltic material.
Maintain temporary restoration until final restoration is carried out. Carry out final
restoration of the pavement to restore both pavement and sub-base to no less than their
pre-existing condition. If appropriate, remove temporary restoration when carrying out final
restoration work.
After their initial temporary restoration, maintain pavements of other than bitumen or
concrete with crushed metal, gravel or equivalent material, making due allowance for
consolidation, and then restore to a condition equivalent to that of the original pavement.
Complete the final restoration of bitumen and concrete pavements within one (1) month of
temporary restoration.
25.3 LAWNS
Reinstate lawns with turf sods cut and set aside from the original surface or with similar turf
imported for the purpose. To make up any deficiencies between the stripped quantity and
the quantity required for reinstatement, use imported topsoil consisting of a sandy loam of
light to medium texture, containing 5% to 10% by weight of humus, and free of weeds.
For areas to be turfed, ensure topsoil is graded to achieve a smooth surface, is free from
lumps, stones or other debris, conforms to finished levels, blends gradually into the
adjoining undisturbed ground and finishes flush with kerbs, footways and other paved
surfaces.
Incorporate into the topsoil at the rate of 40 g/m a fertiliser mix with a nominal
Nitrogen:Phosphorus:Potassium ratio of 10:4:6.
25.4 GRASSED AREAS
For grassed areas that are not lawns, restore by replacing the pre-existing topsoil and
maintaining the disturbed area in a condition that will promote the re-growth of pre-existing
grasses.
COPYRIGHT
WSA 022002-2.3
206
Alternatively, replace pre-existing topsoil with clean topsoil and seed the affected area with
grass seeds or re-plant with runners of the varieties prevalent in the immediate area.
Should re-growth of grass fail to occur, repeat the process until re-growth is established.
25.5 BUSHLAND
Carry out all works in accordance with the requirements of the environmental Regulator.
Restore the works area as near as practicable to the pre-existing condition and leave the
site in such condition as will promote the rapid re-growth of native bush plant species
prevalent in the immediate vicinity.
Return the topsoil to its pre-existing location and place it in such a way that erosion will be
minimised, eg by the use of small contour banks.
Use the pre-existing vegetation as a seed source where possible. Upon backfilling of the
line and spreading of topsoil, replace the pre-existing vegetation over the line, placing
branches and logs across slope to intercept runoff.
Do not use imported topsoil in native bushland areas.
Employ a qualified bush regenerator to control weeds for a period of 2 years following
restoration.
Only local native species are to be used in revegetation of disturbed sites. On steep
slopes, use jute mesh and plantings to stabilise the soil.
25.6 PROVISION FOR SETTLEMENT
Through other than pavements, lawns or other improved surfaces, place trench fill
sufficiently high to compensate for expected settlement. Subsequently, carry out further
filling or trim the original trench fill, in order that the surface level of the completed trench
conforms to the adjacent surface.
Remove all surplus material and dispose of without breaching applicable regulations or
laws and do not be dispose of on any property without the property owners written
permission.
Within public or private property where the reasonable convenience of persons requires
trenches to be levelled off at the time of filling, make any subsequent settlement good as
necessary by placing and compacting additional fill. With the written consent of the Owner,
their agent or lessee, dispose of surplus material by spreading neatly in the vicinity of the
trench in such a way as to minimise further erosion of the backfill and adjacent ground
surfaces.
25.7 MAINTENANCE OF RESTORED SURFACES
Maintain all restored surfaces and improvements in a satisfactory condition until the end of
the defects liability period.
COPYRIGHT
207
WSA 022002-2.3
COPYRIGHT
WSA 022002-2.3
208
DN
PVCsolid wall
PVCprofile wall
PVCsandwich wall
GRP
150
140
152
139
NA
225
220
223
218
NA
300
278
299
276
310
375
354
358
NA
386
NOTES:
1
2 Applies to solid wall, profile wall and sandwich construction PVC pipes conforming to
AS/NZS 1260 and GRP pipes conforming to AS 3571, external diameter series
(centrifugally cast).
3 Where the inside diameter of fittings (eg junctions, bends) is less than the pipe
internal diameter, the pull-through prover method of testing may not be valid.
COPYRIGHT