Beruflich Dokumente
Kultur Dokumente
TESTING OF CONSTRUCTION
EQUIPMENTS AT SITE
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 1 OF 11
INDEX
Sl.
No.
Procedure
No.
Revision
No.
Name of Procedures
Effective
Date
01.
FT 01
00
11.08.97
02.
FT 02
00
11.08.97
03.
FT 03
00
INSPECTION OF HAND
OPERATED CHAIN PULLEY
BLOCK
11.08.97
04.
FT 04
00
11.08.97
05.
FT 05
00
11.08.97
06.
FT 06
00
11.08.97
07.
FT 07
00
11.08.97
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 2 OF 11
Scope
The procedure detailed herein covers the physical inspection of wire ropes for
ascertaining the fitness and capabilities for use.
2.0
Aim
3.0
Inspection Details :
3.1
A complete and through examination of all wire ropes must be made prior
of use
3.2
3.3
Test report as per format (refer to Annexure 2) shall be prepared for all
wire ropes once in a year.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 3 OF 11
ANNEXURE - 1
Replace rope if there
6 or more broken
3 or more broken
strand in one lay
3 or more broken
in standing ropes
are
wire in one lay
wires in one
wires in open lay
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 4 OF 11
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 5 OF 11
Wire breaks occuring near attached fittings are due to fatique stresses concentrated in
these localised section. Replacement of the rope or renewal of attachment by
eliminating fatiqued area suggested.
2.
The rope must be replaced if this wear exceeds 1/3 of the diameter of the wire.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 6 OF 11
4.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 7 OF 11
Rope Stretch
Severe stretch or elongation of rope is also a deterioration factor. All wire ropes will
stretch during their initial periods of use. This is caused by the tightening or wires and
strands in to their respective cores.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 8 OF 11
Corrosion
Corrosion develops inside the rope before any evidence is visible on rope surface.
High Stranding
Replace the rope or renew the end connection to reset the rope lay.
7.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 9 OF 11
These conditions occur when there are multiple layers on the drum and are dangerous
due to wire deformation. Replace the rope.
11.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 10 OF 11
If there is any evidence of heat damage, resulting from torch or are caused by
contact with electrical wire, or by welding.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 11 OF 11
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 12 OF 11
SCOPE :
The test procedure herein covers the physical inspection / tests which are to be
done at site, for ascertaining the fitness for use.
2.0
AIM :
- To assess that pulling and lifting machine is capable of handling rated load for
pulling and lifting.
- Rope gripping mechanisms will prevent self lowering of the lad and arrest /
sustain the load in all working conditions.
- To ensure satisfactory operation of all components of machine, and associated
fittings.
3.0
INSPECTION :
Thorough and complete examination of equipment and accessories should be
done prior to use.
Defective components to be attended/replaced incase listed conditions are not
met.
3.1
WEAR TEST :
- Check the wear on jaws in following manner.
The procedure mentioned, herein, is to be carried out without the dismantling of
machine.
- Refer to sketch as enclosed in Annexure 1
Make on one side of casing the position of rope release handle P in its closed
position in without any rope in the machine.
Insert the rope into the machine and close handle = P =
Put another mark on same side of casing
Measure distance between the two marks.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 13 OF 11
3.3
Inspect the rope as per procedure for inspection of wire ropes (rofer to PN-FEX
002 00 944 FT01), Prior to use. Replace, if required.
3.4
Fill the test report as per format as enclosed in Annexure Z, once in a year
ANNEXURE I
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 14 OF 11
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 15 OF 11
ANNEXURE 2
1.0 Site 2.0 Date of Testing .
3.0 Next Due Date Off Inspection
4.0 Machine Details
4.1 Identification
No.
4.2 Make .
4.3 Nominal Capacity :
Pulling Lifting
Ok/Not/Ok
Recommended .
Not Recommended
..
Engineer (Material
Engineer (QAE)
Engineer (Erection)
Management)/Custodian
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 16 OF 11
SCOPE :
Procedure herein covers, physical inspection and and site test to be conducted before
chain pulley block is declared fit for use.
2.0
AIM :
INSPECTION DETAILS :
3.1
The coplete chain pulley block assemblyis mounted on asitable frame capable of
wihstanding caombined load of pulley block, accessories / fittings and rated
load.
3.2
Load chain should be inspected link by link regularly prior to use for eleogation,
distortion, twists, cracks, cuts, or other deformaties.
Hand wheel chain is completely dry, free from deformities kinks & cute etc.
3.4
3.5
Lubrication :
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 17 OF 11
3.5.2 Pulley Block assembly is lubricated properly at all recommended points and to
be checked for smooth operation prior to loading.
3.6
3.7
4.0
LOAD TEST
4.1
4.2
Test load equivalent to rated lifting capacity of pulley block is selected and
placed directly under the hook with necessary load chain anchorages, associated
fittings. Load is lifted vertically to height of approximately one meter. The load is
held in such condition of sufficient time as to ensure that the load brake is
effective and is capable of preventing self lowering of the load. The load is then
lowered.
4.3
The machine is thoroughly inspected after load test for deformation, cracks,
flaws other defects.
4.4
5.0
ACCEPTANCE :
The Hand Operated Chain Pulley Block is considered fit for use, if meets the
criterions listed above.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 18 OF 11
ANNEXURE 2
1.0
Site ...
2.0
3.0
Equipment Details :
Serial No
Rated Capacity .
Make ..
Chain Spec ..
4.0
4.1
4.2
4.3
4.4
4.5
5.0
OPERATION
Ok/Not Ok
Ok/Not Ok
7.0
Recommended /
Not Recommended
______________________
Engineer (Matl. Management)/
Custodian
____________
Engineer
(QUE)
__________________
Engineer (Erection)
1.0
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 19 OF 11
SCOPE
AIM :
The test shall be conducted to ensure that the welding generator is in sound
condition electrically and mechanically and is in working order in all respects.
3.0
INSPECTION :
3.1
3.2
Ensure that metallic parts and surfaces of the asembly are suitable
protected against corrosion.
3.3
Clean the machine be from dust and dirt particularly incase the machine
has not been in use for sometime.
3.4
3.5
3.6
3.7
3.8
3.9
3.10
TESTS :
4.1
Insulation test :
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 20 OF 11
4.3
No Load test :
The machine is switched on the see that the same is in operating condition.
Input side is connected to the supply voltage and output side is open circuited.
Measure open circuit voltage with regulator at minimum position and at
maximum position. Check the linear increase and decrease in output voltage.
The output circuit voltage shall be compared with the specified rating of the
machine. It may vary from 40 to 90 V DC.
4.4
Check the vibration and bearing sound when the machine is running at no load
and at full load.
4.5
Loat Test :
The generator output terminals are to be connected to suitable test welding
load. With the generator running at the rated speed the welding current shall be
measured at specified load voltage by suitably adjusting the regulator.
The relation between welding load voltage and welding current within the range
of the welding generator shall be in accordance with the formula.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 21 OF 11
U=20+0.04 I
Where U is the load voltage is Volts and
I is the load current in ampere
However the variation in load voltage within +/-10 perc. Shall be accepted.
5.0
6.0
IR test should be repeated if the machine is kept unused for more than a month
or the same is exposed to moisture/water during rainy season.
7.0
ACCEPTANCE :
The machine shall be accepted as fit for use at site in case above listed criterions
are satisfied.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 22 OF 11
ANNEXURE 2
1.0
Site
2.0
Date of Test
3.0
Equipment Details ..
Machine Serial No. ..
Make
Type .
Model ..
Capacity ..
Range
4.0
Physical Inspection .
OK/NOT OK
4.1
OK/NOT OK
4.2
Earthing ..
OK/NOT OK
4.3
Lubrication ..
OK/NOT OK
5.0
Insulation Test .
OK/NOT OK
5.1
5.2
5.3
5.4
Continuity of Coils
OK/NOT OK
6.0
No load Test ..
OK/NOT OK
6.1
Regulator at Max
8.0
Yes/No
Load Test
Sl.No.
Welding Current
Voltage
Electrode Size
Remarks
1.
_____________
________
____________
_________
2.
_____________
________
____________
_________
3.
_____________
________
____________
_________
______________________
Engineer (Matl. Management)/
Custodian
Accepted/Not Accepted
____________
Engineer
(QUE)
__________________
Engineer (Erection)
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 23 OF 11
Scope
The test procedure detailed herein covers the physical inspection/checks/tests to
be done, at site, for deciding that welding transformer is fit for use.
2.0
Aim
The test shall be conducted to ensure that welding transformer is in sound
condition electrically and mechanically and is in working order in all respects.
3.0
Inspections/Checks
3.1
Prior to conducting any test on the machine, it may be ensured that two
separate and distinct connections to earth all metallic parts, which are not
intended to carry current, are provided.
3.2
Clean the machine of dust and other dirt particularly, incase machine has not
been in use for some time.
3.3
Ensure that all metallic parts and surface of assembly are suitably protected
against the corrosion.
3.4
3.5
3.6
3.7
Quality of oil for oil cooled transformers must be ensured check for the oil level.
4.0
Tests.
4.1
Insulation Test :
IR value between primary/secondary terminals and earth may be checked with
the aid of specified meggar. The IR value shall not be less than 2 mega ohms.
Use 500 volt meggar.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 24 OF 11
No Load Test :
The machine is switched on to see that the same is in operating condition.
Input side is connected to supply condition, measure open circuit voltage.
The same is compared with the specified rating of the machine.
4.3
Load Test :
The transformer secondary terminals are connected to suitable test welding
load. Then at the different positions of regulator load voltages and currents are
recorded.
The relationship between current and load voltage is established in accordance
with the formula as under.
U=20+0.04 I
Where;
4.4
4.5
IR test may be repeated in case machine is lying idle for more than a month or
exposed to moisture/water.
5.0
Acceptance
The machine shall be accepted as fit for use incase all above listed criterions are
met.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 25 OF 11
ANNEXURE 2
TEST REPORT FOR ARC WELDING TRANSFORMER
1.0
Site : ..
3.0
Equipment Details :
2.0
Date of testing
Physical Inspection :
4.1
4.2
Earthing :
4.3
5.0
Insulation Test :
5.1
Primary Terminal .
5.3
Continuity of Coil :
Ok/Not Ok .
Primary
: .. Ok/Not Ok ..
Secondary
: .. Ok/Not Ok ..
6.0
6.1
6.2
Other Observations : .
7.0
Load Test
8.0
Sl.No.
Welding Current
Voltage
Electrode Size
Remarks
1.
_____________
________
____________
_________
2.
_____________
________
____________
_________
3.
_____________
________
____________
_________
______________________
Engineer (Matl. Management)/
Custodian
____________
Engineer
(QUE)
__________________
Engineer (Erection)
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 26 OF 11
Scope
The test procedure discussed herein covers the details of test/inspection and checks to
be carried out at site for declaring that crane is fit for use.
2.0
Aim :
To check that :
2.1
2.2
3.0
Inspection Details
3.1
3.2
The hook should be visually inspected for deformation. A 15% increase in throat
measurement or a 10% bend should call for hook replacement.
3.3
3.4
3.5
Check the functioning of engine in all respects for starting and shut off.
4.0
Test Procedure :
4.1
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 27 OF 11
No Load Test :
4.2.1 Check the satisfactory operation of each respective crane function inclusive of
respective brakes and clutches operation as under :
Steering
Slewing
4.3
Load test :
4.3.1 All crane functions and operation of all control devices, as mentioned above,
must be repeated with test load available at site.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 28 OF 11
ANNEXURE 2
1.0
Site : ..
2.0
Date of Testing :
3.0
Equipment Details :
Make : .
Serial No. ..
Model :
4.0
Testing Conditions :
4.1
Test load :
4.2
Boom angle : .
4.3
Boom length :
4.4
Operating Radium : ..
5.0
Test Load
5.1.1 Travelling :
Forward : ..
Backward : ..
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Clockwise :
Anticlockwise : .
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
5.2.1 Slewing :
360 #
5.3
Steering :
Left # Forward : ..
Backward :
Right # Forward :
Backward :
Ok/Not
Ok/Not
Ok/Not
Ok/Not
Ok
Ok
Ok
Ok
Ok/Not
Ok/Not
Ok/Not
Ok/Not
Ok
Ok
Ok
Ok
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 29 OF 11
ANNEXURE CONTINUED ..
No Load
Test Load
5.4.1 Derricking :
Boom #
#
Raised : ..
Lowered : .
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
5.6.1 Engine
Starting :
Shut Off :
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
5.7
6.0
______________________
Engineer (Matl. Management)/
Custodian
____________
Engineer
(QUE)
Ok/Not Ok Ok/Not Ok
Ok/Not Ok Ok/Not Ok
Yes/No
__________________
Engineer (Erection)
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 30 OF 11
Scope :
The test procedure detailed herein covers the physical inspection/checks/site
tests to be done for declaring that electrical powered which is fit for use.
2.0
Aim
3.0
INSPECTION DETAILS :
3.1
Prior to conducting any test the wire rope of the which shall be completely
unwound form the drum and visually inspected to ensure that it is fit for use.
(Refer to procedure no. PN : FEX : 002 : 00 : 94 : FT01)
3.2
3.3
3.4
Flexible coupling bolts & rubber bushes should be inspected, prior to use. The
same are to be replaced, whenever found to be in damaged condition.
3.5
The inspection for above listed items, should be repeated after every incidence
of impact loading.
3.6
Oil level in the gear box and thruster motor ect. Is to be ensured, as
recommended by manufacturer.
3.7
3.8
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 31 OF 11
3.9
3.10
Effective earthign should be provided for the hoist structure, motor frame and
other metal cases of all electrical equipment. It is to be ensured that there is no
loose connection in electrical circuit.
3.11
Check the lubrication of open gear, wire ropes, pulleys, motor and rope drum.
4.0
NO LOAD TEST :
The which is to be run idle for about 30 minutes, various parameters viz. Voltage
current, time and rope speed meter per minute may be recorded. While hoisting
and lowering at different notch position as per format enclosed. Observation for
undue noise, overheating of the bearing gear box, motor ect. May be recorded.
5.0
LOAD TEST :
5.1
The load equivalent to rated lifting capacity of the which may be selected. The
test load may be placed directly under a hook with necessary lashing etc. for
lifting purposes.
5.2
HOISTING :
After satisfactory completion of no load operation test load is to be lifted with
series resistance in the first notch position. The load may be lifted to approx 1M
height before switching over to next notch.
The voltage load current, time of operation may be recorded, in the format. The
procedure may be repeated from the last notch to the first notch.
5.3
BRAKE TESTING :
Last notch position may be changed to min. position, when the brake is applied
to check the effectiveness. The load may be held in the lifted position for atleast
for fifteen minues. The stability of load is recorded, as such.
5.4
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 32 OF 11
LOWERING :
Load is lowered by reversing the direction of the drum, after brake testing.
6.0
7.0
Electrical powered which is considered to be fit for use, in case all above listed
criterions are fulfilled.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 33 OF 11
ANNEXURE 2
1.0
Site . 2.0
3.0
Equipment Details :
Make ..
Serial No. : .
..
Capacity :
4.0
Physical Inspection : .
4.1
Ok/Not Ok
4.2
Earthing : ..
Ok/Not Ok
4.3
Ok/Not Ok
4.4
Ok/Not Ok
4.5
Ok/Not Ok
4.6
Ok/Not Ok
4.7
Ok/Not Ok
4.8
Ok/Not Ok
4.9
Ok/Not Ok
4.10
Brake Lining
Ok/Not Ok
Remarks :
.
.
.
BHEL : PS WR
PW : FEX : T & P : TP
PAGE : 34 OF 11
ANNEXURE 1
5.0
Insulation Test :
IR VALUE
5.1
5.2
5.3
6.0
No Load Test :
Sl.
Drum Controller
No.
6.1
6.2
6.3
|.|
.
.
.
7.0
Position
Notch 1
Notch 2
3
||||||||
. 3
. 2
. 1
Current
R
Voltage
B
....
....
....
|
|
|
|
|
|
....
....
....
Drum Controller
No.
7.1
7.2
7.3
|.|
.
.
.
Position
Notch 1
Notch 2
3
||||||||
. 3
. 2
. 1
Current
R
Voltage
B
....
....
....
|
|
|
|
|
|
....
....
....
Remarks :
Record the readings for hoisting and lowering of load separetly.
8.0
______________________
Engineer (Matl. Management)/
Custodian
____________
Engineer
(QUE)
__________________
Engineer (Erection)