Beruflich Dokumente
Kultur Dokumente
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
Section
Revision Description
HOLDS
Hold No.
Section
Description
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
08-02-2011
PAGE NO:
2 of 64
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
08-02-2011
PAGE NO:
3 of 64
ABBREVIATIONS
Abbreviation
Description
ABS
ASTM
CP
Cathodic Protection
DFT
Fe3O4
FPSO
FROSIO
ISO
ITP
Joule
Kv
Kilovolt
m2
Square metre
mm
millimetre
mg/m2
MDFT
MEK
MIO
MPa
Megapascal
MSDS
NACE
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
08-02-2011
PAGE NO:
4 of 64
NaCl
Sodium Chloride
NDFT
Nominal Dry Film Thickness is the dry film thickness specified for each
coat or for the complete paint system
NORSOK
PFP
pH
Measurement of acidity
ppm
RAL
SSPC
tba
To be advised
TLV
TSA
UV
Ultra Violet
v/cm
VOC
WFT
s/cm
micron
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
08-02-2011
PAGE NO:
5 of 64
CONTENTS
INTRODUCTION ...................................................................................... 8
1.1
General ............................................................................................... 8
1.2
Scope.................................................................................................. 8
1.3
DEFINITIONS ......................................................................................... 9
2.1
2.2
3.1
WARRANTY REQUIREMENTS......................................................................15
4.1
General ..............................................................................................15
4.2
5.1
General ..............................................................................................17
5.2
Documentation.....................................................................................18
5.3
5.4
Personnel ...........................................................................................19
5.5
Reporting............................................................................................20
5.6
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
08-02-2011
PAGE NO:
6 of 64
5.7
5.8
Audits ................................................................................................20
MATERIAL REQUIREMENT.........................................................................21
7.1
General ..............................................................................................23
7.2
Pre-cleaning ........................................................................................24
7.3
7.4
Access................................................................................................28
7.5
7.6
7.7
8.1
General ..............................................................................................31
8.2
8.3
8.4
Application Method................................................................................32
8.5
Overcoating Method...............................................................................33
8.6
8.7
8.8
8.9
REPAIRS..............................................................................................37
9.1
General ..............................................................................................37
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
08-02-2011
PAGE NO:
7 of 64
9.2
9.3
9.4
9.5
9.6
10
DOCUMENTATION ..................................................................................48
ANNEX A.
B.1
B.2
ANNEX C.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
INTRODUCTION
1.1
General
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
08-02-2011
PAGE NO:
8 of 64
Scope
This document is applicable to the Topsides and Substructure Structural steel,
piping and equipment for the FPSO and the WHP on the Project X Development.
The following items and areas are not to be coated unless otherwise specified
on datasheets or on COMPANY drawings:
Equipment chrome plating or nickel plated, copper, brass, plastic and other
similar surfaces;
Galvanized steel surfaces for interior service except where required for
safety or identification purpose or for architectural or decorative
treatment, unless the surface has been damaged;
Instrument and electrical items such as glass faced pressure gauges, light
fittings, cables, instrument panels etc.;
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
9 of 64
Vendor package equipment which will be delivered to the jobsite coated with a
shop applied system shall be coated in accordance with this Specification unless
Vendors specification has been agreed in writing by COMPANY.
Other exclusions from the scope of this specification and covered elsewhere by
alternative project specifications are as given below:
1.3
DEFINITIONS
Within this Requisition the following definitions shall apply:
COMPANY
shall mean
CONTRACTOR
shall mean
DOCUMENT
shall mean
SUB-SUPPLIER
shall mean
SUPPLIER
shall mean
for
the
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
10 of 64
materials
shall
shall indicate
a mandatory requirement
should
shall indicate
a recommendation
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
REFERENCE DOCUMENTS
2.1
Document
Number
(1)
ISO 12944-2
(2)
ISO 12944-7
(3)
ISO 12944-8
(4)
ISO 9001
(5)
ISO 4628-3
(6)
NACE 52302
(7)
ISO 17024
(8)
ASTM G 8
(9)
ASTM G 42
(10)
SSPC-SP 1
(11)
(12)
(13)
(14)
(15)
NACE RP0287
(16)
(17)
(18)
ASTM A 380
(19)
ASTM D 4285
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
11 of 64
Description
Paints and varnishes. Corrosion protection of steel structures by
protective paint systems. Part 2: Classification of Environments
Paints and varnishes. Corrosion protection of steel structures by
protective paint systems. Part 7: - Execution & Supervision of
Paint Work
Paints and varnishes. Corrosion protection of steel structures by
protective paint systems. Part 8: Development of Specifications for
New Work & Maintenance
Quality Management Systems
Paints and varnishes - Evaluation of degradation of coatings Designation of quantity and size of defects, and of intensity of
uniform changes in appearance - Part 3: Assessment of Degree of
Rusting
Guide to Qualification of Tradesman Industrial Maintenance
Painters; NACE; 1988
Conformity assessment - General requirements for bodies
operating certification of persons
Standard test methods for cathodic disbonding of pipeline coatings
Standard test method for cathodic disbonding of pipeline coatings
subjected to elevated temperatures
Solvent Cleaning
Preparation of steel substrates before application of paints and
related products. Surface preparation methods. Part 2: Abrasive
blast cleaning
Preparation of steel substrates before application of paints and
related products. Tests for the assessment of surface cleanliness.
Part 3: Assessment of dust on steel surfaces prepared for painting
(pressures sensitive tape method)
Preparation of steel substrates before application of paints and
related products. Surface roughness characteristics of blastcleaned steel substrates. Part 1: Specification and definitions for
ISO surface profile comparators for the assessment of abrasive
blast- cleaned surfaces
Preparation of steel substrates before application of paints and
related products. Visual assessment of surface cleanliness Part 1:
Rust grades and preparation grades of uncoated steel substrates
and of steel substrates after removal of previous coatings
Field Measurement of Surface Profile of Abrasive Blast Cleaning
Steel Surfaces Using a Replica Tape
Preparation of steel substrates before application of paints and
related products. Tests for the assessment of surface cleanliness.
Part 6: Sampling of soluble impurities on surfaces to be painted
The Bresle method
Preparation of steel substrates before application of paints and
related products. Tests for the assessment of surface cleanliness.
Part 9: Field method for the conduct metric determination of
water soluble salts
Standard Practice for Cleaning, Descaling, and Passivation of
Stainless Steel Parts, Equipment, and Systems
Standard test method for indication oil or water in compressed air
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
(20)
(21)
ISO 11124-2
(22)
ISO 11124-3
(23)
ISO 11126-9
(24)
ISO 11126-10
(25)
ISO 11126-4
(26)
ISO 11126-7
(27)
(28)
(29)
ASTM D 5064
(30)
SSPC - SP 11
(31)
(32)
ASTM E 337
(33)
(34)
SSPC-PA 2
ISO 2808
(35)
ISO 17025
(36)
ISO 19840
(37)
ASTM 4541
(38)
ISO 2409
(39)
ASTM 4752
(40)
NACE RP0188
(41)
ISO 3549
(42)
DIN 8566-2
(43)
CAP 437
(44)
(45)
NORSOK M 501
DNV-RP-401
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
12 of 64
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
2.2
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
13 of 64
Document Number
SFBE-0000-00-PR-BOD-0001
SFBE-5000-00-PL-SPE-0006
SFBE-0000-00-PI-SPE-0010
SFBE-0000-00-PI-SPE-0014
SFBE-0000-00-PI-SPE-0015
SFBE-0000-00-PI-SPE-0016
SFBE-0000-00-PI-SPE-0017
Description
Basis of Design
3LPE Anti-Corrosion Coating Specification
Cathodic Protection Specification
Specification for Fireproofing of Structural Steel and Facilities
Specification for Thermally Sprayed Aluminium
Specification for Thermal and Acoustic Insulation
Specification for the Internal Lining of Vessels and Tanks
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
3.1
Environmental Conditions
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
14 of 64
Equipment shall be suitable for long term, continuous operation in the site
environmental and service conditions as stated in project document SFBE-00-0000-PR-BOD-0001 Basis of Design (Ref. 46).
3.2
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
WARRANTY REQUIREMENTS
4.1
General
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
15 of 64
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
16 of 64
Warranty inspection
Ten (10) years after the acceptance date of the completed coating work:
1.
The degree of rusting shall be in accordance with ISO 4628-3 (Ref. 5) and
shall not be worse than Ri 2 (0.5 % rusting) for new construction. This
degree of rusting shall only be allowed in localised areas and not be
scattered over the total surface area coated;
2.
5.
6.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
GENERAL REQUIREMENTS
5.1
General
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
17 of 64
The CONTRACTOR is responsible for all Quality Assurance and Control activities
and shall be fully responsible for the quality of the work which shall be
performed in strict accordance with this Specification and all other relevant
documents. Unless specifically excluded in the contract, CONTRACTORs scope
of supply shall include the provision of all facilities, equipment, consumables,
labour and documentation necessary to complete the work in accordance with
the requirements detailed herein.
Skid-mounted assemblies and packaged equipment, and all major items such as
vessels and pumps etc., will normally be delivered in the fully coated condition.
The CONTRACTOR shall carry out any necessary repairs to these coatings in
addition to providing coating systems on items within CONTRACTORs own
scope.
During preparation and coating, the CONTRACTOR shall be responsible for the
protection of all structure and equipment surfaces from mechanical damage or
coating over-spray and droppings.
The coating systems listed in Annex A shall be applied. The specific coating
products and the paint Manufacturer shall require approval of COMPANY. Only
Manufacturers with a proven track record of supply of equivalent products to
the offshore/onshore petrochemical industry over at least 10 years, with quality
systems certified to ISO 9001 (Ref. 4), and with experienced locally available
technical representatives will be acceptable. The paint Manufacturer shall be
able to provide supporting data from exposure tests and/or cyclic weathering
testing to confirm the suitability of the materials proposed for the operating and
prevailing environmental conditions.
The final colour schedule for equipment, piping and structures, and the
identification marking of piping, shall be in accordance with Annex B of this
Specification.
The CONTRACTOR shall schedule a pre-job meeting to ensure that job and
quality requirements are fully understood. Attendees shall include a
representative of the COMPANY the CONTRACTORs job superintendent and
coating supervisor and the coating inspector, and should also include the
Manufacturers representative.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
18 of 64
For all coatings work, the CONTRACTOR shall submit appropriate work plans and
a quality plan for implementing the requirements of this specification for review
by the COMPANY.
Full details of Inspection and Testing requirements are included in Section 10 of
this specification and details of Quality Control activities which will be carried
out by COMPANY are included in Section 11 of this specification.
5.2
Documentation
Prior to the commencement of work the CONTRACTOR shall obtain full details of
all coatings materials to be used from the selected Manufacturer(s) including
product data sheets and safety sheets. The following properties of the cured
coating systems shall be reported using standardized and approved laboratory
test methods:
Adhesion;
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
19 of 64
production coating will take place. COMPANY may witness these tests and
conduct testing as seen fit.
5.3
Coating Procedures
Prior to the commencement of work, CONTRACTORs coating procedures shall
be submitted to COMPANY for approval.
The detailed procedures shall include, but not necessarily be limited to the
following:
5.4
Time restrictions between surface preparation and first coat and subsequent
coats;
Finish colours.
Personnel
Only professional skilled blasters and painters shall be used. A certified foreman
shall supervise the blasters and painters. Painters and painting supervisors shall
be trained in accordance with an internationally recognized standard such as
NACE Guide to Qualification of Tradesman Industrial Maintenance Painters
(Ref. 6). Painting inspectors shall be trained and certified to NACE level I,
Frosio, or equivalent. Before any work is commenced the certificates should be
submitted to the COMPANY for review. Certifying bodies shall comply with
ISO 17024 (Ref. 7).
If not certified, the skill of all proposed blasting and painting personnel shall be
verified before commencing any painting or coating works.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
5.5
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
20 of 64
Reporting
A full reporting/recording system, as given in Annex C, shall be maintained by
CONTRACTOR who shall log daily the following data:
5.6
Coating progress;
Surface cleanliness;
Surface profiles;
Visual inspection;
5.7
5.8
Audits
COMPANY reserves the right to conduct quality, safety or environmental audits
at the coating work place prior to or during the work.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
21 of 64
MATERIAL REQUIREMENT
CONTRACTOR is responsible for ensuring suitable control of materials and to
ensure the Manufacturers recommendation on shelf life and storage is adhered
to.
The material shall be delivered to the site in the original containers with labels
intact and seals unbroken.
Manufacturers instructions in respect of storage, shelf life, mixing and
thinning, as well as method of application and recommended time limits
between coats shall be followed by CONTRACTOR.
Coating materials which have gelled or otherwise deteriorated during storage
shall not be used.
All coating materials shall be premixed by mechanical agitators for a sufficient
time to thoroughly mix pigment and vehicle and bring material to a uniform
consistency.
Zinc silicate primer shall be based on two pack inorganic or ethyl silicate media
and shall contain not less than 85 % metallic zinc by weight in the dry film.
Zinc rich epoxy primers shall be based on two pack epoxy media, containing
minimum 90% metallic zinc by weight in the dry film.
Epoxy-acrylic or urethane-acrylic topcoats shall be two-pack products
formulated to provide either high gloss or sheen finish. They shall be suitable for
recoating after extended periods of exposure to marine conditions without
requiring surface roughening.
Epoxy based paint shall be two pack products formulated to provide the
specified film build without sagging or running. They shall contain polyamide or
amine adduct curing agents.
Any coating system that will be used in combination with cathodic protection
shall possess excellent cathodic disbondment properties. This applies
specifically to the jacket splash zone coating system. All such coating systems
shall be tested in accordance with ASTM G8 (Ref. 8). The extent of disbondment
at any point from the periphery of the intended holiday shall not exceed 10 mm
after 28 days at ambient temperature. For the submerged jacket partial coating
system the requirement for a disbondment test will be considered, based on
existing paint manufacturers data. If the coating system will be subject to
elevated temperatures the coating system shall be tested in accordance with
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
22 of 64
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
SURFACE PREPARATION
7.1
General
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
23 of 64
Prior to any surface preparation, all sharp edges shall be profiled to a minimum
radius of 2 mm by grinding and all rough cutting and weld profiles shall be made
smooth. Flame cut areas and weld spatter shall have been ground flush. All oil,
grease, and dirt shall be completely removed in accordance with SSPC SP-1
(Ref. 10). Wiping with rags soaked in thinners will not be accepted.
Preparation methods and procedures for surfaces to be coated shall remove all
foreign matter, surface irregularities and contaminants to bring the surface to
the specified standard of cleanliness prior to the application of coatings.
Metallic surfaces shall be prepared prior to coating by dry abrasive blast
cleaning as outlined in ISO 8504-2 (Ref. 11). The surface profile and the anchor
pattern shall be in accordance with the standard specified for the appropriate
coating system in Annex A.
All surfaces to be coated shall be rendered dust free to ISO 8502-3 (Ref. 12)
rating 1 prior to the application of each coat by blowing the surface with clean
dry air or by using an industrial vacuum cleaner.
Prior to commencing blasting work on the project, blast cleaned steel panels
shall be prepared in compliance with the surface preparation requirements
above. The surface profile shall be measured by microscopic assessment of
replicas taken from the surface or by other direct methods as approved by
COMPANY.
If the surface has been exposed to salt laden atmosphere, any salts shall be
removed by high pressure washing with clean fresh water prior to blasting or
mechanical cleaning. CONTRACTOR shall be required to demonstrate by surface
testing that the salt level is not detrimental to the applied coating, see Section
7.3.1.
Prefabrication primers are allowed. However, after assembly these primers shall
be removed by blasting and the surface shall be blasted to the initial specified
surface cleanliness unless otherwise agreed with the COMPANY.
Alternative surface cleaning is only acceptable after written approval of the
COMPANY.
Stainless steel surfaces shall not be treated with carbon steel cleaning tools or
any tools previously used on carbon steel.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
7.2
Pre-cleaning
7.2.1
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
24 of 64
Surfaces to be coated shall be free of any contamination and any excessive rust
scale shall be removed.
All welded areas and appurtenances shall be given special attention for removal
of welding flux in crevices. Welding spatter, slivers, laminations and underlying
mill scale not removed during fabrication and exposed before and during blast
cleaning operations shall be removed by mechanical means. Edges shall be
ground smooth as stated in Section 7.1.
Excessive salt contamination of parts that have been stored in and exposed to
the open air should be removed prior to blast cleaning. Salt contamination shall
be assessed as specified in Section 7.3.1. All bolt holes and other regions which
could be contaminated with oil or grease shall be solvent cleaned prior to the
commencement of blast cleaning. Solvent cleaning shall be carried out in
accordance with SSPC-SP1 (Ref. 10). When emulsion or detergent type
degreasers are used, this treatment shall be followed by copious rinsing using
fresh and clean potable water or pressure water/steam wash. All degreasers
shall be biologically degradable.
Where rectification has been necessary on blast-cleaned surfaces, the dressed
areas shall be pre-cleaned as initially specified.
7.2.2
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
25 of 64
For the treatment of stainless steels, attention shall be given to the level of
free halides in cleaning materials to be used. If un-coated stainless steels have
to be hot-water cleaned, the temperature of the water shall be not higher than
60 C.
7.3
Blast Cleaning
Blast cleaning shall employ only sharp angular abrasive, which must be free
from dust, salts and other impurities. The abrasive shall be selected to achieve
the specified surface amplitude and shall be regularly checked and sieved to
remove fines and impurities. Blast abrasives used on open sites or in facilities
not specifically controlled to preserve the cleanliness of spent abrasive shall not
be recycled. Expendable abrasive shall not be recycled. Abrasives based on
metallic slag shall not contain any free metals.
Only aluminium oxide or non-metallic abrasives shall be used for stainless steel
and other noble metallic surfaces.
Blast abrasives shall be free from oil, grease, or moisture. The maximum
permissible chloride content shall be 25 ppm.
Sand or silica producing abrasives shall not be used.
Blast cleaning shall not be done in areas close to coating operations and/or wet
coated surfaces in order to prevent dust or grit contamination.
Spent abrasive shall be completely removed from the prepared surface by either
vacuum cleaning and/or stiff brushing.
Blast cleaned surfaces shall be prepared to the required quality of cleanliness by
reference to the visual illustrations in ISO 8501-1 (Ref. 14). Surface profiles shall
be continuously checked against surface comparators in accordance with ISO
8503-1 (Ref. 13) and verified using Testex surface profile tape per NACE RP 0287
(Ref. 15) or equal at the frequency given in section 10.2. The surface profile
shall be in accordance with the coating system sheets given in Annex A. For
carbon steel, low alloy steels and stainless steels to be coated with Thermally
Sprayed Aluminium, the surface profile shall be between 70 m and 110 m.
Blasted surfaces shall be examined for traces of oil, grease or other
contamination and tested for the presence of soluble salts. If present,
contaminants shall be removed by solvent washing or for salts, by water washing
or steam cleaning, and the affected areas re-blasted.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
7.3.1
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
26 of 64
7.3.2
Surface Dust
The dust level on the blast-cleaned surface at the time of coating shall not
exceed quantity-rating 2 in accordance with ISO 8502-3 (Ref. 12). Checks on
dust levels shall be made at least once on each component and once per 100 m2
of prepared surface and a minimum of three checks per day during the progress
of the work.
7.3.3
Presence of Millscale
Sa 2 blast-cleaned carbon steel surfaces to be used for new construction or
modifications shall be tested to ensure they are free of mill scale. The cleaned
surfaces shall be examined using magnifying instruments or chemical tests, such
as a copper sulphate test as outlined in ASTM A380 (Ref. 18).
Checks on the presence of mill scale shall be made on each component and at
least once per 100 m of prepared surface and a minimum of three checks per
day during the progress of the work.
7.3.4
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
27 of 64
ASTM D 4285 (Ref. 19) at least twice per twelve hours and following every
compressor start-up. In no case shall the temperature of the compressed air
be allowed to exceed 110 C.
b. Blasting nozzles shall be discarded and replaced when the nozzle diameter
has increased through wear by more than 50 % of the original diameter.
Blasting equipment, its operators and the equipment being blasted shall be
properly earthed to prevent the occurrence of electrostatic discharges.
Abrasive blast cleaning equipment shall be an intrinsically safe construction and
equipped with a remote shut-off valve triggered by the release of a dead man's
handle at the blasting nozzle.
7.3.5
Abrasives
Abrasives for use in blast cleaning steels shall be in accordance with ISO 8504-2
(Ref. 11) and Table 7.1. Test methods shall be in accordance with the tests
specified in ISO 11127 (Ref. 20). Each batch of abrasive should be tested to
check that the abrasive meets the requirements as specified in the relevant ISO
standard.
The conductivity of abrasives to be used for stainless steels shall be a maximum
of 150 S/cm. The COMPANY shall approve the use of alternative abrasive
materials.
Table 7.1 ABRASIVE SPECIFICATION
Type
Metallic
Natural Mineral
Synthetic Mineral
7.3.5.1
Generic Name
Characteristics
Iron Grit
Steel Grit
Staurolite
Specular Haematite
Crystalline Fe2O3
Garnet
Coal Slag
Aluminium Silicate
Aluminum Oxide
Crystalline Corundum
Standard
Selection of abrasives
There is a wide variation in performance between the products within a given
generic class of abrasives. Surface anchor profile is directly proportional to the
abrasive particle size (the larger the abrasive particle size, the deeper the
profile). Cleaning rate is inversely proportional to the abrasive particle size (the
larger the abrasive particle size, the slower the cleaning rate). A balanced
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
28 of 64
mixture of particle sizes will produce the optimum level of cleanliness, cleaning
rate and surface profile.
Steel or iron grit is commonly used as recyclable abrasives. In general, when
steel shot is used, it shall be used together with steel grit and approved by the
COMPANY.
The abrasives shall be free from oil, grease, moisture, chloride contamination
etc.
7.3.6
SSPC
NACE
Sa 3
SP-5
Sa 2
SP-10
Sa 1
SP-7
SP-1
St 3
SP-3
SP-11
Water Jetting
SP-12
TR 2
6G198
White Metal
Near-White Metal
Sweep Blast Cleaning
Solvent Cleaning
Power Tool Cleaning
7.4
Access
Access for coating work should be constructed so as to provide easy and
sufficient access for surface preparation, painting and inspection of all surfaces.
Scaffolding shall be constructed in accordance with local regulations and the
requirements of the COMPANY or as otherwise agreed with the COMPANY.
7.5
Environmental Conditions
Surface preparation shall not take place when the ambient air temperature is
below 5 C, when the relative humidity is greater than 85 %, or when the metal
surface temperature is less than 3 C above the ambient dew point.
Prepared surfaces shall be kept free from any contamination and shall be
completely free from blast residues, dust or grit.
7.6
Additional Preparation
Intended weld areas shall be masked to a distance of 50 mm to either side of
the weld area after blast cleaning and before priming.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
29 of 64
A 300 mm wide strip of uncoated blast cleaned surface shall be left between
primed and unblasted surfaces to prevent damage to the newly dried coating
when additional blasting is done. When blast cleaning is resumed, the 300 mm
strip of previously blasted surface shall require only a light brush blast to
remove any rust that might remain.
When rectification has been necessary on blast cleaned or previously coated
surfaces, the dressed areas shall be reblasted to remove all dust and
contaminants and to provide adequate paint key. Blast cleaning shall overlap a
minimum of 25 mm into the adjoining coated surface.
7.7
7.7.1
General
Alternative surface cleaning shall only be acceptable by written approval of the
COMPANY. Restrictions specified in section 7.1 shall be adhered to.
Alternative primers such as surface tolerant primers may be required for
alternative methods of surface cleaning. These shall be in accordance with the
Manufacturers recommendations. Alternative primers need the approval of the
COMPANY.
7.7.2
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
7.7.3
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
30 of 64
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
COATING APPLICATION
8.1
General
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
31 of 64
In general the requirements for the coating systems in this specification cover
their application to surfaces prepared by dry blast cleaning.
All application procedures and equipment shall be available for review by the
COMPANY.
The Manufacturers product data sheets and specifications for mixing,
application and curing shall be considered an integral part of this Specification.
The CONTRACTOR shall be responsible for obtaining the product and safety data
sheets of each material from the Manufacturer.
All coating systems shall be applied in accordance with this specification and the
Manufacturers instructions and data sheets. Any conflicting requirements shall
be brought to the attention of the COMPANY.
Each coat shall be of a contrasting colour to the previous coat unless otherwise
approved by COMPANY.
All paints in any one particular paint system, whether shop or site applied, shall
originate from a single Manufacturer.
To ensure that only correctly blasted surfaces are coated, a minimum of 100 mm
around the edges of prepared areas shall be left uncoated, unless adjoining a
coated surface. If they adjoin a coated surface, the connection to the existing
paint film shall be made as described in this section.
In cases where the COMPANY has delivered an object to the CONTRACTOR in
order to be painted, the COMPANY will inform the CONTRACTOR about the
layers of coating which have already been applied. The CONTRACTOR shall
complete the required system in accordance with this specification. No coating
shall be applied within 50 mm to areas that need to be welded later.
The specified primer coating / first coat shall be applied as soon as practicable
after completion of blast cleaning (or other approved preparation) of that area.
In no case shall the coating be applied to cleaned surfaces showing evidence of
fresh rusting or contamination (including condensation). Blast cleaned surfaces
shall be coated within a maximum of 4 hours after blast cleaning of carbon steel
and within 1 hour after sweep blasting of stainless steel/duplex stainless.
Zinc rich primers shall be applied over abrasive blast cleaned carbon and low
alloy steel surfaces only. When using an Inorganic zinc rich ethyl silicate
coating, a surface profile with angular amplitude must be achieved.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
32 of 64
Paints containing metallic zinc shall never be applied, or dripped onto stainless
steel components.
8.2
8.3
8.4
Application Method
Coating application shall be airless spray unless otherwise specified.
Spraying is the preferred method of application. Lines and spray equipment shall
be thoroughly cleaned with the Manufacturer's recommended cleaner before the
addition of new coating materials. The painting CONTRACTOR shall supply a
complete range of tips with varying spray angles and sizes, as recommended by
the Manufacturer. The spray pressure shall be uniform and the spray pattern
smooth.
Spray method including overlap, gun adjustment and direction of spray shall be
in accordance with the Manufacturers recommendations.
The spray equipment and nozzle sizes shall meet the recommendations set forth
by the Manufacturer for each specific coating material. Lines and pots shall be
thoroughly cleaned before adding new materials. Only the Manufacturers
recommended cleaning agents shall be used.
Coatings shall be applied in a uniform manner to the specified film thickness
without runs, sags or other blemishes and with strict observance of the
recommended time intervals between coats.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
33 of 64
Overcoating Method
Coatings shall be dried and cured in accordance with the Manufacturers
recommendations prior to over-coating. Over-runs, drips and smears shall be
removed and any coating damage or imperfection shall be repaired before overcoating. If the DFT does not meet the requirements of this specification,
corrective action shall be taken.
Where zinc rich primers are applied they shall be over-coated as soon as
possible but only after sufficient cure if the primer is an inorganic zinc primer.
The Manufacturers maximum over-coating times shall not be exceeded.
Zinc salts (white rust) that have formed during the intervening period shall be
removed in accordance with the Manufacturer's instructions prior to overcoating.
8.6
Environmental Conditions
Coating work shall not take place during the following conditions:
Under adverse weather conditions, e.g. rain, fog, snow or when such
conditions are likely before the coating has become dry;
When metal surface temperature is < 3 C above the ambient dew point
(< 5 C for sprayed aluminium);
Unless otherwise agreed, the CONTRACTOR shall supply all the weather
protection, scaffolding and any other equipment necessary to ensure that the
work is carried out in accordance with this specification and the agreed
programme. This includes, for example, heating and air-drying equipment.
Dew point determination shall be done in accordance with ISO 8502-4 (Ref. 31)
and humidity measurement shall be made in accordance with ASTM E 337
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
34 of 64
Holding Primers
A holding or temporary protective primer may be applied to prepared metal
surfaces to facilitate shop or site handling procedures. Such primers shall in no
way replace the function or film thickness of any part of the specified coating
system. Overcoating of zinc epoxy or acrylic based holding primers will not be
permitted by the COMPANY. These primers shall be completely removed by blast
cleaning prior to application of specified primer / first coat. Sweep blasting of
inorganic zinc shop primers may be allowed where CONTRACTOR can
demonstrate to COMPANY'S satisfaction, by submission of supporting test data
based on long term cyclic testing, that there is no reduction in system adhesion
or performance. CONTRACTOR shall also demonstrate that sufficient controls
are in place to ensure adequate cleanliness and condition of the aged primer
before overcoating.
Alternative surface cleaning is only acceptable after written approval of the
COMPANY.
In all cases, areas of localised breakdown, and weld areas or damaged areas
shall be cleaned to the full specified standard.
In areas where cathodic protection will be applied, the full coating system
including the holding primer shall be tested for cathodic disbondment in
accordance with ASTM G8 (Ref. 8) or ASTM G42 (Ref. 9).
8.8
Coating thickness
The coating systems are detailed in Annex A "Coating Systems Summary Sheets"
and the nominal dry film thickness (DFT) is given for each coat. The DFT of any
coat shall not be greater than 40 % above nor 10 % below the nominal value
specified. The exception to this is for Thermally Sprayed Aluminium (TSA) where
the minimum overall thickness shall be 200 m. The DFT shall be measured in
accordance with SSPC-PA 2 (Ref. 33).
The minimum dry film thickness (MDFT) is the acceptance thickness for the total
applied coating system, based on a 95 % probability of this value being exceeded
by any individual measurement. In practice, this requires statistical records to
be maintained of thickness measurements.
Spot checks shall be carried out during the course of the painting operation to
ensure that film wet film thickness (WFT) is being maintained. These shall be
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
35 of 64
performed according to the procedure described in ISO 2808, Method No. 1A comb gauge (Ref. 34).
8.9
8.10
Weld areas
No coating, except "weldable" grades of zinc based holding primers, shall be
applied within a minimum of 50 mm or edges / areas prepared for welding. The
zinc based holding primer shall be a grade which is approved by a certifying
authority such as Lloyds Register or equivalent as not being detrimental to the
resultant weld.
The following procedure shall be followed with regard to welding, where zinc
silicate or zinc rich epoxy and tie coat are used:
Intended weld area shall be masked after blast cleaning and before priming,
as stated in Section 6.6;
When ready to weld, the first tape shall be removed from the base steel
exposing the weld area;
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
36 of 64
tape shall be removed and the weld area pencil blasted, extending this to
sweep blast the 50 mm of primed surface before proceeding with priming
and coating;
8.11
Any masking tape used shall be removed as soon as possible to avoid damage
to the surface underneath.
8.12
8.13
8.14
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
REPAIRS
9.1
General
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
37 of 64
Insufficient Thickness
In the event that a completely coated surface is found to have insufficient
coating thickness, this surface may, subject to specific COMPANY approval,
receive an additional coat or coats until the specific thickness is achieved. The
COMPANY may alternatively require the surface to be blast cleaned and
recoated. Surfaces to receive additional coating shall be properly cleaned of all
foreign matter or contaminants and prepared as recommended by the
Manufacturer.
9.3
Excess Thickness
In the event that a coated surface is found to have excessive thickness, it shall
be brought to COMPANY's attention who will decide on the appropriate action to
be taken. Acceptance by COMPANY of excessive thickness will be considered
only if the measured thickness is confirmed by the Manufacturer in writing as
not being detrimental to the satisfactory service life and performance of the
coating system and if testing demonstrates that there is no loss in system or
intercoat adhesion.
9.4
Film Defects
Defects such as misses, incorrect colour, gloss level and poor hiding power shall
be repaired by applying additional coating as required.
Defects such as poor finish, texture, sagging, runs, dry spray and over-spray
shall be removed by abrading the film to remove the defect and then applying
additional coating as required.
Defects such as poor adhesion, pinholes, holidays and cracking shall be
completely removed by blast cleaning to substrate and reapplying the complete
system.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
38 of 64
Damaged areas, defects in the coating system such as over-runs, drips and
smears that have to be removed or areas with inadequate DFT shall be recleaned. The re-cleaning shall carry over on to the secure surrounding coating
for not less than 250 mm all round and the edges shall be feathered (over a
width of at least 70 mm). After surface cleaning the specified coating system or
the required layers of the specified coating shall be re-applied. Any additional
coats shall blend in with the final coating on adjoining areas. Manufacturers
shall be consulted if the existing coating requires abrading before over-coating
to obtain good bonding.
9.5
Overcoating may be permitted before complete curing of the zinc rich epoxy
provided that all volatile material has evaporated.
It shall be noted that the above procedure is for repairs only. Under no
circumstances shall this procedure be used in place of original priming to
specification or galvanized surfaces.
Surface preparation by any other method than blast cleaning shall only be
permitted with the written approval of the COMPANY.
COMPANY may require that CONTRACTOR completely removes and re-apply the
full coating system where the extent of repairs is considered to be excessive.
Inorganic zinc silicate shall not be overcoated by itself. Insufficient coating
thickness shall be reblasted and recoated.
Repair to damaged galvanizing when the extent of damage exceeds 40 mm2,
shall be subject to COMPANY approval.
9.6
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
39 of 64
been agreed between the SUPPLIER of the fireproof material and the SUPPLIER
as being compatible with the fireproofing system and materials. Approval for
the use of a specific type of fireproofing shall be obtained in writing from the
COMPANY.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
10
10.1
General
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
40 of 64
CONTRACTOR shall monitor all work and shall conform to the requirements of
this specification against a project specific Inspection Report, detailed in
Annex C.
The CONTRACTOR shall protect all equipment, structures and any other areas
from mechanical damage, environmental damage, blockage or obstruction,
damage caused by over blasting, dripping paint, paint splashes and overspray.
The CONTRACTOR shall be responsible for all inspection and quality control
functions necessary to achieve coating standards in accordance with this
specification.
All testing and inspection equipment shall be kept accurately calibrated at all
times and shall be covered by current calibration certificates issued by the
equipment SUPPLIER or a test laboratory accredited to ISO 17025 (Ref. 35) or
equivalent for conducting such work.
It is the CONTRACTORs responsibility to ensure that monitoring and testing
work is carried out to show that the coatings comply with this specification. The
COMPANY reserves the right to carry out any additional tests at random to
ensure compliance and the CONTRACTOR shall have suitable calibrated test
equipment available for COMPANY use.
All personnel and paint products applied under fireproofing shall be approved by
the intumescent fireproofing material SUPPLIER, and the COMPANY.
10.2
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
10.3
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
41 of 64
10.4
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
DOCUMENT NUMBER:
PEDIL
SFBE-0000-00-PI-SPE-0006
REV:
Petrofac
D1
DATE:
PAGE NO:
08-02-2011
42 of 64
Up to 1
Above 1 to 3
10
Above 3 to 10
15
Above 10 to 30
20
Above 30 to 100
30
Above 100
Note: Areas above 1,000 m2 should be divided into smaller inspection areas
DFT shall be taken covering each coat prior to application of the following coat.
The minimum measurement location frequency shall be one (1) per two (2)
square metres of flat surface, with additional measurements taken at changes in
section, corners or edges. Minimum, maximum and average shall be recorded for
each coated item on the inspection record sheets.
Acceptance criteria for the completed coating system, based on the NFDT are
stated in Section 8.8, and Annex A.
10.4.1
Adhesion Tests
Adhesion testing shall be carried out during all coating system qualification
trials and as a routine test for atmospheric exposed organic coatings.
The quality of adhesion between the coating system and the steel substrate, and
of the adhesion between the coating layers, shall be measured using either:
a)
Or:
b)
A crosscut test in accordance with ISO 2409 (Ref. 38), Class 0 for coating
systems with a maximum total NDFT of 150 m.
Testing shall be done on fully cured systems only, i.e. not less than 14 days after
the application of the final layer. The adhesion requirements for TSA are
specified in Specification for Thermal Sprayed Aluminium (Ref. 50).
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
43 of 64
Adhesion testing shall be carried out on each component and at least once per
100 m of coated surface. Spots damaged by the adhesion tests shall be repaired
in accordance with this specification.
Acceptance criteria for adhesion testing shall depend upon coating type and
available test data for equivalent systems. As a minimum, adhesion/cohesion
levels of 5 MPa for standard organic coatings and 7 MPa for glass flake epoxy.
Lower individual values shall require further investigation and remedial action.
Antiskid system for helidecks and walk ways:
Unless otherwise specified by the COMPANY, the surface friction coefficient ()
of anti skid coating systems applied to helidecks shall be = 0.8. The test
method to be used shall be approved by the COMPANY.
10.4.2
10.5
Holiday Testing
100% holiday detection in accordance with NACE RP 0188 (Ref. 40) shall be
carried out on all coatings used for partial immersion or total immersion service
except for thermally sprayed coating systems. The coatings shall be free of
pores and holidays.
The high voltage technique shall be used; nominally set at 5 V/m based on
NDFT, or as agreed with the Manufacturer but not exceeding 25 kV in total.
For coatings that are < 500 m DFT, the wet sponge technique may be used if
approved by the COMPANY.
Defects found shall be marked, repaired and retested in accordance with this
Specification. The CONTRACTOR shall provide the necessary equipment for
calibrating the holiday detector.
10.6
Additional Tests
COMPANY reserves the option to require CONTRACTOR to perform such testing
of coating materials as may be necessary to prove that the quality is in
accordance with the Manufacturers specifications and data sheets and is fully
suitable, without reduction in performance or other detrimental effects, under
the prevailing application condition. Qualities to be tested may include, but not
be limited to, the following:
Volume Solids;
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
44 of 64
Viscosity;
Pigment Dispersion;
Adhesion to Substrate;
Drying Time;
Cure Time;
Percentage Glass flake in Dry Film (glass flake containing coatings only);
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
11
QUALITY CONTROL
11.1
General
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
45 of 64
The COMPANY or its Representative shall have the right to inspect, check or
review, at all times, any or all of the activities, equipment, inspection
equipment, or products designated for the work. All parts of the work shall be
accessible for this purpose.
On behalf of the COMPANY, regular quality checks will be carried out by a
qualified and independent third party inspector, which in no way relieves the
CONTRACTOR of any responsibility with respect to the quality of the coating
work.
The COMPANYs representative assigned to the painting work shall be given at
least four hours notice of any change in the schedule of the painting activities.
Whenever any section is to be assembled that will prevent subsequent
inspection of an area, the COMPANYs representative shall be notified in time,
so that inspection and repair activities can be carried out before proceeding
with the assembly.
11.2
Final Inspection
As part of the overall Quality Plan, a final inspection shall be conducted prior to
the final acceptance of the paintwork. This final inspection shall include a visual
check of the appearance and overblast of the coating work, and checks on DFTs
of the total applied coating system and work completed.
The CONTRACTOR and the COMPANY shall both be represented and they shall
sign an agreed acceptance form as part of the warranty agreement.
As part of the acceptance procedure, the CONTRACTOR shall prepare a report
that includes the following.
General:
Scope of work;
Inspection equipment:
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
46 of 64
Surface preparation:
Coating application:
Inspection reports:
11.3
11.4
Quality Plan
Before commencing any work, a written project specific quality plan shall be
submitted to COMPANY approval. This plan shall include:
Detailed scope of the work to be done including, per item or area, the
required surface preparation and coating system to be applied;
Full details of the blast and paint equipment including, where appropriate:
dehydration, temperature, any other environmental control measures,
methods of access, etc;
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
11.5
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
47 of 64
Detailed procedures and plans for testing and inspection including the
methods and equipment to be used and the frequency of their application
and acceptance criteria. An example of an inspection and testing plan (ITP)
is given as attached in Annex C;
Qualification of personnel.
Reporting
The CONTRACTOR shall submit inspection reports not less than once per week.
These reports shall include details of weather conditions, air humidity,
temperature, particulars of application, e.g. blast cleaning, wet and dry film
thickness, and any anomalies. If required by the COMPANY, the reports shall also
detail the progress of work versus the approved programme.
11.6
Relative humidity
minimum accuracy
b)
minimum accuracy
c)
Dew point
0.2 C.
minimum accuracy
2 %;
0.2 C
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
12
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
48 of 64
DOCUMENTATION
CONTRACTOR shall maintain records of all coating and inspection work carried
out in accordance with this specification (per Annex C).
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
49 of 64
SYSTEM
NUMBER
MATERIAL
EXPOSURE
APPLICATION
Piping, External Surfaces of Vessels and
Process Systems
SYSTEM 1
Carbon Steel
Non
Insulated,
low
maintenance
Atmospheric Exposure,
and
/or
high
Temperature
SYSTEM 2
Carbon Steel
Insulated
All items
SYSTEM 3
Carbon Steel
Fireproofed
All items
SYSTEM 4
Stainless Steel
SYSTEM 5
Carbon Steel
Non Insulated
Insulated
All items
Galvanized
SYSTEM 6
Carbon Steel
Decking
Walkways
Escape routes
Helidecks
Lay down areas
SYSTEM 7
Carbon Steel
Caissons, J Tubes
SYSTEM 8
Carbon Steel
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
A.1
SYSTEM 1
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
50 of 64
PRE TREATMENT:
Remove all grease and salts and other
contaminants with a water miscible
detergent and high pressure fresh water
washing
and
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
51 of 64
7. For COMPANY approved applications a COMPANY approved surface tolerant epoxy mastic may be used in
place of the zinc primer.
8. The epoxy phenolic shall be an immersion grade with greater than 6 months test data in sea water at
160 C.
9. System 1D may be applied for bulk valves in service up to 160 C.
10. Zinc silicate shall have a minimum 85 % zinc dust in the dry film. Zinc dust shall conform to ISO 3549.
11. Primed surface of system 1E shall be free of zinc dust prior to top coating.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
SYSTEM 2
PRE TREATMENT:
Remove all grease and salts and other contaminants
with a water miscible detergent and high pressure
fresh water washing
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
52 of 64
GENERIC SYSTEM
SYSTEM 2A Insulated, operating temperature up to
120 C
1 x 50 m Epoxy Primer, see note 2
2 x 150 m Epoxy Mastic
TOTAL MDFT 350 m See Note 9 for alternative
NOTES:
1. Solid content of epoxy shall be > 75 %.
2. The epoxy primer in system 2A shall not contain any zinc.
3. The epoxy phenolic shall be an immersion grade with greater than 6 months test data in sea water at
160 C.
4. System 2B may be applied for bulk valves in service up to 160 C.
5. Zinc silicate shall have a minimum 85 % zinc dust in the dry film. Zinc dust shall conform to ISO 3549
(Ref. 41).
6. Primed surface of system 2C shall be free of zinc dust prior to top coating.
7. TSA shall be in accordance with Norsok M-501 (Ref. 44) System 2. Aluminium wire shall be grade 99.5% to
DIN 8566-2.(Ref. 42).
8. The sealer in system 2D shall be suitable for temperatures up to 500 C.
9. For standardization purposes, System 2A can be replaced by System 2B, where CONTRACTOR prefers.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
SYSTEM 3
PRE TREATMENT:
Remove all grease and salts and other
contaminants with a water miscible detergent
and high pressure fresh water washing
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
53 of 64
NOTES:
1. Zinc rich Epoxy shall be 2 pack formulations containing minimum 80% zinc dust by mass in the dry film. Zinc
dust shall conform to ISO 3549 (Ref. 41). It shall be overcoated before formation of zinc salts, otherwise
these shall be removed completely prior to overcoating.
2. Under intumescent epoxy fireproofing: The primer shall be approved by fireproofing SUPPLIER based on
results of shear strength.
3. Solid content of epoxy shall be > 75 %.
4. Under cementitious fireproofing: Alternative coating system may be offered, subject to fireproofing
SUPPLIERs recommendations.
5. The specific sealing/topcoat requirements for cementitious fireproofing shall be agreed with COMPANY and
the fireproofing SUPPLIER.
6. Repair system shall be approved compatible systems.
7. Intumescent epoxy fireproofing SUPPLIER, grade, qualification data, application and inspection procedures
shall be approved by COMPANY.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
SYSTEM 4
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
54 of 64
PRE TREATMENT:
Remove all grease and salts and other
contaminants with a water miscible detergent
and high pressure fresh water washing
SURFACE PREPARATION:
SWEEP BLAST ONLY, see note 3
SURFACE PROFILE: 25 45 m
Mechanical preparation ST 3 (local area only) subject to
COMPANY approval
GENERIC SYSTEM
SYSTEM 4A Non-Insulated and Atmospheric
Exposure
Austenitic Steel: Operating temperature 50
160 C
Duplex Steel: Operating temperature 90
160 C
1 x 125 m Epoxy Phenolic
1 x 125 m Epoxy Phenolic Topcoat
TOTAL MDFT 250 m see note 4
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
SYSTEM 5
PRE TREATMENT:
Remove all grease and salts and other
contaminants with a water miscible detergent
and high pressure fresh water washing. Finally,
galvanizing to be scrubbed with bristle brushes
and suitable detergent to remove all traces of
flux
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
55 of 64
SYSTEM 5
1 x 125 m Epoxy Mastic
1 x 75 m Polyurethane Acrylic, see note 4
TOTAL MDFT 200 m
NOTES:
General Notes:
1. Touch-up of damaged galvanizing;
1 x 2 pack zinc rich epoxy primer, DFT 70 m.
Specific Notes:
2. CONTRACTOR shall demonstrate that sweep blasting will not cause cracking, flaking or lifting of galvanizing.
3. Etch priming may be used as an alternative to sweep blasting subject to COMPANY approval.
4. Final coat shall be light grey or white unless otherwise noted in Annex B or C.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
SYSTEM 6
DECKING
PRE TREATMENT:
Remove all grease and salts and other
contaminants with a water miscible detergent
and high pressure fresh water washing
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
56 of 64
GENERIC SYSTEM
SYSTEM 6A Light Duty general Walkways and
Decks
1 x 60 m Zinc Rich Epoxy Primer, see note 3
1 x 400 m Glass Flake Epoxy (or HB Epoxy)
incorporating aggregates, see note 4
1 x 75 m Polyurethane Acrylic, see notes 5
and 6
TOTAL MDFT 475 m
NOTES:
1. Repair systems to be based on approved compatible systems.
2. Primer selection and application and overcoating to be subject to MANUFACTURERs written recommendation.
3. The epoxy primer in System 6A and 6B is only necessary to maintain the integrity of the blasted steel surface. In
situations where the primer is required the MDFT shall increase to 535 m for System 6A.
4. Aggregates to be approved non-slip and non-sparking type. For Helideck the system shall comply with CAP 437.
Offshore Helicopter Landing Areas: A Guide to Criteria, Recommended Minimum Standards, and Best Practice
Civil Aviation Authority Standard for Helideck Design (Ref. 43).
5. Topcoat only required where safety or marking / colour requirement dictate.
6. Approved photoluminescent marking/colour requirements dictate.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
SYSTEM 7
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
57 of 64
PRE TREATMENT:
Remove all grease and salts and other contaminants with a
water miscible detergent and high pressure fresh water
washing
SURFACE PREPARATION:
BLAST CLEAN: 7A, 7C: Sa 2.5 7B: Sa 3
SURFACE PROFILE: 7A: 30 85 m, 7B : 50 85 m
Mechanical preparation ST 3 (local area only) subject to
COMPANY approval
GENERIC SYSTEM
SYSTEM 7A Maintainable Systems
1 x 60 m Epoxy Primer, see note 2 and 3
1 x 400 m Glass Flake Epoxy
1 x 75 m Polyurethane Acrylic note 4
Ant-fouling paint note 4
TOTAL MDFT 400 m
NOTES:
General Notes:
1. The coating system (including any primer) for immersed services shall be certified as having high resistance to
cathodic disbondment. All systems shall be tested in accordance with ASTM G8 or G42 depending on temperature.
The extent of disbondment at any point from periphery of the intended holiday shall not exceed 10mm after 28
days at ambient temperature.
Specific Notes:
2. Solid content of epoxy shall be > 75%.
3. The epoxy primer in System 7A is only necessary to maintain the integrity of the blasted steel surface. In situations
where the primer is required the MDFT shall increase to 460 m.
4. Anti-fouling paint shall be used for the immersed areas of the caissons and J Tubes and polyurethane acrylic shall
not be used in these submerged areas. The anti-fouling paint shall be tin and copper free, shall provide antifouling properties for a minimum 2year life when exposed to seawater.
5. Jacket and appurtenances below the splash zone will not be coated and will be protected by sacrificial anode CP
system.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
SYSTEM 8
SUBMERGED SECTION OF
JACKET STRUCTURE
PRE TREATMENT:
Remove all grease and salts and other
contaminants with a water miscible
detergent and high pressure fresh water
washing
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
58 of 64
SURFACE PREPARATION:
BLAST CLEAN: Sa 2.5,
SURFACE PROFILE: 30 85 m,
GENERIC SYSTEM
SYSTEM 8
1 x 300 m Abrasion Resistant high solids polyamide cured Epoxy
TOTAL MDFT 300 m
NOTES: System 8 Continued
1. Solid content of epoxy shall be > 72%.
2. This coating system is applied in order to reduce quantity of anodes. Weld and node areas will be left
uncoated as per jacket painting drawing produced by Fabrication Contractor.
3. If desired this system may be applied as two coats of 150 m per coat.
4 System shall have proven high compatibility with cathodic protection.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
Petrofac
CLIENT:
PEDIL
REV:
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
59 of 64
Colour
RAL code
Broom yellow
1032
White/red bands
9010 / 3002
Carmine red
3002
Grey white
9002
Black
9005
Dusty grey
7037
Top-side of helidecks
Signal green
6032
Carmine red
3002
Grey white
9002
Structural steel
Vent stacks, flare booms and
crane booms etc
Remarks
Including handrails, ladders, walkway
framework (bordesses) and staircases
Width of the band to be agreed (approx.
4.5 m)
NOTES:
Unless otherwise specified by the COMPANY, stream identification and direction shall be applied on piping systems
after the final coats have been applied and cured, The type and model shall be agreed between the COMPANY and
the CONTRACTOR. The banding systems shall be durable and in the form of plastic tape or self sprung coil of the
appropriate size to fit the pipe. However, identification tapes shall not contain ingredients such as free chloride that
could damage either the coating, or the pipe substrate material (e.g. stainless steel or nickel-chromium alloy), and
shall be applied at proper intervals to enable easy identification of the pipe, contents, and fluid direction. For
insulated lines this identification shall be applied to the outer surface of the insulation. The COMPANY shall specify
the colour of the topcoat and banding to be applied.
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
B.2
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
60 of 64
BACKGROUND COLOUR
120 mm
50 mm
DECORATION COLOUR
Figure C1
120 mm
CODING COLOUR
Colour Bands
The bands shall be applied where identification of the fluid is most important,
i.e. on pipes around equipment, machineries and near valves.
TABLE C.2 PIPING IDENTIFICATION COLOURS
COMMODITY
CODE
FLUID
BACKGROUND COLOUR
CODING COLOUR
AB
Breathing Air
Blue 5017
AG
Gas to atmosphere
Yellow 1023
Red 3020
BD
Blowdown
Yellow 1023
Blue 5017
CA
Compressed Air
Blue 5017
Red 3020
CD
Closed Drain
Orange 2004
Red 3020
CH
Chemicals
Violet 4005
Brown 8016
DP
Red 3020
DW
Potable Water
Green 6024
Orange 2004
FF
Fire Foam
Red 3020
FG
Fuel Gas
Yellow 1023
FH
HP Flare
Yellow 1023
Blue 5017
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
COMMODITY
CODE
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
61 of 64
FLUID
BACKGROUND COLOUR
CODING COLOUR
FL
LP Flare
Yellow 1023
Blue 5017
FO
Fuel Oil/Diesel
Brown 8016
FW
Red 3020
Green 6024
GY
Glycol
Violet 4005
Blue 5017
HC
HP Condensate
Yellow 1023
Brown 8016
HD
Orange
Red 3020
HM
Heating Medium
Grey 7035
HO
Hot Oil
Orange
Red 3020
IA
Instrument Air
Blue 5017
Red 3020
LC
LP Condensate
Yellow 1023
Brown 8016
LO
Lube Oil
Yellow 1023
Blue 5017
MC
MP Condensate
Red 3020
Green 6024
ML
Methanol
Violet 4005
Black 9005
OS
Oil (Sludge)
Brown 8016
Yellow 1023
OW
Orange 2004
Black 9005
PO
Product Oil
Brown 8016
Red 3020
PW
Produced Water
Green 6024
Yellow 1023
RO
Raw Oil
Brown 8016
Yellow 1023
RS
Sewage (Raw)
Orange 2004
Black 9005
RW
Green 6024
Violet 4005
SD
Sludge (Sewage)
Orange 2004
Black 9005
SO
Slop Oil
Brown 8016
Yellow 1023
SW
Sea Water
Green 6024
Black 9005
TG
Yellow 1023
Blue 5017
TS
Treated Sewage
Orange 2004
Black 9005
TW
Green 6024
Brown 8016
UA
Plant/Utility Air
Blue 5017
Red 3020
UN
Nitrogen
Blue 5017
Yellow 1023
UW
Utility Water
Green 6024
Blue 5017
WF
Well Fluid
Brown 8016
Yellow 1023
WW
Waste Water
Green 6024
Brown 8016
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
62 of 64
Project: Project X
Coating system: A1
Date:
Item
Inspection test
items
1.0
Reference
Documentation
2.0
Material Receipt
2.1
Coating Material
Receipt
2.2
Coating Material
Receipt
3.0
Frequency
Acceptance standard
Report
form (1)
CONTRAC COMPANY
TOR (2)
(2)
All
All
M, V, R
Inspection of
All surfaces
Surface Condition
R, W
W, M
3.1
Solvent or
Detergent
Cleaning
All surfaces
R, W
W, M
3.2
High Pressure
Water/Steam
Cleaning
All surfaces
R, W
3.3
Climatic
Conditions (air
Temperature and
Dew Point
readings)
M, W, R
3.4
Steel
Temperature
3.5
Compressed Air
Supply Blotter
test
Twice/12 hours
R, W
W, M
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
63 of 64
Project: Project X
Coating system: A1
Date:
Item
Inspection test
items
Frequency
Acceptance standard
Report
form (1)
CONTRAC COMPANY
TOR (2)
(2)
3.6
Blast Nozzle
Pressure
Every 2 hours
3.7
Surface Profile
W, R, M
W, M
3.8
Surface Dust
Once per
Rating 2, ISO 8502-3, clause 6.1
100 m or three
times/ per day
W, M, R
W, M
3.9
Presence of
Millscale
Once per
Free of mill scale
100 m or three
times/ per day
W, M, R
W,M
3.10
Soluble Salt
Contamination
Test
(chlorides, etc.)
Once per
Residual chlorides shall be 50 mg/m ISO 8502-6
100 m or three and ISO 8502-9
times/ per day Pitted areas shall be checked for iron salts.
H, V, R
W, H
3.11
Visual Inspection
after Abrasive
Blasting
All
H, W, V,
R
W, H
4.0
Calibration of
Inspection
Equipment
Start of
Dry film thickness gauges: start of shift and
production then thereafter every three hours at the mid range of
every 3 hours
the coating thickness. Holiday detection: start of
shift and thereafter every four hours. 2500 volts
100 volts,
Adhesion tester: daily
V, W, R
5.0
Spray Pressure,
Tip Size and Fan
Angle.
At start of
spraying
5.1
Primer
Application
All
W, R
5.2
Stripe Coat
Application of
Primer
All
V, W, R
5.3
Dry Film
Thickness
5 per m2
PROJECT:
PROJECT NO:
JU-10701A
DOCUMENT TITLE:
ORIGINATOR:
CLIENT:
PEDIL
REV:
Petrofac
D1
DOCUMENT NUMBER:
SFBE-0000-00-PI-SPE-0006
DATE:
PAGE NO:
08-02-2011
64 of 64
Project: Project X
Coating system: A1
Date:
Item
Inspection test
items
Frequency
Acceptance standard
5.4
Report
form (1)
CONTRAC COMPANY
TOR (2)
(2)
Second Stripe
Coat Application
All
W, R
5.5
All
W, V, R
5.6
Visual Inspection
All
R, W, V
5.7
H, R, W
H, W, M
5.8
Holiday Test
100 % surface
area
5.9
Cure Test
2 per sprayer
per day
R, W
5.10
Adhesion Test
1 per 5 m2
R, V, W
5.11
Coating Repair
As required
R, V, W
Legend:
H
Hold
Monitor
Record
Visual
Witness
NOTES:
(1) Indicate reference to CONTRACTORs Quality Control reporting forms or documents on which the quality data is to be recorded
and/or reported.
(2) These are examples of actions. Actions and action parties shall be agreed for each coating job.