LEVEL 1
Concrete Quiz Qualifier
CSA A23.1-04 Study Question
(A passing grade of 80% is required)
Name:
Date:
1.
What is the minimum specified compressive strength requirement for
suspended parking slabs and decks?
A. 25 MPA
B. 32 MPA
C. 35 MPA
2.
What is the specified air content range for C1 exposure class concrete with
a maximum size aggregate of 20mm?
A. 5% to 8%
B. 3% to 6%
C. 0%
3.
4.
When conducting "Full Time Monitoring (FTM)" of concrete for suspended
parking slabs and ramps, is it good practice to do some reinforcing steel concrete
cover spot checks?
A. Yes, of course
B. No, not our job
5.
What is the minimum concrete cover for a C1 exposure class condition (i.e.
suspended parking slabs)?
A. 20mm
B. 40mm
C. 60mm
6.
7.
1|Page
QUIZ 9G
8.
9.
+/-_____mm
+/-_____mm
+/-_____mm
10.
11.
12.
When conducting a FTM test on a suspended parking slab how often should
an actual slump test be done?
A. every load
B. once per day
C. every second or third load
13.
14.
15.
Who is responsible to provide and maintain proper facilities for safe storage
and proper curing of concrete test specimens on the project site for the initial
curing period?
A.
B.
C.
D.
testing company
owner
contractor
all of the above
16.
When strength test cylinders fail and cores are drilled from a structure what
are the minimum requirements for the core tests to be considered acceptable?
2|Page
QUIZ 9G
17.
18.
When the measured slump of the concrete falls below the specified slump,
what is the time limit for when water can be added?
A. no time limit
B. 60 minutes from when concrete arrives on site
C. 60 minutes from when concrete was batched
19.
When the measured slump of a superplasticized concrete mix falls below
the specified slump, how should the concrete be retempered?
A. superplasticizer only
B. water and superplasticizer
C. water only
20.
21.
At what volume of the delivered concrete load is to be sampled for the
testing representative?
A. any part of the volume
B. as soon as discharging begins
C. after 10% of the load is discharged
D. before the last 10% of the load is discharged
E. both C and D
3|Page
QUIZ 9G
LEVEL 2
Concrete Quiz Qualifier
(A passing grade of 80% is required)
True
False
1.
This work method covers CSA A23.1 Alternative 1?
True
False
2.
The Ready-mix supplier is responsible for the mix proportions, quality, and
performance of delivered concrete?
Yes
No
3.
Can the Ready-mix supplier initiate remedial action on site to correct nonconforming concrete?
4.
Give three examples of remedial action which could be done on site by the supplier?
1.
2.
3.
5.
If the test results indicate non-conforming concrete who does the technician advise first?
Answer:
True
False
6.
After remedial action by the supplier to retemper the concrete, the technician
shall resample and retest the concrete?
7.
If the concrete cannot be brought into compliance the technician shall notify the
supplier and the contractor?
True
False
8.
If the supplier brings the concrete into compliance, what comment would you write on the
Quality Concrete Report (QCR) and concrete test record?
Answer:
9.
Non-conforming concrete that does not meet project specifications should
be rejected after the supplier and contractor have been notified of the
results. Who has the final decision to reject the concrete off-site?
Tester
Driver
Contractor
10
Under what circumstances could the non-conforming (rejected) concrete be placed on site?
Answer:
11.
If superplasticizer is added to the concrete on site, can the concrete be
retempered with water within the first hour after batching?
12.
There are two main types of concrete pours that typically require
full time monitoring, what are they?
1.
2.
4|Page
Yes
No
QUIZ 9G
13.
The Technicians' testing duties are different for a full time monitoring (FTM) test compared to
a concrete spot test (CST). What are the main differences?
14.
Give 5 examples of non-conforming concrete problems or situations?
1
2
3
4
5
15.
List the typical test requirements for "normal weight plastic concrete"
Answer:
16.
List the typical test requirements for "suspended slabs" or crane bases?
Answer:
17.
List the typical test requirements for "tilt up panel projects"?
Answer:
18
List the typical test requirements for "extruded curb (low slump) concrete mix"
Answer:
19.
What is the first thing you do after you set up your equipment, but just before you obtain your
concrete sample?
Answer:
20.
What does CSA specify as the maximum time limit from batch time to complete discharge?
Answer:
21.
If non-conforming concrete gets placed, what information must be obtained?
Answer:
Why:
5|Page
QUIZ 9G
22.
Anyone working with concrete needs to be
environmentally aware. Note two things the tester
is responsible for?
1.
2.
23.
What would you consider
the responsibilities for the
following parties.
(Connect the matching
pairs)
Ready-Mix Supplier
CSA Testing
Contractor
Concrete Quality
Testing Company
Specification
Structural Engineer
24.
After completing the test you should store the cylinders in the designated location. What extra
precautions should you take during the summer months?
Answer:
25.
After completing the test you should store the cylinders in the designated location. What extra
precautions should you take during the winter months?
Answer:
26.
Put the following 10 steps
in order for conducting
onsite concrete testing.
(first to last)
6|Page
QUIZ 9G
27.
In addition to the
company copy who
else gets copies of
the following
reports. Match up
the distribution
parties.
Owner
Contractor
Driver & Contractor
Contractor
Judgement Questions
28.
When you arrive on site and check the mix supplied, you discover the wrong mix has been
delivered to site. What do you do?
Answer:
29.
When you arrive on site and visually check the concrete you observe the slump is high. What
do you do?
Answer:
30.
When you arrive on site to test the concrete being placed in a suspended parking slab.
Describe each step of your testing procedure in order.
Answer
31.
If the first load of concrete delivered for a suspended parking slab pour has a low air. What
should, or could you do?
Answer:
32.
If a fresh load of concrete arrives on site and the measured slump is low. How would you
increase the slump?
Answer:
33.
A load of concrete is on site and is 75 minutes old, and the measured slump is low. How
would you increase the slump?
Answer:
7|Page
QUIZ 9G
34.
If a fresh load of superplasticized concrete arrives on site and the measured slump is low.
How would you increase the slump?
Answer:
35.
A load of superplasticized concrete is on site and in now 120 minutes old. The slump was
measured to be low 10 minutes prior. How would you increase the slump, or what else would
you do?
Answer:
Management Approval:
Print name:
Date:
8|Page
Signature: