Beruflich Dokumente
Kultur Dokumente
(CGE577)
1
CHAPTER 5:
CASING
Contents
2
Casing Properties
Casing Setting Depth/ Casing Seat Selection
Casing Selection: Size Selection and Grade Selection
DEFINITION OF CASING
3
FUNCTIONS OF CASING
4
1.
2.
3.
4.
5.
6.
To keep the hole open and to provide support for weak, vulnerable or fractured
formations. If the hole is left uncased, the formation may cave in and redrilling
of the hole will then become necessary.
To isolate porous media with different fluid/pressure regimes from
contaminating the pay zone. This is basically achieved through the combined
presence of cement and casing. Therefore, production from a specific zone can
be achieved.
To prevent contamination of near-surface fresh water zones.
To provide a passage for hydrocarbon fluids; most production operations are
carried out through special tubings which are run inside the casing.
To provide a suitable connection for the wellhead equipment and later the
christmas tree. The casing also serves to connect the blowout prevention
equipment (BOPS) which is used to control the well while drilling.
To provide a hole of known diameter and depth to facilitate the running of
testing and completion equipment.
CASING ACCESSORIES
- CASING CONNECTION
5
CASING JOINT
6
Length of Joint
Range
Length (ft)
Average length
(ft)
16-25
22
25-34
31
34+
42
Casing couplings
Casing joints
CASING HANGER
9
To suspend or hang casing string which rests
Lifting-up a Casing
10
Casing to be
lifted to the rig
floor
Hydraulic casing
tong is used to
make-up the
casing
Installing Casing
12
Derrickman is
connecting the
elevator to the
top of casing
and lowers into
the hole
TYPES OF CASING
13
1.
2.
3.
4.
5.
6.
CASING CONFIGURATION
14
Casing string is designed such that the largest diameter is run first followed by
smaller diameter casings.
1. Stove Pipe
(Marine-conductor/ Foundation-pile for offshore drilling)
16
formations
To provide a circulation system for the drilling mud
To ensure the stability of the ground surface under the rig.
This pipe does not usually carry any weight from the
wellhead equipment and can be driven into the ground or
seabed with a pile driver.
A typical size for a stove pipe ranges from 26 in. to 42 in.
2. Conductor Pipe
17
3. Surface Casing
18
4. Intermediate Casing
19
5. Production Casing
20
6. Liner Casing
21
Types of Liner
22
1.
2.
3.
4.
Production liner
Run instead of full production casing
Provide isolation across the producing or injecting zones
Tie-back liner
A section of casing extending upwards from top of an existing liner to
the surface and complete the pressure seal during production.
To provide an upper section of casing which had seen no drilling.
Scab liner
A section of casing that does not reach the surface
Used to repair existing damaged casing sealed from to and bottom by
packers
Scab-tie-back liner
A section of casing extending from the top of an existing liner but
does not reach the surface.
Types of Liner
23
Advantages of Liner
24
shorter length
Running and cementing times are reduced
The length of reduced diameter is reduced which allows
completing the well with optimum sizes of production
tubings.
Complete wells with less weight landed on wellheads and
surface pipe where rig capacity cannot handle full string;
when running heavy 9-5/8" casing.
Disadvantages of Liner
25
CASING PROPERTIES
26
Casing is classified in terms of its size, weight, grade and connection type
Size
The size of a casing is given by the outside diameter (O.D) of the casing.
The standard sizes are 30, 20, 13 3/8, 9 5/8, 7 and 4.5
The pipe less than 4.5 OD is called the tubing.
Casing Weight
The standard weight is specified in weight per unit length
The same OD casing may have different weight and different internal diameter.
Thus the casing weight indicate the wall thickness of the pipe.
Casing Grade
The steel properties of the casing varies widely depending on the chemical
composition.
The API grade indicated the chemical composition (letter) and the minimum yield
strength of a casing (number).
CASING PROPERTIES
27
Grade
Minimum
Yield Strength
(psi)
Minimum
Tensile Strength
(psi)
H-40
40000
60000
J-55
55000
75000
K-55
55000
95000
C-75
75000
95000
L-80
80000
95000
N-80
80000
100000
S-95
95000
110000
P-110
110000
125000
V-150
150000
160000
Casing sizes and string configuration are dictated by the size of the
The bit size to drill a certain interval must be slightly larger than the
31
Bit size to drill a hole in which this casing can be run, 8-5/8-in (Table 7.7)
This 8-5/8-in bit has to pass through the intermediate casing
The intermediate casing size through which the above bit would pass, 9-5/8-in (Table
7.8)
Bit size to drill a hole in which the 9 5/8-in casing can be run, 12--in (Table 7.7).
This 12--in bit has to pass through the surface casing
The surface casing size through which the above bit would pass, 13-3/8-in (Table 7.8)
The bit size to drill a hole in which the 13 3/8-in casing can be run, 17- -in (Table
7.7)
This 17--in bit has to pass through the conductor pipe
The conductor pipe size through which the above bit would pass, 18-5/8-in (Table 7.8)
The bit size to drill a hole in which the 18 5/8-in conductor pipe can be run, 24-in.
To pass a bit through a casing, the drift diameter has to be greater than the bit size
1.
2.
3.
4.
5.
Plot the pore pressure gradient, the mud pressure gradient and the
fracture gradient against depth (Figure 1).
Always start at the highest mud weight; in this example the highest
mud weight is used at TD.
Starting at hole TD (11 000 ft), draw a vertical line (line 1) through
the mud gradient until it intersects the fracture gradient line.
In this example the mud gradient at TD is 0.94 psi/ft and a vertical
line through it (line 1) intersects the fracture gradient line at 10 500 ft
(point A).
Above 10,500 ft, the mud gradient, 0.94 psi/ft, will exceed the
fracture gradient of the open hole section and this section must
therefore be cased off before raising the mud weight to 0.94 psi/ft to
drill the bottom section.
9.
10.
11.
12.
Between 10 500 ft and 11 000 ft the open hole should be cased with either a
production liner or a production casing.
Above 10 500 ft the hole must be drilled with a mud weight less than 0.94
psi/ft.
The new mud gradient is obtained by drawing a horizontal line from point A
to the mud gradient line. Point B in gives the new mud gradient as 0.88
psi/ft.
Move vertically from point B (line 2) until the fracture gradient line is
intersected at 8850 ft at point C. Point C establishes the maximum depth
that can be drilled before changing to the new mud gradient of 0.88 psi/ft.
Hence, between points B and C, an intermediate casing can be set at point B.
Another protective casing should also be set at point D, 8850 ft.
From point C move horizontally to the mud gradient line to point D, where
the mud gradient is 0.68 psi/ft.
A vertical line from point D (line 3) shows that a hole can be drilled with a
mud gradient of 0.68 psi/ft to surface without fracturing the formation.
38
Figure 1:
Casing seat selection
based on mud weight
1.
2.
3.
4.
5.
6.
TD
Figure 2
the fracture gradient. Propose the casing setting depths and the sizes (use 7
production csg.)
TVD
(ft)
Pore pressre
(psi)
Fracture pressure
(psi)
3000
1320
2490
5000
2450
4200
8300
4067
6972
8500
4504
7225
9000
5984
7650
9500
6810
8123
10000
7800
9200
11000
10900
12045
CASING DESIGN
42
Casing design involves 3 distinct operations:
1.
2.
3.
Calculate the loads on the casing and select the most suitable casing grades
and weights for a specific operation, both safely and economically.
operational scenario (while running the casing, drilling subsequent hole section
and producing life of the well)
Minimal cost can be achieved by using lowest possible wt/ft and lowest
Mud to surface
Pressure due to influx when kick happened
Evacuation of the casing
Leakage on production tubing
There are three basic loads/forces which the casing is subjected to:
Collapse
2.
Burst
3.
Tension
Casing needs to withstand loads applied during installation, drilling
process and production. They must first be calculated and must be
maintained below the casing strength properties.
Eg: The collapse pressure must be less than the collapse strength of the
casing and so on.
Casing should initially be designed for collapse, burst and tension.
Refinements to the selected grades and weights should only be
attempted after the initial selection is made.
1.
1. Collapse Load
51
specimen of casing
Collapse pressure originates from the column of mud used to drill the
hole, and acts on the outside of the casing. Since the hydrostatic
pressure of a column of mud increases with depth, collapse pressure is
highest at the bottom and zero at the top.
Pc Pe Pi
How to measure???
Determine the maximum collapse load that
a casing string will be required to withstand
in the worst case scenario:
Determine the lowest pressure that may be
applied inside the casing and the
corresponding highest realistic external
pressure applied.
Casing is assumed empty due to lost circulation at casing setting depth (CSD) or at TD
of next hole.
Internal pressure inside casing is zero
External pressure is caused by mud/cement/pore pressure in which casing was run in
(depends on the load condition).
Hence using the above assumptions and applying Equation 1, only the external
pressure need to be evaluated.
Pore pressure
Mud weight
Column of cement
Pi
Mud weight
= 10ppg
Pi
Cement top
@ 7000ft
Cement = 15.8ppg
Mix water = 8.5ppg
Gas Zone
@ 8500ft
(at surface)
(at top of cement)
(at casing shoe)
53
Po
9-5/8 csg
@8000 ft
Reservoir Press.
= 4000 psi
Gas Gradient
=0.1psi / ft
Formula:
Pressure (psi) = 0.052 x vertical depth (ft) x
fluid weight (ppg)
54
2. Burst Load
55
steel to yield
In oil well casings, burst occurs when the effective internal pressure
Pb Pi Pe
Hydrocarbon influx
Tubing leak
(at surface)
(at top of cement)
(at casing shoe)
(at surface)
(at top of cement)
(at casing shoe)
57
Mud weight
= 10ppg
Cement top
@ 7000ft
Cement = 15.8ppg
Mix water = 8.5ppg
Gas Zone
@ 8500ft
Po
Pi
9-5/8 csg
@8000 ft
Reservoir Press.
= 4000 psi
Gas Gradient
=0.1psi / ft
Formula:
Pressure (psi) = 0.052 x vertical depth (ft) x
fluid weight (ppg)
58
Weight
40 #/ft
43.5 #/ft
47 #/ft
53.5 #/ft
43.5 #/ft
Drift ID
8.68 in.
8.60 in.
8.53 in.
8.38 in.
8.60 in.
Collapse
2570psi
3810psi
4750psi
6620psi
4430psi
Burst
3950psi
6330psi
6870psi
7930psi
8700psi
Tensile
630 klb
1005 klb
1086 klb
1244 klb
1381 klb
Cost
lowest
Select this ?
highest
Casing empty
Fluid SG outside pipe is the mud SG
Beneficial effect of cement is ignored
Design Factor of 1.0
At Surface
Well has a BHP equal to the formation pore
pressure/ reservoir pressure and the producing fluid
is gas.
A gas leak occurs (0.1 psi/ft) in the production
tubing at surface
The CITHP/ shut in pressure is acting on the inside
of the top of casing. This pressure will then act on
the column of packer fluid.
At shoe
Packer Fluid density inside casing/tubing annulus is
the mud density
Fluid density outside casing is the saturated salt
water density (gradient 0.465 psi/ft)
Design Factor of 1.1
Pb Pi Pe 15341 psi
Burst Load at Casing Shoe:
From Table 3.3, grade V-150 & SOO-155 meet the burst requirement.
0
5000
10000
15000
20000
25000
30000
0
2000
4000
6000
8000
10000
12000
14000
Pc
Pb
V-150 38#
V-150 41#
V-150 46#
MW-155
SOO-140
SOO-155
16000
18000
20000
Most axial tension arises from the weight of the casing itself. Other
tension loadings can arise due to: bending, drag, shock loading and
during pressure testing of casing.
In casing design, the uppermost joint of the string is considered the
weakest in tension, as it has to carry the total weight of the casing
string.
The total surface tensile load (sometimes referred to as installation
load) must be determined accurately and must always be less than the
yield strength of the top joint of the casing.
The installation load must be less than the rated derrick load capacity
so that the casing can be run in or pulled out of hole without causing
damage to the derrick.
1.
2.
3.
3.
4.
In the initial selection of casing, check that the casing can carry its own weight in
mud and when the casing is finally chosen, calculate the total tensile loads and
compare them with the joint or pipe body yield values, using the lower of the two
values.
A design factor (1.6 to 1.8) of coupling or pipe body yield strength divided by
total tensile loads in tension should be used.
SF
Yp
Total Tensile Load = Cumulative Wet Weight carried by top joint + Shockload +
bending force + drag force + pressure testing force
Calculated Safety Factor, SF should exceed the specified SF (1.6 to 1.8).
68
Depth (ft)
Grade
From To
0 6000 V-150 38#
6000 12000 MW-155
12000 19000 V-150 46#
Length
6000
6000
7000
Total
SF
Tensile
686428 2.083248
520900 3.056249
380972 3.527818
Yp
Total Tensile Load
Where:
Wet Weight/ Buoyant weight = Wn x Length x BF
Shockload
Yp
69