Beruflich Dokumente
Kultur Dokumente
Volume of excavation
Volume A
Volume B
Volume C
Total Volume
2907.356
7125.132
1013.164
11045.652 (before swelling)
13807.065
Excavators
1
2
3
4
5
6
7
8
9
10
Cost
$13,807.07
$14,533.75
$15,341.18
$16,243.61
$17,258.83
$18,409.42
$19,724.38
$21,241.64
$23,011.78
$25,103.75
Productivity
Rate
50
50
lcm/h
$/h
For 5 excavators, each excavator working at 80% productivity, hence 40 lcm/h equals to 10 lcm in 15m
Truck cycle 30+15=45min.
Therefore, optimum number of trucks per excavator is 45/15 = 3.
For 6 excavators, each excavator working at 75% productivity, hence 37.5 lcm/h equals to 10 lcm in 1
Truck cycle 30+16=46min.
Therefore, optimum number of trucks per excavator = 46/16 = 2.875.
Choose 2 or 3 trucks per excavator.
Amount to haul
9561.729705882 lcm
If 5 excavators,
Per excavator
1,912.35 lcm
Truck loads
191.23 loads
If 2 trucks are used, truck cycle governs.
Duration of hauling
71.7129727941 h
Truck cost per detail
$2,868.52
Total cost
$14,342.59
COST
TIME TAKEN (HRS)
EXCAVATION
HAULING
$17,258.83
69.04
$14,342.59
47.81
Bedding
Materials:
Volume of Gravel Bedding
Area of Bedding
Cost
Productivity
Rate
No. of compactors
403.67 m3
1009.1856 m2
120 $ per m3
30 m2 per hr
20 $ per hr
Productivity
Duration in hrs
Cost
1
100%
33.64
2
95%
17.71
3
90%
12.46
4
85%
9.89
5
80%
8.41
6
75%
7.48
7
70%
6.87
8
65%
6.47
9
60%
6.23
672.79
708.20
747.54
791.52
840.99
897.05
961.13
1035.06
1121.32
COST
TIME TAKEN
Total Material Cost
48440.4 $
Duration in Days
4.20
2.21
1.56
1.24
1.05
0.93
0.86
0.81
0.78
49281.39
8.41
Scaffolding
Scaffolding Cost
Productivity (installation)
Productivity (disassemble)
Rate of installation
Rate of disassembling
25
0.10
0.05
5
5
Radius from centre to build
outer scaffold (m)
35.35
18.61
13.09
10.40
8.84
7.86
7.22
6.80
6.55
6.43
1988.69
Radius from centre to outer
scaffold (m)
13.87
7.30
5.14
4.08
3.47
3.08
2.83
2.67
2.57
2.52
3 times dismantling of
h=8.6m outer scaffold
cost
959.91
$ per m2
hr per m2
hr per m2
$/hr/man
$/hr/man
Perimeter of outer scaffold (m)
area of 1/3 outer
scaffold, h=9.1 (m2)
116.5530874482
353.5443652595
area of 1/3 outer lower,h=5.1 (m2)
198.1402486619
Labour cost
530.32
558.23
589.24
623.90
662.90
707.09
757.60
815.87
883.86
964.21
3 times erection of h=5.1m outer
3 times erection of
scaffold
h=9.1m inner scaffold
1114.54
1245.86
Perimeter of outer scaffold (m)
area of 1/3 outer
scaffold, h=9.1 (m2)
91.4203462195
277.3083835324
area of 1/3 outer lower,h=5.1 (m2)
164.4503204669
Labour cost
207.98
218.93
231.09
244.68
259.98
277.31
297.12
319.97
346.64
378.15
22574.04
10
Labour cost
($/h/crew)
Productivity (m2/h/crew)
20
15
10
1.50
Labour cost
297.21
312.85
330.23
349.66
371.51
396.28
424.59
457.25
495.35
540.38
dismantling
Labour cost
123.34
129.83
137.04
145.10
154.17
164.45
176.20
189.75
205.56
224.25
10
228.98
241.03
254.43
269.39
286.23
305.31
327.12
352.28
381.64
2.78
416.33
inner scaffolding
material cost $
5537.17747967
for height 4.542, inner scaffold erecting
Crew
Time taken (h)
Labour
1
12.51
2
6.58
3
4.63
4
3.68
5
3.13
6
2.78
7
2.55
8
2.41
9
2.32
10
2.27
cost
187.64
197.51
208.49
220.75
234.55
250.19
268.06
288.68
312.73
341.16
10
1.47
220.41
Reinforcement
Total weight of rebar
Rebar cost
Total cost of rebar
195252.93 kg
$550/ton
$ 107,389.11
Fabrication
Rebar fab for 1/2 slab
Volume of Concrete
Rebar weight
Rate
Unit cost
No. of man
302.76 m3
54496.8 kg
100kg/hr/man
$5/hr/man
Duration in
Productivity
Duration in hours Cost
days
1
100%
544.97
2724.84
68.12
2
100%
272.48
2724.84
34.06
3
100%
181.66
2724.84
22.71
4
100%
136.24
2724.84
17.03
5
100%
108.99
2724.84
13.62
6
95%
95.61
2868.25
11.95
7
90%
86.50
3027.60
10.81
8
85%
80.14
3205.69
10.02
9
80%
75.69
3406.05
9.46
10
75%
72.66
3633.12
9.08
No. of man
Duration in
Productivity
Duration in hours Cost
days
1
100%
180.16
900.82
22.52
2
100%
90.08
900.82
11.26
3
100%
60.05
900.82
7.51
4
100%
45.04
900.82
5.63
5
100%
36.03
900.82
4.50
6
95%
31.61
948.23
3.95
7
90%
28.60
1000.91
3.57
8
85%
26.49
1059.79
3.31
9
10
80%
75%
25.02
24.02
1126.03
1201.09
3.13
3.00
No. of man
Duration in
Productivity
Duration in hours Cost
days
1
100%
107.37
536.84
13.42
2
100%
53.68
536.84
6.71
3
100%
35.79
536.84
4.47
4
100%
26.84
536.84
3.36
5
100%
21.47
536.84
2.68
6
95%
18.84
565.09
2.35
7
90%
17.04
596.48
2.13
8
85%
15.79
631.57
1.97
9
80%
14.91
671.04
1.86
10
75%
14.32
715.78
1.79
Erection
Rebar install for 1/2 slab
Volume of Concrete
302.76 m3
Rebar weight
54496.8 kg
Rate
15hr/ton
66.67kg/hr
Unit cost
$5/hr/man
$15/hr/crew
No. of crew
Duration in
Productivity
Duration in hours Cost
days
1
100%
817.41 12261.17
102.18
2
95%
430.22 12906.49
53.78
3
90%
302.74 13623.52
37.84
4
85%
240.42 14424.90
30.05
5
80%
204.35 15326.46
25.54
6
75%
181.65 16348.22
22.71
7
70%
166.82 17515.95
20.85
8
65%
157.19 18863.33
19.65
Volume of Concrete
Rebar weight
Rate
Unit cost
No. of crew
100.09 m3
18016.404 kg
15hr/ton
66.67kg/hr
$5/hr/man
15/hr/crew
Duration in
Productivity
Duration in hours Cost
days
1
100%
270.23
4053.49
33.78
2
95%
142.23
4266.83
17.78
3
90%
100.09
4503.88
12.51
4
85%
79.48
4768.81
9.94
5
80%
67.56
5066.86
8.44
6
75%
60.05
5404.65
7.51
7
70%
55.15
5790.70
6.89
8
65%
51.97
6236.14
6.50
No. of crew
Duration in
Productivity
Duration in hours Cost
days
1
100%
161.04
2415.64
20.13
2
95%
84.76
2542.78
10.59
3
90%
59.65
2684.04
7.46
4
85%
47.37
2841.93
5.92
5
80%
40.26
3019.55
5.03
6
75%
35.79
3220.85
4.47
7
70%
32.87
3450.91
4.11
8
65%
30.97
3716.37
3.87
No. of crew
Productivity
Duration in
days
1
2
3
4
5
6
7
8
100%
95%
90%
85%
80%
75%
70%
65%
272.48
143.41
100.92
80.14
68.12
60.55
55.61
52.40
4087.26
4302.38
4541.40
4808.54
5109.08
5449.68
5838.94
6288.09
34.06
17.93
12.62
10.02
8.52
7.57
6.95
6.55
No. of crew
Duration in
Productivity
Duration in hours Cost
days
1
100%
90.08
1351.23
11.26
2
95%
47.41
1422.35
5.93
3
90%
33.36
1501.37
4.17
4
85%
26.49
1589.68
3.31
5
80%
22.52
1689.04
2.82
6
75%
20.02
1801.64
2.50
7
70%
18.38
1930.33
2.30
8
65%
17.32
2078.82
2.17
No. of crew
Duration
Productivity
Duration in hours Cost
days
1
100%
53.68
805.25
2
95%
28.25
847.63
3
90%
19.88
894.73
4
85%
15.79
947.36
5
80%
13.42
1006.57
6
75%
11.93
1073.67
7
70%
10.96
1150.36
8
65%
10.32
1238.85
in
6.71
3.53
2.49
1.97
1.68
1.49
1.37
1.29
Fabrication
Rebar for 1/2 slab
Rebar for whole slab
Rebar for 1/3 Bottom Wall
Rebar for whole bottom wall
Rebar for 1/3 Upper Wall
Rebar for whole upper wall
Sum
Total cost
Labor Cost
3205.69
1059.79
631.57
118,874.58
for
for
for
for
for
for
Labor Cost
1/2 slab
whole slab
1/3 Bottom Wall
whole bottom wall
1/3 Upper Wall
whole upper wall
Total cost
14424.90
4768.81
2841.93
51,682.02
170,556.59
Labor Cost
6288.09
2078.82
1073.67
Total cost
39,261.84
158,136.42
4808.54
1589.68
947.36
Material Cost
29973.24
6411.3882353
59946.48
9909.0222
3179.3654118
29727.0666
5905.1883
1894.7128235
11485.466471
17715.5649
107389.1115
28849.804569
14306.43
8525.78
51682.015017
9617.0823529
1589.68
6236.45
4769.0481176
947.36
3221.01
22033.64
2842.0692353
17228.199706
Formwork
Concrete Works
Formwork fabrication
Formwork installation
Productivitiy
2m2/hr/man
1 hr/m2
Curve
Middle (3 portions)
Total
1/3 of Walls
Total formwork
Rate
Total Cost
Rates
$5/hr/man
$5/hr/man
695.9121517259 m2
25 $ per m2
17397.8037931467 $
Fabrication
Formwork fab for 1/2 slab
(curve+middle)
Productivity
Rate
2m2/hr/man
$5/hr/man
No. of man
Productivity
55.5956 m2
1
2
3
4
5
6
7
8
9
10
Duration in
hours
100.00%
27.80
100.00%
13.90
100.00%
9.27
100.00%
6.95
100.00%
5.56
95.00%
4.88
90.00%
4.41
85.00%
4.09
80.00%
3.86
75.00%
3.71
333.5511365174 m2
2m2/hr/man
$5/hr/man
No. of man
Productivity
1
2
3
4
5
6
7
8
9
10
Duration in
hours
100.00%
166.78
100.00%
83.39
100.00%
55.59
100.00%
41.69
100.00%
33.36
95.00%
29.26
90.00%
26.47
85.00%
24.53
80.00%
23.16
75.00%
22.24
298.1654152085 m2
2m2/hr/man
$5/hr/man
No. of man
Productivity
1
2
3
4
5
6
7
8
9
10
2m2/hr/man
$5/hr/man
No. of man
Productivity
Duration in
hours
100.00%
149.08
100.00%
74.54
100.00%
49.69
100.00%
37.27
100.00%
29.82
95.00%
26.15
90.00%
23.66
85.00%
21.92
80.00%
20.71
75.00%
19.88
8.6 m2
Duration in
hours
0.85
0.63
Installation
1m2/hr/man
$5/hr/man
No. of crew
Productivity
34.4772 m2
1
2
3
4
5
6
7
8
9
10
1m2/hr/man
$5/hr/man
No. of crew
Productivity
15/hr/crew
Duration in
hours
1
34.4772
0.95
18.15
0.9
12.77
0.85
10.14
0.8
8.62
0.75
7.66
0.7
7.04
0.65
6.63
0.6
6.38
0.55
6.27
21.1184 m2
1
2
3
4
5
6
7
8
9
15/hr/crew
Duration in
hours
1
21.1184
0.95
11.11
0.9
7.82
0.85
6.21
0.8
5.28
0.75
4.69
0.7
4.31
0.65
4.06
0.6
3.91
10
0.55
3.84
No. of crew
Productivity
1
2
3
4
5
6
7
8
9
10
Duration in
hours
1 333.551136517
0.95 175.553229746
0.9 123.537457969
0.85 98.1032754463
0.8 83.3877841293
0.75 74.1224747816
0.7 68.0716605138
0.65 64.1444493303
0.6 61.7687289847
0.55 60.645661185
No. of crew
Productivity
1
2
3
4
5
6
7
8
9
10
Duration in
hours
1 298.165415208
0.95 156.929165899
0.9 110.431635262
0.85 87.6957103554
0.8 74.5413538021
0.75 66.2589811574
0.7 60.8500847364
0.65 57.3395029247
0.6 55.2158176312
0.55 54.2118936743
1m2/hr/man
$5/hr/man
15/hr/crew
No. of crew
Productivity
Duration in
hours
5.4 m2
1
2
3
4
5
6
7
8
9
10
1
0.95
0.9
0.85
0.8
0.75
0.7
0.65
0.6
0.55
5.4
2.8421052632
2
1.5882352941
1.35
1.2
1.1020408163
1.0384615385
1
0.9818181818
Unit
(crew of 3 men)
areas
34.4772
21.1184
55.5956 m2
Material cost
861.93 $
527.96 $
1389.89 $
163.9911365174
169.56
147.4454152085
150.72
5.4
3.2
640.3165517259 m2
4099.77841293 $
4239 $
3686.13538021 $
3768 $
135 $
80 $
16007.9137931 $
Cost
Duration in
days
138.99
3.47
138.99
1.74
138.99
1.16
138.99
0.87
138.99
0.69
146.30
0.61
154.43
0.55
163.52
0.51
173.74
0.48
185.32
0.46
Cost
Cost
Cost
Duration in
days
833.88
20.85
833.88
10.42
833.88
6.95
833.88
5.21
833.88
4.17
877.77
3.66
926.53
3.31
981.03
3.07
1042.35
2.90
1111.84
2.78
Duration in
days
745.41
18.64
745.41
9.32
745.41
6.21
745.41
4.66
745.41
3.73
784.65
3.27
828.24
2.96
876.96
2.74
931.77
2.59
993.88
2.48
Duration in
days
25.29
0.08
Formwork installation
for curve of 1/2 slab
( to be done twice)
Productivity
Rate
Cost
Duration in
days
517.158
4.30965
544.38
2.27
574.62
1.60
608.42
1.27
646.45
1.08
689.54
0.96
738.80
0.88
795.63
0.83
861.93
0.80
940.29
0.78
No. of crew
1
2
3
4
5
6
7
8
9
10
Formwork installation
for middle slab
Productivity
Rate
Cost
Duration in
days
316.776
2.6398
333.45
1.39
351.97
0.98
372.68
0.78
395.97
0.66
422.37
0.59
452.54
0.54
487.35
0.51
527.96
0.49
No. of crew
1
2
3
4
5
6
7
8
9
575.96
0.48
10
Formwork installation
for 1/3lower wall
Productivity
Rate
Duration in
Cost
days
5003.2670477608 41.693892065
5266.60
21.94
5559.19
15.44
5886.20
12.26
6254.08
10.42
6671.02
9.27
7147.52
8.51
7697.33
8.02
8338.78
7.72
9096.85
7.58
No. of crew
1
2
3
4
5
6
7
8
9
10
Formwork installation
for 1/3 upper wall
Productivity
Rate
Duration in
Cost
days
4472.4812281272 37.270676901
4707.87
19.62
4969.42
13.80
5261.74
10.96
5590.60
9.32
5963.31
8.28
6389.26
7.61
6880.74
7.17
7454.14
6.90
8131.78
6.78
No. of crew
1
2
3
4
5
6
7
8
9
10
Formwork installation
for one block
Productivity
Rate
Cost
Duration in
days
81
0.675
85.26
0.36
90.00
0.25
95.29
0.20
101.25
0.17
108.00
0.15
115.71
0.14
124.62
0.13
135.00
0.13
147.27
0.12
No. of crew
1
2
3
4
5
6
7
8
9
10
Fabrication
Formwork
Workers
1/2 Slab(curve+middle)
1/3 lower Wall
1/3 upper wall
2 blocks
sum
Rate ($/hr)
5
8
8
8
Time (Hr)
5
5
5
5
5.56
24.53
21.92
0.63
TOTAL FAB COST
Installation
Formwork
1/2 Slab
Middle Slab
Lower wall
Upper wall
block
Dismantling
Formwork
1/2 Slab
Middle Slab
Lower wall
Crews
Rate ($/hr)
6
5
8
8
3
Crews
Upper wall
Installation w/ Crane
Formwork
Crews
1/2 Slab
Middle Slab
Lower wall
Time (Hr)
15
15
15
15
15
Rate ($/hr)
7.66
5.28
64.14
57.34
2.00
TOTAL INSTALLATION COST
Time (Hr)
1
1
1
15
15
15
15
8
8
8
8
TOTAL DISMANTLING COST
66931.05
Rate ($/hr)
6
6
10
Time (Hr)
15
15
15
2.55
1.56
20.22
Upper wall
block
10
1
46430.97
15
15
18.07
1.80
34.4772 m2
3m2/hr/man
$5/hr/man
Productivity
15/hr/crew
60$/hr/crane
Duration in
hours
Cost
1
11.49
0.95
6.05
0.9
4.26
0.85
3.38
0.8
2.87
0.75
2.55
0.7
2.35
0.65
2.21
0.6
2.13
0.55
2.09
Duration in
days
172.39
1.44
181.46
0.76
191.54
0.53
202.81
0.42
215.48
0.36
229.85
0.32
246.27
0.29
265.21
0.28
287.31
0.27
313.43
0.26
21.1184 m2
3m2/hr/man
$5/hr/man
15/hr/crew
60$/hr/crane
Productivity
Duration in
hours
Cost
1
0.95
0.9
0.85
0.8
0.75
0.7
0.65
0.6
7.04
3.70
2.61
2.07
1.76
1.56
1.44
1.35
1.30
Duration in
days
105.59
0.88
111.15
0.46
117.32
0.33
124.23
0.26
131.99
0.22
140.79
0.20
150.85
0.18
162.45
0.17
175.99
0.16
0.55
333.5511365174 m2
3m2/hr/man
$5/hr/man
15/hr/crew
Productivity
191.99
0.16
60$/hr/crane
Duration in
hours
Cost
1
111.18
0.95
58.52
0.9
41.18
0.85
32.70
0.8
27.80
0.75
24.71
0.7
22.69
0.65
21.38
0.6
20.59
0.55
20.22
298.1654152085 m2
1m2/hr/man
$5/hr/man
15/hr/crew
Productivity
1.28
Duration in
days
1667.76
13.90
1755.53
7.31
1853.06
5.15
1962.07
4.09
2084.69
3.47
2223.67
3.09
2382.51
2.84
2565.78
2.67
2779.59
2.57
3032.28
2.53
60$/hr/crane
Duration in
hours
Cost
1
99.39
0.95
52.31
0.9
36.81
0.85
29.23
0.8
24.85
0.75
22.09
0.7
20.28
0.65
19.11
0.6
18.41
0.55
18.07
Duration in
days
1490.83
12.42
1569.29
6.54
1656.47
4.60
1753.91
3.65
1863.53
3.11
1987.77
2.76
2129.75
2.54
2293.58
2.39
2484.71
2.30
2710.59
2.26
5.4 m2
3m2/hr/man
$5/hr/man
15/hr/crew
60$/hr/crane
Productivity
Duration in
hours
Cost
1
0.95
0.9
0.85
0.8
0.75
0.7
0.65
0.6
0.55
1.80
0.95
0.67
0.53
0.45
0.40
0.37
0.35
0.33
0.33
Duration in
days
27.00
0.23
28.42
0.12
30.00
0.08
31.76
0.07
33.75
0.06
36.00
0.05
38.57
0.05
41.54
0.04
45.00
0.04
49.09
0.04
Labour Cost
Material cost
138.99
981.03
876.96
25.29
2022.27
L FAB COST
Each installation
1389.89
8338.7784129347
7454.135380212
215
17397.8037931467
19420.08
Total Cost
689.54
395.97
7697.33
6880.74
90.00
1379.09
395.97
23092.00
20642.22
540.00
46049.28
L INSTALLATION COST
Each dismantling
Total cost
120
120
120
240
120
360
120
360
1080
L DISMANTLING COST
Each installation
229.85
140.79
3032.28
mobile crane
each installation
153.232
93.8595555556
1212.9132236996
2710.59
8131.78
27.00
162.00
TOTAL LABOUR COST
17991.12
TOTAL INSTALLATION COST WITH CRANE
1084.2378734854
108
TOTAL MOBILE CRANE COST
153.232
93.85956
1212.913
1084.238
108
3252.7136204562
648
7939.7768471105
25930.90
sum
11384.50
810.00
25930.90
Concreting
Rate
1/2 Slab
2/2 Slab
Lower wall 1
Lower wall 2
Lower wall 3
Upper wall 1
Upper wall 2
Upper wall 3
Total
1/2 slab concreting
Crew
Unit Price
Work rate
No. of crew
100 $ per m3
302.76 m3
302.76 m3
100.09 m3
100.09 m3
100.09 m3
59.65 m3
59.65 m3
59.65 m3
$
$
$
$
$
$
$
$
1084.74 m3
30,276.00
30,276.00
10,009.11
10,009.11
10,009.11
5,964.84
5,964.84
5,964.84
$ 108,473.85
302.76
3 units
5/hr/man
10m3/hr/crew
15/hr/crew
Productivity
Duration in Hours
$ Cost
1
100%
30.28
2
95%
15.93
3
90%
11.21
4
85%
8.90
5
80%
7.57
6
75%
6.73
454.14
478.04
504.60
534.28
567.68
605.52
100.09
3 units
5/hr/man
10m3/hr/crew
15/hr/crew
Productivity
Duration in Hours
$ Cost
1
100%
10.01
2
95%
5.27
3
90%
3.71
4
85%
2.94
5
80%
2.50
6
75%
2.22
59.65
3 units
150.14
158.04
166.82
176.63
187.67
200.18
Unit Price
Work rate
No. of crew
5/hr/man
10m3/hr/crew
15/hr/crew
Productivity
Duration in Hours
$ Cost
1
100%
5.96
2
95%
3.14
3
90%
2.21
4
85%
1.75
5
80%
1.49
6
75%
1.33
89.47
94.18
99.41
105.26
111.84
119.30
Total Cost
Duration in Days
3.78
1.99
1.40
1.11
0.95
0.84
Duration in Days
1.25
0.66
0.46
0.37
0.31
0.28
Duration in days
0.75
0.39
0.28
0.22
0.19
0.17
108,473.85
1068.56
845.68
110,388.09
Finishing
Areas
Lower Wall, h=4.5
Upper Wall=h=4.0
Slab with d=6m
Slab (outer circle)
491.973 m2
442.336 m2
28.274 m2
980.9116 m2
1943.496
504.5929669412 m2
2 m2/man/hour
$5/hr/man
No of workers
Productivity
1
2
3
4
5
6
7
8
9
10
11
12
$5/hr/man
No of workers
Productivity
Duration in hrs
100%
252.30
100%
126.15
100%
84.10
100%
63.07
100%
50.46
95%
44.26
90%
40.05
85%
37.10
80%
35.04
75%
33.64
70%
32.77
65%
32.35
163.991 m2
2 m2/man/hour
1
2
3
4
5
6
7
8
9
10
Duration in hrs
100%
82.00
100%
41.00
100%
27.33
100%
20.50
100%
16.40
95%
14.39
90%
13.02
85%
12.06
80%
11.39
75%
10.93
11
12
70%
65%
10.65
10.51
COST
Cost
Duration in Days
1261.48
31.54
1261.48
15.77
1261.48
10.51
1261.48
7.88
1261.48
6.31
1327.88
5.53
1401.65
5.01
1484.10
4.64
1576.85
4.38
1681.98
4.20
1802.12
4.10
1940.74
4.04
Upper wall 1/3, h=3.5m
Work Rate
Unit cost
Cost
Duration in Days
409.98
10.25
409.98
5.12
409.98
3.42
409.98
2.56
409.98
2.05
431.56
1.80
455.53
1.63
482.33
1.51
512.47
1.42
546.64
1.37
No of workers
1
2
3
4
5
6
7
8
9
10
585.68
630.74
1.33
1.31
11
12
147.445 m2
2 m2/man/hour
$5/hr/man
Productivity
Duration in hrs
100%
100%
100%
100%
100%
95%
90%
85%
80%
75%
Cost
73.72
36.86
24.57
18.43
14.74
12.93
11.70
10.84
10.24
9.83
Duration in Days
368.61
9.22
368.61
4.61
368.61
3.07
368.61
2.30
368.61
1.84
388.01
1.62
409.57
1.46
433.66
1.36
460.77
1.28
491.48
1.23
70%
65%
9.57
9.45
526.59
567.10
1.20
1.18
tion in Days
Backfill
Volume of backfill
Excavated volume
Volume A
Volume B
Backfill required
Productivity
Volume required
Rate
Cost
No. of units
13807.065 lcm
2702.084
184.744
2886.828 ccm
3396.2682352941 bcm
4245.3352941177 lcm
10 lcm/h
4245.335294118 ccm
10 m3 per hr
50 $ per hr
Productivity
Duration in Hours
Cost
1
100%
424.53
2
95%
223.44
3
90%
157.23
4
85%
124.86
5
80%
106.13
6
75%
94.34
7
70%
86.64
8
65%
81.64
9
60%
78.62
10
55%
77.19
$
21226.68
22343.87
23585.20
24972.56
26533.35
28302.24
30323.82
32656.43
35377.79
38593.96
COST
haul
Duration in Days
53.07
27.93
19.65
15.61
13.27
11.79
10.83
10.21
9.83
9.65
BACKFILL
30323.82
Overhead
Start
End
Total calender Days
Total Calender Months
Mobilization and demobilization
Total working days
Overhead Cost
Project Manager
Foreman x 3
Project Manager for 121.5 days
Foreman for 121.5 days
TOTAL OVERHEAD COST
9/21/2015
2/13/2016
146
6
9
121.5
$
3500
6000
17718.75
30375
48094
Mobilisation
Equipments/Labor
Project manager
Foreman
Quantity/Un
Duration (hr)
1
48
3
48
Total
Demobilisation
Equipments/Labor
Project manager
Foreman
Quantity/Un
Duration (hr)
1
24
3
24
Total
Labour/Equipment Cost
875
1500
2375
Labour/Equipment Cost
437.5
750
1187.5
equipment cost
Mobilisation
Excavation
Hauling
Bedding
Scaffolding erection
scaffolding dismantling
Reinforcement fabrication
reinforcement erection(w/ crane)
Formwork fabrication
formwork installation(w/crane)
formwork dismantling
concreting
finishing
backfill
overhead
Demobilisation
sum
labour cost
0
2375
17258.83
0.00
14342.5945588235
0
840.99
0
0
5052.74
0
3145.51
0 11485.46647059
17228.1997058824
22033.64
0
2022.27
7939.7768471105
17991.12
0
1080
0
1914.24
0
5822.66
30323.82
0
0
48094
0
1187.5
87934.2138912281 122203.9098329
material cost
0
0.00
0
48440.4
14375.79
0
107389.11
0
17397.803793147
0
0
108473.85
0
0
0
0
296076.95190431
sum of cost
2375
17258.83
14342.5945588
49281.39
19428.52
3145.51416488
118874.577971
39261.8436597
19420.0767688
25930.8954093
1080
110388.094412
5822.66273183
30323.8235294
48093.75
1187.5
506215.0756
506215.076