Sie sind auf Seite 1von 47

PowerCube 1000

V300R005C13

Installation Guide
(G2, ICC500, ESU-A)
Issue

02

Date

2014-02-15

HUAWEI TECHNOLOGIES CO., LTD.

Copyright Huawei Technologies Co., Ltd. 2014. All rights reserved.


No part of this document may be reproduced or transmitted in any form or by any means without prior
written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions


and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.

Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees or
representations of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.


Address:

Huawei Industrial Base


Bantian, Longgang
Shenzhen 518129
People's Republic of China

Website:

http://www.huawei.com

Email:

support@huawei.com

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

About This Document

About This Document


Propose
This document describes how to install the cabinet, boards, modules and cables for reference.
Figures used in this document are for reference only.

Safety Precautions
To ensure safety of humans and the equipment, pay attention to the safety symbols on the
equipment and all the safety instructions in this document. The "NOTE", "CAUTION", and
"WARNING" marks in other documents do not represent all the safety instructions. They are
only supplements to the safety instructions. When operating Huawei equipment, in addition to
following the general precautions in this document, follow the specific safety instructions
given by Huawei. Huawei will not be liable for any consequences that are caused by the
violation of safety regulations and design, production, and usage standards.

Local Safety Regulations


Only trained and qualified personnel are allowed to install, operate, and maintain Huawei
equipment.

Personnel Requirements
Only trained and qualified personnel are allowed to install, operate, and maintain Huawei
equipment. You can modify default parameters only after being granted approval from
Huawei technical support.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

ii

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

About This Document

Symbols

Indicates an imminently hazardous situation which, if not avoided, will result in death or
serious injury.

Alerts you to a potentially hazardous situation that could, if not avoided, result in equipment
damage, data loss, performance deterioration, or unanticipated results.

Provides additional information to emphasize or supplement important points in the main text.

Human Safety

To prevent electric shock, get the tool insulated and wear insulated gloves when
connecting cables.

To prevent inhalation or eye contact with dust, take adequate preventive measures when
drilling holes.

To avoid potential damage, wear protective shoes when moving batteries.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

iii

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

Contents

Contents
About This Document .................................................................................................................... ii
1 Network Diagram ......................................................................................................................... 1
1.1 Network Diagram ......................................................................................................................................................... 1

2 Install Preparation ........................................................................................................................ 2


2.1 Installation Dimensions ................................................................................................................................................ 2
2.2 Tools ............................................................................................................................................................................. 3
2.3 Appearance and Installation Positions .......................................................................................................................... 4
2.4 Cables Routing Reference ............................................................................................................................................ 6

3 Install Equipment ......................................................................................................................... 9


3.1 Installing an ICC500 Cabinet ....................................................................................................................................... 9
3.2 Installing PSUs ........................................................................................................................................................... 12
3.3 Installing a ESMU ...................................................................................................................................................... 13
3.4 Installing an ESS-A .................................................................................................................................................... 13
3.5 Turning off the Power Switch ..................................................................................................................................... 15

4 Install Cables ............................................................................................................................... 17


4.1 Installing Cables for ESS-A (ESU-A2400Wh/D) ....................................................................................................... 17
4.2 Installing a CAN Communications Cable with an RJ45 connector for the ECC500 .................................................. 19
4.3 (Optional) Installing a Communications Cable .......................................................................................................... 20
4.4 Installing Cables for Sensors ...................................................................................................................................... 21
4.5 Installing AC Power Cables ........................................................................................................................................ 26
4.6 Installing Load Power Cables ..................................................................................................................................... 26

5 Power On the PowerCube 1000 ................................................................................................ 27


5.1 Checking Before Power-on ......................................................................................................................................... 27
5.2 Connecting the AC Input and ESS Supply.................................................................................................................. 27
5.3 Setting parameters ...................................................................................................................................................... 30
5.4 Check the ESS-A ........................................................................................................................................................ 32
5.5 Connecting the Mains Supply ..................................................................................................................................... 34
5.6 Powering On Loads .................................................................................................................................................... 34
5.7 Checking After Power-On .......................................................................................................................................... 35

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

iv

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

Contents

A Appendix ..................................................................................................................................... 36
A.1 Installing Floating Nuts ............................................................................................................................................. 36
A.2 Preparing Terminals ................................................................................................................................................... 38
A.3 Port Description ......................................................................................................................................................... 38

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

1 Network Diagram

Network Diagram

1.1 Network Diagram


An integrated controller and converter 500 (ICC500) is applicable to mains+energy storage system-A
(ESS-A) scenario.

(a1) AC input power cable between the mains and the alternating current distribution unit (ACDU)
(d1) DC power cable between ESS-A and the direct current distribution unit (DCDU)
(d2) DC cable between the DCDU and the DC load
(s1) (Optional) Communications cable between the ECC500 and the transport network
(s2) Signal cable between the ESS-A and the ECC500

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

2 Install Preparation

Install Preparation

2.1 Installation Dimensions


Figure 2-1 Installation Dimensions
Unit: mm

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

2 Install Preparation

2.2 Tools
Before you begin, get the following tools ready.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

2 Install Preparation

2.3 Appearance and Installation Positions


Figure 2-2 Appearance (with 100 Ah ACBs)

(1) Fan assembly

(2) Filler panel

(3) ECC500

(4) DCDU

(5) PSU subracks

(6) RTN(+)

(7) NEG(-)

(8) ESMU

(9) ESU-A2400wh/D

(10) ACDU

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

2 Install Preparation

Figure 2-3 Appearance (with 200 Ah ACBs)

(1) Fan assembly

(2) Filler panel

(3) ECC500

(4) DCDU

(5) PSU subracks

(6) RTN(+)

(7) NEG(-)

(8) ESMU

(9) ESU-A2400wh/D

(10) ACDU

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

2 Install Preparation

2.4 Cables Routing Reference


Figure 2-4 Reference for routing cables through the cable holes at the bottom of the cabinet

(1) AC input power cable

(2) Signal cable for customer equipment

(4) Load power cable

(5) Signal cable

Issue 02 (2014-02-15)

(3) Power cable for customer equipment

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

2 Install Preparation

Figure 2-5 Cables routing reference (with 100 Ah ACBs)

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

2 Install Preparation

Figure 2-6 Cables routing reference (with 200 Ah ACBs)

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3 Install Equipment

Install Equipment

3.1 Installing an ICC500 Cabinet


Procedure
Step 1 Mark the position of the cabinet based on the delivered marking-off template to confirm the
positions of the expansion bolt.
Figure 3-1 Mark the position of the cabinet

(1) Marker

Issue 02 (2014-02-15)

(2) Marking-off template

(3) Mounting hole

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

(4) concrete floor

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3 Install Equipment

Step 2 Drill holes and install expansion tubes.


Figure 3-2 Drill holes and install expansion tubes

(1) Bolt

(2) Spring washer

(3) Flat washer

(4) Expansion tube

(5) Socket wrench

Step 3 Install the cabinet.


Figure 3-3 Using a crane

Figure 3-4 Using a pallet truck

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

10

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3 Install Equipment

Step 4 Secure the cabinet.


Figure 3-5 Secure the cabinet

Step 5 Connect the ground cable.


Figure 3-6 Connect the ground cable

(1) Site ground bar

(2) Cabinet ground bar

Ground the cabinet immediately after installing it.


----End

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

11

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3 Install Equipment

3.2 Installing PSUs

To avoid personal injury, install filler panels in vacant subracks.

Install a maximum of six PSUs based on the required capacity.

Procedure
Step 1 Remove the bolts from the handle. Ensure that the module handle is open.
Step 2 Pull handle out.
Step 3 Gently push the PSU into the related slot along the guide rail.
Step 4 Push the handle upwards, lock the handle.
Step 5 Tighten the bolts in the handle and secure the handle.
Figure 3-7 Installing aPSU

----End

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

12

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3 Install Equipment

3.3 Installing a ESMU


Procedure
Step 1 Install the ESMU in the cabinet.
Figure 3-8 Installing a ESMU

----End

3.4 Installing an ESS-A


Context

Misoperations on ESUs will cause damage.


To prevent short circuits or electrolyte overflow, pay attention to the following items before
installing ESUs:

Remove the watch and metal jewelry such as bracelets, bangles, and rings from your wrist.

Use dedicated insulated tools.

Carry ESUs gently.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

13

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3 Install Equipment

Procedure
Step 1 Install the ESU-A2400Wh/N or ESU-A2400Wh/D.
Figure 3-9 Secure equipment by using Phillips bolts

Figure 3-10 Secure equipment by using antitheft bolts

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

14

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3 Install Equipment

Step 2 Set the dual in-line package (DIP) switch addresses in ascending order from the bottom
ESMU to the top ESMU by referring to the following table.

The addresses of ESMU must be different from each other.


----End

3.5 Turning off the Power Switch


Procedure
Step 1 Remove the fuse from the DCDU.
1.

Remove the DCDU panel.

2.

Switch all DC load circuit breakers to OFF.

3.

Flip the battery switch to NORMAL.

4.

Remove the fuse from the DCDU by using a fuse extracting unit.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

15

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3 Install Equipment

Step 2 Flip all switches on the ESMU to OFF.

Step 3 Switch the AC circuit breaker on the ACDU to OFF.

----End

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

16

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

4 Install Cables

Install Cables

4.1 Installing Cables for ESS-A (ESU-A2400Wh/D)


Procedure
Step 1 Take down the power cable from the right side of the ESMU and connect the power cable to
the ESMU

Step 2 Install cables for ESS-A


1.

Connect an electronic label communications cable between the ESS-A and the ESMU.

2.

Connect DB15 signal cables between the ESU-A and the ESMU.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

17

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

4 Install Cables

Step 3 Install cables between ESS-A and the busbar.

Before connecting a cable, partially tighten the ESU bolt.

Then tighten the ESU bolt to a torque of 3.5 N.m to 5.0 N.m after connecting the cable.

1.

Issue 02 (2014-02-15)

Remove the protective cover from the ESMU and install the negative ESS-A cable. Then
reinstall the protective lid and protective cover.

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

18

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

2.

4 Install Cables

Install the positive ESS-A cable and then the protective lid.

----End

4.2 Installing a CAN Communications Cable with an RJ45


connector for the ECC500
When the CAN port serves as the last level on the communications circuit, switch the toggle switches 1
and 2 of the DIP switch corresponding to the CAN port both to bit 1. Otherwise, signal transmission may
be unreliable.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

19

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

4 Install Cables

4.3 (Optional) Installing a Communications Cable


Communication over Huawei communications equipment
The ECC500 connects to the baseband unit (BBU) of base transceiver station (BTS) for
in-band communication.
The BTS is required to be later than GBSS12.0 and supports in-band networking.
Figure 4-1 Communication over Huawei communications equipment

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

20

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

4 Install Cables

4.4 Installing Cables for Sensors


Procedure
Step 1 Install the smoke sensor and the environment temperature sensor.
1.

Remove the panel.

2.

Instal the smoke sensor and the environment temperature sensor.


There are two types of smoke sensors, please install the delivered sensors.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

21

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

3.

4 Install Cables

Reinstall the panel.

Step 2 Connect signal cable to the smoke sensor. Connect the cable to the SMOKE port on the
MUS01A module.
There are two types of smoke sensors, please install the delivered sensors.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

22

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

(1) White

Issue 02 (2014-02-15)

4 Install Cables

(2) Purple

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

23

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

4 Install Cables

Step 3 Connect signal cable to the environment temperature sensor. Connect the cable to the
TEM_HUM port on the MUS01A module.

(1) White

(2) Purple

(3) Yellow

(4) Green

Step 4 Install the water sensor.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

24

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

4 Install Cables

Step 5 Connect signal cable to the water sensor. Connect the cable to the WATER port on the
MUS01A module.

The cable between the water sensor and the ECC500 is already connected before delivering,
please check cable connections.

----End

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

25

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

4 Install Cables

4.5 Installing AC Power Cables

Before connecting AC input power cables, switch all circuit breakers to OFF.

When connecting cables, wear insulation gloves and use insulated tools.

The following figure is for reference only.

Figure 4-2 Installing AC Power Cables

4.6 Installing Load Power Cables


Figure 4-3 Installing Load Power Cables

Connect DC power cables to the circuit breakers for controlling primary or secondary loads based on
site requirements.

The following figure is for reference only.

(1) Primary load

Issue 02 (2014-02-15)

(2) Secondary load

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

26

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

Power On the PowerCube 1000

5.1 Checking Before Power-on


Procedure
Step 1 All cables are connected in accordance with the wiring diagram.
Step 2 Turn off all switches.
Step 3 The cabinet is secured, and cables are connected properly.
Step 4 No short circuit occurs between the 48 V power cable and any of the ground bar, positive
busbar, three-phase live wire, neutral wire, and ground cable.
Step 5 No short circuit occurs between the three-phase live wire, the neutral wire, and the ground
cable.
----End

5.2 Connecting the AC Input and ESS Supply


Context
In the scenario with only the mains, power on and commission the PowerCube 1000 directly if the mains
is normal. If the mains is abnormal, connect a mobile D.G. to the PowerCube 1000 and then perform
power-on and commissioning.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

27

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

Procedure
Step 1 Switch the AC circuit breaker on the upper-level device for the ACDU to ON. Check that the
AC input phase voltage is 85 V AC to 290 V AC and the line voltage is 147 V AC to 502 V
AC by using a clamp meter.

Check the AC input phase voltage

Check the AC input line voltage

Step 2 Check the AC input circuit breaker on the ACDU is OFF.

Step 3 Reinstall fuses by using a fuse extracting unit.

Before reinstalling the fuse, switch the AC input circuit breaker on the ACDU to OFF.
Otherwise, the fuse will produce sparks during operation.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

28

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

Step 4 Switch on the AC circuit breakers on the ACDU.

Step 5 Check that the AC input voltage is between 80 V AC to 220 V AC, and the system voltage is
between 44.5 V DC and 57.6 V DC by using a clamp meter.
Figure 5-1 Check the AC input voltage

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

29

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

Figure 5-2 Check the system voltage

----End

5.3 Setting parameters


Context

The ECC500 takes 1 minute to start.

The user name is admin, and the password is 001.

The following table describes the buttons on the panel.

The data on the LCD is for reference only.

Button
or

Name

Description

Arrow
Key

Allows you to view menu items and set the value of a menu item.

Cancel

Returns to the previous menu without saving the settings of the


current menu item.

Enter

Enters the main menu from the standby screen, enters a submenu
from the main menu, or changes or saves the settings of a submenu
item.

NOTE
After a menu is displayed, the standby screen is displayed and the LCD screen becomes dark if no
button is pressed for 5 minutes.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

30

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

Procedure
Step 1 Select ENGLISH when starting the ECC500.

Step 2 Set system parameters.


Main Menu

Second-Level

Third-Level

Fourth-Level

Value

Func Para Set

System Para

Set Date

N/A

Actual date

Set Time

N/A

Actual time

Set Time Zone

N/A

Actual time zone

Set ID

N/A

The same as the site


number or name

Step 3 Tear the ESN label from the ECC500 and paste it on your notebook. Record the site name
corresponding to the ESN label. The ESN is used for setting up a site on the NetEco.

Step 4 Check ESS parameters.


Main Menu

Second-Level

Third-Level

Fourth-Level

Value

Device Para Set

Site Summary

Battery Type

N/A

ESU-A

NOTE
The ECC500 restarts after the battery type is reset and the restarting takes about 1 minutes.

Step 5 Set EPS parameters.


Main Menu

Second-Level

Third-Level

Fourth-Level

Value

Device Para Set

Site Summary

DG Cfg Mode

N/A

No DG

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

31

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

Step 6 (Optional) Set communications parameters.


For details, please refer to ECC500 (PowerCube) User Manual (Document ID: SE0000641658).

Communication over Huawei communications equipment

Main Menu

Second-Level

Third-Level

Fourth-Level

Value

Func Para Set

Comm Para

Host Para

Host Type

NetEco

Host Addr

27

----End

5.4 Check the ESS-A


Procedure
Step 1 Flip all the power switch on the ESMU to ON.

Step 2 If the ESS-A are powered on for the first time, initialization starts automatically to balance the
voltage differences between ESU strings
Step 3 Wait 15 minutes until the initialization is complete and check that:

Typically, the initialization is complete within 15 minutes

If the voltage difference between ESU strings is great, the initialization may take 3.5 hours

Stay at the site before the initialization is complete

1.

The ECC500 operating information displays that the battery status changes from Firston
to Boost Charge, Discharge or Float Charge.

2.

The RUN indicators on all ESMUs blink at short intervals (If an indicator blinks slowly,
it is on for 1s and then off for 1s. If an indicator blinks fast, it is on for 0.125s and then
off for 0.125s.), and the CHG or DCHG indicators are steady on

3.

The ECC500 displays that the ESS voltage ranges from 50 V DC to 57 V DC

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

32

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

4.

No ECC500 or ESMUs generate an alarm

Set parameters as shown in the following figure to check that the displayed number of
ESMUs is the same as the actual number

The following figure is for reference only.

----End

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

33

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

5.5 Connecting the Mains Supply


Procedure
Step 1 Check the AC input circuit breaker on the ACDU are ON.
Step 2 Switch on the AC circuit breakers on the upper-level device for the ACDU.
----End

5.6 Powering On Loads


Procedure
Step 1 Switch on all load circuit breakers one by one.
Step 2 During the process, measure the busbar voltage using a clamp meter after switching on each
circuit breaker. Then continue to switch on another circuit breaker after ensuring that the
busbar voltage ranges from 44.5 V DC to 57.6 V DC.
Figure 5-3 Checking Voltage

----End

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

34

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

5 Power On the PowerCube 1000

5.7 Checking After Power-On


Procedure
Step 1 Switch on the load circuit breakers as required.
Step 2 Check the DCDU battery switch to NORMAL.

Step 3 Verify that the values on the ECC500 LCD screen are the same as the actual configurations
and no alarm indicator on any component is on. If an alarm is generated or an Alarm indicator
is on, please contact the professional engineers of HUAWEI.
Step 4 If no exception occurs after the PowerCube 1000 runs for about 1 hour, the commissioning is
complete.
Step 5 Reinstall all panels and check that the cabinet paint is intact and repaint the areas devoid of
paint.
Step 6 Seal cable holes by using fireproof mud and clean up unnecessary things.

Step 7 Close and lock the cabinet door, and hand the keys over to the person in charge.
----End

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

35

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

A Appendix

Appendix

A.1 Installing Floating Nuts


This section describes the positions and procedures for installing floating nuts for different
heights of components.

Prerequisites
A flat-head screwdriver and a pair of protective gloves have been prepared.

Procedure
Step 1 Determine the mounting holes for floating nuts based on the component height.

Figure A-1 shows the positions for installing floating nuts for a 1 U component.
Figure A-1 Positions for installing floating nuts for a 1 U component

Figure A-2 shows the positions for installing floating nuts for a 2 U component.
Figure A-2 Positions for installing floating nuts for a 2 U component

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

36

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

A Appendix

Figure A-3 shows the positions for installing floating nuts for a 3 U component.
Figure A-3 Positions for installing floating nuts for a 3 U component

Figure A-4 shows the positions for installing floating nuts for a 4 U component.
Figure A-4 Positions for installing floating nuts for a 4 U component

Step 2 Install floating nuts using a flat-head screwdriver, as shown in Figure A-5.

When installing floating nuts, wear protective gloves and do not exert excessive force.
Otherwise, the flat-head screwdriver may hurt your hand or damage the device.
Figure A-5 Installing a floating nut

----End

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

37

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

A Appendix

A.2 Preparing Terminals


This section describes how to prepare cord end terminals and OT terminals.
Cut a cable of a proper length and install an OT terminal or a cord end terminal. Figure A-6
and Figure A-7 show the procedures for preparing a cord end terminal and an OT terminal
respectively.
Figure A-6 Preparing a cord end terminal

(1) Cable

(2) Cord end terminal

(3) Crimping tool

Figure A-7 Preparing an OT terminal

(1) Cable

(2) OT terminal

(4) Hydraulic pliers

(5) Heat gun

(3) Heat shrink tubing

A.3 Port Description


For details about how to change default dry contact settings, see the ECC500 (PowerCube) User Manual
(Document ID: SE0000641658).

Expansion DO Board (MUE04A)


Figure A-8 shows the expansion DO board panel.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

38

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

A Appendix

Figure A-8 Expansion DO board panel

(1) DO_1

(2) DO_2

(3) DO_3

(4) DO_4

(5) DO_5

(6) DO_6

(7) DO_7

(8) DO_8

Table A-1 describes the ports on the expansion DO board.


Table A-1 Port description
Silk Screen

Type

Default Associated Alarm

Default Status

DO_1

Dry contact output

Smoke Alarm

If any of the dry contacts


is closed, an alarm is
generated.

If the dry contacts are


open, no alarm is
generated.

Water Detector Alarm


High Ambient Temperature
Low Ambient Temperature
High Ambient Humidity
Low Ambient Humidity
DO_2

Dry contact output

Door Status Sensor Alarm

DO_3

Dry contact output

All PSU Communication Failure

Communication Failure (PSU)

PSU Fault

AC SPD Fault

DO_4

Dry contact output

Bus Bar Undervoltage

DO_5

Dry contact output

High Battery Temperature

DO_6

Dry contact output

HEX Fault

Internal Fan Fault

External Fan Fault

Compressor Fault

Air-conditioner Fault

Mains Failure

AC Failure

DO_7

Dry contact output

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

The status is user-defined.

39

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

A Appendix

Silk Screen

Type

Default Associated Alarm

Default Status

DO_8

Dry contact output

Cell Fault

BMU Fault

BMU Communication Failure

Note: The expansion DO board can be configured with all alarms that the ECC500 supports. For the alarm list,
see the ECC500 (PowerCube) Alarm Online Help.

Expansion IO Board (MUE05A)


Figure A-9 shows the expansion IO board panel.
Figure A-9 Expansion IO board panel

(1) DO_1

(2) DO_2

(3) DI_1

(4) DI_2

(5) DI_3

(6) DI_4

(7) DI_5

(8) DI_6

Table A-2 describes the ports on the expansion IO board.


Table A-2 Port description
Silk Screen

Type

Default Associated Alarm

Default Status

DO_1

Dry contact output

Reserved

Reserved

DO_2

Dry contact output

DI_1

Dry contact input

AC SPD Fault

If an AC SPD is connected, set


MUE05A_DI_1 Set to Normal
Close.

If the dry contact is open, no


alarm is generated.

If the dry contact is closed, an


alarm is generated.

DI_2

Dry contact input

Fan Failure

DI_3

Dry contact input

Hex Fault

The status is user-defined.

If a heat exchanger is connected,


set MUE05A_DI_3 Set to
Normal Close.
DI_4

Dry contact input

Issue 02 (2014-02-15)

Air-conditioner Fault

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

40

PowerCube 1000
Installation Guide (G2, ICC500, ESU-A)

A Appendix

Silk Screen

Type

Default Associated Alarm

Default Status

DI_5

Dry contact input

D.G.1 operating status

If the dry contact is open, D.G.1


stops.

If the dry contact is closed, D.G.1


starts.

The status is not user-defined.


DI_6

Dry contact input

D.G.2 operating status

If the dry contact is open, D.G.2


stops.

If the dry contact is closed, D.G.2


starts.

The status is not user-defined.

Issue 02 (2014-02-15)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

41

Das könnte Ihnen auch gefallen