Sie sind auf Seite 1von 1

SCHEDULE "An

CONTRACT NO.

9.2.2

9.3

30621127/00

If COMPANY REPRESENTATIVE is not present at the time scheduled


for the final tests, CONTRACTOR will advise COMPANY by fax of this
fact, and the final test will proceed without further delay; provided
that the Representative of the independent inspection agency
described in Paragraph 8.3 of this Schedule "A" is present. In any
case, either the COMPANY REPRESENTATIVE or the Independent
Inspection Agency shall participate in final tests.

Failure to Pass Pre-Shipment Inspection and Testing

Where pre-shipment inspection or testing demonstrates that a unit or units


do not conform to specification, COMPANY shall have the right to reject the
affected unit, or part thereof, and to demand that CONTRACTOR replace such
unit or part thereof, with a conforming unit or part prOVided that
CONTRACTOR cannot bring such unit or part thereof into conformity with
specification, within a reasonable time.
9.4

Inspection and Testing Conducted According Scope of Work and


Technical Specifications. PTS No. 07EG908

Inspection and testing of materials and equipment shall be conducted in the


manner stipulated in the Scope of Work and Technical Specifications, PTS No.
07EG908.
9.S

Inspection and Testing shall also be Conducted as per Manufacturer


Standard Quality Assurance Program

Further to Paragraph 9.4 of this Schedule "An, inspection and testing of


materials and eqUipment shall also be conducted as per Manufacturer
Standard Quality Assurance Program which is based on National and
International Standards.
10.

Inspection and Testing by CONTRACTOR and COMPANY at WORK SITE


10.1

Inspection and Testing of the PROJECT

CONTRACTOR shall be responsible for Inspecting and testing the PROJECT In


its entirety and all component parts of the PROJECT, Including those parts
installed by SUBCONTRACTORS. CONTRACTOR shall prOVide whatever
inspection and testing the CONTRACT requires a.s per CONTRACTOR's
Standard Quality Assurance Program.
10.2

COMPANY REPRESENTATIVE's Presence at all WORK Locations

COMPANY shall be entitled to have COMPANY REPRESENTATIVE present at all


locations where CONTRACTOR or SUBCONTRACTORS are engaged in the
performance of the WORK, at any and all times, to review and inspect all
aspects of their performance of the WORK and to perform or witness
whatever tests are reqUired by the CONTRACT or which COMPANY otherwise
considers necessary.
10.3

No Waiver of COMPANY's Rights in Relation to WORK Defects

Inspection or non-inspection, or witnessing


shall not be construed as waiving any of
defects in the WORK, nor shall acceptance
CONTRACTOR of its responsibilities under
Remedy of Defects", of this Schedule "A".

or non-Witnessing, by COMPANY
COMPANY's rights in relation to
of any part of the WORK relieve
Paragraph 18, "Warranties and

A-14
Conversion of Open Cycle Gas Turbines to Combined Cycle at Qurayyah Power Plant
Schedule '''A"