Beruflich Dokumente
Kultur Dokumente
i
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Contents
1. Executive Summary 1
1.1 Overview 1
1.2 Next steps 3
2. Introduction 4
3. Reliance Statement 6
4. Background 7
4.1 Scope 7
4.2 Level of flood mitigation 9
4.3 Flooding and the Brisbane River catchment 9
4.4 Wivenhoe Dam 10
4.5 Brisbane River flooding 10
4.6 Historical flood events 10
4.7 Frequent Moderate Flood Events 17
4.8 Other flood influences 17
5. Dam Operation 20
5.1 Dam operating rules 20
5.2 Alternative Dam Operation Strategies 26
7. Hydrologic Modelling 39
7.1 Model description 39
7.2 Hydrologic modelling 42
8. Water Security 49
8.1 Level of Service (LOS) Objectives and LOS Yield 49
8.2 Mechanisms to defer new infrastructure requirements 50
8.3 Operation of desalination and purified recycled water 51
ii
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
9.3 New flood retention dam 54
9.4 Bypass channel for Brisbane River 57
9.5 Channel upstream of Wivenhoe Dam to divert flow 57
9.6 Connect flood plains, new wetlands, other waterways 57
9.7 Watershed management 57
9.8 Backflow prevention 58
9.9 Levees and walls 58
9.10 Brisbane River 59
12. References 85
12.1 Queensland Water Commission 85
12.2 Seqwater 85
12.3 Department of Environment and Resource Management 85
12.4 Brisbane City Council 86
12.5 Other references 86
Table Index
Table 1 List of abbreviations 4
Table 2 Comparative Assessment Criteria 8
Table 3 Historical flood events – peak flow and flood
volume comparison* 11
Table 5 Semidiurnal Tidal Planes 2011 (Maritime Safety
Queensland) 18
Table 6 Gate operating rules 22
Table 7 Increasing flood capacity of Wivenhoe Dam –
adjustments to level 33
Table 8 Summary of potential upstream impacts 37
iii
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Table 9 Adopted scaling factors for combined flows to the
Moggill gauge 40
Table 10 Hydrologic model scenarios 43
Table 11 2011 Flood – Brisbane River Hydrology Model 47
Table 12 1974 Flood – Brisbane River Hydrology Model 47
Table 13 1893 Flood – Brisbane River Hydrology Model, 47
Table 14 Probable Maximum Precipitation Design Flood
simulation results 48
Table 15 Summary of scenarios tested 50
Table 16 Probability of reaching ‘Grid 12’ Dam triggers for
desalinated and PRW 51
Table 17 Assessment criteria 52
Table 18 Alternative Options – Workshop Evaluation
Summary 53
Table 19 Influence of Lockyer Creek and Bremer River flows,
base case scenario (S0) 56
Table 20 Key costs and timing assumptions 71
Table 21 Economic analysis – summary results 77
Figure Index
Figure 1 Brisbane River Catchment 15
Figure 2 1893 Flood Hydrograph 16
Figure 3 1974 Flood Hydrograph 16
Figure 4 2011 Flood Hydrograph 17
Figure 5 Gate Operating Rules Schematic 21
Figure 6 Comparison of 2007 and 2011 gate operating rules
(0 m 3/s to 35,000 m3/s) 23
Figure 7 Comparison of 2007 and 2011 gate operating rules
(0 m 3/s to 5,000 m3/s) 23
Figure 8 Wivenhoe lake level and flow – 100 % Full Supply
Volume (0 m3/s to 35,000 m3/s) 25
Figure 9 Wivenhoe lake level and flow – 100 % Full Supply
Volume (0 m3/s to 5,000 m3/s) 26
Figure 10 Existing gate operating rules – Alternative FSVs (0
m 3/s to 35,000 m3/s) 27
Figure 11 Existing gate operating rules – Alternative FSVs (0
m 3/s to 5,000 m3/s) 28
Figure 12 Existing gate Operating Rules – 2 metre Dam
raising (0 m3/s to 35,000 m3/s) 29
iv
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 13 Existing gate Operating Rules – 2 metre Dam
raising (0 m3/s to 5,000 m3/s) 29
Figure 14 2011 Operating Rules against modified Operating
Rules (0 m3/s to 35,000 m3/s) 30
Figure 15 2011 Operating Rules against modified Operating
Rules (0 m3/s to 5,000 m3/s) 31
Figure 16 Wivenhoe Dam level, inflow and outflow – January
2011 33
Figure 17 Water level and outflow comparison – alternative
FSV 34
Figure 18 Target operating line for Wivenhoe Dam and
Somerset Dam (Seqwater, 2011) 41
Figure 19 Comparison of Seqwater simulated and recorded
hydrographs (Moggill gauge) 42
Figure 20 Estimated flood damage curve – Brisbane City
Council* 63
Figure 21 Economic Analysis Methodology 65
Figure 22 Economic Modelling framework 66
Figure 23 Combined Stage Damage Curve 68
Figure 24 Loss probability curve – Brisbane (Illustrative)* 70
Figure 25 Economic analysis and cost benefit analysis 73
Figure 26 NPV ($) for 1893 Flood Event options 74
Figure 27 NPV ($) for 1974 Flood Event options 74
Figure 28 NPV ($) for 2011 Flood Event options 75
Figure 29 Area of land inundated in Brisbane (hectares) –
various flow rates 80
Figure 30 Length of road inundated in Brisbane – various flow
rates 80
Appendices
A Hydrologic Model
B Economic Analysis - Cost Summary
C Economic Analysis - Sensitivity Analysis Results
D Queensland Water Commission Report
E Maps
v
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
1. Executive Summary
1.1 Overview
In September 2011, as part of the overall Queensland Government response to the January 2011
Brisbane floods, the Department of Employment, Economic Development and Innovation (DEEDI)
commissioned GHD Pty Ltd (GHD) to carry out a rapid assessment of various options to improve
mitigation of floods downstream of Wivenhoe Dam. Subject to Government consideration, the Study
results may be used to inform more detailed investigations.
This Study report presents a preliminary rapid assessment and evaluation of potential options to improve
flood mitigation downstream of Wivenhoe Dam based on three larger historically recorded events (1893,
1974 and 2011). The variability of the characteristics of these historical events is reflected in the
effectiveness of Wivenhoe Dam to mitigate floods.
The Study includes consideration of the costs of increasing flood mitigation against the relative benefits
gained through reduced damages downstream. The costs associated with changing the timing of water
supply infrastructure required to maintain the current Level of Service (LoS) objectives were also
examined.
The modelling undertaken in the Study has been based on simplified hydrologic and economic modelling
techniques. While this provides some guidance and indicative outcomes, more sophisticated modelling
techniques will be required to verify and validate the findings of this study. The Study does not consider,
within its scope, modelling the full range of flood events including the impact of the more frequent and
moderate flooding events.
Caution should be exercised in the review of the options considered given the significant variability of
historical flood events and the potential for consequential flood risks. This variability was demonstrated in
the hydrologic modelling outputs where flood mitigation benefit may be apparent for one or two of the
historic flood events, but rarely all three showed significant benefit for all scenarios.
The Study considered scenarios involving a range of structural and non-structural options to assess the
potential improvements in flood mitigation and associated benefit, including:
lowering the Full Supply Volume (FSV) to 50% with no change to the Dam wall;
lowering the FSV to 75% with no change to the Dam wall;
raising the Dam wall by 2 metres while maintaining FSV;
raising the Dam wall by 2 metres with FSV at 75%; and
variation of the operating releases from the Dam.
The hydrologic modelling used to compare these options adopted The Manual of Operational Procedures
for Flood Mitigation at Wivenhoe Dam and Somerset Dam, Version 8, September 2011 (2011 FOM).
The 2011 (FOM) states that the ‘selection of release rates at any point in time is a matter for the
professional engineering judgment of the Duty Flood Operations Engineer...’. This allows each event to
be managed based on inflows, outflows, predicted stream flows and lake levels as well as other
operating rules stated in the manual.
1
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
However, this manner of operating the dams would give any number of gate operating strategies for
each separate option and scenario that was investigated during the Study. Therefore, in order to identify
a finite number of scenarios and be able to duplicate and consistently model the options to allow direct
comparisons to be easily made, our simplistic model used the more rigid set of progressive operating
rules within the manual called ‘Loss of Communications’ procedures.
1.2 Findings
In general, the following broad findings were made:
A 2 metre increase in the crest level of the Dam provides approximately 437,000 ML (437 GL) of
additional flood mitigation capacity giving a total volume in the flood storage compartment of
approximately 2,404 GL and a subsequent total volume in Wivenhoe Dam of 3,596 GL;
Reducing the FSV to 75% and using the 2011 FOM (version 8) shows a decrease of the flood peak
at the Port Office for the three events;
Lowering the FSV levels permanently will require planned water infrastructure to be brought forward
(3 years for a permanent FSV of 75% and 11 years for a permanent FSV of 50%) at a significant
economic cost;
Two out of three of the flood events modelled showed that alternative operation of the Wivenhoe and
Somerset Dam may have the potential to reduce peak levels at the Port Office gauge. However, for
the modelled 1974 event, the early release strategies increased the peak flood level at the Port
Office gauge compared to the 1974 event (including Wivenhoe and Somerset operated as per the
2011 FOM);
However, it has been found by other studies that early release strategy can have a greater impact on
the more frequent and moderate flood events including increased flows during smaller flood events.
This requires further detailed modelling in order to fully determine the impacts;
Additionally, previous hydrologic modelling has demonstrated that early release strategies worsen
downstream flood impacts associated with more frequent flood events. Five such events have been
recorded since Wivenhoe Dam was constructed. Accordingly, determining an optimum release
strategy will require extensive detailed modelling including a complete re-evaluation of the design
hydrology for the basin. This work is outside the scope of this study;
This outcome confirms the need for the Wivenhoe and Somerset Dam optimisation study
recommended by the Queensland Floods Commission of Inquiry which has already been initiated by
Seqwater (long-term study). This study will allow Brisbane River system, including the Wivenhoe
and Somerset dams as a whole to be fully modelled in detail. GHD understands that although the
catchment areas of Bremer River and Lockyer Creek are not within the scope, their impacts on the
Brisbane River system will be included;
The cost of raising the dam crest by 2 metres is estimated to be approximately $400 million. This
cost does not include substantial modification to the gates (potentially up to $330 million), potential
upgrades associated with the requirement for Probable Maximum Flood (PMF) or fishways
(potentially greater than $100 million). The cost has been based on this rapid assessment and is
likely to increase during any preliminary design phase;
It is estimated that it would take approximately four years to raise the crest of the dam. However, this
is based on no delays in the design, approvals, consultation and construction of the project; and
2
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Based on the three events modelled the flood mitigation benefits were variable for many of the
options investigated across the three flood events. For example, while the options of alternative
operation of the Wivenhoe and Somerset Dam and the 2 metre raise (100% FSV), had minimal
impacts during the 2011 flood event, these same options showed no benefit for the 1974 flood event,
with most benefit realised during the 1893 flood event.
While the above results provide an overview of performance of three larger historical floods in the
Brisbane River, caution should be applied in drawing conclusions from this information because of the
potential for significant variability in actual flood events in terms of flow patterns and flood risk. A more
detailed assessment of a broader range of scenarios using a more complex hydrologic model is
considered necessary before any detailed conclusions are reached.
The Study clearly demonstrates that there is no single solution to improving flood mitigation downstream
of Wivenhoe Dam given the significant variation in flood benefits realised across the nominated flood
events. However, before consideration is given to an additional infrastructure to improve flood mitigation,
opportunities may exist to improve performance through better use of existing assets and procedures.
These opportunities should be assessed in greater detail within the scope of the long-term study.
3
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
2. Introduction
As part of the overall Queensland Government response to the January 2011 Brisbane floods, DEEDI
commissioned GHD to carry out a high-level, rapid assessment of various options to improve the
mitigation of floods downstream of Wivenhoe Dam. The Study objective is to identify a number of high
level options to improve the flood mitigation performance of Wivenhoe Dam. It was not intended that this
study would provide one answer or to provide a definitive outcome. It was always intended that this rapid
assessment would provide a number of high level options that would enable further in-detail
investigation. It was also intended that a number of options would be identified which could be eliminated
from future investigation due to the indicative high cost or the construction period required or the
technical feasibility.
The Study objective is to provide a preliminary assessment of flood mitigation options and identify any
consequential water supply issues. The Study includes consideration of the costs of increasing the flood
mitigation against the relative benefits gained through reduced damages downstream together with
consideration of the impact on the timing for water supply infrastructure required to maintain the current
LoS objectives.
Abbreviation Meaning
EL Equivalent Level
2011 FOM Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam
and Somerset Dam, Version 8, September 2011
4
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Abbreviation Meaning
m3 Cubic metres
3
m /s Cubic metres per second (flow rate)
W2, W4 etc Reference predetermined stages of flow control from Wivenhoe Dam
prescribed by the Manual of Operational Procedures for Flood Mitigation at
Wivenhoe Dam and Somerset Dam, Version 8, September 2011
5
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
3. Reliance Statement
Due to the limited time available to produce this Report, caution should be exercised on any reliance of
the accuracy of the simplistic economic and hydrological modelling results from the Study. It has not
been possible, within the limitations of the Study, to check the reliability of all information and data, which
for the purpose of this Study, has been presumed to be accurate.
While GHD has attempted to review the results of available modelling against previous studies and
documentation, no formal validation or independent checks have been undertaken.
The scope of this Study has been limited to three historical flood events, so will not represent more
extreme events or types of flooding such as storm tide. Similarly, options for flood mitigation considered
have not taken into account consequential impacts on other areas of the Wivenhoe, Somerset and
Brisbane River systems. Importantly, the Study does not include, within its scope, modelling of the full
range of flood events including the impact of the more frequent and moderate flood events.
Construction rates have been based on detailed cost estimates prepared for recent dam upgrade
projects in South East Queensland in 2011. At present there is considerable volatility in construction
pricing, so construction rates should be viewed with caution. In addition, risk pricing has not been
included, which may change the cost estimate further. Dam work is subject to stringent environmental
controls and geotechnical and other conditions can differ from what is expected based on existing data.
Likewise, the impact of wetter than average seasons on construction cost rates has not been assessed.
A detailed hydrology model of the Brisbane River catchment was not available for this study, and so
sophisticated routing of flows downstream of Wivenhoe Dam was not possible. The hydrologic modelling
conducted for this study is based on level-pool reservoir routing through the dams, and a lagging and
summation of hydrographs downstream of Wivenhoe Dam to estimate the peak flow rate at the Moggill
gauge. No hydraulic modelling has been undertaken for the purposes of this Study.
6
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
4. Background
4.1 Scope
The scope of this Study presented in the project Terms of Reference has been developed and refined
during the initial project planning phase and through consultation with the Steering Committee.
The purpose of this Study was to undertake an eight week rapid assessment to identify preferred options
to improve mitigation of floods downstream of Wivenhoe Dam. There are a number of concurrent studies
being undertaken by various stakeholders, including Seqwater and Brisbane City Council, in response to
the recommendations of the Queensland Floods Commission of Inquiry Interim Report. As such, this
Study should be viewed within the context of the overall strategy for flood management including local
flood mitigation solutions, development zoning and community awareness.
Any relevant preliminary findings from the Wivenhoe Dam Study and the Preliminary Optimisation Study
may be incorporated into the Seqwater long term study activity.
This Study has considered potential mitigation options against three major historical events, namely:
1893 flood event;
1974 flood event; and
2011 flood event.
Relevant data for each of these events has been supplied by Seqwater. Since the Study does not
consider the full range of flood events, caution should be exercised in the review of options given the
significant variability of three historical flood events and the potential for consequential flood risks.
The scope of this Study, limited by the time available, is for the identification and assessment of broad
options presenting alternatives to the present operation and functioning of Wivenhoe Dam. These broad
options are intended to be capable of mitigating the nominated historical events as closely as possible to
3 3
the dual control discharges of 1,900 m /s and 3,500 m /s from the Dam.
The Study consisted of two principal elements for the assessment of options to improve the mitigation of
flooding impacts:
A Wivenhoe Dam Study considering options to improve the flood mitigation potential of Wivenhoe
Dam; and
A Preliminary Optimisation Study seeking to identify various alternative options for flood mitigation.
Short-listed options for Wivenhoe Dam have been subjected to an economic assessment including
assessment of the reduced flood level in the Brisbane River and consequential benefits of each option.
Flood damage curves were used to determine the cost and therefore the economic benefit associated
with each option.
7
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
raising of the Dam crest by 2 metres (with FSV at 75% of current levels);
lowering the FSV to 75% of current levels;
lowering the FSV to 50% of current levels; and
raising the downstream bridges and modifying the operational releases from the Dam.
A 2 metre increase in the crest level of the Dam provides approximately 437,000 ML (437 GL) additional
storage. For each option the Wivenhoe Dam Study considered:
the cost and time for implementation of the measures;
likely impacts upstream of the Dam wall including potential impact on existing infrastructure;
the likely benefit in terms of reduced flood damages (based on the 1893, 1974 and 2011 flood
events); and
consequential impact on the Water Supply Infrastructure Program.
The development of these options used Manual of Operational Procedures for Flood Mitigation at
Wivenhoe Dam and Somerset Dam, Version 8, September 2011. GHD understands that there is now a
Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam Version 9
November 2011. However, this manual was released after the modelling for this study was completed so
Revision 9 has not been assessed nor the impact on the outcomes of this Study.
All options for the raising of the Dam wall have been considered against the required capacity to pass the
latest estimate of Probable Maximum Flood (PMF) as required by 2035 under the ‘Guidelines on
Acceptable Flood Capacity for Dams.’
For each option a comparative assessment of the following was made:
Net reduction in damage costs Capital and operational costs for construction of new
infrastructure
The need to ‘bring forward’ water supply infrastructure
investment to maintain levels of service
The hydrological and hydraulic nature of the contributing catchments within the Brisbane River system is
complex and subject to extreme variability between historic flood events. Management of flooding in the
system is equally complex and a single solution is unlikely to be sufficient.
Due to the timing and the short timeframe for the report to be undertaken and finalised, only existing
available data was used. For example, the flood damage curves from 2006 were used with an escalation
‘factor’ as much of the information from 2011 is not currently available.
8
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Infrastructure options include:
raising of bridge crossings immediately downstream from Wivenhoe Dam;
flood retention storages in tributary river systems discharging downstream of Wivenhoe Dam
(Lockyer Creek and Bremer River);
levees; and
backflow prevention devices.
Non-infrastructure options were also considered, such as modifications to the operational procedures for
Wivenhoe Dam. This preliminary study is limited in its scope, time frame and this is reflected in the use of
the simplified economic and hydrologic models. GHD understands that the long term Wivenhoe and
Somerset Dam optimisation study which will investigate the ‘system’ as a whole was a recommendation
of the recent Flood Inquiry and is already underway.
9
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
4.4 Wivenhoe Dam
Construction of Wivenhoe Dam was formally proposed in 1971 by the Queensland Government with the
dual purposes of providing a suitable urban water source and as a flood mitigation strategy.
An optimum flood storage volume was determined using the benefit-cost relationship between the cost of
Dam storage and assumed flood damages in 1974. Preliminary design considerations demonstrated that
even with the introduction of significant flood storage in Wivenhoe Dam, ‘major flooding can still occur’ in
[4]
the Lower Brisbane River .
The Wivenhoe Dam has previously been classified using the ANCOLD Guidelines as an Extreme Hazard
Dam, as the design flood is the PMF which currently exceeds the spillway capacity. The Dam was
upgraded in 2005 to provide for the spillways to pass the 1 in 100,000 Annual Exceedence Probability
(AEP) flood. The AEP is simply the probability that a particular flood will occur in any one year. This
[5]
upgrade included construction of a three-bay fuse plug spillway on the right abutment . A secondary
fuse plug and auxiliary spillway on the left abutment, intended to improve the capacity of the spillways to
the PMF, is due for completion by 2035.
2 2
Approximately half of the Brisbane River catchment (6,232 km of 13,222 km ) is located downstream of
[6]
the Wivenhoe Dam , and the flooding effects of rainfall in the lower catchment are therefore unaffected
by operation of the Dam.
10
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Table 3. The summary flows and volumes include all catchment areas downstream to Moggill, west of
Brisbane City (95% of the total catchment area). The estimates in Table 3 were supplied by Seqwater
for the purposes of this Study, and are based on Seqwater calibrated hydrology models.
Table 3 Historical flood events – peak flow and flood volume comparison*
3 3 3
Catchment Peak flow (m /s) Volume (ML) Peak flow (m /s) Volume (ML) Peak flow (m /s) Volume (ML)
4.6.1.1 Rainfall
Bureau of Meteorology records of the four-day peak of the 1893 flood suggested:
939 mm of rainfall was recorded in the Stanley River catchment; and
[8].
358 mm of rainfall in the Upper Brisbane River catchment.
A maximum total of 1,026 mm of rainfall was recorded in the Brisbane River catchment during the month
of the 1893 flood. However, rainfall records for the time are largely inadequate for detailed analysis.
11
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Flows into the Wivenhoe Dam area during the 1974 event were approximately half that of the 1893
and 2011 floods; and [9]
[7]
The Port Office gauge recorded a level of approximately 5.5 metres in the 1974 flood.
Rainfall
A monsoonal trough was present over South East Queensland in January 1974, south of normal latitude,
saturating the Brisbane River catchment.
Over a five-day period between January 24 and 29, a minimum of 300 mm of rainfall was
experienced in all parts of the Brisbane River catchment;
Between 500 mm and 900 mm of rain was recorded within the metropolitan area;
Over 1,300 mm of rain fell at Mount Glorious; and
The most intensive rainfall occurred during a 24 hour period on Friday January 25, with between 300
mm to 500 mm recorded.
The 1974 flood saw more significant rainfall within the Lower Brisbane River and Bremer River
catchments relative to the 1893 flood, but less significant rainfall in the upper reaches of the Brisbane
River catchment.
Rainfall
The following, unusually heavy falls were recorded in the catchment areas upstream of the Wivenhoe
[12]
and Somerset dams.
rainfalls between 600 mm and 1,000 mm were recorded in parts of the Brisbane River Catchment in
[13]
December 2010 and January 2011;
total daily rainfall of between 150 mm and 250 mm was experienced on average in the Brisbane
[1]
River catchment between January 9 and 11; and
Seqwater records of the three-day 2011 flood suggested 412 mm of rainfall was recorded in the
Stanley River catchment, and 307 mm of rainfall in the Upper Brisbane River catchment, producing
the most significant peak flow rates.
12
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Sinclair Knight Merz concluded, based on review of overall data collected at alert stations, that the ‘AEP
of the rainfalls for the whole [Wivenhoe] Dam catchment is likely to be between a 1 in 100 and 1 in 200
year event’.[8]
Flood characteristics
[3]
Characteristics of the January 2011 flood include:
a long duration (and lengthy associated rainfall period);
a large total flow volume;
a double peak in flow rate; and
under-forecast rainfall intensity prior to the peak of the flood – up to 65% less than those actually
recorded.
13
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 1 is a schematic representation of the Brisbane River catchment and associated tributaries,
demonstrating peak flows at flood volumes for each of the three historical flood events.
Figure 2, Figure 3 and Figure 4 demonstrate the simulated hydrographs for the historical floods
considered in the Study (including discrete hydrographs for each river catchment within the larger
Brisbane River catchment) as provided by Seqwater.
Key information regarding the benefits of Wivenhoe Dam and the 2011 FOM on these three major flood
events is presented in Table 4.
For the 1893 and 1974 flood events (prior to construction of Wivenhoe Dam), recorded flood levels
are significantly higher than the modelled flood levels which we undertaken assuming Wivenhoe
Dam had been in place; and
For the 2011 flood event (following construction of Wivenhoe Dam) the recorded flood level is
2 metres lower than the level modelled assuming Wivenhoe Dam was not constructed.
Table 4 Summary of Peak Flood level at the Port Office for the scenarios tested at low tide
Peak Recorded Level at Port Office without Wivenhoe Dam present Sep 2011
Flood Event (year)
Wivenhoe Dam (metres AHD) FOM (metres AHD)
[7]
1893 8.3* [actual] 4.9 [modelled]
[7]
1974 5.5 [actual] 3.5 [modelled]
[9] [7]
2011 6.46 [modelled] 4.46 [actual]
*Note: Somerset Dam was not present during the 1893 flood. This is the recorded levels at the Port Office without the benefit of
Somerset or Wivenhoe Dams.
14
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Linville Peachester
Upper Brisbane Upper Brisbane
Catchment: Catchment: 2.5 hrs
6h
rs
ck
5 Stanley River
hr SOMERSET DAM Catchment:
ye
s
rC
Lockyer
Catchment:
6h
1893: 2,460 m3/s rs WIVENHOE DAM 6,990 km2 Stanley River
1974: 4,423 m3/s Catchment:
2011: 5,461 m3/s
1893: 1.08 GL
O’Reillys Weir 2,974 km2
1974: 0.55 GL
Lockyer 2011: 0.71 GL
Catchment: 1.75
h rs 9,964 km2
2 hrs
1893: 0.51 GL
1974: 0.77 GL
2011: 0.70 GL Lowood 10,012 km2
40 min
Twin Bridge
20 min
Fernvale Bridge
1 hr
Kalbar Rosewood
Mt Crosby Local
Savages Crossing 10,144 km2 Area:
5 Kholo Crossing
hr 639 km2 1893: 0.18 GL
ar
s 1974: 0.20 GL
ril
2011: 0.70 GL
lC
re
Amberley 1 hr
ek
2
913 km
Mt Crosby Weir 10,509 km2
4
hr
s
4.5 hrs
1 hr
David Trumpy Bridge 1,868 km2 Colleges Crossing
5 hrs
Peak Flows T.T. T.T. Project: Wivenhoe Options Study – Rapid Assessment
Dam Condition of use:
This document may only be Date: 01/11/2011 Title: Brisbane River Catchment
used by GHD’s client (and any
Location Flood Volumes other person who GHD has This Drawing must not
A Brisbane River Catchment Details TT TT agreed can use this document) be used for
for the purpose for which it has Scale NTS Construction
Drawn Checked
prepared and must not be used
River Name Cumulative Catchment by any other person or for any Original Size
Rev: A
G:\41\24452\Tech\Visio\Catchment_Schematic.vsd other purpose.
A3
Figure 2 1893 Flood Hydrograph
16
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 4 2011 Flood Hydrograph
17
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
4.8.1 Tidal influences
Tidal conditions have a significant effect on the height of flooding at the Port Office gauge, downstream
in the Brisbane River catchment. This is most clearly illustrated by the difference between the 1974 flood
3 3
and the 2011 flood. Although the flows were of similar magnitude (between 9,500 m /s and 10,500 m /s),
there was a 1 metre difference in flood level at the Port Office gauge (4.46 metres versus 5.46 metres).
This variation in flood levels primarily relates to the following tidal conditions:
the 2011 flood occurred during a small tidal range with high tides of under 1.0 metre; and
the 1974 flood coincided with king tides in excess of 2.2 metres.
The scope of this project has not considered mitigation of tidal backwater flow due to extreme high tides.
Table 5 indicates the Semidiurnal Tidal Planes for 2011. The numbers represent height (in metres)
above Lowest Astronomical Tide (LAT).
The highest high tide or king tide for Brisbane was 2.71 metres (above LAT) on January 21 and May 17,
2011 1.
1
Maritime Safety Queensland 2010
18
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
A storm surge is an atmospherically forced ocean response caused by extreme surface winds and low
surface pressure associated with severe and/or persistent offshore weather systems. The term ‘storm
tide’ refers to the rise of water associated with a storm, plus tide, wave set-up, and freshwater flooding.
Brisbane City Council does not have a contemporary storm tide assessment, however, Moreton Bay
Regional Council to the north and Gold Coast City Council to the south have recently undertaken storm
tide studies.
19
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
5. Dam Operation
20
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 5 Gate Operating Rules Schematic
21
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
The gate operating rules incorporate a number of procedures, which provide a different priority in
decision making for gate releases, and therefore downstream flows, based on the inundation of
community infrastructure downstream. These procedures were updated and approved in September
2011. The 2011 FOM procedures are summarised in Table 6 and the Flood Rules (Ver 7) have been
provided for comparison. The 2011 operating rules use a flowchart decision tool for the management of
flood waters within the W1 category. In contrast, the 2007 operating rules have defined flow rates for the
categories 1A-E as described below.
Note: the 2011 FOM and the simplistic model accounts for the interaction between Wivenhoe Dam and Somerset Dam through the
target operating line provided in the manual. In the following sections, when Wivenhoe Dam operation is described, it is in the
context of both Wivenhoe and Somerset dam operating together.
W2 68.5 74 - 3,500
W4 74 80 - no limit
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam 22
3 3
Figure 6 Comparison of 2007 and 2011 gate operating rules (0 m /s to 35,000 m /s)
Figure 7 Comparison of 2007 and 2011 gate operating rules (0 m3/s to 5,000 m3/s)
23
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
5.1.4 W1 operating protocol
For lake levels from 67.0 metres to 68.5 metres Australian Height Datum (AHD), floodwaters are stored
in the Dam in order to restrict the flow rates in the Brisbane River downstream so that key bridges at
Colleges Crossing, Burtons and Kholo remain open for as long as possible. This is intended to minimise
disruption to the community that use these bridges.
3 3
Figure 8 Wivenhoe lake level and flow – 100 % Full Supply Volume (0 m /s to 35,000 m /s)
25
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
3 3
Figure 9 Wivenhoe lake level and flow – 100 % Full Supply Volume (0 m /s to 5,000 m /s)
26
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
A number of different operating rules have been investigated to assess their impact on peak flows and
water levels for the 1893, 1974 and 2011 floods. Each flood has different characteristics which make it
practical to use as a test for the effectiveness of the option:
1893 – flow centred on the Somerset Dam area, highest flows into the Wivenhoe Dam;
1974 – flow centred on the Bremer River and local Brisbane creeks, a scenario for which the
Wivenhoe Dam has the least mitigation potential; and
2011 – flow centred on Wivenhoe Dam, Lockyer Creek and the stretch of Brisbane River between
the Dam and Mt Crosby Weir with very little flow in the local Brisbane creeks.
3 3
Figure 10 Existing gate operating rules – Alternative FSVs (0 m /s to 35,000 m /s)
27
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
3 3
Figure 11 Existing gate operating rules – Alternative FSVs (0 m /s to 5,000 m /s)
The lowered FSV options use the same operating rules at higher flows. The benefit relies solely on the
additional flood storage volume available within the Dam by starting the flood event with a lower FSV in
the reservoir.
28
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
3 3
Figure 12 Existing gate Operating Rules – 2 metre Dam raising (0 m /s to 35,000 m /s)
Figure 13 Existing gate Operating Rules – 2 metre Dam raising (0 m3/s to 5,000 m3/s)
29
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
The 2011 FOM is shown in blue below the new gate curves in Figure 12. The option of raising Wivenhoe
3
Dam by 2 metres needs to have an operating curve that discharges 10,000 m /s from the Dam at 77.7
metres AHD to match the location of the new fuse plugs which have also been raised by 2 metres.
At this point the gates must be fully open to allow the increase in flow in the Brisbane River downstream
of the Dam due to the triggering of the fuse plugs to be approximately 20%.
If the 2 metre raising was considered with the lowered FSV, the transition to the W4 limit allows
3
regulation of the flow to an appropriate limit. In this case, 2,000 m /s has been adopted to minimise
3
closure of the Brisbane Valley highway bridges. Alternatives might include setting this limit at 3,500 m /s
to match flow limits for Brisbane urban areas whereby damage is minimised. This operating curve still
has to ensure the gates are fully open at the new W4 level of 76 metres AHD. It is assumed that the fuse
plugs will trigger at 77.7 metres AHD with the 2 metre raise.
The cases where the fuse plugs are triggered have been rejected because they do not provide a
mitigation of floods (which is the primary objective of the study). When the fuse plug is triggered, there is
a move to a zone where the outflows increase in all cases modelled.
3 3
Figure 14 2011 Operating Rules against modified Operating Rules (0 m /s to 35,000 m /s)
30
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
3 3
Figure 15 2011 Operating Rules against modified Operating Rules (0 m /s to 5,000 m /s)
31
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
6. Dam Raising Options
The following section considers the options for raising Wivenhoe Dam in relation to the effects on flood
mitigation.
Figure 16 demonstrates the operation of Wivenhoe Dam during the January 2011 Flood Event.
32
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 16 Wivenhoe Dam level, inflow and outflow – January 2011
W4 Release
It should be noted that recent reports on the raising of Wivenhoe Dam consider increasing the FSV from
67 metres AHD to 69 metres AHD, with a corresponding raise to the Dam crest (from 80 metres AHD to
82 metres AHD) in order to maintain the flood capacity of the Dam. These reports are not applicable in
the context of this Study, as increasing the Dam’s ability to mitigate floods requires that the FSV be
maintained at its current level, with an increase to the overall Dam crest level, thereby improving the
flood capacity rather than water supply volume.
The primary level changes considered in this Study are summarised in Table 7.
FSV 67 67
W4 trigger limit 74 76
33
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 17 Water level and outflow comparison – alternative FSV
82
80
78
76
Elevation (m AHD)
74
64
5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000
Discharge (m3/s)
The proposed 2 metre raising of the Dam crest level permits the W4 level to shift to level of 76 metres
AHD. The fuse plugs would subsequently need to be raised to 77.7 metres AHD. However, the operating
requirement that the gates fully open at 77.7 metres AHD means that the gates need to be progressively
opened as outlined in the operating rules.
The elevation-discharge curve in Figure 17 shows flows ‘throttled back’ until 76 metres AHD with very
3
similar outflows to the current arrangement for flows below 5,000 m /s (due to the progressive gate
opening). The results demonstrated in Figure 17 would be refined in a more detailed assessment of the
Dam raising. The current operating curve triggers W4 at 74 metres AHD. This level corresponds with a
3
4,750 m /s outflow, which represents a 1 in 500 AEP event according to the outflow AEP curve.
Of note is the impact of the Probable Maximum Precipitation – Design Flood (extreme design flood) on
the raised structure. The current arrangement only passes the 1 in 100,000 AEP event, which does not
meet current design guidelines. Raising the Dam by 2 metres allows the Probable Maximum Precipitation
– Design Flood to pass through the structure with a peak water level 81.3 metres AHD. This indicates
that the Dam crest could be 0.7 metres lower, or further changes to the W4 trigger level could be
implemented, to further increase flood mitigation.
It should be noted that there is a significant level of technical uncertainty associated with the 2 metre
dam raise. Elements of the structure may, or may not need upgrading to cope with the increased water
levels during extreme flood events. The most significant of these relates to the inability of the spillway
gates to be lifted completely above the water flowing through the spillway. Currently a substantial
deflector beam is provided below the spillway bridge to deflect the water away from the gate. The 2
34
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
metre dam raise increases the water load on this deflector beam by 2 metre. Preliminary assessments
show that this wall can be strengthened to withstand the increased load but these issues need to be fully
considered within the scope of a more detailed study. This study will need to include hydraulic modelling
to better quantify the design loading and outside the scope of this preliminary assessment. If the
subsequent detail investigation shows that the wall is not capable of being strengthened then a new
spillway structure will be required at significant additional cost in the order of $330 million.
There are elements of dam raising option that are outside the scope of this current Study and may result
in significant uncertainty in overall project cost. These elements include aspects such as the necessity
for a fish passage to meet current environmental approvals. If required, this structure would comprise
substantial fish lifting system similar to that being used at Paradise Dam. As fish passage is also
required during flood periods, this structure would be very substantial and may cost greater than $100
million. Due to the uncertainties surrounding the requirement of this structure, these additional costs
have not been included in the economic assessment.
35
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
construction of a new saddle dam in the Coominya saddle;
raising the existing saddle dams (1 and 2;)
raising the dividing walls in the fuse plug spillway
raising the fuse plug embankments through upstream and downstream addition of fill; and
modifications to and raising of dam monitoring and water control systems.
An indicative implementation schedule for the raising of the Dam is presented below.
The approximate volume of earth fill required (including filter zones, rip rap and bulk fill) is of the order of
3 3
750,000 m for the main Dam, and an additional 110,000 m for the saddle dams. On this basis, the
following implementation times might be expected:
Year 1 – geotechnical investigations, detailed design, tender documentation and relevant approvals
(minimum 12 month duration expected);
Year 2 – first six months, procurement;
Year 2 – second six months, mobilisation, site establishment, miscellaneous concrete works,
development of borrow sources for fill material; and
Year 3 – earthworks and spillway and bridge works following wet season.
The selection of earth fuse plugs in 2005 was based on these being the most economic system of
auxiliary spillway at the time.
If it was decided that the existing fuse plugs should be upgraded, steel and concrete ‘Hydroplus’ fuse
plug gates could be used to directly replace the existing embankments.
In addition to the gates themselves, the existing concrete ogee crest buried beneath the existing
embankment would require reconstruction into a flat crest. Sufficient reinforcing would be required in
order to withstand the hydraulic gradient imposed by the fuse plugs. The estimated capital cost of such a
solution would be in the order of $80 million.
36
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
If the fuse plugs where to be replaced with a radial or similar gate structure to facilitate early release of
water, the cost of the new works would be in the order of $300 million.
Roads As the FSV remains unchanged the impact on roads will be minimal and then only
during extreme events. The existing road network is currently not designed for
extreme flood events and as such, any temporary disruption to the highway
network around Wivenhoe Dam during extreme events would be tolerable.
However, some cost impacts should be expected as some roads will be subject to
more frequent flooding.
Environment Environmental impacts would be minimal and temporary during extreme events.
Appendix E shows known sites of environmental, recreational and cultural interest
that would be affected during extreme events by the raising of the Dam.
Land Land impacts may be considered within the bounds of the increased flood
resumption envelope. While there is no know policy to determine the extent of impacted land,
for the purpose of this Study GHD has assumed the land area between 75 metres
AHD and 77 metres AHD levels as a result of the 2 metre Dam raising.
The area of land between 75 metres AHD and 77 metres AHD levels for
Wivenhoe Dam is approximately 2,378 hectares. This is comprised of road
parcels, easement parcels and lot parcels.
There is already 16,424 hectares that is currently classed as ‘Lake Wivenhoe’ on
the cadastral database, which suggests that it is already owned by Seqwater.
Slityard Creek Initial advice gained from the power station operators suggest that the station can
power station tolerate water levels in Wivenhoe up to a level of 77 metres AHD without damage
or effect on the operation of the power station. A 2 m dam raising takes the
annual exceedance probability of a water level of 77 metres AHD from about 1 in
7,000 to 1 in 5,000. This is a small change in probability for an extremely rare
event. This may be better managed as an insurable risk rather than any upgrades
to capital works. However the effect of a 2 metre raising of the dam on the power
station, including a review on any potential impact on electricity supply, should be
assessed during the long-term study. Further consultation with the power station
owners should also occur.
Esk and The new Toowoomba raw water supply off take from Wivenhoe Dam was recently
37
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Area of impact Impact
Toowoomba constructed as part of the LinkWater – Toowoomba Alliance. It is understood that
water supply the pump station at the Dam was damaged during the January 2011 flood as a
result of rising water levels in the Dam. Increasing the flood level in the Dam will
clearly have an impact on the pumping facility and this would need to be
considered in any raising option.
Similarly, the adjacent Esk raw water supply off take would also need to be
considered.
Commercial While not considered in detail as part of this Study some consideration should be
operations given to the impact on any commercial gravel and sand operations within
(gravel) Wivenhoe Dam.
38
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
7. Hydrologic Modelling
39
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Table 9 Adopted scaling factors for combined flows to the Moggill gauge
1893 0.790
1974 0.700
2011 0.525
Table 9 indicates a similar scaling factor for the 1893 and 1974 floods, and that flow attenuation appears
to be more significant during the 2011 Flood Event. The higher attenuation during the 2011 event may be
due to the larger contribution of flow from the Lockyer Creek catchment in this event. However, more
detailed analysis would be required to investigate this phenomenon further, but for the purposes of this
Study, this approach was considered satisfactory to enable comparisons of flood mitigation options to be
undertaken.
The hydrologic model for flood routing through Wivenhoe Dam allows for investigation of different release
rate scenarios at Wivenhoe Dam, and differing permanent water supply levels. The flood routing through
Wivenhoe Dam takes into consideration the objectives of the two strategies for Somerset Dam Flood
Operations:
to mitigate the rural and urban flooding downstream of Wivenhoe Dam; and
to protect the safety of the dams.
The 2011 FOM nominates the actions to take while protecting the safety of the dams as:
‘to raise the crest gates to enable uncontrolled discharge; and
to utilise the regulator valves and sluice gates to release water from Somerset Dam, with the aim of
moving towards the Wivenhoe/Somerset Operating Target Line. Ideally, at the peak of a Flood Event,
the dams’ lake levels should plot on or very close to the Wivenhoe/Somerset Target Line. However,
this may not be possible to achieve in practice.’
A plot of the target operating line is shown in Figure 18.
40
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 18 Target operating line for Wivenhoe Dam and Somerset Dam (Seqwater, 2011)
41
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 19 Comparison of Seqwater simulated and recorded hydrographs (Moggill gauge)
12,000
Simulated
Recorded
10,000
8,000
Flow Rate (m3/s)
6,000
4,000
2,000
0
28 Dec 2010 02 Jan 2011 07 Jan 2011 12 Jan 2011 17 Jan 2011 22 Jan 2011 27 Jan 2011
Date
42
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
During the event, the water level in Wivenhoe Dam was adjusted to manage releases and avoid the
release of flows coinciding with the peaks from other downstream river catchments, principally Lockyer
Creek and Bremer River.
The results of the model simulations for the three historical flood events considered in this Study (1893,
1974 and 2011 floods) are summarised in Table 11, Table 12 and Table 13, and graphed in Appendix A.
S1 Straight to W2 with Peak outflow from the Dam of 3,500 m 3/s is reached as quickly
FSV maintained at as practically possible. Flooding of existing crossings is
100% assumed as being not as important a consideration as the
reduction of potential flood damage downstream of the Dam.
Some retention of flood water within the Dam occurs while the
gates are opened to the desired release capacity (2011 FOM).
S2 Steady increase in The steady increase in flow output from the Dam to W4 trigger
flow to W4 with the level with the FSV reduced to 75%. This seeks to have a steady
FSV maintained at increase in peak outflow to the W4 trigger level.
75%
S3 A 2 metre raising of The 2 metre raising of the Dam and the fuse plugs and the FSV
the Dam Wall including at 75%. This seeks to increase the flood mitigation storage
the fuse plug levels volume within the Dam, by both raising the Dam and reducing
with the FSV reduced the FSV. This assumes the W4 trigger level is increased from 74
to 75% metres AHD to 76 metres AHD and the trigger for the first fuse
plug is increased from 75.7 metres AHD to 77.7 metres AHD.
S4 A 2 metre raising of The 2 metre raising of the Dam and the fuse plugs and the FSV
the Dam including the at 100%. This seeks to increase the flood mitigation storage
fuse plug levels with volume within the Dam, only by raising the Dam. This assumes
the FSV kept at 100% the W4 trigger level is increased from 74 metres AHD to 76
metres AHD and the trigger for the first fuse plug is increased
from 75.7 metres AHD to 77.7 metres AHD.
43
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
S5 Uncontrolled flow to This option assumes the gates are permanently kept open to
3,500 m3/s allow a maximum release of 3,500 m3/s. That is, all inflows are
allowed to pass through the Dam with no storage of flood waters
within the Dam.
S6 Restrict releases to The minimum gate opening rule is applied until a peak outflow
3
3,500 m /s (not rate of 3,500 m3/s is reached. Outflows are maintained and do
feasible – sensitivity not exceed this flow. Under this option water is temporarily held
only) behind the gates as they are progressively opened.
S7 Restrict releases to The minimum gate opening rule is applied until a peak outflow
3 3
1,900 m /s (not rate of 1,900 m /s is reached. Outflows are maintained do not
feasible – sensitivity exceed this flow rate. Under this option water is temporarily held
only) behind the gates as they are progressively opened.
S8 Reduce FSV to 75% or Maintain the existing 2011 FOM gate opening, with a reduction
50% in the FSV to 75% and 50% of the existing.
44
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
7.2.3 Scenarios 5 (5S) to Scenario 7 (S7)
S6 and S7 may not be technically feasible and have been included for the purposes of sensitivity
analyses only as they were in the scope document for the project. S5 was a variation of S6 and was
identified during the course of the Study.
Additional scenarios were also considered which either:
3 3
reduced the peak outflow from Wivenhoe Dam to 1,900 m /s or 3,500 m /s, and or
maintained the present minimum gate opening operation at the Dam while reducing the present FSV
capacity to 50% or 75%.
3
S5 aims to limit the peak outflow from Wivenhoe Dam to 3,500 m /s. In Scenario 5, the gates are kept
3
open to a capacity of 3,500 m /s such that any inflow to the Dam is freely discharged in an uncontrolled
manner.
This scenario assumes that the Dam operator does not need to consider the magnitude of any flood
event, as the Dam is assumed to have sufficient capacity to contain the flood without overtopping or
triggering the existing fuse plug level.
Scenario 5 is similar to the ‘Straight to W2’ (S1) scenario, with the exception that water is released
instead of being retained while the gates are opened under the W2 scenario.
This strategy appears to work favourably during the 2011 flood situation where the peak flow rate at the
3
Moggill gauge is reduced by approximately 1,500 m /s, and the simulated peak water level in Wivenhoe
Dam is 73.7 metre (approximately 1.1 metre lower than the base case).
However, in the 1974 flood simulation, even though the peak water level in Wivenhoe Dam is reduced
significantly (by approximately 2.3 metres), the peak flow rate the at Moggill gauge is exacerbated by
3
approximately 1,700 m /s relative to the base case. This is because the flood gates are not used to
mitigate or delay the flood peak within the Dam to allow the flood waters from the Lockyer Creek
catchment and the Bremer River catchment to pass. The timing of peak flow rates downstream of the
Dam in the Lockyer Creek catchment and the Bremer River catchment are impacted by the flood waters
from the Dam.
The 1893 flood simulation yielded a peak water level in Wivenhoe Dam of 77.0 metre (or 1.3 metre
increase compared to the base case), which would result in the triggering of the fuse plug and a peak
3
flow at Moggill gauge of 8,300 m /s.
Detailed modelling would be required to more accurately assess these estimates. Therefore, S5 appears
to only have a favourable outcome in one of the three historical flood events and it is not considered a
feasible scenario.
3 3
S6 and S7 reduce the peak outflow rates from Wivenhoe Dam to either 1,900 m /s or 3,500 m /s,
based on a minimum gate opening sequence to achieve these discharge rates. The results
demonstrate that these scenarios are not feasible, as there is no beneficial outcome to any of the
three historical flood simulations. The 2011 hydrograph resulted in the fuse plug being triggered in
three of the six modelled combinations;
The 1974 Flood Event simulations suggest the scenario has some benefit; though, the reduction in
flow rate at the Moggill gauge is approximately 700 m 3/s (or only 9%); and
45
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
The 1893 flood scenarios trigger the fuse plug at all three FSV capacities (50%, 75%, and 100%),
limiting release rates.
46
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Table 11 2011 Flood – Brisbane River Hydrology Model
47
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
7.2.5 Probable Maximum Precipitation Design Flood routing
Flood routing was conducted using the Probable Maximum Precipitation Design Flood hydrographs
provided by Seqwater for this Study. These hydrographs were originally created for the Wivenhoe
Alliance Hydrological Study (2005). While the PMF was investigated by the Wivenhoe Alliance, these
were not available for this Study, and it was beyond the scope of this Study to generate the necessary
run-off hydrographs.
Simulations were conducted for the base case (S0) and the primary scenarios (S1-S4) and the results
are shown in Table 14. The critical storm duration for peak outflow was the 36 hour duration event. The
base case and scenarios S1 and S2 retain the existing embankment crest of 80 metres AHD, and it is
anticipated that the Probable Maximum Precipitation - Design Flood overtops this crest by between 0.6
and 0.9 metres. While the existing embankment is overtopped during these scenarios, these options do
not require substantial Dam upgrade capital works to convey the Probable Maximum Precipitation
Design Flood until 2035.
Scenarios S3 and S4 include a two metre increase in the embankment crest to 82.0 metres AHD and the
results suggest that the Probable Maximum Precipitation Design Flood event should not overtop the
raised crest. Adopting a revised capacity volume of 75% of the current capacity resulted in a decrease of
0.9 metres in the peak water level (compared to S4), and if no freeboard were required for this event,
then the embankment crest may need only to be increased to approximately 81.0 metres.
S0 S1 S2 S3 S4
base Straight Steady 2m Dam 2m Dam
Parameter case to W2 to W4, raise FSV raise FSV
2001 FSV FSV 75% 75% 100%
FOM 100%
3
Peak Inflow to Wivenhoe Dam (m /s) 47,100 47,100 47,100 47,100 47,100
Peak Outflow from Wivenhoe Dam (m3/s) 31,700 31,200 30,500 32,000 31,500
Peak Water Level, Wivenhoe Dam (metres AHD) 80.9 80.8 80.6 80.9 81.8
Peak Water Level, Somerset Dam (metres AHD) 111.3 111.3 111.3 111.3 111.3
48
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
8. Water Security
The Queensland Water Commission (QWC) is responsible for the Water Security Objectives for South
East Queensland. They develop long-term water supply strategies to ensure the water supply for South
East Queensland.
As such, they have been involved in this Study to investigate the Water Security Objectives of altering
the FSV of Wivenhoe Dam.
While their report is attached, it is not in the form of formal advice as they have not been asked to
endorse or suggest a response, but purely to review the effects of lowering the FSV and the effect on the
long-term water strategy and the triggering of new infrastructure. The two options they were asked to
review were the permanent reduction in the FSV of Wivenhoe Dam to 75% and 50%. Due to the impact
of lowering the FSV any further than 50% and the real potential of trigging the need for immediately
building additional infrastructure, it was deemed this would be inappropriate within the context of this
rapid assessment project.
The assumptions and constraints are contained within the QWC report (Appendix D), however the LoS
Objectives are re-stated here as they are important factors in the assessment of the FSV and the
timelines for augmentation of the infrastructure.
The following explanation of the LoS objectives is taken from the ‘Report on the impacts of lowering the
FSV of Wivenhoe Dam on water supply security’ (Version 5, 28 Oct 2011).
49
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
The Level of Service Yield is the maximum demand that can be supplied, for given infrastructure and
operating conditions, while still meeting the LOS objectives. It is a modelled maximum supply.’
Medium population growth for the South East Queensland region has also been assumed for these
modelling outputs with consumption based on 200 l/p/d.
The main conclusions of this QWC Study are that the shortfall in water supply – reduction in LoS yield for
a permanent reduction in the FSV in Wivenhoe Dam – is to bring the new water source, identified as a
desalination plant, forward by 3 years. Table 15 shows the comparison in the shortfall in water supply,
the year new infrastructure is required to maintain the LoS objectives and the number of years earlier
It should be noted that the shortfall in LoS yield differ slightly from the QWC Report as they have referred
the volumes to the current published SEQ Water Strategy (2010), whereas the following LoS yield
includes the recent Hinze Dam upgrade and the associate additional 15,000 megalitres per annum
(ML/a).
Currently, the Strategy indicates that based on the LoS yield, new infrastructure is not required until
2030. By permanently reducing the FSV of Wivenhoe Dam to 75% or 50%, in order to maintain the LoS
objectives and yield, the new infrastructure will need to be brought forward by 3 and 11 years
respectively.
Wivenhoe FSV
Number of years
infrastructure is brought - 3 11
forward
Year of additional
2031 2028 2020
infrastructure
50
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
x demand hardening (i.e. not reaching to 200 l/p/day).
All of these approaches would effectively change the LoS objectives and this is something to be
considered if deferring capital is a requirement. Also, this rapid assessment does not investigate the
economic impact of changing the LoS objectives and introducing restrictions earlier. However, given the
economic impact of water restrictions on some businesses, this will need to be assessed in any future
detailed study.
Table 16 Probability of reaching ‘Grid 12’ Dam triggers for desalinated and PRW
Probability (%)
Wivenhoe FSV (%) Operating the Desalination Plant PRW into Wivenhoe
100 12 1.6
75 55 17.6
50 100 74
51
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
9. Downstream Flood Mitigation Options
9.1 Introduction
This section considers a broad range of options to increase flood mitigation aside from those considered
for Wivenhoe Dam.
Within the constraints of the Study timeline a high level review of options was considered in a
quantitative manner, principally through a workshop with key stakeholders to brainstorm the options from
an initial long list. Table 17 provides an overview of the outcomes of this workshop and a list of the
options considered. Further commentary on the viability of the options is provided in this section. It is
recognised that some of the options considered may be applied at a local, as well as a regional, scale as
a suite of solutions within a risk based flood management approach.
The workshop assessment considered each identified option against the following broad criteria:
Criteria Description
Community impact Impact on the community, either directly or indirectly as a result of the
measure, such as relocation and displacement, reduction in amenity
and social impact.
Table 18 presents a summary of the options identified and the outcome of the workshop evaluation of
each option to produce a short-list of options for further consideration.
52
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Table 18 Alternative Options – Workshop Evaluation Summary
Options Description
Expand storage capacity of Splityard Creek Dam (storage for hydro plant)
1 Expand Splityard Creek
and pump out of Wivenhoe into Splityard during the flood event
New flood-mitigation-only Dam. Land cleared of structures/trees, but able to
New flood retention dam
2 be used in non-flood periods, possibly for cropping or non-permanent
– Linville
activities
New flood-mitigation-only Dam. Land cleared of structures/trees, but able to
New flood retention dam
3 be used in non-flood periods, possibly for cropping or non-permanent
– Emu Creek
activities
New flood-mitigation-only Dam. Land cleared of structures/trees, but able to
New flood retention dam
4 be used in non-flood periods, possibly for cropping or non-permanent
– Bremer River
activities
New flood-mitigation-only Dam. Land cleared of structures/trees, but able to
New flood retention dam
5 be used in non-flood periods, possibly for cropping or non-permanent
– Lockyer Creek
activities
Bypass channel for Surface-level channel between Brisbane River and the ocean with
6
Brisbane River resumption of houses required
Channel upstream of Surface-level channel between the Dam and other areas (for example,
7
Wivenhoe to divert flow inland)
Connect flood plains,
Various interventions to divert water into existing flood plains and to convert
8 new wetlands, other
some existing flood areas to permanent wetlands
water ways
Planting vegetation on slopes of dam and upstream to 'absorb' some of the
9 Watershed management
floodwater
Deploy dredging vessels to remove soil, etc. from river to increase flow
12 Dredge Brisbane River
capacity
Strategic annual water release from Wivenhoe to remove soil, etc. from river
13 Flush Brisbane River
to increase flow capacity
53
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
9.2 Expand Splityard Creek Dam storage
Flood Community
Cost Time Environment Risk
mitigation impact
It is understood that some additional storage many be available within the Splityard Creek Dam, adjacent
and above Wivenhoe Dam, as part of the existing Pump Storage Hydroelectric Power Scheme. However,
the available storage volume is comparatively small so has no material impact on flood mitigation
compared to the flood volumes stored in the Wivenhoe Dam. Similarly the flow rates required to
significantly reduce the outflow from Wivenhoe Dam during flood events are very large. The additional
pumping infrastructure required to transfer the flood water from Wivenhoe Dam to Splityard Creek Dam
at the required flow rates would be prohibitively complex and expensive.
9.3.1 Linville and Emu Creek within the Wivenhoe Dam Catchment
Flood Community
Cost Time Environment Risk
mitigation impact
These sites are no longer considered as the likely benefit of storage upstream of Wivenhoe Dam is
considered to be minimal, against expected high costs and environmental impact. Any flood waters
stored within the Wivenhoe catchment would still need to pass through Wivenhoe Dam and therefore it
would only delay the release of the volume of water. Given the cost of the structure, there would be
greater impact in investing in Wivenhoe Dam itself.
54
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
9.3.2 Lockyer Creek and Bremer River catchments
Flood Community
Cost Time Environment Risk
mitigation impact
The benefits of mitigating peak flow rates downstream of Wivenhoe Dam were investigated for the base
case scenario. Three alternative downstream conditions were considered here:
excluding flow from the Lockyer Creek catchment;
excluding flow from the Bremer River catchment; and
excluding flow from both the Lockyer Creek and Bremer River catchments.
These results are summarised in Table 19.
In order to provide benefit from an impoundment on either the Lockyer Creek or the Bremer River, the
peak flow rates need to be mitigated. This means that the majority of the volume of the flood waters
needs to be stored temporarily and slowly released in the manner of a detention basin.
If the peak flow rates from the Lockyer Creek and Bremer River catchments were mitigated, the
reduction in peak flow at the Moggill gauge are estimated to be 16%. 29% and 32% respectively for the
1893, 1974 and 2011 flood events.
If the peak flow rates from the Bremer River catchment were mitigated, the reduction in peak flow rates
at the Moggill gauge are approximately 5%, 36% and 21% respectively for the 1893, 1974 and 2011
flood events.
Mitigating the flows in the Lockyer Creek and Bremer River catchments would mean the peak flow rates
in the Brisbane River at the Moggill gauge would be reduced to flows of below 4,5000 m3/s or lower
which dramatically reduces the flood damage in Brisbane for the 1974 and 2011 flood events.
3
However, in the case of the 1893 flood simulation, the estimated peak flow rate of 8,000 m /s at the
Moggill gauge is still considered to be significant and equates to only an approximate 20% reduction in
peak flow rate when compared to the simulation of the 1893 flood event with Wivenhoe Dam present and
using the 2011 FOM. While the 1893 flood event suggests that mitigation on Lockyer Creek and Bremer
River does not alleviate the flood damage as much as the 1974 and 2011 events, there is a reduction in
3
the peak flow of approximately 2,100 m /s which is still significant.
While these mitigation options were not considered in conjunction with the other primary scenarios (S1-
S4), it is likely that a similar percentage reduction in the peak flow rate may occur for the respective
floods.
55
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Table 19 Influence of Lockyer Creek and Bremer River flows, base case scenario (S0)
Scenario
Flood Excluding
Parameter Excluding Excluding
event Lockyer Creek
Lockyer Creek Bremer River
and Bremer
flow flow
River flow
These options were only considered at a high level, as it has a potentially high cost, significant
community concern and environmental impacts as experienced on similar recent new dam projects in
Queensland. The hydrological effects of impounding either the Lockyer Creek or the Bremer River need
significant investigation particularly given the potential impact on Ipswich and surrounds. There may be
opportunities to provide a series of impoundments in order to achieve the required volume, however,
detailed investigations would need to be undertaken to progress this option and site selection would be a
critical component.
Caution would again be required after construction of these dams, as similarly to Wivenhoe Dam, these
should be seen as flood mitigation and not flood ‘proofing’ structures. All floods behave differently and
therefore, while flood retention structures may reduce flooding during one event, they may not be as
effective during a different flood event. This is highlighted by some of the results discussed above where
it is concluded that there was a benefit in the reduction in the peak flow of the Brisbane River at the
Moggill gauge by the construction of flood mitigation dams on the Lockyer Creek and the Bremer River
during the 1974 and 2011 flood events, but not for the 1893 event.
Some recent cost estimates for dams holding 300,000 ML were approximately $700/ML. Therefore, no
economic analysis was undertaken on the cost and benefits of these options as the preliminary
investigation was very high level. Significant further investigations need to be undertaken including site
selection, number and size of the impoundments and detailed hydrological assessment to confirm the
benefit of these structures prior to any economic analysis being undertaken.
56
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
9.4 Bypass channel for Brisbane River
Flood Community
Cost Time Environment Risk
mitigation impact
This option was considered at a high level only, and was proposed to by-pass extreme flows via an
allocated flood channel around populated areas. Given the surrounding topography and urbanisation of
Brisbane this option is not considered practical and would be prohibitively expensive with very high
environmental and community impact. This option is not considered further, however may have some
merit in some regional towns.
This option considered an upstream channel to divert extreme flows in the upper watershed to an
adjacent catchment. The technical feasibility of this option, given the size of the large catchment area
required to be diverted to be effective and availability of suitable adjacent catchments to receive such
water, is highly questionable. The expected cost of this option would also limit the viability of proceeding
and as such has not been considered further.
Various interventions were considered to divert water into existing flood plains and to convert some
existing flood areas to permanent wetlands. This option is considered to be of limited value only in terms
of flood mitigation. It may have some localised effects and small flood events may be able to be slightly
mitigated. However, in the context of the volumes required in order to have significant impact on the
peak flows in the Brisbane River this option is not considered further.
This option considered the potential to increase time taken for run-off from the catchment to reach the
Dam through land use management in the upper catchment areas. This is a catchment based approach
aimed at reducing runoff rates in the upper catchment and reducing rates of flow down watercourses.
Flood mitigation effects would be limited to smaller events given the potential for the natural covering to
slow run-off rates of more extreme events.
The disadvantages of this option are the length of time it takes to establish ground cover, the significant
area involved which would need to be set aside and legislative framework that would be required to
manage such a large area, across multiple regions. This option would have had limited effect during
some of the historical nominated events, for which the majority of rainfall fell in catchments downstream
of the Dam. Land resumption and compensation for planting would outweigh the benefits of such an
approach. As the benefit of this option is in the vegetation cover, this land would need to be set aside
with no grazing or cropping allowed. Due to the identified constraints this option is not considered further.
57
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
9.8 Backflow prevention
Flood Community
Cost Time Environment Risk
mitigation impact
Localised backflow devices may have a benefit but the benefit will be restricted to localised areas. The
installation of backflow devices is the subject of a separate study currently being undertaken by Brisbane
City Council. The effectiveness of the devices is limited to mitigation of backflow from the river. They will
not prevent localised flooding due to high rainfall in the catchment upstream of the backflow device such
as was prevalent in the 1974 event. In addition, the benefits gained from the use of backflow devices
need to be compared against risk of operational failure.
Backflow devices could form part of any localised levee solution, however, have not been considered in
detail as part of this Study. If backflow prevention devices are considered on a local scale, significant
hydrological investigation needs to be undertaken to identify the potential for consequential flood risk
elsewhere due to the displacement and diversion of the flood waters. Otherwise there is the potential to
exacerbate flooding in neighbouring areas. The significance and effect of this issue needs to be fully
investigated anywhere these devices are considered for installation.
Levee banks have been identified in the flood mitigation options short-listing and have the potential to
provide localised flood mitigation benefits to some urban areas of Brisbane
To determine the extent of these benefits and provide concept level cost estimates, a conceptual
arrangement for levees has been developed.
Conceptually, levee banks would comprise an earthen structure with a crest width of approximately
5 metres and side slopes of 2 to 1 (Horizontal to Vertical). For taller structures, a central sand filter zone
may be needed to control seepage and potential piping issues in order to mitigate internal erosion of the
soil via seepage flows. Much of the access to locations where levee banks may be of use is currently
occupied by high value residential or commercial properties along the river bank. This significantly
constrains the construction of these levees or increases the cost due to the land resumptions involved
and the resulting compensation that would be required.
Where constrained access does not permit a levee, walls may replace the levee however, this would
need careful engineering consideration to prevent seepage under the structures. Earthen structures can
be constructed on river bank margins, but some locations may need to be augmented in subsequent
phases of design to improve river bank stability, in particular on the recession limb of floods when the
potential for river bank collapse is high.
The adopted crest level of the levees has been designed to mitigate flooding caused by the anticipated
3
10,000 m /s peak flow at the Port Office gauge – being representative of the nominated flood events
considered in this Study. This proposed peak design flow is marginally higher than the peak flow during
the January 2011 flood of approximately 9,500 m 3/s.
Levee banks have generally been positioned close to the river bank, and isolated from important
infrastructure such as major highways, where possible. In some areas, road and transport infrastructure
58
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
has already been constructed in the most suitable levee bank positions, and therefore relocation of the
existing road infrastructure would be necessary.
Levees along major creeks should either:
extend to the point of limited backflow influence from the Brisbane River; or
include a gated structure to permit local flooding to discharge.
Local flooding tends to occur significantly prior to the arrival of the flood peak in the Brisbane River. As
such, local flood gates can discharge the local peak through the levee bank and be subsequently closed
for the Brisbane River peak. Alternatively, stormwater pumping facilities may be incorporated to manage
localised water build up behind the levees.
It should be noted that levee banks only provide flood protection up to the design flood event. For floods
with peak flows exceeding the design event, the levees will be overtopped, resulting in further damage.
Overtopping of the levee can result in rapid rises in water level within the flood protected area and may
cause more significant flood damage than if no levees were constructed. In some instances, loss of life
can occur if overtopping causes rapid failure of the levee and the population at risk cannot be evacuated
prior to the event.
Localised flooding behind levees and walls is also a risk, particularly where backflow devices fail to
operate correctly or the capacity of pumping facilities are exceeded.
Cost estimates and an economic evaluation for the proposed levees have not been determined as part of
this Study. However, it is anticipated the cost of land resumption alone for regional levees would exceed
the economic benefits.
However, despite these concerns, levees may be a valuable option to protect specific local areas, for
example, areas with a high population density, or important industrial zones. Consideration of any levee
scheme should include significant hydrological investigation to identify the potential for consequential
flood risk elsewhere in the catchment due to the displacement and diversion of the flood waters.
Deploy dredging vessels to remove soil, sediment and debris from the river bed to increase flow
capacity. This has not been considered further as there would be limited flood mitigation benefits and
expected high operational costs and environmental impacts of both the operation of the dredging vessels
and the disposal of the resulting material.
59
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
9.10.2 Flush Brisbane River
Flood Community
Cost Time Environment Risk
mitigation impact
Periodic release of high flows from Wivenhoe Dam could be undertaken to flush accumulated sediment
from the river bed. Flushing would be best undertaken when there is a low king tide to achieve maximum
effect and minimise river water levels. It would probably only be needed every 5-10 years.
While a 'low cost' option when considered in association with a reduction in reservoir level, it has not
been considered further due to the limited flood mitigation benefit, the expected community concern and
potential environmental impacts. The recent 2011 flood event has had a significant impact on Moreton
Bay and the sea grass beds, resulting in turtle and dugong casualties, therefore, significant
environmental investigations would need to be undertaken in order to prove that flushing would not have
similar effects.
60
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
10. Economic Analysis
10.1 Overview
Economic evaluation (cost benefit analysis) considers the costs and benefits for society as a whole. It is
concerned with efficiency and impacts on resource consumption and includes broader social effects such
as ill health and stress that may not have a market value. This contrasts with financial analysis which
considers costs and benefits to an individual or entity. It is based on the cash value of the resources and
effects with no market value are not considered.
The preliminary economic evaluation of flood mitigation options involved application of a Rapid Appraisal
2 3
Method (RAM) within a benefit cost analysis framework . RAM is an approach used in other regions of
Australia such as Victoria, which adopts a cost benefit analysis framework to assess the economic costs
and economic benefits associated with flood mitigation/management initiatives. It involves estimation of
benefits on the basis of a reduction in average annual damage and costs from engineering estimates of
capital investments and operations.
Furthermore, consistent with the guidance of the former Queensland Department of Natural Resources
4
and Mines (DNRM) , the economic analysis incorporates consideration of three groups of estimated
damages associated with floods:
Direct (tangible) damages: the physical impact of the flood. For example, damages to the structure
and contents of buildings, agricultural enterprises and regional infrastructure;
Indirect (tangible) damages: losses from disruption of normal economic and social activities that arise
as a consequence of the physical impact of the flood, for example, costs associated with emergency
response, clean-up and community support, as well as disruption to transport, employment and
commerce; and
Intangibles (or ‘non market’ impacts): losses which cannot be quantified in monetary terms (as there
is an absence of a market price and/or methods to approximate market prices). For example, loss in
biodiversity or increased stress levels for residents following a major flood event affecting their
homes.
Economic evaluation considers 'total cost' to the community.' From a government perspective, it is
important to understand that the 'costs' in the analysis largely accrue to the state, while a significant
proportion of the 'benefits' are received by individuals. Therefore, the funding considerations associated
with additional costs will require careful consideration from a State budgetary perspective (as alluded to
in footnote 2).
The steps undertaken in preparation of this economic evaluation are set out below and illustrated in
Figure 21. Furthermore a diagram showing the economic framework is provided at Figure 22.
2
See Rapid Appraisal Method (RAM) for Floodplain Management, National Resources and Environment, Victoria, May 2000 and
Economic Costs of Natural Disasters in Australia, Bureau of Transport Economics, Report 103, Canberra, 2001.
3
Cost Benefit Analysis (also known as Benefit Cost Analysis) is an analysis tool used to rank alternative projects or initiatives by
identifying and quantifying the benefits (or losses avoided) and costs to society. It aims at valuing benefits and costs in money
terms and producing a summary measure of net benefit, typically a Net Present Value (NPV) or Benefit Cost Ratio (BCR). If the
NPV is greater than zero or the BCR is greater than one, the project / initiative is considered to provide a positive net benefit to
society.
4
Guidance on the Assessment of Tangible Flood Damages, Queensland Department of Natural Resources and Mines, September
2002
61
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
i. Definition of Study area – identified as the area downstream of Wivenhoe Dam subject to
flooding in January 2011 due to releases from the Dam5.
ii. Estimation of damages for key flood events – initially involved use of flood damage curves
developed in 2007 as part of the Brisbane Valley Flood Damage Minimisation Study6 for
Brisbane City Council, Ipswich City Council and Esk Shire Council (refer to Figure 20). The flood
damage curves are also known as stage-damage curves and show the relationship between
inundation and damage incurred. In this analysis the flood damage curves that form the basis of
3
the estimation of damage reduction (benefits) show the peak flow rate (as measured in m /s) on
the horizontal axis and expected total damage (in $ million) on the vertical axis. As the peak flow
increases (inundation increases) and the expected level of damage rises. This data provided (in
$AUD 2007) estimated flood damage, relating to direct residential and non-residential properties
3
for peak flow rates of 1,000 to 10,000 m /s in these three urban locations. The January 2011
3
flood event was assessed at being equivalent to 9,000-9,500 m /s at the Port Office gauge.
7
The 2007 curve was rescaled to $AUD 2011 using a construction cost index . The 2007 curves
3 3
were also rescaled at 500 m /s intervals for the range - 1,000 to 10,000 m /s to facilitate
subsequent evaluation. Data was also collected from the Queensland Reconstruction Authority,
Department of Transport and Main Roads, Queensland Rail, and other sources to adjust the
residential and non-residential values to obtain a broader estimate of damages to ‘capture’ direct
and indirect tangible costs. The estimate developed, while significant, is likely to be an
underestimation of actual damages due to data limitations and the difficulties to ‘capture’ each
and every cost incurred in major disaster events.
The Queensland Government report, Resources for Reconstruction, Discussion Paper 1
(September 2011) - notes that the ’...estimated cost for the recovery of state and local
government roads, local government assets and private dwellings is in the vicinity of $10.8
billion’. Similarly, the ’...World Bank concluded that the cost of damage and losses in
Queensland could be up to $15 billion when the impacts on mining, tourism, agriculture and
commercial sectors are included.’ Furthermore, the report estimates cost of reconstruction of
state-owned and local government roads and other assets at slightly over $1 billion for the
metropolitan region. The Insurance Council of Australia (General Insurance Claims Response –
2010/11 Queensland Flood and Cyclone, Update 27 October 2011) notes ‘reserved and paid
value Queensland floods’ totals $2.4 billion.
5
For data collection and analysis purposes this includes Brisbane City Council, Ipswich City Council and Esk Shire Council areas
6
Feasibility and Final Report for Brisbane Valley Flood Damage Minimisation Study, Phase Three – Damage Mitigation Feasibility,
prepared by City Design, Brisbane City Council. August 2007
7
Derived from: Cordell Building Indices, Cordell Housing Index Price (CHIP), Queensland, February 2010
62
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 20 Estimated flood damage curve – Brisbane City Council*
1,400
1,200
1,000
800
$ m 2006
600
400
200
0
1000 2000 3000 4000 5000 6000 7000 8000 10000
Residential Damage Non-Residential Damage GRAND TOTAL Damages
Peak Flow Rates (m3/s)
*Source: Feasibility and Final Report for Brisbane Valley Flood Damage Minimisation Study, 2007
iii. Estimation of Average Annual Damages (AAD)8. This involves translation of the damage
estimates for varying levels of peak flow rates associated with flooding into a loss-probability
curve to calculate estimated AAD. A loss-probability curve uses AEP values corresponding to
Average Recurrence Intervals (ARI) for flood events which are plotted against damages
associated with peak flow rates. The area under the curve (i.e. a triangle or triangle plus a
parallelogram) equates to the AAD.
iv. Determination of options for flood mitigation, while maintaining water supply security, for each of
the three major flood events (January 2011, 1974 and 1893) and varying operating regimes flow
3 3
release rates for example, 1,900 m /s, 3,500 m /s and patterns for differing levels of FSV (100%,
75% and 50%) – a total of 45 options were modelled hydrological, or which 32 emerged as
‘practical’ from an operations and dam safety perspective.
v. Determination of the cost associated with options such as the economic costs of bringing forward
facilities for water supply augmentation to maintain the necessary LoS, capital costs of new
infrastructure, for example, associated with raising the Dam wall, raising bridges and relocation
of roads, and additional operating costs for existing (and new) facilities such as desalination and
PRW.
8
ADD is the average damage per year that would occur in a nominated development situation from flooding over a very long period
of time. AAD provides a basis for comparing the economic effectiveness of different management measures against floods of all
sizes, i.e. their ability to reduce the AAD.
63
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
vi. Economic evaluation of options incremental to the base case – the existing operating regime,
existing estimated AAD and planned/committed investment. The analysis involves evaluation of
benefits and costs of options relative to the base case (the ‘without’ case) – which in this analysis
9
is in effect a ‘Do Nothing’ case . Included for each option are those costs ‘over and above’
currently planned, both new costs (capital and operating) as well as the economic costs
associated with bringing planned investment forward, and those benefits that accrue from an
option compared with the current situation. Benefits are measured as the change in AAD from
the current estimate to a new (typically, lower) AAD estimate associated with mitigation
initiatives. The change in AAD reflects the costs avoided/cost reduction with a flood mitigation
initiative.
The base case AAD has been estimated by plotting for various AEPs – the expected damage
values ($ million) associated with that magnitude of event for a range of flood events where city
3 3
centre peak flows range from 1,000 m /s to 10,000 m /s. The various ‘options’ are modelled
using a hydrologic model to estimate the change in peak flow rate in the ‘with’ investment and/or
change of operating regime case.
vii. A 20 year evaluation period has been adopted (2011 to 2031, with Year 0 = 2011 and the
evaluation year = 2011) with a real discount rate of 7% for the Discounted Cash Flow (DCF )
analysis. The 20 year evaluation period is sufficiently long enough to 'capture' all the expected
cost and benefits of the options under consideration. The calculation of residual values for assets
has been done to reflect that assets will generate future benefits beyond the evaluation period.
viii. Calculation of measures of net economic worth - NPV and Benefit Cost Ratio (BCR) are
calculated. Sensitivity analysis of key factors and assumptions is applied to test the robustness
of the outcomes under realistic changes in key variables. Furthermore, given the degree of
uncertainty with some estimates (particularly, capital costs), it has been deemed appropriate to
consider this aspect in the analysis and utilise contingency values to reflect an optimism bias
10
uplift factor .
ix. Provision of supplementary discussion of factors to further inform the analysis. In this case, this
involves discussion of outcomes from hydrological modelling, Geographic Information System
(GIS) mapping used to develop inundation maps for various levels of flows, analysis of traffic
flows on impacted roads and bridges and consideration of possible impacts on the Regulatory
Asset Base (RAB) for the bulk water assets of South East Queensland.
9
This incorporates adoption of the SEQ Water Strategy (2010)
10
For example, the UK Treasury’s Green Book: Appraisal and Evaluation in Central Government advises application of an
Optimism Bias (OB) factor on non-standard civil engineering projects of 6% to 66% to expected capital expenditure based on
empirical research of completed projects. http://www.hm-treasury.gov.uk/d/5(3).pdf. Treatment of OB is also recommended in the
Australian Government’s guide – Handbook of Cost Benefit Analysis (Department of Finance & Administration, 2006) but no
specific values are provided.
64
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 21 Economic Analysis Methodology
65
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 22 Economic Modelling framework
Note: Table 21 demonstrates the ‘options’ from the hydrological modelling which did not involve water levels exceeding the trigger
level of the first fuse plug. The cases where the fuse plugs are triggered have been rejected because they do not provide a
mitigation of floods (which is the primary objective of the study).
66
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
City Council and Esk Shire Council region for a 10,000 m3/s flow of $3.8 billion was developed (Figure
23). The difference (‘adjustments’) between the 2011 and 2007 estimates include:
application of a building/property cost escalation of 25.3% to bring mid 2006 $AUD values to late
2011 $AUD dollar values;
inclusion of damage estimates for Brisbane City Council of $440 million including:
– $137m for roads
– $61 million for clean-up costs
– $75 million for the floating walkway
– $2 million to salvage the floating walkway
– $75 million for ferry terminals
– $38 million for city parks.
inclusion of $478 million for costs estimated by Transport Network Reconstruction Program for State
roads in the region and $8 million for urban rail infrastructure and systems damage; and
inclusion of estimates for indirect tangible costs for residential and commercial damages of 15% and
55% respectively in line with advice provided in the Guidance on the Assessment of Tangible Flood
11
Damages (2002).
It is worth noting that there is considerable uncertainty as to the actual costs of a major flood event due
to the difficulty in collecting data on all costs incurred, where ‘all costs’ includes direct, indirect and
intangible costs. For example, The World Bank report – Queensland Recovery and Reconstruction in the
Aftermath of the 2010/2011 Flood Events and Cyclone Yasi12 notes that ‘losses’ of economic flow
(forgone revenue or production losses) could account for 30% of total ‘damage’.
11
It is noted that the Victoria Rapid Appraisal Method Study (2000) cited earlier implies use of a value of 30% overall or 20% for
rural areas and 45% for urban centres.
12
A report prepared by the World Bank in collaboration with the Queensland Reconstruction Authority, June 2011.
67
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 23 Combined Stage Damage Curve
68
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
For each option assessed, hydrologic modelling was used to estimate the mitigated peak flow rate. The
peak flow rate derived for each option enabled estimation of a new AAD associated with that particular
option. The new peak flow in effect moves the damage curve so that what previously would be the
3 3
damage expected with a flood of 8000 m /s is now associated with a peak flow of 10,000 m /s. For
3
example an event that would result in a peak flow of 10,000 m /s would be expected to result in damage
of approximately $3.6 billion. However, following the implementation of an option or management
strategy and the resulting flood mitigation, the peak flow of the event would be reduced to a flow of 8,000
3
m /s and therefore have a reduce damage impact equivalent to that lower flow. This new damage curve
is then used to develop a revised loss-probability curve and results in a new estimate of AAD. This
process is reiterated for each option as new peak flow rates are derived from the hydrologic modelling.
Therefore, each option has its own individual peak flow rate and resultant AAD estimate (i.e. an AAD
associated with a particular mitigation option).The relative reduction in AAD therefore represents the
economic benefit associated with a particular option. That is, the benefit that is derived from that
reduction in flow associated with the flood mitigation option analysed is equal to the ‘new’ or ‘with project’
AAD subtracted from the base case/ ‘without project’ (‘old’) AAD). In essence, what the analysis does is
use the change in the level of damage expected by a flood event (as measured by peak flow rate) to re-
estimate the AAD associated with the introduction of option and the resulting mitigation. Mitigation
options include a combination of procedural and operational changes, and in many cases incorporate
investment in additional capital items to enable the operational change whilst maintaining water security
(LoS) objectives.
The AEP is the inverse of the average recurrence interval (ARI), the ‘one in every x years’ measure. AEP
is the likelihood of occurrence of a flood of a given size or larger in any one year. The AEP is expressed
as a percentage. If a given flood level has an AEP of 5%, it means there is a 5% risk (i.e. a probability of
0.05 or a chance of 1-in-20) of a flood that size or larger occurring in any one year. ARI is another way of
expressing the likelihood of a flood event. It is the long-term average number of years between the
occurrence of a flood as big as, or larger than, the selected event. For example, a flood as big as, or
larger than, the 20 year average recurrence interval flood event will occur on average once every 20
years. The average recurrence interval of a flood should not be taken as an indication of when a flood of
that size will occur next.
69
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 24 Loss probability curve – Brisbane (Illustrative)*
$4,000
$3,500
$3,000
$2,500
Damage $m
$2,000
$1,500
$1,000
$500
Probability
*Note: ‘Current Total Damage’ includes both blue and red areas. For each option, a new loss probability curve is estimated (and
‘new’ AAD) and compared with the base loss probability curve (and ‘old’ AAD).
13
Report on impacts of lowering the FSV of Wivenhoe Dam on water supply security, Queensland Water Commission, October
2011 and updates November 2011. ‘Information Material Only’.
70
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
10.4.1 Assumptions
Options which trigger activation of the fuse plugs within the hydrologic model have not been considered
in the economic analysis. Fuse plugs are designed to be triggered in extreme flood events only. Also the
peak flow rates at Moggill of the modelling scenarios where the plugs were triggered showed either the
same or higher peak flow rates than those scenarios where the plugs remained intact.
In order to successfully implement many of the options it would be necessary to undertake a range of
capital works and/or bring forward some currently planned future investments. Table 21 details the
capital expenditure items associated with the implementation of each option. Details of particular capital
requirements are set out in Table 21.
Table 20 projects the key cost and timing assumptions have been used in the evaluation of options:
14
Capital costs include desalination plant as well as additional capacity at Wyaralong Dam and associated pipe networks; these
latter items at an estimated cost of $369 million.
15
Expenditure profile for the desalination plant over 4 years is: Year 1= 5%, Year 2 = 5%, Year 3 = 25% and Year 4 = 65%.
16
Preliminary indicative cost associated with lowering the operating level of Wivenhoe Dam were provided by SEQ Water Grid
Manager (pers. comm. 20/10/2011 and 1/11/2011). Estimates were based on use of both PRW and Desalination for supply
augmentation and incorporates probabilities of changes to existing PRW and Desalination operating costs.
17
Capital costs estimates for desalination plant derived from data for a number of plants either completed or planned for
development in Australia, namely: Sydney (Kurnell, $1890m, 90 GL/annum capacity); Melbourne (Wonthaggi, $3.5 billion, 150
GL/annum); South East Queensland (Tugun, $1.2 billion, 49 GL/annum); Perth (Kwinanna, $387 million, 45 GL/annum); Perth
(Binnngup, $1.4 billion, 100 GL/annum); Adelaide (Port Stanvac, $1.83 billion, 100 GL/annum)
18
Capital costs include desalination plant as well as additional capacity at Wyaralong Dam and associated pipe networks; these
latter items at an estimated cost of $369 million.
19
Expenditure profile for the desalination plant over five years is: Year 1= 5%, Year 2 = 5%, Year 3 = 15%, Year 4 = 20% and Year
5 = 55%.
71
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Option Costs Timing
New desalination operating costs from 2016 of
$1.09 million/GL/a.
Raise the wall at Capital cost of $395 million. Four year planning, approvals and
Wivenhoe Dam construction period commencing
Capital cost estimate includes for the raising of
by 2 metres in 2012 for Dam raising and
the Wivenhoe Dam wall, plus for road
relocation of roads and other
relocation costs and costs of other facilities
assets impacted.
relocation upstream. This estimate does not
include the cost of raising bridges downstream
of the Dam such as Burtons Bridge at Borallan
or College’s Crossing at Chuwar. This cost
does not include substantial modification to the
gates (potentially up to $330 million), potential
upgrades associated with the requirement for
Probable Maximum Flood (PMF) or fishways
(potentially greater than $100 million). The
cost has been based on this rapid assessment
and is likely to increase during any preliminary
design phase.
Raise the heights $67.3 million for College’s Crossing Undertake road diversions
of two downstream of Wivenhoe Dam in
$37.9 million for Burton’s Bridge
strategically one year (2012) for 3,000 m3/s
important bridges immunity.
downstream of
Residual values have been
Wivenhoe Dam –
estimated using a straight line
College’s
depreciation method and the
Crossing (Mt
following economic lives have
Crosby Road)
been used: Dam wall extension
and Burton’s
(50 years), new desalination plant
Bridge – to 2000
3 and associated infrastructure (30
m /s immunity in
years), new roads (20 years) and
one year (2012)
bridges (100 years). In the
including planning
Discounted Cashflow Analysis,
and construction:
residual values have been treated
as negative costs (as opposed to
benefits) i.e. as an offset against
capital costs of options
(implementing a project).
10.5.1 Overview
Figure 25 sets out the relationship between the economic analysis inputs and the cost benefit analysis
(including sensitivity testing).
72
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 25 Economic analysis and cost benefit analysis
Discounted Cash Flow analysis was used to estimate the net economic worth of options assessed.
Measures obtained were NPV20 and BCR21 for each option incremental to the base case. The following
additional indicators were calculated:
change in AAD value – actual ($ millions) and percentage; and
probable damage value of future event where peak flow rates equate to those estimated for the
option;
probable damage value relative to January 2011 of a future event where peak flow rates equate to
those estimated for the option;
Present Value Costs; and
Present Value Benefits.
20
NPV – The discounted value of the expected benefits of a project, less the discounted value of the expected costs.
21
BCR – The ratio of the expected present value of net recurrent benefits to the present value project costs.
73
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
The NPV for each option is presented in Figure 26, Figure 27 and Figure 28 for the 1893, 1974 and 2011
flood events respectively.
74
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 28 NPV ($) for 2011 Flood Event options
75
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
The following options result in the most significant reduction in peak flow rate (to between 7300 and
6700 m3/s) and therefore the largest benefit streams:
– Year 1893 Flood 2 Metre Raise to W4 and Fuse Plug Levels 75% FSV
– Year 1974 Flood Release Rate = 3,500 m 3/s 75% FSV
– Year 1974 Flood 2011 FOM 75% FSV
– Year 1974 Flood Release Rate = 1,900 m 3/s 75% FSV
– Year 1974 Flood Release Rate = 3,500 m 3/s 50% FSV
– Year 1974 Flood 2011 FOM 50% FSV
3
– Year 1974 Flood Release Rate = 1,900 m /s 50% FSV
3
– Year 2011 Flood Restrict Release Rate to 1,900 m /s 50% FSV
However, four of these options are very capital intensive and actually generate negative NPVs
(costs far outweigh benefits);
Options involving FSV 75%, (where capital requirements are at the lower end of the range of those
involved) are broadly the next best performing options with significant positive NPVs;
The equal best performing options (i.e. the largest NPV) are the options of the 2011 Flood utilising
FSV 100% with uncontrolled flow to 3,500 m3/s or Straight to W2. This option marginally out
performs the following:
– 1974 Flood FSV 100% – Release rate 3,500 m3/s1974
– Flood FSV 100% –2011 FOM
– 1974 Flood FSV 75% – Release Rate 3,500 m3/s
– 1974 Flood FSV 75% –2011 FOM
– 1974 Flood FSV 100% – Release rate 1,900 m3/s
– 1974 Flood FSV 75% – Release Rate 1,900 m3/s
All of these options generate an expected NPV of between $1 billion and $1.3 billion; and
The two best performing options are characterised a substantial reduction in peak flow rates (down to
7600 m3/s)and therefore a very substantial economic benefit and nil capital cost requirements.
.
76
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Table 21 Economic analysis – summary results
Option Hydrology Capital Expenditure Items Initial Economic Analysis Initial Economic Damage Analysis
Model
Option FSV Flood Estimated Desal Raise Wall Raise Bridges PV Costs PV Benefits NPV BCR Reduced % Probable
Event Peak Flows Earlier ($million) ($million) ($million) AAD Reduced damage
(m3/s) ($million) AAD ($million)
1893
S5 - uncontrolled ¥ 28 15 3,220
100% 1974 9,500 63.4 321.9 258.5 5.1
3,500 m3/s
¥ 109 57 1,610
2011 7,600 63.4 1,268.20 1204.8 20
S6 – Restrict 1893
Release Rate to
3 1974 7,800 - 1,174.50 1,174.50 - 101 53 1,769
3,500 m /s (not 100%
feasible –
sensitivity only) 2011
S6 – Restrict 1893
Release Rate to
3 1974 7,200 337.8 1,455.80 1,118.00 4.31 126 66 1,291
3,500 m /s (not 75%
feasible –
sensitivity only) 2011 7,600 337.8 1,268.20 930.4 3.75 109 57 1,610
77
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Option Hydrology Capital Expenditure Items Initial Economic Analysis Initial Economic Damage Analysis
Model
Option FSV Flood Estimated Desal Raise Wall Raise Bridges PV Costs PV Benefits NPV BCR Reduced % Probable
Event Peak Flows Earlier ($million) ($million) ($million) AAD Reduced damage
3
(m /s) ($million) AAD ($million)
S6 – Restrict 1893
Release Rate to
3,500 m3/s (not 50% 1974 7,100 2,084.40 1,502.60 -581.8 0.72 130 68 1,211
feasible –
2011 7,500 2,084.40 1,315.10 -769.3 0.63 113 59 1,530
sensitivity only)
S7 – Restrict 1893
Release Rate to
1,900 m3/s (not 100% 1974 7,800 63.4 1,174.50 1,111.00 18.5 101 53 1769
feasible –
sensitivity only) 2011
S7 – Restrict 1893
Release Rate to
3 1974 7,200 401.2 1,455.80 1,054.50 3.63 126 66 1,291
1,900 m /s (not 75%
feasible –
sensitivity only) 2011
S7 – Restrict 1893
Release Rate to
1,900 m3/s (not 50% 1974 7,100 2,147.90 1,502.6 -645.2 0.7 130 68 1,211
feasible –
2011 6,700 2,147.90 1,668 -479.9 0.78 144 75 929
sensitivity only)
78
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
10.5.4 Sensitivity analysis
In order to demonstrate the impact of some key variables, and to assess the general robustness of the
economic analysis, a number of sensitivity tests were conducted, including:
adjustments to the real discount rate (use of 4% and 10%);
reductions in benefits associated with options (20% reduction);
an uplift in benefits to reflect possible underestimation (20% uplift);
impact of a need to bring forward water capacity earlier than envisaged (for FSV 75% options,
bringing forward desalination and associated costs by six years as opposed to three years. The six
years was undertaken as a sensitivity analysis);
inclusion of capital costs for road diversion downstream of the Dam wall to an immunity level of 3000
3
m /s for the 2 metre Dam raising options only ($133 million spent as follows: 5% in 2013 and 95% in
2014, which includes a total contingency estimate of 80%); and
a pessimistic case – uplift of capital costs to reflect possible underestimation or optimism bias (20%
uplift) and a reduction of benefits of 20%.
These sensitivity tests did not materially alter the ranking of options. Details of the sensitivity tests are set
out in Appendix C.
79
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Figure 29 Area of land inundated in Brisbane (hectares) – various flow rates
40000
35000
30000
25000
20000
15000
10000
5000
40000
35000
30000
25000
20000
15000
10000
5000
80
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
With respect to bridges downstream of the Dam that become inundated when water is released, the
following traffic flows (as measured by Average Annual Daily Traffic) data has been found to provide an
indication of the order of possible impacts and highlights the traffic levels impacted relative to major
roads in the same general area.
Reducing the Wivenhoe Dam FSV by either 25% or 50%, while maintaining the LoS objectives, will
necessitate the bringing forward of planned water supply augmentations. These include upgrading
Wyaralong Dam, provision of a distribution network, and implementation of new desalination capacity.
These new assets, as noted previously, are significant and implementing them sooner than currently
planned may hold implications for the size of the Regulatory Assets Base. This in turn may have
implications for bulk water pricing in South East Queensland.
The economic impacts on businesses and the community of the potential to trigger restrictions more
frequently by lowering the FSV of the Dam to 50% or 75% or not meeting or changing the LoS objectives
has not been included in this analysis but should be investigated further in future studies.
22
2009 North Coast Region Traffic Census / 2009 Metropolitan Traffic Census
81
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
10.5.6 Further issues
During investigations for the preliminary economic evaluation it became clear that further research and
data exchange would prove helpful in gaining a better and deeper insight into the benefits of flood
mitigation.
These are described briefly below:
Further analysis to provide a broader basis for the benefits of mitigation, including full access to
detailed physical surveys of damage associated with the January 2011 Flood Event, and further
disaggregation of other direct and indirect costs associated with public infrastructure and other
assets. Provision of this data would enable a more refined estimate of flood damage curves, and
estimation of AAD;
Improved data collection and dissemination of information associated with indirect and intangible
costs. Limited time did not allow ready access to non-published information and the ability to source
data from insurance companies (or peak bodies). Discussions with welfare groups and others would
enable refection of some of the intangible costs associated with floods to be discussed;
Traffic counts on the minor river crossings downstream of Wivenhoe Dam would enable a better
understanding of the scale of impact associated with low immunity levels for a number of existing
structures;
Examination of how the application of cost benefit analysis might disadvantage certain mitigation
measures and groups within our community;
Research on the long-term socio-economic impact of the January 2011 Flood Event on the
community;
Development of the January 2011 Flood Event into a major case study;
Financial impact analysis of the implication of a possible change in the Regulatory Assets Base on
South East Queensland’s bulk water pricing; and
Analysis using the actual damage curves from January 2011 rather than the scaled 2007 damage
curves.
82
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
11. Summary and Recommendations
11.1 Summary
Given the simplistic nature of the hydrologic and economic modelling used in this preliminary rapid
assessment to investigate options to increase the flood mitigation performance of Wivenhoe Dam, the
following broad findings could are made:
A 2 metre increase in the crest level of the Dam provides approximately 437,000 ML (437 GL) of
additional flood mitigation capacity giving a total volume in the flood storage compartment of
approximately 2,404 GL and a subsequent total volume in Wivenhoe Dam of 3,596 GL;
Raising the Dam wall by 2 metres or permanently lowering the existing FSV to 75% has a relatively
limited impact reducing peak levels at the Port Office gauge; in the range of 0 metres to 0.6 metres
for the nominated events compared to the base case for all events;
The provision of larger available flood storage through combining the raising of the Dam wall with
permanent reductions in FSV has a greater impact on reducing peak water levels in the dam and
peak flows at the Moggill gauge than either raising the Dam wall or reducing the FSV by themselves.
The estimated resultant impact of this is a reduction in flood levels at Port Office by between 1.2 m
and 0.7 m, for 1893 and 2011. However, 1974 showed an increase in flood peak of 0.1 m at the Port
Office gauge;
Reducing the FSV to 75% and using the 2011 FOM (version 8) shows a decrease of the flood peak
at the Port Office for the three events. However, this will require planned water infrastructure to be
brought forward (3 years for a permanent FSV of 75% and 11 years for a permanent FSV of 50%) at
a significant economic cost;
Two out of three of the flood events modelled showed that alternative operation of the Wivenhoe and
Somerset Dam may have the potential to reduce peak levels at the Port Office gauge. However for
the modelled 1974 event, the early release strategies increased the peak flood level at the Port
Office gauge compared to the 1974 event (including Wivenhoe and Somerset operated as per the
2011 FOM);
However, it has been found by other studies that any early release strategy inadvertently has a
greater impact on the more frequent and moderate flood events including increased flows during
smaller flood events. This requires further detailed modelling in order to fully determine the impacts;
Additionally, previous hydrologic modelling has demonstrated that early release strategies worsen
downstream flood impacts associated with more frequent flood events. Five such events have been
recorded since Wivenhoe Dam was constructed. Accordingly determining an optimum release
strategy will require extensive detailed modelling including a complete re-evaluation of the design
hydrology for the basin. This work is outside the scope of this study;
This outcome confirms the need for the Wivenhoe and Somerset Dam optimisation study
recommended by the Queensland Floods Commission of Inquiry which has already been initiated by
Seqwater (long-term study). This study will allow Brisbane River system, including the Wivenhoe
and Somerset dams as a whole to be fully modelled in detail. GHD understands that although the
catchment areas of Bremer River and Lockyer Creek are not within the scope, their impacts on the
Brisbane River system will be included;
83
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
The cost of raising the dam crest by 2 metres is estimated to be approximately $400 million. This
cost does not include substantial modification to the gates (potentially up to $330 million), potential
upgrades associated with the requirement for Probable Maximum Flood (PMF) or fishways
(potentially greater than $100 million). The cost has been based on this rapid assessment and is
likely to increase during any preliminary design phase;
It is estimated that it would take approximately four years to raise the crest of the dam. However, this
is based on no delays in the design, approvals, consultation and construction of the project;
Based on the three events modelled the flood mitigation benefits were variable for many of the
options investigated across the three flood events. For example, while the options of alternative
operation of the Wivenhoe and Somerset Dam and the 2 metre raise (100% FSV), had minimal
impacts during the 2011 flood event, these same options showed no benefit for the 1974 flood event,
with most benefit realised during the 1893 flood event;
Additional storage on the Bremer and Lockyer Rivers would have a significant impact on Flood levels
a Moggill during the 1974 and 2011 events, reducing damage to low levels. However would have
limited effect on the 1893 event due to the variability in the geographic rainfall patterns. The
identification of suitable storage sites and likely significant costs of such storages may be
problematic; and
After considering the impact a range of structural and non-structural options on flood mitigation, the
largest reductions in flood damage result from improved operational rules. As there are minimal costs
associated with changes to gate operational rules, these options have the greatest Net Present
Value from an economic perspective. However, due to the simplistic hydrologic modelling that was
used, the full effects need to be investigated in more detail before significant changes are made.
Before consideration is given to raising the Dam level or permanently lowering FSV, efforts should be
made to further investigate maximising the available storage in the Dam in conjunction with improved
operational rules.
11.2 Recommendations
Further detailed analysis should be undertaken on options to optimise flood mitigation effects through an
integrated assessment of available storage and potential operational changes to the discharge from
Wivenhoe and Somerset dams including the effects of inflows from other tributaries (Lockyer and Bremer
Rivers).
This would entail, but not limited to:
Further examination and development of damage curves, including identification and survey of
affected private and public property;
Optimisation of the operation of the Wivenhoe and Somerset dams;
Development of decision support tools for the operation of the Wivenhoe and Somerset dams;
Risk based assessment of release strategies, for example over a broad range of rainfall events
against downstream coincidence of peak flows; and
Integration of changes to Wivenhoe and Somerset dams operation as part of a catchment wide flood
management plan, incorporating early warning, land use planning and localised flood prevention
solutions.
84
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
12. References
12.2 Seqwater
Aerial Imagery – South-East Queensland (2009);
Brisbane River Cumec Events (2004 Model results based on 2002 ALS 5 metre Elevated Grid. Model
3 3
run at 2,000 m /s to 8,000 m /s);
Wivenhoe Dam Infrastructure and Utility Locations; and
Bridge Levels with Deck-heights.
23
In consideration of permitting use of this data, there must be acknowledgement and agreement that the Data Custodian gives no
warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accepts no liability
(including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any
use of the data. Data must not be used for marketing or be used in breach of the privacy laws.
85
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
12.4 Brisbane City Council24
Brisbane City Council provided the following data for the purposes of this Study:
flood line – 1974 Pre-Wivenhoe Dam;
Brisbane River Inundation (15 inundation extent profiles corresponding to peak discharge at the Port
Office gauge). This data is based on the Brisbane River Hydraulic Model PMF Final Report. The key
limitations that apply to the data are:
TUFLOW Model primarily calibrated to the 1974 event:
– calibration of the model to the January 2011 Flood Event has not yet been undertaken
– 30 metres of grid used in model and/or model outputs
– survey and bathymetry are from prior to the 2011 event
GIS data used to compute the flood damage to residential and non-residential properties in the
report, ‘Feasibility and Final Report for Brisbane Valley Flood Damage Minimisation Study no 242.
Prepared by Brisbane City Council. BCC009.7972’ – Brisbane City Council (2010).
[12] SKM, January 2011 Flood Event: Report on the operation of Somerset Dam and Wivenhoe Dam,
March 2011
[13] ICA Hydrology Panel, Flooding in the Brisbane River Catchment (January 2011), 20 February 2011
24
As above
86
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
[14] City Design, Brisbane River Flood Study, 1999
[15] Allens Arthur Robinson, Seqwater – Response to Mr Babister’s Report, 1 September 2011 (MGI:
120128021)
87
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Appendix A
Hydrologic Model
Results
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Scenario 0 – Base Case
Scenario 1 – Straight to W2 (100% FSV)
Scenario 2 – Steady Increase to W4 (75% FSV)
Scenario 3 – 2 Metre Raise to W4 & Fuse Plug Levels (75% FSV)
Scenario 4 – 2 Metre Raise to W4 & Fuse Plug Levels (100% FSV)
Scenario 5 – Uncontrolled Flow to 3,500 m3/s (100% FSV)
Scenario 6 – 3500 m3/s – No Failure (100% FSV)
Scenario 6 – 3500 m3/s – Failure (100% FSV)
Note: Failure hydrograph is approximate only, and the peak may be higher than estimated.
Scenario 7 – 1900 m3/s – No Failure (100% FSV)
Scenario 7 – 1900 m3/s – Failure (FSV 100%)
Note: Failure hydrograph is approximate only, and the peak may be higher than estimated.
Scenario 8 – Sep 2011 FOM – (75% FSL)
Scenario 8 – Sep 2011 FOM – (50% FSL)
Appendix B
Economic Analysis - Cost Summary
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
GHD
DRAFT - NOT FOR EXTERNAL USE
Contingency 15% 48.1 30% 306.9 30% 616.6 60% 148.4 60% 491.8 60% 25.2 14.1
Escallation Allowance 0 0 0 0 0 0 0 0 0 0
Total estimate (Direct and Indirect) 368.5 1329.9 2671.8 395.7 1311.4 67.3 37.6
Evaluation Year (starts) 2023 2023 2018 2012 2012 2012 2012
Assumed Capex Expenditure Profile 2 years 4 Years 5 years 4 years 4 years 2 years
Year 1 30% 5% 5% 5% 5% 5% 5%
Year 2 70% 5% 5% 5% 5% 95% 95%
Year 3 25% 15% 45% 45%
Year 4 65% 20% 45% 45%
Year 5 55%
Economic Assumptions
Discount Rate 7%
Eventuation Period Year 0 = 2011 and Year 20 = 2031
Sensitivity parameters:
4% real discount rates
10% real discount rates
20% reduction in benefits
20% increase in benefits
for 75% FSL bring forward desal etc by 6 years as opposed to 3 years
20% increase in capital costs plus 20% reduction in benefits (a pessimistic scenario in effect)
ID Item Description Unit Quantity Rate (2001) Amount (2001) Rate (2011) Amount (2011)
General
Establishment LS 1 10000 $10,000 $300,000 $300,000
Clearing of existing road and services Sq m 35000 5 $175,000 $50 $1,750,000
$0 $0
Excavation $0 $0
Excavation Right Embankment cu m 34000 5 $170,000 $25 $850,000
Excavation Left Embankment cu m 12400 5 $62,000 $25 $310,000
$0 $0
Earthworks $0 $0
Left Embankment $0 $0
Rip Rap cu m 141857 30 $4,255,710 $100 $14,185,700
River Gravel cu m 10800 20 $216,000 $80 $864,000
Clay Core cu m 9600 7 $67,200 $25 $240,000
Sand Filter cu m 4640 30 $139,200 $100 $464,000
Gravel Filter cu m 2640 30 $79,200 $100 $264,000
River Run Fill cu m 68528 20 $1,370,560 $50 $3,426,400
Rolled Sandstone - bulk fill cu m 312213 6 $1,873,278 $25 $7,805,325
$0 $0
Right Embankment $0 $0
Rip Rap cu m 63179 30 $1,895,370 $100 $6,317,900
River Gravel cu m 2400 20 $48,000 $80 $192,000
Clay Core cu m 8800 7 $61,600 $25 $220,000
Semi Pervious Soil cu m 6160 20 $123,200 $25 $154,000
Sand Filter cu m 6160 30 $184,800 $100 $616,000
Gravel Filter cu m 6160 30 $184,800 $100 $616,000
River Run Fill cu m 22872 20 $457,440 $50 $1,143,600
Rolled Sandstone - bulk fill cu m 85815 6 $514,890 $25 $2,145,375
$0 $0
Protection works $0 $0
Wave Wall 0.7 m lineal m 4600 350 $1,610,000 $1,000 $4,600,000
Spillway Riasing
General
Establishment LS 1 10000 $10,000 $300,000 $300,000
Hydraulic Model LS 1 75000 $75,000 $250,000 $250,000
$0 $0
Retaining Walls (92 m type A, 190 m type B 27 m removable panels) $0 $0
$0 $0
Approach Embankment Type A $0 $0
Concrete cu m 286 350 $100,100 $2,500 $715,000
Reinforcing t 75 1200 $90,000 $3,000 $225,000
Excavation cu m 133 20 $2,660 $100 $13,300
$0 $0
Gravity Retaining Wall Type B $0 $0
Concrete cu m 595 350 $208,250 $2,500 $1,487,500
Reinforcing t 76 1200 $91,200 $3,000 $228,000
$0 $0
Retaining Wall around Inlet structure (removable panels) $0 $0
Concrete cu m 9 350 $3,150 $2,500 $22,500
Reinforcing t 3 1200 $3,600 $3,000 $9,000
Removable panels sq m 84 200 $16,800 $1,000 $84,000
$0 $0
Retaining Wall Around Spillway Structure $0 $0
Left Bank Vertical Wall Raise $0 $0
Remove existing road m 130 50 $6,500 $500 $65,000
Excavation cu m 1911 15 $28,665 $25 $47,775
Concrete cu m 1100 400 $440,000 $2,500 $2,750,000
Cut off Trench cu m 86 350 $30,100 $5,000 $430,000
Reinforcement t 160 1200 $192,000 $3,000 $480,000
Compacted Select Backfill cu m 1458 15 $21,870 $35 $51,030
$0 $0
Right Bank Vertical Wall Raise $0 $0
Left Bank Vertical Wall Raise $0 $0
Remove existing road m 100 50 $5,000 $500 $50,000
Excavation cu m 3600 15 $54,000 $25 $90,000
Concrete cu m 1050 400 $420,000 $2,500 $2,625,000
Cut off Trench cu m 72 350 $25,200 $5,000 $360,000
Reinforcement t 157 1200 $188,400 $3,000 $471,000
Sand Filter cu m 420 30 $12,600 $100 $42,000
Compacted Select Backfill cu m 2622 15 $39,330 $35 $91,770
$0 $0
Spillway Strengthening (done Wivenhoe Alliance 2003-5) $0 $0
$0 $0
Deflector Wall Modifications (assumes extend wall or new wall and gates OK) $0 $0
Modify / extend existing deflector baffle LS 1 $0 $5,000,000 $5,000,000
$0 $0
Existing Fuse Plug Modifications (raise by 2m) $0 $0
Concrete Training Walls cu m 254 $0 $2,500 $635,000
Bulk Fill cu m 8032 $0 $35 $281,120
Clay Core cu m 722 $0 $25 $18,050
Wivenhoe Dam - Dam Raising to RL 82.1 with Downstream Raise and 0.7 m Wave Wall
Items from GHD 2001
Ref "Engineering Feasibility Study into Augmentation of the Flood Passing Capacity of Wivenhoe Dam" , GHD February 2001
ID Item Description Unit Quantity Rate (2001) Amount (2001) Rate (2011) Amount (2011)
Filter Zones cu m 459 $0 $100 $45,900
Rip Rap cu m 8032 $0 $100 $803,200
$0 $0
$0 $0
Access Tracks / Bulkhead Doors $0 $0
Track to service bridge LHS each 1 30000 $30,000 $100,000 $100,000
Track to service bridge RHS each 1 30000 $30,000 $100,000 $100,000
Sliding Bulkhead for 3t gantry each 1 50000 $50,000 $100,000 $100,000
$0 $0
Left Bank Control Building and Misc $0 $0
Bulkhead Door each 1 10000 $10,000 $30,000 $30,000
Reinforce Viewing Window each 1 1000 $1,000 $5,000 $5,000
Electrical cable portal each 2 500 $1,000 $2,000 $4,000
Winch cable portal each 1 63750 $63,750 $200,000 $200,000
Water quality bulkhead winch motors (3hp) each 6 6000 $36,000 $10,000 $60,000
Water sampling pumps each 11 500 $5,500 $3,000 $33,000
3t gantry crane wheel motors each 4 2000 $8,000 $10,000 $40,000
Relocate Flood Alert Systems each 2 300 $600 $10,000 $20,000
Radial Gates Securing Mechanism each 5 5000 $25,000 $25,000 $125,000
General
Establishment LS 1 10000 $10,000 $75,000 $75,000
$0 $0
Earthworks $0 $0
Excavation OTR cu m 2760 2.5 $6,900 $15 $41,400
Excavation Rippable Rock cu m 2300 10 $23,000 $50 $115,000
Rip Rap cu m 1274 30 $38,220 $100 $127,400
Transition Zone cu m 978 15 $14,670 $75 $73,350
Miscellaneous Fill cu m 16208 6 $97,248 $25 $405,200
Wivenhoe Dam - Dam Raising to RL 82.1 with Downstream Raise and 0.7 m Wave Wall
Items from GHD 2001
Ref "Engineering Feasibility Study into Augmentation of the Flood Passing Capacity of Wivenhoe Dam" , GHD February 2001
ID Item Description Unit Quantity Rate (2001) Amount (2001) Rate (2011) Amount (2011)
$0 $0
Protection Works $0 $0
Roadbase on crest (300 thick) sq m 920 12.6 $11,592 $100 $92,000
Hydromulch sq m 5750 1.5 $8,625 $10 $57,500
General
Establishment LS 1 10000 $10,000 $75,000 $75,000
$0 $0
Earthworks $0 $0
Excavation OTR cu m 3000 2.5 $7,500 $15 $45,000
Excavation Rippable Rock cu m 2500 10 $25,000 $50 $125,000
Rip Rap cu m 3966 30 $118,980 $100 $396,600
Transition Zone cu m 3208 15 $48,120 $75 $240,600
Miscellaneous Fill cu m 46074 6 $276,444 $25 $1,151,850
Clay Core cu m 5074 7 $35,518 $25 $126,850
$0 $0
Protection Works $0 $0
Roadbase on crest (300 thick) sq m 1000 12.6 $12,600 $100 $100,000
Hydromulch sq m 6250 1.5 $9,375 $10 $62,500
General
Establishment LS 1 10000 $10,000 $75,000 $75,000
$0 $0
Earthworks $0 $0
Excavation OTR cu m 2988 2.5 $7,470 $15 $44,820
Excavation Rippable Rock cu m 4980 10 $49,800 $50 $249,000
Rip Rap cu m 2475 30 $74,250 $100 $247,500
Transition Zone cu m 2520 15 $37,800 $75 $189,000
Miscellaneous Fill cu m 7983 6 $47,898 $25 $199,575
$0 $0
Protection Works $0 $0
Roadbase on crest (300 thick) sq m 2400 12.6 $30,240 $100 $240,000
Hydromulch sq m 3984 1.5 $5,976 $10 $39,840
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
Base Summary
Peak Flow Rate at Port Office reduction in % reduction in Probable damage of Probable damage
PV Costs PV Benefits NPV ($) BCR
(m3/s) AADs ($ m) AADs event relative to Jan 2011
Year 2011 Flood ($ m) ($ m) $ $
Base Case Sep 2011 FOM 100% FSL 9100 50 26% 2,782 110 - 579,483,505 579,483,505
Straight to W2 100% FSL 7600 109 57% 1,610 - 1,063 63,429,584 1,268,233,552 1,204,803,969 19.99
Sep 2011 FOM 100% FSL 9100 50 26% 2,782 110 - 579,483,505 579,483,505
Uncontrolled Flow to 3,500 m3/s 100% FSL 7600 109 57% 1,610 - 1,063 63,429,584 1,268,233,552 1,204,803,969 19.99
Restrict Release Rate to 1,900 m3/s 50% FSL 6700 144 75% 929 - 1,743 2,147,871,555 1,668,029,565 - 479,841,990 0.78
Restrict Release Rate to 3,500 m3/s 50% FSL 7500 113 59% 1,530 - 1,142 2,084,441,971 1,315,113,361 - 769,328,609 0.63
Sep 2011 FOM 50% FSL 7700 105 55% 1,690 - 983 2,084,441,971 1,221,353,743 - 863,088,227 0.59
Steady Increase to W4 75% FSL 7600 109 57% 1,610 - 1,063 337,802,083 1,268,233,552 930,431,469 3.75
Restrict Release Rate to 3,500 m3/s 75% FSL 7600 109 57% 1,610 - 1,063 337,802,083 1,268,233,552 930,431,469 3.75
Sep 2011 FOM 75% FSL 8500 74 39% 2,301 - 372 337,802,083 862,292,439 524,490,356 2.55
2 Metre Raise to W4 & Fuse Plug Levels 100% FSL 8500 74 39% 2,301 - 372 245,116,642 535,998,283 290,881,641 2.19
2 Metre Raise to W4 & Fuse Plug Levels 75% FSL 7600 109 57% 1,610 - 1,063 582,918,725 1,268,233,552 685,314,828 2.18
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
INFORMATION MATERIAL ONLY
20 October 2011
Version 4
i
QWC INFORMATION MATERIAL ONLY
Document Control
This document has been prepared with all due diligence and care, based on the best available
information at the time of publication. The agency holds no responsibility for any errors or omissions
within this document. Any decisions made by other parties based on this document are solely the
responsibility of those parties. Information contained in this document is from a number of sources and,
as such, does not necessarily represent government or agency policy.
D/11/050389 ii
QWC INFORMATION MATERIAL ONLY
Table of Contents
1 PURPOSE ........................................................................................................................2
2 METHODOLOGY...........................................................................................................3
2.3 LevelofService(LOS)ObjectivesandLOSYield....................................................................8
3 RESULTS ...................................................................................................................... 10
4 CONCLUSIONS............................................................................................................ 14
APPENDIXA:GRID12STORAGESINSOUTHEASTQUEENSLAND .................. 15
D/11/050389 iii
QWC INFORMATION MATERIAL ONLY
Abbreviations
ML megalitres
2010 Price Path Bulk water price review in November 2010 (residential
Review consumption increasing from 180 L/p/d in 2011 to 200
l/p/d by 2018)
2010 SEQ Water Infrastructure as per 15 July 2010 SEQ Water Strategy
Strategy including Tugun desalination, Purified Recycled Water,
Infrastructure Southern Regional Water Pipeline, Eastern Pipeline
Interconnector, Northern Pipeline Interconnector (65
ML/d northerly flow), Cedar Grove Weir and Bromelton
Offstream Storage.
D/11/050389 iv
Executive Summary
The purpose of this report is to provide information on the potential impacts on the security
of supply in South East Queensland (SEQ) of permanent reductions of the Full Supply
Volume (FSV) of Wivenhoe Dam. This modelling assessment is solely to assist the Rapid
Assessment of the Wivenhoe Dam Wall Raising Project.
The underlying assumptions used include the demand and supply capacity contained in
the SEQ Water Strategy, with demand forecasts updated to align with the recent base
case in the 2011 Annual Review of the South East Queensland Water Strategy.
Nine scenarios of permanent reduction of Wivenhoe Dam by 25% and 50% of FSV with
the recent commissioning of Hinze Dam raising and the proposed Wyaralong Water
Treatment Plant (WTP) have been considered. Further investigation would be required to
understand the full extent of the impacts. This assessment is based on sensitivity analysis
of the total grid capacity and no detailed assessment has been undertaken at the bulk
distribution level.
x Permanent reduction in the full supply volume of 25% will lower the Level of Service
(LOS) yield by about 30,000 ML/a and a 50% reduction would lower it by about 95,000
ML/a.
x The reduction in LOS yield may require the construction of new infrastructure to be
brought forward by about 4 years (to about 2026 from 2030) for the 25% FSV
reduction based on a forecast demand (Base Case of 200 l/p/d residential and 130
l/p/d non-residential). It should be noted that demand is sensitive to weather conditions
and has been tracking below the Water Strategy target of 200 l/p/d residential, which
could reflect the recent wet climatic conditions.
x The reduction in LOS yield may require the construction of new infrastructure to be
brought forward by about 12 years (to about 2018 from 2030) for a 50% FSV reduction
based on forecast demand (Base Case of 200 l/p/d residential and 130 l/p/d non-
residential).
x The commissioning of the raised Hinze Dam increases the LOS yield by 15,000 ML/a,
20,000 ML/a and 25,000 ML/a for Wivenhoe Dam at 100%, 75% and 50% FSV
respectively.
x The proposed Wyaralong WTP Stage 2 (74 ML/d) provides an additional 5,000 to
20,000 ML/a of LOS Yield after Hinze Dam Raising.
Wivenhoe Dam system contributes about 50% of the LOS yield of SEQ. Hence any major
reduction in FSV would need to be carefully considered.
This report does not recommend a particular scenario for adoption as other factors such
as social, economic and environmental may also need to be considered. It provides the
long term water demand/supply balance in the SEQ Water Strategy.
Advice from the responsible agency or entity on operational and regulatory impacts such
as increased pumping costs and the Water Resource Plan would have to be considered.
1
QWC INFORMATION MATERIAL ONLY
1 Purpose
The purpose of this report is to provide information on the potential impacts on the security
of supply in South East Queensland (SEQ) of permanent reductions of the Full Supply
Volume (FSV) of Wivenhoe Dam. This modelling was done to support the Rapid
Assessment of the Wivenhoe Dam Raising Project being managed by the Department of
Employment, Economic Development and Innovation.
This report outlines the results of the assessment, from a water supply security
perspective for South East Queensland (SEQ) of the effects of lowering the FSV of
Wivenhoe Dam to either 75% or 50% of its FSV on the LOS yield and the long term supply
demand balance of South East Queensland.
This assessment does not consider the environmental, social and economic impacts of the
dam operating levels in relation to flood mitigation for downstream properties and
infrastructure. Furthermore the potential impacts of climate change on the supply and
demand are not assessed given the short timeframe available for the study.
This modelling assessment was requested by GHD, the Project’s consultants. This
assessment is provided solely for the purpose of assisting the Rapid Assessment of the
Wivenhoe Dam wall raising Project. The report including the input data, methodology,
assessment, results, observations and the conclusions are not to be used for any other
project or purpose and are not to be used in any report without QWC’s prior review and
approval.
D/11/050389 2
QWC INFORMATION MATERIAL ONLY
2 Methodology
The methodology used for the assessments is described in this section. To assess the
long term impacts of the permanent lowering of the full supply volume of Wivenhoe Dam,
an assessment framework which was developed previously for similar investigations was
adopted.
The LOS yield assessments were carried out in the following sequence of infrastructure
assumptions:
x 2010 Infrastructure;
x 2010 Infrastructure with the commissioning of Hinze Dam Raising and the
proposed Wyaralong Water Treatment Plant Stage 2 (74 ML/d).
Hinze Dam Raising (commissioned in July 2011) has provided an additional 149, 656 ML
storage, bringing the FSV to 310, 727 ML.
The Wyaralong WTP capacity was based on a proposed allocation of about 27,000 ML/a
(74 ML/d).
For consistency with the 2010 SEQ Water Strategy, the existing volume is maintained in
the model for the 40% trigger of Grid 12 storage.
D/11/050389 3
QWC INFORMATION MATERIAL ONLY
Table 2 lists the assumptions used, the reasons for the options selected and the section
reference for the results for the modelling scenario.
D/11/050389 4
Table 2: Summary of assessment framework showing details of each LOS assessment scenario
Model
WATHNET
5
QWC INFORMATION MATERIAL ONLY
WATHNET
D/11/050389 6
QWC INFORMATION MATERIAL ONLY
D/11/050389 7
2.3 Level of Service (LOS) Objectives and LOS Yield
The Regional Water Security Program for SEQ (under the Water Act 2000) establishes the
desired LOS objectives which form a basis for the SEQ Water Strategy and are
implemented through the SEQ System Operating Plan. These objectives provide long
term security of water supply and are defined as follows:
x During normal operating mode, sufficient water will be available from the SEQ Water
Grid to meet an average regional urban demand of 375 litres per person per day
(including residential, non-residential and system losses).
o Medium Level Restrictions will not occur more than once every 25 years, on
average
o Medium Level Restrictions will only reduce consumption by 15 per cent below
the total consumption volume in normal operating mode
o Regional water storages do not reach 5 per cent of combined storage capacity
o Wivenhoe, Hinze and Baroon Pocket dams do not reach minimum operating
levels
o It is expected that Medium Level Restrictions will last longer than six months,
no more than once every 50 years on average.
The Level of Service Yield is the maximum demand that can be supplied, for given
infrastructure and operating conditions, while still meeting the LOS objectives. It is a
modelled maximum supply.
The LOS yields for the cases of 25% and 50% lowering of the FSV of Wivenhoe Dam
permanently were assessed using the same infrastructure and operating conditions as
those for the July 2010 SEQ Water Strategy LOS yield of 485,000 ML/annum.
This modelling assumed the Demography and Planning (formerly known as the Planning
Information and Forecasting Unit, PIFU) medium series population growth (May 2011
edition) and that demand would increase over five years, from the actual consumption
levels for 2010/2011 to 200 l/p/d for residential and 130 l/p/d non-residential (including
power stations and losses).
8
QWC INFORMATION MATERIAL ONLY
D/11/050389 9
3 Results
3.1 LOS yields
Table 3 presents the model results for LOS yield for scenarios of permanent reduction in
the FSV of Wivenhoe Dam.
The SEQ Water Strategy LOS yield for no reduction of FSV of Wivenhoe Dam is 485,000
ML/a.
For a reduction in the FSV of Wivenhoe Dam by 25% the LOS yield is 455,000 ML/a which
is a decrease in the LOS yield of 30,000 ML/a.
For a reduction in the FSV by 50% the LOS yield is 390,000 ML/a which is a decrease of
95,000 ML/a. This is more than three times the reduction in LOS yield for a 25% reduction.
The commissioning of the raised Hinze Dam increases the LOS yield by:
x 15,000 ML/a for Wivenhoe Dam at 100% FSV (Scenarios 1.1.1 and 2.1.1);
x 20,000 ML/a for Wivenhoe Dam at 75% FSV (Scenarios 1.1.2 and 2.1.2) and;
x 25,000 ML/a for Wivenhoe Dam at 50% FSV (Scenarios 1.1.3 and 2.1.3).
The increase in LOS yield is greater as the FSV of Wivenhoe Dam decreases. This is
likely to be due to Hinze Dam Raising improving the 40% trigger level statistics which
contributes to a higher LOS yield. However the LOS yield increase due to the raising
becomes limited as shown in Scenario 2.1.2 and 2.1.3 (Table 3).
A similar effect is seen when Wyaralong Dam WTP is included in the model.There is an
increase in LOS yield of only 5,000 ML/a when Wivenhoe Dam is at 100% of its FSV but
an increase of 20,000 ML/a for the 75% and 50% FSV (Scenarios 3.1.2 and 3.1.3 in Table
3).
10
QWC INFORMATION MATERIAL ONLY
Figure 1 shows that new infrastructure would need to be brought forward by about 4 years
to about 2026 from 2030 for a 75% FSV. For 50% FSV, new infrastructure would be
brought forward by about 12 years to 2018 from 2030.
As a comparison, Figure 2 shows the long term water supply demand balance with the
LOS yields for Wivenhoe at 100%, 75% and 50% of FSV – with Hinze Dam raising
included.
Figure 2 shows that new infrastructure would need to be brought forward by about 3 years
to about 2028 from 2031 for a 75% FSV. For 50% FSV, new infrastructure would be
brought forward by about 11 years to 2020 from 2031.
D/11/050389 11
QWC INFORMATION MATERIAL ONLY
Figure 1: Long term water supply demand balance (with 2010 Infrastructure and
base case demand)
Scenario Wivenhoe %
900,000 of FSV
1.1.1 100%
800,000 1.1.2 75%
1.1.3 50
700,000
600,000
500,000
400,000
300,000
200,000
100,000
0
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Year
Figure 2: Long term water supply demand balance (with 2010 Infrastructure plus
Hinze Dam raising and base case demand)
900,000
Scenario Wivenhoe %
of FSV
2.1.1 100%
800,000 2.1.2 75%
2.1.3 50%
700,000
600,000
500,000
400,000
300,000
200,000
100,000
0
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Year
D/11/050389 12
QWC INFORMATION MATERIAL ONLY
D/11/050389 13
QWC INFORMATION MATERIAL ONLY
4 Conclusions
The following observations can be drawn from this assessment exercise:
x Permanent reduction in the full supply volume of 25% will lower the Level of Service
(LOS) yield by about 30,000 ML/a and a 50% reduction would lower it by about 95,000
ML/a.
x The reduction in LOS yield may require the construction of new infrastructure to be
brought forward by about 4 years (to about 2026 from 2030) for the 25% FSV
reduction based on a forecast demand (Base Case of 200 l/p/d residential and 130
l/p/d non-residential). It should be noted that demand is sensitive to weather conditions
and has been tracking below the Water Strategy target of 200 l/p/d residential, which
could reflect the recent wet climatic conditions.
x The reduction in LOS yield may require the construction of new infrastructure to be
brought forward by about 12 years (to about 2018 from 2030) for a 50% FSV reduction
based on forecast demand (Base Case of 200 l/p/d residential and 130 l/p/d non-
residential).
x The commissioning of the raised Hinze Dam increases the LOS yield by 15,000 ML/a,
20,000 ML/a and 25,000 ML/a for Wivenhoe Dam at 100%, 75% and 50% FSV
respectively.
x The proposed Wyaralong WTP Stage 2 (74 ML/d) provides an additional 5,000 to
20,000 ML/a of LOS Yield after Hinze Dam Raising.
Wivenhoe Dam system contributes about 50% of the LOS yield of SEQ. Hence any major
reduction in FSV would need to be carefully considered.
This report does not recommend a particular scenario for adoption as other factors such
as social, economic and environmental may also need to be considered. It provides the
long term water demand/supply balance in SEQ.
Advice from the responsible agency or entity on operational and regulatory impacts such
as increased pumping costs and the Water Resource Plan would have to be considered.
It is therefore considered that permanent reduction of Wivenhoe Dam FSV by 25% and
50% would potentially have significant impacts including:
x Impacts on the security of supply due to a reduction in LOS yield, particularly in the
severe case of a 50% reduction;
x New infrastructure may need to be brought forward about 4 years to meet the LOS
objectives for a 25% reduction and by about 14 years for a 50% reduction;
x Cost impact of bringing forward the next supply augmentation;
x Increased likelihood of triggering desalination and/or PRW;
x Impact on the future bulk water pricing and long term SEQ debt, including an
increase in operational costs, for a 25% and particularly the 50% permanent
reduction scenario; and
x Increased likelihood and extent of water restrictions, particularly in the case of the
50% reduction.
D/11/050389 14
QWC INFORMATION MATERIAL ONLY
(Megalitres)
Southern
Hinze* 161,073
Central
Somerset 379,849
Wivenhoe 1,165,238
Northern
Cooloolabin 13,800
Wappa 4,694
* Based on 2010 SEQ Water Strategy Infrastructure. With Hinze Dam Raising commissioned in July 2011, the
Full Supply Volume is 310,727 ML.
D/11/050389 15
Appendix E
Maps
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam
ay
hw
ig
H
et t
B u rn
D'A
Bru
g
ui
ce
la
y
wa
rH
H ig
i gh
ig
H wa
h
ya
h w ay
Bun y
w ay
i l a r Hi gh
BR
IS
D 'A g u
BA
CALOUNDRA
N E
R IV
ER
YARRAMAN
ay
w
D
ig h
ay 'A g
w ui
eH
gh la r H
Hi i g hway D 'Aguilar H igh w
nd
Bru c
K a y
g la EE
En
R
CR
ew KILCOY
E
V
RI
R
WOODFORD
N
Y S TA N L E Y
CO
O SOMERSET
EEK
R REGIONAL
Stanley River
C
U
COUNCIL
EM
Somerset
Dam
Ne
wE
Brisbane River TOOGOOLAWAH MORETON
BAY
ng
EK
la
RE
nd
REGIONAL
C
Hi
OK
gh
COUNCIL
w
B RO
ay
NARANGBA
SS
RE
ESK
C
CROWS NEST
Cressbrook Wivenhoe
Creek Dam
Perseverance Dam
Dam
y
wa Splityard
i gh COOMINYA Creek Dam MOUNT NEBO
H
d
an
R
gl
HAMILTON IV E
En
Atkinson's
W
FERNVALE ER
AN
w
Dam
ar
Enoggera ISB
Ne
go
re
Hi HY S CREE K Dam BR
g hw M U RP Lake
ay Manchester Gold Ck
Dam BRISBANE
Dam
LO
C
KY GATTON MOGGIL ROCKLEA
E R C RE
TOOWOOMBA
EK
GRANTHAM BRISBANE
IPSWICH CITY
Pa
ROSEWOOD
ay COUNCIL
ci f
hw
ic
M
Lockyer Creek ot
g
ER
Hi
e IV
or
or R
IPSWICH SPRINGFIELD
wa
G ER wa
y
y
h
EM
CITY
Hig
LOCKYER
BR
Pa
COUNCIL
g ham
c if
VALLEY
ic
Mo
REGIONAL LOGAN
nnin
to r
CITY
wa
Cu
COUNCIL HARRISVILLE
y
COUNCIL
Bremer River
SCENIC KALBAR
RIM BEAUDESERT
REGIONAL
COUNCIL
Ne
Moogerah
w
ng g h a m H ig h w ay
E
ni n Dam
Cun
la
n d
Hi
gh
wa
y
C u n ni n g
h am H i ghw a y
LEGEND
Town Dam or Lake Based on or contains data provided by the State of QLD (DERM) [2011].
In consideration of the State permitting use of this data you acknowledge
Highway Catchment Boundary and agree that the State gives no warranty in relation to the data
(including accuracy, reliability, completeness, currency or suitability)
Major Watercourse and accepts no liability (including without limitation, liability in
negligence) for any loss, damage or costs (including consequential damage)
Minor Watercourse relating to any use of the data. Data must not be used for marketing
or be used in breach of the privacy laws.
o
Paper Size A4 Job Number 41-24452
Department of Employment,
0 5 10 15 20 25 Revision 0
Economic Development and Innovation
Date 13 Nov 2011
Kilometres
Map Projection: Transverse Mercator
Horizontal Datum: GDA 1994
Grid: GDA 1994 MGA Zone 56 Project Locality Figure 1
G:\41\24452\GIS\Maps\Deliverables\4124452_100_A4.mxd Level 4, 201 Charlotte St Brisbane QLD 4000 Australia T 61 7 3316 3000 F 61 7 3316 3333 E bnemail@ghd.com W www.ghd.com
© 2011. Whilst every care has been taken to prepare this map, GHD and DATA CUSTODIANS make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose
and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be
incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Data source: DERM - Catchment Boundary, Local Government Area, Waterways, Roads, Dams; Geoscience Australia - 250k Topo Data. Created by: TH
Brisbane River 282.4 km (upper Brisbane at Linville)
R
K
E
E V
CR RI
R EY
YA S TA N L
O Emu Ck 10.7 km (upper Brisbane)
CO
R EEK
C
Stanley River
U
EM
Brisbane River
EK
E
CR
OK
RO
SB
E S
CR
K
R EE
Y ER C B RISB A NE
CK
LO RI
VE
R
K
EE
CR
ER
Lockyer Creek RIV L
IL
ER
RR
Ma Ma Ck 21.2 km EM
WA
BR
LEGEND
Town Wivenhoe Dam Based on or contains data provided by the State of QLD (DERM) [2011].
In consideration of the State permitting use of this data you acknowledge
Detention Basins Catchment Boundary and agree that the State gives no warranty in relation to the data
(including accuracy, reliability, completeness, currency or suitability)
Major Watercourse and accepts no liability (including without limitation, liability in
negligence) for any loss, damage or costs (including consequential damage)
Minor Watercourse relating to any use of the data. Data must not be used for marketing
or be used in breach of the privacy laws.
o
Paper Size A4 Job Number 41-24452
Department of Employment,
0 5 10 15 20 25 Revision 0
Economic Development and Innovation
Date 10 Nov 2011
Kilometres
Map Projection: Transverse Mercator
Horizontal Datum: GDA 1994
Grid: GDA 1994 MGA Zone 56 Detention Basin Overview
Level 4, 201 Charlotte St Brisbane QLD 4000 Australia T 61 7 3316 3000 F 61 7 3316 3333 E bnemail@ghd.com W www.ghd.com
G:\41\24452\GIS\Maps\Deliverables\4124452_101_A4.mxd
© 2011. Whilst every care has been taken to prepare this map, GHD and DATA CUSTODIANS make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose
and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be
incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Data source: DERM - Catchment Boundary; Geoscience Australia - 250k Topo Data; Seqwater - Wivenhoe Dam. Created by: TH
Beam Creek f
! MORETON
Somerset BAY
Dam
REGIONAL
Stanley River
TOOGOOLAWAH COUNCIL
Catchment
f
! Cressbrook
f
!
Waterfall
Creek Gully
f
!
Stanley
M
ou
Gully
nt
Be
f
!
Siverton
pp Creek
o
Ro O'Sheas Haslingdens
f
!
ad
f
! Bridge Bridge
f
!
oa d
k - Ki lc oy R
Brisbane River Es
Bris
Reedy
ba n
Catchment Creek
e Va
f
!
lley
Meirs
H ig
Gully
hway
f
! Coal Creek
f
! Gallanani
Creek
SOMERSET
f
! A. & P.M.
Conroy
Bridge
REGIONAL
COUNCIL f
!
ESK
Esk Creek
f
! Middle
Creek
f
!
d Bri sban MORETON
oa e Va
p to n R l ley Deep Creek
- H am Hi BAY
Es k gh
Wi
wa REGIONAL
ve
y
nh
COUNCIL
oe
So
-
f
!
m
Tea Tree er
se
Creek t R
oa
Northbrook
f
!
d
Creek
Five Mile
Creek f
! N o rthb
roo k P a rkw ay
Wivenhoe
Tea tree
Gully f
! Dam
f
! Kipper
Creek
d
Ro a
f
!
Logan
BRISBANE
k
Creek
n - Es
CITY
COUNCIL
t to
Ga
Splityard
Bris Creek Dam
b an
e
Va
l le y
COOMINYA High
way
Lockyer Creek
Wes t R
oa d
Catchment
Atkin s o
ns
Da
m
Ro
LOCKYER ad m
o n D a R oa d
ns
VALLEY ki
At
f
!
REGIONAL Atkinson's Fernvale
Dam C lare n d o bridge
nR
COUNCIL oa
d
f
!
LEGEND
Town Highway Catchment Boundary Based on or contains data provided by the State of QLD (DERM) [2011].
f
! Bridge Main Road Dam or Lake
In consideration of the State permitting use of this data you acknowledge
and agree that the State gives no warranty in relation to the data
(including accuracy, reliability, completeness, currency or suitability)
Major Watercourse Local Road Wivenhoe Dam Water Level at 77m (AHD) and accepts no liability (including without limitation, liability in
negligence) for any loss, damage or costs (including consequential damage)
Minor Watercourse LGA Boundary relating to any use of the data. Data must not be used for marketing
or be used in breach of the privacy laws.
o
1:200,000 (at A4) Job Number 41-24452
Department of Employment,
0 1 2 3 4 5 Revision 0
Economic Development and Innovation
Date 13 Nov 2011
Kilometres
Map Projection: Transverse Mercator
Horizontal Datum: GDA 1994
Grid: GDA 1994 MGA Zone 56 Wivenhoe Dam Locality
G:\41\24452\GIS\Maps\Deliverables\4124452_106_A4.mxd Level 4, 201 Charlotte St Brisbane QLD 4000 Australia T 61 7 3316 3000 F 61 7 3316 3333 E bnemail@ghd.com W www.ghd.com
© 2011. Whilst every care has been taken to prepare this map, GHD and DATA CUSTODIANS make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose
and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be
incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Data source: GHD - Dam Level at 77m; DERM - Catchment Boundary, Road, Watercourse; Geoscience Australia - 250k Topo Data; Seqwater - Wivenhoe Dam, Bridge Locations. Created by: TH
Based on or contains data provided by the State of QLD (DERM) [2011].
In consideration of the State permitting use of this data you acknowledge
and agree that the State gives no warranty in relation to the data
(including accuracy, reliability, completeness, currency or suitability)
and accepts no liability (including without limitation, liability in
negligence) for any loss, damage or costs (including consequential damage)
relating to any use of the data. Data must not be used for marketing
or be used in breach of the privacy laws.
Somerset
Dam
TOOGOOLAWAH
M
ou
nt
Be
pp
o
Ro
ad ad
o y Ro
k - Kilc
Es
Bris
ba n
eValle
y
H ig
hwa
y
ESK
W iv
e nh
Bri sban
oa d
oe -
e Va l
p to n R l ey
- Ham Hi
So
Esk gh
me
wa
y
rs
et
Ro
d
a
ay
k P a r kw
oo N o rthb
h br rook P a r k w ay
t
or
Wivenhoe
Dam
ad
k Ro
n - Es
tto
Ga
Splityard
Bris Creek Dam
ban
e
Va
l l ey
COOMINYA High
w ay
Wes t R
oad
A tk ins
on
sD
am
Ro
ad a m Ro a
s on D d
k in
At
Atkinson's
Dam C larend o
nR
oa
d
LEGEND
Town Major Watercourse Dam or Lake Endangered RE - Dominant
House Minor Watercourse Wivenhoe Dam Water Level at 77m (AHD) Endangered RE - Sub-dominant
House - unaffected Highway Nature Refuge Of Concern RE - Dominant
Infrastructure - Power Main Road Protected Areas Of Concern RE - Sub-dominant
Infrastructure Local Road Remnant Vegetation that is a Least Concern RE
o
1:200,000 (at A4) Job Number 41-24452
Department of Employment,
0 1 2 3 4 5 Revision 0
Economic Development and Innovation
Date 17 Nov 2011
Kilometres
Map Projection: Transverse Mercator
Horizontal Datum: GDA 1994
Grid: GDA 1994 MGA Zone 56 Wivenhoe Dam Locality
G:\41\24452\GIS\Maps\Deliverables\4124452_107_A4.mxd Level 4, 201 Charlotte St Brisbane QLD 4000 Australia T 61 7 3316 3000 F 61 7 3316 3333 E bnemail@ghd.com W www.ghd.com
© 2011. Whilst every care has been taken to prepare this map, GHD and DATA CUSTODIANS make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose
and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be
incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Data source: GHD - Dam Level at 77m; DERM - Catchment Boundary, Road, Watercourse; Geoscience Australia - 250k Topo Data; Seqwater - Wivenhoe Dam, Bridge Locations. Created by: TH
f
! Coal Creek Road/Region Map ID Site Description AADT %CV
Warrego Hwy 1 Wim Site Bremer River 40240 12.08
f
! Gallanani
Creek
2 West of Kholo Road overpass
3 1 km West of Brisbane Valley Hwy
34158
24490
16.53
17.35
f
! A. & P.M.
Conroy
Bridge
Brisbane Valley
4 West of Seminary Road
5 Bris. Valley Hwy North of Lovers Lane
23830
8580
~~~~
10.5
f
!
ESK Hwy 6 Sandy Creek (North Branch) 7600 11
m
n!
f
Middle
Creek 7 Rd 412 Forest Hill - Ferny Road 2900 16
"
)9
Esk Creek
f
!
B risban 8 Rd 411 Coominya Connection Road 2800 16
eV
al l Deep Creek 9 Rd 414 Esk - Hampton Road 4100 14
ey
Hi Wivenhoe-
gh 10 Brisbane Valley Highway Junction 500 6
ay Somerset Rd
w
11 Mount Glorious Road 500 6
f
! Tea Tree
Creek
Mount Crosby 12 Colleges Crossing
Source: ht t p:/ / 131940.qld.gov.au/ Traf f ic-Census.aspx; 2009 Nort h Coast Region Traf f ic Census; 2009 Met ropolit an Traf f ic Census
9539 4.18
ad
f
!
Ro
Northbrook
f
!
sk
m
n
Creek
n
o
a tt
"
)
G
11
M
Wivenhoe
!
f f
!
ou
Kipper
nt
Tea tree Dam Gl
Creek or
Gully io
us
f
!
Ro a
Logan
Creek
d
m
n
Brisbane River Splityard
Mo
un
"
Creek Dam
) Catchment
tN
Mo un t Glo r o u s R o a d
8 bo i
e
Bris Ro
b an ad
COOMINYA e Va
l l ey H
Wes t R ig h MOUNT NEBO
oa d wa
y
d
m
n
a
t io n R o
"
) 10
Con n ec
f
!
Atkinson's Fernvale
Dam bridge
Twin
f
! f
!
i n ya
m
n
C la r e
n d o n R oa d Bridges Savages
om
"
)
Crossing
Co
M
ou
nt T 7
a r am FERNVALE
pa Ro a
d LOWOOD
ad
t H ill - Fernv a le R o
r es
Fo
Lake
d
le R o a
Manchester
Dam
d
Lockyer Creek
Fe rn va
f
!
oa
R
Burtons La k e
M a n ch e
Catchment
le
Bridge st e
va
rR
R oad o ad
er n
o ad
tv iew
H ill - F
gh
nR
n
m
ri
B
inde
ad
"
)
r es t
-M
Ro
6
ad
f
!
Fo
m
n
Ro
rg
od
u Mt Crosby
ar b
Lo w o
K h ol o
"
)
Weir
5
m
n
Geh rke R oa d
f
! Colleges
"
)
W
f
!
ar
12 Crossing
m
n
re g
o Hig hw ay Kholo
ad
Bridge
"
)
Ro
4
m
n m
n
ur g
"
) m
n
a rb
3
"
) "
)
-M
2
Ta 1
d
lle
oo
g a ll a
ew
Ro
ad
os
R
Bremer River Ro
ad
ay
o ad e
o dR an
hw
wo Catchment IPSWICH B r is b
os e
H ig
-R
a b in
Karr
am
Rob er ts
ROSEWOOD on R oa gh
d in
nn
Cu
LEGEND
m
n
"
) Traffic Count Location
Major Watercourse LGA Boundary Based on or contains data provided by the State of QLD (DERM) [2011].
In consideration of the State permitting use of this data you acknowledge
Minor Watercourse Catchment Boundary and agree that the State gives no warranty in relation to the data
Town (including accuracy, reliability, completeness, currency or suitability)
f
!
Highway Dam or Lake and accepts no liability (including without limitation, liability in
Bridge Main Road negligence) for any loss, damage or costs (including consequential damage)
relating to any use of the data. Data must not be used for marketing
Local Road or be used in breach of the privacy laws.
o
1:225,000 (at A4) Job Number 41-24452
Department of Employment,
0 1 2 3 4 5 Revision 0
Economic Development and Innovation
Date 13 Nov 2011
Kilometres
Map Projection: Transverse Mercator
Horizontal Datum: GDA 1994
Grid: GDA 1994 MGA Zone 56 Traffic Count Data
G:\41\24452\GIS\Maps\Deliverables\4124452_110_A4mxd.mxd Level 4, 201 Charlotte St Brisbane QLD 4000 Australia T 61 7 3316 3000 F 61 7 3316 3333 E bnemail@ghd.com W www.ghd.com
© 2011. Whilst every care has been taken to prepare this map, GHD and DATA CUSTODIANS make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose
and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be
incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Data source: GHD - Dam Level at 77m; DERM - Catchment Boundary, Road, Watercourse; Geoscience Australia - 250k Topo Data; Seqwater - Wivenhoe Dam, Bridge Locations. Created by: TH
GHD
201 Charlotte Street Brisbane QLD 4000
GPO Box 668 Brisbane QLD 4001
T: (07) 3316 3000 F: (07) 3316 3333 E: bnemail@ghd.com.au
© GHD 2011
This document is and shall remain the property of GHD. The document may only be used for the purpose
for which it was commissioned and in accordance with the Terms of Engagement for the commission.
Unauthorised use of this document in any form whatsoever is prohibited.
Document Status
41/24452/428742 Investigation of Options to increase the flood mitigation performance of Wivenhoe Dam