Beruflich Dokumente
Kultur Dokumente
Process Systems Engineering Centre (PROSPECT), Faculty of Chemical Engineering, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor, Malaysia
Centre for Process Integration and Intensication e CPI2, Research Institute of Chemical and Process Engineering, Faculty of Information Technology, University of Pannonia,
Egyetem u. 10, H-8200 Veszprm, Hungary
b
a r t i c l e i n f o
a b s t r a c t
Article history:
Received 19 October 2011
Accepted 11 February 2012
Available online 22 February 2012
Total Site Heat Integration (TSHI) is a methodology for the integration of heat recovery among multiple
processes and/or plants interconnected by common utilities on a site. Until now, it has not been used to
analyze a sites overall sensitivity to plant maintenance shutdown and production changes. This feature
is vital for allowing engineers to assess the sensitivity of a whole site with respect to operational changes,
to determine the optimum utility generation system size, to assess the need for backup piping, to
estimate the amount of external utilities that must be bought and stored, and to assess the impact of
sensitivity changes on a cogeneration system. This study presents four new contributions: (1) Total Site
Sensitivity Table (TSST), a tool for exploring the effects of plant shutdown or production changes on heat
distribution and utility generation systems over a Total Site; (2) a new numerical tool for TSHI, the Total
Site Problem Table Algorithm (TS-PTA), which extends the well-established Problem Table Algorithm
(PTA) to Total Site analysis; (3) a simple new method for calculating multiple utility levels in both the PTA
and TS-PTA; and (4) the Total Site Utility Distribution (TSUD) table, which can be used to design a Total
Site utility distribution network. These key contributions are clearly highlighted via the application of the
numerical technique to two Case studies.
2012 Elsevier Ltd. All rights reserved.
Keywords:
Total site problem table algorithm (TS-PTA)
Total Site
Heat cascade
Numerical approach
Site minimum utility targets
Process integration
1. Introduction
Pinch Analysis is an established technology for reducing energy
consumption that has been widely applied in various industries for
more than 30 years. Dhole and Linnhoff [1], Raissi [2] and Klemes
et al. [3] extended traditional heat integration, which focuses on
direct heat transfer among process streams at a single site, to heat
integration for multiple sites. This is known as Total Site Heat
Integration (TSHI), sometimes called site-wide integration. Direct
heat transfer is not always suitable for inter-process heat recovery
due to the required high degree of operational exibility and the
long-distance piping needed, which makes it very costly [4]. TSHI
using indirect heat transfer utilising existing utility systems is
typically more cost effective because the existing plant piping
system can be used. TSHI heat integration is linked by a common
central or sectional utility system.
Dhole and Linnhoff [1] have introduced Site Sink and Source
Proles (SSSP), a graphical tool that can be used to evaluate fuel
consumption, cogeneration, emissions and cooling needs for
an integrated site. A simple exergy model was proposed for
* Corresponding author. Tel.: 60 07 5535533; fax: 60 07 5581463.
E-mail address: shasha@cheme.utm.my (S.R. Wan Alwi).
1359-4311/$ e see front matter 2012 Elsevier Ltd. All rights reserved.
doi:10.1016/j.applthermaleng.2012.02.026
398
Energy Sector (LIES). In a LIES, heat sources and sinks can be derived
from small-scale industrial plants, large building complexes (such as
hotels and hospitals), ofces and residential areas.
One of the major challenges in implementing the Total Site
concept involving renewable energy is the variation of energy
supply and demand with time and location. Therefore, Varbanov
and Klemes [9] suggested performing Total Site targeting in a set of
time slices to maximise heat recovery within each time slice. Varbanov and Klemes [10] then further extended the concept to heat
storage, heat waste minimisation and carbon footprint reduction. A
Total Site heat cascade is also introduced in this work to illustrate
these concepts.
Bandyopadhyay et al. [11] proposed a modication of the Site
Grand Composite Curve (SGCC) that incorporates assisted heat
transfer. This type of heat transfer takes into account the nonmonotonic parts or pockets of the process GCC, which were not
considered by Dhole and Linnhoff [1], although this may not be
practical for many integrated sites. The results of their study show
that the modied SGCC tends to increase heat recovery potential,
particularly those within each process, a feature which is not
considered in the TSP. However, the economy of this design has to
be explored, as an increased integration using nonstandard steam
mains can be costly.
Kapil et al. [12] proposed the recovery and upgrading of lowgrade heat from processes. The work has proposed a new methodology for estimating the cogeneration potential for a site utility
system via bottom-up and top-down procedures. Ghannadzadeh
et al. [13] presented Iterative Bottom-to-Top Model (IBTM) as a new
shaftwork targeting model to estimate the cogeneration potential
for site utility systems prior to the detailed design.
Fodor et al. [14] further developed a TSHI targeting method to
allow for a variation of the minimum temperature difference
(DTmin) among Total Site processes. Previous works by Dhole and
Linnhoff [1] and Klemes et al. [3] assumed a uniform DTmin on
a Total Site. Fodor et al. [14] and Varbanov et al. [15] proposed the
use of a utility and process-specic DTmin between utility and
process streams, which is more realistic in practical applications.
The Total Site methodology and the concepts developed by
Dhole and Linnhoff [1] and used in recent studies are based on
a graphical method, with the typical advantages and disadvantages
of such approaches. Numerical methodologies that provide similar
benets such as the Problem Table Algorithm (PTA) for heat pinch
and the Water Cascade Analysis (WCA) for water pinch are therefore desirable.
The PTA is a numerical tool for intra-process heat integration
proposed by Linnhoff and Flower [16]. This tool is the equivalent to
the use of Composite Curves (CCs) and Grand Composite Curve
(GCCs) in the graphical method and supports a more precise
graphical construction by providing exact values for the crucial
points. The algorithm was extended to multiple utility targeting by
Costa and Queiroz [17]. The PTA was also recently extended to the
Unied Targeting Algorithm (UTA) by Shenoy [18]. The UTA is
a powerful tool for obtaining the maximum resource recovery for
Process Integration problems including heat and mass exchange,
water, hydrogen, carbon emissions and material reuse networks.
However, the method proposed by Costa and Queiroz [17] involves
rather complex calculations, whereas the UTA cannot be used for
TSHI problems. To make the PTA a more powerful tool, simpler
method for multiple utility targeting would be benecial. Additionally, the PTA can also be extended to TSHI.
In the current study, a new numerical tool for targeting TSHI is
proposed, known as the Total Site Problem Table Algorithm
(TS-PTA). This numerical tool is an alternative to the graphical TSHI
approach and is suitable for both the uniform and non-uniform
DTmin methods proposed by Dhole and Linnhoff [1], Klemes et al.
[3], Fodor et al. [14] and Varbanov et al. [15]. Although graphical
approaches are advantageous in terms of providing valuable visual
insights, they are difcult to construct, especially for large problems, and may yield some inaccuracies inherent in the graphical
nature of the method. The Problem Table Algorithm (PTA), which is
a numerical tool introduced by Linnhoff and Flower [16] as an
alternative to the Composite Curves, has been among the preferred
analytical tools used to compensate for the limitations of the
graphical approaches. In this work, the PTA method is extended to
include TSHI analysis.
The previous works cited have generally not deeply studied the
exibility of integrated plants. A numerical tool therefore offers
a good opportunity to evaluate the sensitivity of each plant in TS
integration. The Total Site Sensitivity Table (TSST) can be used as
a tool to explore site-wide sensitivities to various operational
changes and variations. A typical case is when one site process must
be closed down for regular maintenance or due to an accident.
Using the TSST, the effect of a plant shutdown can be assessed, and
suitable measures can be taken during the design and operational
stages to ensure other site utility supplies are not disrupted.
2. Methodology
A summary of the procedure involving the four methodologies
is described in the following.
2.1. Tool 1: Total Site Problem Table Algorithm (MU-PTA)
The initial steps follow the same procedure as the PTA for
individual process. First, the shifted temperatures for the process
streams in each individual process are calculated as described in
Smith [19], Kemp [20] and Klemes et al. [21]. The PTA is constructed
as described by Linnhoff and Flower [16] and Smith [19]. The
multiple utility cascade procedure for each individual plant is as
follows:
a. Above the pinch region:
i. Subtract half of the minimum temperature difference
within each process, DTmin,pp/2, from the shifted temperature to return it to a normal temperature, and then add the
minimum temperature difference between the utility and
process stream (DTmin,up) [14,15].
ii. Cascade the heat available in each temperature interval
from the highest temperature to the pinch temperature.
When a negative value results, an external heat enthalpy
representing the utility is added immediately to the
temperature interval during cascading.
iii. The amount of each utility type required can be determined
by summing the external heat enthalpies from below each
utility temperature to the next utility temperature.
b. Below the pinch region:
i. DTmin,pp/2 is added, and DTmin,up is subtracted, to the shifted temperatures [14,15].
ii. The heat available in each temperature interval is cascaded
from the lowest temperature to the pinch temperature, and
the external cooling utility required is immediately added
to the temperature interval when there is positive value in
the cascade.
iii. The amount of each utility type to be generated is obtained
by adding the external cooling utility above each utility
temperature but below the next-highest temperature
utility.
This tool also could be used for single process Heat Integration
which has different temperature shifting at the beginning.
Table 1
Stream data for Plant A of Case study 1 with DTmin 20 C; modied example from
Canmet ENERGY [22].
399
Table 2
Stream data for Plant B of Case study 1 with DTmin 10 C; modied example from
Kemp [20].
Stream
Ts ( C)
Tt ( C)
DH(MW)
mCp (kW/ C)
Ts ( C)
Tt ( C)
B1
B2
B3
B4
B5
200
240
200
30
50
50
100
119
200
250
0.450
0.210
1.863
0.680
0.400
3.0
1.5
23.0
4.0
2.0
195
235
195
35
55
45
95
114
205
255
Hot
Hot
Hot
Cold
Cold
Table 3
Site utility data for Case study 1.
Stream
Ts ( C)
Tt ( C)
DH(MW)
mCp (kW/ C)
Ts ( C)
Tt ( C)
Utility
Temperature ( C)
A1
A2
A3
A4
200
150
50
50
100
60
120
220
2.00
3.60
4.90
2.55
20
40
70
15
190
140
60
60
90
50
130
230
270
179.93
133.59
15e20
Hot
Hot
Cold
Cold
400
mCp (kW/ C)
T ( C)
( C)
20
40
70
15
(kW/ C)
(kW)
230
40
-15
45
-25
-45
50
integration. The multiple utility cascade methodology is an extension of the PTA with an additional 4 columns. The multiple utility
cascade calculations are similar to GCCs and can be used identify
pockets and target the exact amounts of utilities needed within
a given utility temperature interval. Note that multiple utility
cascades must be performed based on the pinch regions for each
plant that were determined in Step 1.
3.2.1. Multiple utility cascades in the region above the pinch of each
individual plant
All shifted temperatures (T0 ) in the region above the pinch
(column 1, Table 5) from Table 4 PTA are reduced by DTmin,pp/2 to
return them to normal temperatures and then the minimum
temperature difference between the utility and the process
(DTmin,up) is added, as shown in column 2, Table 5; the resulting
temperature is labeled T00. The utility temperatures listed in Table 3
were also added into Table 5 to make it easier to determine the
utility distribution at a later stage.
Heat is again cascaded starting from the highest temperature
segment to the pinch temperature, as shown in column 7, Tables 5a
and 5b. Note that there are no changes in the calculations of sum
mCp and sum DH for each temperature level. This cascade is
known as a multiple utility heat cascade; it differs from the
previous heat cascade in the PTA (column 6, Tables 4a and 4b)
because it is performed interval-by-interval. If a negative value is
encountered while cascading one of the temperatures, external
utilities are immediately added at that point (the amount of
external utility added is listed in column 8) equal to the negative
value. The cascade then becomes zero at that temperature, e.g., at
40
-600
1650
-350
1900
100
2350
-900
1350
-2250
-1850
400
-1350
60
10
2250
-1000
90
30
450
130
40
Initial
Heat
Cascade
250
140
10
7
Single
Utility
Heat
Cascade
-600
190
50
400
401
Table 4b
Single utility cascade table for Plant B of Case study 1.
(kW)
Initial
Cascade
Single
Utility
Cascade
100
-40
60
-55
45
-100
1641.5
1741.5
1613
1713
1493
1593
1483
1583
1443
1543
mCp (kW/ C)
T' ( C)
( C)
1.5
23
(kW/ C)
255
20
-2
-40
235
30
-0.5
-15
205
10
-4.5
-45
195
81
21.5
1741.5
114
19
-1.5
-28.5
95
40
-3
-120
55
10
-1
-10
45
10
35
-4
-40
402
T
( C)
T
( C)
mCp (kW/ C)
( C)
20
40
70
15
(kW/ C)
(kW)
270
0
-15
190
Heat Sink/
Source
600
MPS
LPS
1650
600
50.35
50.35
199.65
140
250
6.41
45
288.45
133.59
538.45
3.59
45
161.55
130
700
40
-25
-1000
90
300
0
30
-45
-1350
1350
60
60
60
Pinch
10
50
HPS
39.93
90
Utility
Consumed/
Generated
(kW)
-600
179.93
130
Multiple
Utility
Heat
Cascade
10.07
140
230
40
190
0
40
230
40
400
50
-400
0
35
15
generating utilities (see the lower part of column 7 and 8 in Table 5).
For the region below the pinch, the negative values encountered
during multiple utility cascading represent pockets in the GCC.
The amount of utility that can be generated can be determined
by adding the amounts of excess heat from above the utility
temperature to the next utility temperature level. For example,
plant A can generate 400 kW of CW using process heat between 50
and 10 C. For plant B, 216.50 kW of medium pressure steam (MPS)
at 190 to 179.93 C and 996.31 kW of LPS between 179.93 and
133.59 C can be generated, whereas 330.19 kW of CW is consumed.
The proposed method differs from the one developed by Costa
and Queiroz [17]. The method in this study was developed through
a detailed observation of multiple utility targeting in the GCC. In
addition, the method proposed herein is a direct continuation of
the PTA, in which the multiple utility cascade actually uses most of
the information from the PTA. The method proposed by Costa and
Queiroz [17] includes an interpolation step for nding the upper
and lower temperature boundaries after utility targeting. However,
0
0
CW
400
the proposed methodology targets utilities according to temperature intervals, with the utility temperatures becoming temperature
boundaries, to distinguish the amounts of each utility type. The
calculations involved in this proposed method are also simpler than
those of the previously proposed method.
3.3. Step 3: construct the Total Site Problem Table Algorithm
(TS-PTA) to determine the amounts of utilities that can be
exchanged among processes
This part is an extension of the PTA to represent the Site CC in
TSHI. The utilities available from each plant are arranged from
highest to lowest temperature. The utilities generated below the
pinch temperature for all sites, as determined in Step 3, are added
together to represent the net heat source (see column 3, Table 6).
The utilities consumed above the pinch temperature for all sites, as
determined in Step 2, are added together to represent the net heat
sink (see column 4, Table 6). Fig. 3 shows the TSP and the Site
403
Table 5b
PTA with multiple utility heat cascade for Plant B of Case study 1.
T
( C)
Multiple
Utility
Utility Consumed/
Heat
Generated
Cascade
(kW)
mCp (kW/ C)
T
( C)
( C)
1.5
23
(kW/ C)
(kW)
270
0
10
-2
-40
40
240
0
30
-0.5
-15
15
210
205
100
0
20
235
HPS
260
255
Heat Sink/
Source
0
10
-4.5
-45
45
200
190
Pinch
195
10.07
21.5 216.51
-216.50
179.93
0
46.34
21.5 996.31
0
24.59
21.5 528.69
-1.5
-28.5
330.19
-170
40
-3
-120
50
-50
10
-1
-10
40
-40
10
-4
-40
30
35
CW
90
45
996.31
-198.5
19
55
LPS
-330.19
109
95
216.50
-996.31
133.59
114
MPS
0
15
15
Table 6
Total site Problem Table algorithm (TS-PTA) for Case study 1.
1
Utility
Utility Temp. ( C)
Net heat
source (kW)
Net heat
sink (kW)
Net heat
requirement (kW)
Initial heat
cascade
Multiple utility
heat cascade
External utility
requirement (kW)
HPS
270
MPS
LPS
179.93
133.59
0
216.50
996.31
700
0
1650
1137.19
700
437.19
483.50
653.69
216.50
700
700
216.50
653.69
437.19
1137.19
CW
15e20
730.19
0 (Pinch)
730.19
L730.19
730.19
407
404
Table 7
Total site Utility Distribution (TSUD) table for Case study 1.
Ts ( C)
Tt ( C)
DH (kW)
mCp (kW/ C)
Ts ( C)
Tt ( C)
A1
A2
A3
A4
A5
170
150
25
70
30
80
55
100
100
65
5000
6477
1500
1050
5250
55.5556
68.1818
20.0000
35.0000
150.0000
160
140
35
80
40
70
45
110
110
75
Hot
Hot
Cold
Cold
Cold
405
heat sources and heat sinks in the various plants are listed separately according to utility type, as shown in columns 3 and 4. The
external utilities calculated from Step 4 are also listed in Table 7.
Arrows within the table show that heat sources can be transferred
to heat sinks for the same type of utility. If there are extra heat
sources, heat can be transferred to the lower utility levels.
4. Application of the TS-PTA to TS sensitivity with changes
and variations
Table 9
Stream data for Plant B [8] with DTmin,pp 10 C.
Stream
Ts ( C)
Tt ( C)
DH (kW)
mCp (kW/ C)
Ts ( C)
Tt ( C)
B1
B2
B3
B4
B5
B6
200
20
100
150
60
75
80
100
120
40
110
150
10,000
4000
10,000
8443
1000
7000
83.3333
50.0000
500.0000
76.7575
20.0000
93.3333
195
25
105
145
65
80
75
105
125
35
115
155
Hot
Cold
Cold
Hot
Cold
Cold
Table 10
Stream data for Plant C [8] with DTmin,pp 20 C.
Stream
Ts ( C)
Tt ( C)
DH (kW)
mCp (kW/ C)
Ts ( C)
Tt ( C)
C1 Hot
C2 Hot
C3 Cold
C4 Cold
C5 Cold
C6 Cold
C7 Cold
C8 Cold
C9 Cold
C10 Cold
C11 Cold
85
80
25
55
33
25
30
25
30
18
21
40
40
55
85
60
60
121
28
100
25
121
23.85
96.40
17.70
77.40
6.48
77.00
12.74
151.68
59.50
100.80
5.00
0.5300
2.4100
0.5900
2.5800
0.2400
2.2000
0.1400
50.5600
0.8500
14.4000
0.0500
75
70
35
65
43
35
40
35
40
28
31
30
30
65
95
70
70
131
38
110
35
131
Table 11
Stream data for Plant D [8] with DTmin,pp 10 C.
Stream
Ts ( C)
Tt ( C)
DH (kW)
mCp (kW/ C)
Ts ( C)
Tt ( C)
D1 Cold
D2 Cold
15
15
60
80
6000
5000
133.3333
76.9232
20
20
65
85
Table 12
Site utility temperatures.
Utility
Temperature ( C)
170
125
50e60
20
As mentioned previously, the TS-PTA can be benecial for analysing the sensitivity of the TSHI to plant shutdowns due to maintenance or upsets and to design mitigation strategies. This is
illustrated using Case study 2 from Perry et al. [8]. Here, there are
four sites considered in Locally Integrated Energy Sectors (LIES):
two industrial process plants, a hospital complex and a combined
residential and ofce complex. The stream data for the four plants
are listed in Table 8e11 . Plants A and C are assumed to have the
same DTmin,pp of 20 C, whereas Plants B and D both have a DTmin,pp
of 10C. Table 12 shows the types of utilities serving the area, with
a DTmin,up of 10 C.
Steps 1 to 4 were performed for the processes in Case study 2.
The nal TS-PTA values for the standard operation of the plants
comprising the TS are listed in Table 13. Due to its numerical nature,
it is very convenient to manipulate data in the TS-PTA to obtain new
values for various cases. For example, to consider a plant shutdown,
we omit the contributions from the shutdown plant from the heat
sinks and sources in columns 3 and 4 of Table 13. The new external
utility requirements are then obtained. Table 14 summarises the
external utility variations when one of the plants is shutdown. We
refer to Table 14 as the proposed Total Site Sensitivity Table (TSST),
which can be used to gain many insights into utility system design.
The variance in Table 14 is calculated by subtracting the amounts of
external utilities during plant shutdowns from the values needed
during normal operation. A positive variance above the Total Site
Pinch indicates that the central utility has a heat surplus that is not
used in any sinks. The utility systems have the following options:
(i) Fewer utilities can be generated, if permitted by the turn down
ratio.
(ii) The heat surplus can be disposed of using an external cooling
utility, which would incur a penalty cost.
(iii) The heat surplus can be sold to other plants.
(iv) For HP or MP steam, if a plant has a combined heat and power
system (CHP) with a double-stage extraction turbine, the heat
surplus can be used to generate extra electricity for the plant.
(v) The heat surplus can be cascaded downwards to locations with
negative variances provided they are still located in the same
TS-PTA pinch region.
A positive variance below the Total Site Pinch represents surplus
cooling utility produced by the utility plant, and it can be cascaded
Table 13
Total Site Problem Table algorithm (TS-PTA) during normal operation.
Utility
Utility Temp.( C)
HP
170
Net heat
source (kW)
Net heat
sink (kW)
Net heat
requirement (kW)
Initial heat
cascade
Final heat
cascade
Multiple utility
cascade
11,937.90
3.04
11,934.86
4805.18
6484.70
ST
HW
125
50e60
3.04
2967.17
1495.71
7769.31
7606.92
3.04
3.04
4802.14
4802.14
6111.22
6111.22
10,916.40
CW
10
35.15
Amount of
utility needed
L227.27
35.15
10,881.25
35.15
406
Table 14
Total Site Sensitivity Table (TSST).
Utility
Plant A
shutdown
HP
3.04
3.04
ST
4802.14
7769.31
HW
6111.22
Pinch
35.15
6821.32
Pinch
35.15
CW
Variance from
normal operation
Plant B
shutdown
Variance from
normal operation
Plant C
shutdown
3.04
2967.17
810.77
3991.37
4665.19
136.95
710.08
6896.82
Pinch
0
758.60
5863.17
Pinch
35.15
248.06
35.15
Variance from
normal operation
3.04
Plant D
shutdown
Variance from
normal operation
3.04
1161.15
Pinch
1247.65
0
3640.99
4863.57
35.15
STEP 1: Perform Problem Table Algorithm (PTA) for all individual process
Cascade the net heat requirement from top to bottom by taking the most negative value in the
previous cascade as hot utility provided
Above Total Site Pinch
Cascade the net heat requirement from top to bottom by assuming no hot utility provided
5. Methodology summary
Fig. 4 presents a summary of the overall procedure for the four
useful tools proposed in this study: the Problem Table Algorithm
with multiple utility targets, the Total Site Problem Table Algorithm
(TS-PTA), the Total Site Utility Distribution (TSUD) table, and the
Total Site Sensitivity Table (TSST).
6. Conclusions
In the following, we present a summary of the contributions of
this work:
1) A new method was developed for calculating multiple utility
levels in the PTA that is simpler than that presented by Costa
and Queiroz [17]. This work introduced the use of multiple
utility cascades to determine multiple utility levels for individual PTAs and TS-PTAs. This tool enables the multiple utility
targeting for individual processes to be done effectively using
the numerical approach which produces more accurate results.
2) The TS-PTA was introduced for TSHI. We further demonstrated
that the TS-PTA yields more accurate results for TSHI analysis
when compared with a graphical approach, which is prone to
inaccuracies. The tool saves time and effort in determining
amounts of heat interchange among plants compared with
graphically constructed CCs, GCCs, TSPs and SCCs. This tool
could be explored further for the variable supply and demand
Total Site problem as proposed by Varbanov and Klemes [9].
Also, TS-PTA could be used for continuous and batch processes
that may not be conveniently solved using graphical tools.
407
Acknowledgements
The authors would like to thank the Universiti Teknologi
Malaysia for providing nancial support through the UTM International Education Experience Fund and the nancial support from
the Hungarian project TMOP-4.2.2/B-10/1-2010-0025 and to the
University of Pannonia in Hungary for supporting the collaboration.
Nomenclature
Ts
Tt
T0
T00
CC
GCC
CW
HP
HW
LIES
LPS
mCp
PTA
Qcmin
Qhmin
SCC
SGCC
SSSP
TS
TSP
TSHI
TSST
TSUD
TS-PTA
UTA
DH
DTmin,pp
DTmin,up
408
References
[1] V.R. Dhole, B. Linnhoff, Total site targets for fuel, co-generation, emission and
cooling, Comput. Chem. Eng. 17 (1993) S101eS109.
[2] K. Raissi, Total site integration. PhD Thesis, UMIST, Manchester, UK, 1994.
[3] J. Klemes, V.R. Dhole, K. Raissi, S.J. Perry, L. Puigjaner, Targeting and design
methodology for reduction of fuel, power and CO2 on total site, Appl. Therm.
Eng. 7 (1997) 993e1003.
[4] S. Ahmad, D.C.W. Hui, Heat recovery between areas of integrity, Comput.
Chem. Eng. 15 (12) (1991) 809e832.
[5] F. Marchal, B. Kalitventzeff, Energy integration of industrial sites: tools,
methodology and application, Appl. Therm. Eng. 18 (1998) 921e933.
[6] K. Matsuda, S. Tanaka, M. Endou, T. Iiyoshi, et al., Energy saving study on
a large steel plant by total site based pinch technology, Appl. Therm. Eng.
(2012). doi:10.1016/j.applthermaleng.2011.11.043.
[7] P.S. Varbanov, S. Doyle, R. Smith, Modelling and optimization of utiltiy
systems, Chem. Eng. Res. Des 82 (A5) (2004) 561e578.
[8] S. Perry, J. Klemes, I. Bulatov, Integrating waste and renewable energy to
reduce the carbon footprint of locally integrated energy sectors, Energy 33
(2008) 1489e1497.
[9] P.S. Varbanov, J.J. Klemes, Total site integrating renewables with extended
heat transfer and recovery, Heat Transfer Eng. 31 (9) (2010) 733e741.
[10] P.S. Varbanov, J.J. Klemes, Integration and management of renewables into
total slice with variable supply and demand, Comput. Chem. Eng. 35 (9)
(2011) 1815e1826.
[11] S. Bandyopadhyay, J. Varghese, V. Bansal, Targeting for cogeneration potential
through total site integration, Appl. Therm. Eng. 30 (2010) 6e14.
[12] A. Kapil, I. Bulatov, R. Smith, J.K. Kim, Site-wide low-grade heat recovery with
a new cogeneration targeting method, Chem. Eng. Res. Des (2012).
doi:10.1016/j.cherd.2011.09.001.
[13] A. Ghannadzadeh, S. Perry, R. Smith, Cogeneration targeting for site utility
systems, Appl. Therm. Eng. (2012). doi:10.1016/j.applthermaleng.2011.10.006.
[14] Z. Fodor, P. Varbanov, J. Klemes, Total site targeting accounting for individual
process heat transfer characteristics, Chem. Eng. Trans. 21 (2010) 49e54.
[15] P.S. Varbanov, Z. Fodor, J.J. Klemes, Total site targeting with process specic
DTmin, Energy (2012). doi:10.1016/j.energy.2011.12.025.
[16] B. Linnhoff, J.R. Flower, Synthesis of heat exchanger networks, AIChE J. 24
(1978) 2 parts. Part I: systematic generation of energy optimal network, 633642. Part II: evolutionary generation of networks with various criteria of
optimality, 642-654.
[17] A.L.H. Costa, E.M. Queiroz, An extension of the problem table algorithm for
multiple utilities targeting, Energ. Convers. Manage. 50 (2009) 1124e1128.
[18] U.V. Shenoy, Unied targeting algorithm for diverse process integration
problems of resource conservation networks, Chem. Eng. Res. Des 89 (12)
(2011) 2686e2705.
[19] R. Smith, Chemical Process: Design and Integration, John Wiley & Sons
Chichester, UK, 2005.
[20] I. Kemp, Pinch analysis and process integration, in: B. Linnhoff,
D.W. Townsend, D. Boland, G.F. Hewitt, B.E.A. Thomas, A.R. Guy, R.H. Marsland
(Eds.), A User Guide on Process Integration for Efcient Use of Energy, second
ed.. IChemE, Rugby, UK, 1994 Elsevier, Amsterdam, The Netherlands, 2007.
[21] J. Klemes, F. Friedler, I. Bulatov, P. Varbanov, Sustainable in Process Industry:
Integration and Optimization, McGraw Hill, New York, US, 2010.
[22] Canmet ENERGY, Pinch Analysis: For the Efcient Use of Energy, Water and
Hydrogen, Natural Resource Canada, Varennes, 2003.