Beruflich Dokumente
Kultur Dokumente
2015
Completion of
section 02 qty
(09/07/2016)
25-Jun-16
11-May-16
19-May-16
27-Apr-16
7-May-16
59
Total Duration
5-May-16
27-Apr-16
End Date
27-Apr-16
24
Start Date
Completion of
section 01 qty
(25/05/2016)
26-Apr-16
End Date
2-Apr-16
Total Duration
40
Start Date
Milestone S/S
qty (25/04/2016)
14-Apr-16
Total Duration
5-Mar-16
End Date
42
Start Date
Milestone 06 qty
(01/03/2016)
2-Mar-16
Total Duration
20-Jan-16
End Date
11
Start Date
Milestone 04 qty
(30/11/2015)
19-Nov-15
Total Duration
DELIVERY
PERIOD from
Milestone 03 qty
the date of
(30/09/2015)
confirmed order
9-Nov-15
End Date
17
Start Date
UNIT
End Date
DESCRIPTION
Start Date
ITEM
1-Sep-15 17-Sep-15
Total Duration
PROJECT: MTC Primary & Secondary Roads Construction Abu Dhabi International Airport Electrical and Street Lighting Works
G
5.0
I
K
12-14 weeks
1.00
1.00
2.00
500kVA Transformer
1000kVA Transformer
2000kVATransformer
No.
No.
No.
1
1
2
1
1
-
5
5
16-18 weeks
No.
14
28-30 weeks
900.00
-
500.00
-
22kv Cabling
Low Voltage Switchboard compact station TA 1/4order date: 28th Nov 2015
Low Voltage Cabling XLPE 4Cx6
Low Voltage Cabling XLPE 4Cx10
Low Voltage Cabling XLPE 4Cx16
Low Voltage Cabling XLPE 4Cx25
Low Voltage Cabling XLPE 4Cx35
Low Voltage Cabling XLPE 4Cx70
Low Voltage Cabling XLPE 4Cx95
Low Voltage Cabling XLPE 4Cx120
Bare Copper BC 25 for Earthing system
ECC cable
order date: 30th Jan 2016
Control Cabinet
MDB Distribution Board MV Substation
Ground Rods
14
5,035
No.
m
m
m
m
m
m
m
m
m
lm
15,963
7,876
170
2,356
22,000
23,839
No.
16
No.
3,920
2
21,297
858
21,297
11
22
12-14 weeks
12-14 weeks
60
14
60
60
2,692
18
12-14 weeks
12-14 weeks
28-30 weeks
1-Sep-15
2-Sep-15
A
B
C
11-Feb-16
2.00
5-Mar-16
16-Mar-16
7,000.00
827.00
2,147.00
2,000.00
-
16-Mar-16
7.00
2-Apr-16
14-Apr-16
16-Apr-16
18-Apr-16
19-Apr-16
21-Apr-16
9,897.00
31.00
545.00
2-Apr-16
14-Apr-16
7-May-16
19-May-16
7-May-16
7-May-16
8-May-16
10-May-16
16,297.00
27-Apr-16
10-May-16
4.00
11-May-16
17-May-16
104.00
169.00
35.00
17-May-16
17-May-16
17-May-16
25-Jun-16
25-Jun-16
25-Jun-16
24-Mar-16
31-Mar-16
24
12-14 weeks
2.00
2-Apr-16
14-Apr-16
10
2.00
2-Apr-16
14-Apr-16
No.
71
12-14 weeks
12-14 weeks
71.00
No.
10
12-14 weeks
2.00
5-Mar-16
16-Mar-16
No.
14
2.00
5-Mar-16
20-Mar-16
No.
2.00
15-Apr-16
14-Apr-16
No.
12
4-6 weeks
Ex- Stock
12-14 weeks
Dual Charger single battery bank 48V DC battery system as per ADDC
standards
070 Other items
Other items not priced elsewhere- The Contractor shall list below and price
any other items not priced elsewhere which are deemed necessary for the
completion of the works.
No.
12
No.
No.
No.
308
225
43
274
217
43
No.
No.
93
-
63
-
13
No.
88
18
No.
No.
No.
No.
16-18 weeks
16-18 weeks
8-10 weeks
35
205
6
41
2
5,035
3,920
18
16-18 weeks
30.00
6.00
-
25.00
9.00
-
48.00
-
12.00
43
86
215
5
12-Sep-15
17-Sep-15
12-Sep-15
14-Sep-15
12-Sep-15
17-Sep-15
7.00
17-Nov-15
19-Nov-15
17-Nov-15
19-Nov-15
17-Nov-15
19-Nov-15
16-Mar-16
12-Apr-16
14-Apr-16
115.00
8.00
22.00
50.00
39.00
48.00
-
20-Feb-16
2-Mar-16
15.00
50.00
-
3,920.00
30-Jan-16
18-Feb-16
20-Feb-16
2-Mar-16
22-Apr-16
25-Apr-16
22-Apr-16
25-Apr-16
22-Apr-16
22-Apr-16
25-Apr-16
25-Apr-16
26.00
17-May-16
25-Jun-16
22-Apr-16
25-Apr-16
30.00
17-May-16
25-Jun-16
22-Apr-16
25-Apr-16
20.00
17-May-16
25-Jun-16
22-Apr-16
25-Apr-16
107.00
6.00
17-May-16
17-May-16
25-Jun-16
25-Jun-16
16-18 weeks
No.
No.
20-22 weeks
No.
Warning Tape
LM
32,260
24,847
20
4-6 weeks
900.00
9-Sep-15
10-Sep-15
500.00
16-Nov-15
17-Nov-15
500.00
20-Feb-16
No.
64,520
49,694
62
8-10 weeks
1,800.00
3-Sep-15
9-Sep-15
1,000.00
11-Nov-15
16-Nov-15
1,000.00
20-Feb-16
E
F
G
No.
No.
No.
No.
43
5-Mar-16
2.00
10
2.00
No.
5-Mar-16
24-Feb-16
31-Mar-16
200.00
-
24-Feb-16
21-Mar-16
2.00
11-Feb-16
24-Mar-16
24-Mar-16
No.
E
F
H
I
10-Nov-15
10-Feb-16
21-Mar-16
21-Mar-16
2.00
No.
order date: 26th Dec 2015
9-Nov-15
3,000.00
3,000.00
-
20-Jan-16
6.00
3,920.00
59 days
24 days
40 days
No.
42 days
11days
17days
8-10 weeks
43
64
16-18 weeks
6.00
1-Feb-16
14-Feb-16
2.00
-
21-Mar-16
25-Mar-16
2.00
12-Apr-16
14-Apr-16
4.00
19-Apr-16
23-Apr-16
25-Feb-16
10,000.00
6-Apr-16
26-Apr-16
12,947.00
27-Apr-16
7-May-16
25-Feb-16
20,000.00
4-Apr-16
24-Apr-16
25,894.00
27-Apr-16
7-May-16
43.00
17-May-16
25-Jun-16
193