Beruflich Dokumente
Kultur Dokumente
All person involved in the construction project shall use proper protective gears and
equipments. Any person that does not wear proper protective gears and
equipments shall not be allowed to enter the job site and commence their
respective works.
The Contractor shall always consult or request the approval of the Supervising
Engineer on or before proceeding into the subsequent scope of work listed in this
article. This should be constantly observed by the two parties to prevent technical
misconstruction during the duration of the project.
Bedrock shall be reached or stable ground where the foundation structure shall set.
If the bedrock or solid ground is established before the minimum depth of
excavation reflected on the detailed plans, the Contractor shall seek approval to the
Engineer before discontinuing the excavation works.
The Supervising Engineer and the Contractor shall inspect the layout, stakes, batter
boards, and any other markings for the excavation works. It will be their
responsibility to inspect all excavation dimensions including the provision for
necessary clearances for work areas as the activity progresses.
If in case that the depth of excavation is high enough that the cut slope turned out
to be unstable, the Contractor shall provide sand bag buttresses as a temporary
slope protection or may use any other slope protection method applicable.
Reinforcing steel bar sizes to be installed shall conform with the plans; must be free
from rust and shall be firmly tied with gauge 16 GI tie wire.
All boreholes shall be 16mm in diameter and a minimum drilled depth of 200mm.
Boreholes shall be filled with cement grout before inserting the dowel rebar.
The Supervising Engineer shall always inspect the spacing, longitudinal, transverse,
horizontal and vertical alignments of the rebar that are being installed.
All reinforcing bars to be installed shall be of grade 230.
Prior to placement of boulders, the surface of the foundation should be clean and
free from any debris. Lean concrete shall be poured on the foundation with
specified thickness as stated on the plans and drawings.
Concrete mix for the foundation shall be 1:2:4 (One 40kg bag of cement: Two (2)
parts of sand: Four (4) parts of gravel). Gravel diameter size should range from
inch to 1 1/2 inch. Both fine and coarse aggregates that will be used in concreting
activities shall be washed with clean water to remove soil and other debris.
Water to be used for concreting shall be visibly clean and free from any
contaminants.