Request For Information

Project [BP-1B-04] - Msheireb


View Date 29/1/2015
Downtown Doha Project Phase 1B Sub & Super
Structure Works
Carillion (Qatar) LLC / Qatar
Building Company JV
Doha, 30024
Phone: +974-4441-2649
Fax: +974-4441-2687

Primary
Responder

CC

From

RFI No. BP-1B-0405974

Hashem N Pendaliday
Gulf Engineering & Industrial Consultancy
Doha 9811
Qatar
Phone: +974-4442-2120
Fax: +974-4442-2150

Issue Date

12/1/2015

Status

Closed

Reason for
Request

Insufficient
Information

GEIC 1BDC (Gulf Engineering & Industrial


Consultancy)
Bassam Hajbeh (TiME Qatar)
MDD P1B1CPDCC (TiME Qatar)

Priority

High

Response Due

19/1/2015

Resolved Date

Alec Bailey
Carillion (Qatar) LLC / Qatar Building
Company JV

Subject
Site Wide -ETA -Lighting -AD17 fixture location and mounting height.
Drawing No. BP-1B-04-05974 - CQB-ETA-CQ002-ELIDetail No.
RFI-00959
CSI Code
26 00 00 - ELECTRICAL
Other Ref. No.
Information Requested
Reference:
1. P1B-DWG-HHH-03-ARC-BMD-4502rev.02,
2. P1B-DWG-HHH-03-ARC-BMD-4501rev.03
3. P1B-DWG-HHH-09-ARC-BMD-4500rev.02,
4. P1B-DWG-HHH-05-ARC-BMD-4501rev.04
5. P1B-DWG-I01-02-ARC-BMD-4500rev.02,
6. P1B-DWG-HHH-09-ARC-BMD-4501rev.03
7. P1B-DWG-I01-12-ARC-BMD-4502rev.02,
8. P1B-DWG-I01-12-ARC-BMD-4501rev.02
9. P1B-DWG-I02-21-ARC-BMD-4534rev.00
10. P1B-DWG-I02-21-ARC-BMD-4533rev.00
11. P1B-DWG-I02-21-ARC-BMD-4536rev.00
12. P1B-DWG-I02-21-ARC-BMD-4535rev.01
13. P1B-DWG-I02-22-ARC-BMD-4529rev.00
14. P1B-DWG-I02-22-ARC-BMD-4528rev.00
15. P1B-DWG-000-03-ARC-BMD-4590rev.02
16. P1B-DWG-000-03-ARC-BMD-4591rev.03
17. P1B-DWG-000-03-ARC-BMD-4592rev.01
18. P1B-DWG-000-03-ARC-BMD-4593rev.01
19. P1B-DWG-000-03-ARC-BMD-4594rev.01
20. Approved material submittal of AD17 (CQB-ETA-CQ002-ELI-MAT-00097 Rev-03)
21. TQ letter reference MDD/CR/BP-1B-04/2014/0616 DATED 29TH OCTOBER 2014
Description: - With reference to the above subject and letter reference (MDD/CR/BP-1B04/2014/0616 DATED 29TH OCTOBER 2014), kindly advise / clear the below points.
Issue 1: Ad17 mirror light fixture located adjacent to the mirror also locates counter top, please
provide Mounting height and distance for the fixture both X and Y direction.
Issue 2: It not possible to install the mirror light as shown in the IFC enlarge plan drawings
referenced above because the IFC shows that it is installed above the mirror which it does not

work and we cannot accommodated in the space gap (100mm) because the space is not sufficient
to install.
In additional; Please provide the exact location including the dimension for all mirrors light adjacent
to the Mirrors because the exact dimension not shown in the IFC water closet standard detail
drawings
Specification attached for your quick reference (Section 102800, 265100). Kindly expedite in order
to proceed the drawings and installation works etc.
Regards,
Steve Ronald
Suggestion
Discipline

Response Information
Responder
Date
Response
Hashem N 29/1/2015 Issue 1: Provide grooming mirror at 1524mm AFF to center of mounting
Pendaliday
bracket for typical mirrors. Mount grooming mirrors located in ADA Fit-Out
locations at 1015mm (MAX.) AFF to bottom of mirrored (reflective) surface.
Issue 2: Although mounting the grooming mirrors on the wall mirror as
indicated in the IFC documents is achievable, it is acceptable to propose
minimizing the wall mirrors outer extents to allow for the grooming mirror to
mount on the wall tile if that is the Contractors preference. Submit
proposed solutions for Msheireb Properties approval. Include coordinated
locations of the shaver outlets within proposals for Supervision Consultant
review.
Include a copy of this RFI with related submittals. Reference this RFI
response on applicable submittals and identify the affected portions of the
work.
This response does not authorize any change in contract Cost or Time.

Hashem N Pendaliday
(Gulf Engineering & Industrial Consultancy)

29/1/2015

Printed Name

Date

Authorized Signature

Supporting documents and attached files


This RFI has the following supporting documents and attached files:
Description
Date
File Director: BP-1B-04-05974 - CQB-ETA-CQ002-ELI-RFI00959.pdf 4586KB
Attached file
Supporting document

Open as

12/1/2015

Distribution
Recipient
Alec Bailey

Company
Carillion (Qatar) LLC / Qatar Building
Company JV

Method
Message

Date
29/1/2015

Bassam Hajbeh

TiME Qatar

BMD 1B04DC
Duncan Kidd

Burns and McDonnell


Carillion (Qatar) LLC / Qatar Building
Company JV
Gulf Engineering & Industrial Consultancy
Gulf Engineering & Industrial Consultancy

GEIC 1BDC
Hashem N
Pendaliday
Ifthikhar Gaur
Lewis O'Brien

Gulf Engineering & Industrial Consultancy


Carillion (Qatar) LLC / Qatar Building
Company JV
Mario Agbayani
Gulf Engineering & Industrial Consultancy
MDD P1B1CPDCC
TiME Qatar
Melvin DSouza
Carillion (Qatar) LLC / Qatar Building
Company JV
Robert Kennaley
Burns and McDonnell
Saqlain Raza
Carillion (Qatar) LLC / Qatar Building
Company JV
Stephen Ronald
Carillion (Qatar) LLC / Qatar Building
Company JV
Tom Beckenbaugh Burns and McDonnell
Yasser Fahmy
Gulf Engineering & Industrial Consultancy
Yasser Sabry
Gulf Engineering & Industrial Consultancy

Email:
bhajbeh@tcco.com
Message
Message

12/1/2015

Message
Message

29/1/2015
29/1/2015

Message
Message

29/1/2015
29/1/2015

Message
Message
Message

29/1/2015
29/1/2015
29/1/2015

Message
Message

29/1/2015
29/1/2015

Message

29/1/2015

Message
Message
Message

29/1/2015
29/1/2015
29/1/2015

29/1/2015
29/1/2015