Presenters
- Construction Manager
Overview / Scope
Construct Klarman Hall, a 67,500 gross square foot addition to Goldwin
Smith Hall including an Atrium, 330-seat Auditorium, office and meeting
space and a new caf. The new space will be connected to Goldwin Smith
Hall at the ground first and second floors.
Construct site utilities, shoring and underpinning to permit excavation for
concrete foundations and slabs on grade. Construct steel superstructure,
stone cladding and glass and aluminum curtainwall and store front; metal
framed skylights. Construct the atrium roof and facades to be installed by
Josef Gartner USA as the single source vendor.
Construct interior finishes of drywall, stone and acoustic panels, glass and
aluminum windows and doors and wood doors. Floor finishes are carpet
and colored polished concrete floor for Atrium.
Pursue LEED Platinum certification.
Budget
Total Project Cost
$62,700,000
Construction Budget
$43,792,000
Project Team
Cornell University Facilities,
Gregg Crossett, CM
NK Architects
Stephen Welliver
Jason Edsall
Part-time, as needed
Tammy Schickler,
LEED AP
Full-time
LEED Agent
DeAnna DeMark
Part-time, as needed
Project Administrator
Full-time
Part-time, as needed
Kris Kimmel
Spike Fisk
General Construction
Superintendent
Full-time
Dave Gombas
Site Superintendent/Safety
Full-time
Guy Eldridge
Self-Perform Superintendent
Trade Contractors
Communication Plan
CONSTRUCTION SCHEDULE
v0_-v1_-v4_
Schedule
Mobilize on Site
SCHEDULE SEQUENCE
ENTRY
GATE
v00t3a6
Mobilize on Site
SCHEDULE SEQUENCE
ENTRY
GATE
v00t3a6
Mobilize on Site
SCHEDULE SEQUENCE
v10t3a6
MOBILE
HYDRAULIC
BOOM CRANE
v10t3b0
ROCK 803-9
v10t406
Underpinning Complete
SCHEDULE SEQUENCE
ROCK 800-0
ROCK 803-9
v10t410
ROCK 800-0
PIT 782
v10t416
PIT 775
ROCK 800-0
PIT 782
80 TON MOBILE
HYDRAULIC
BOOM CRANE
v10t420
PIT 775
80 TON MOBILE
HYDRAULIC
BOOM CRANE
v10t426
PIT 775
80 TON MOBILE
HYDRAULIC
BOOM CRANE
v10t430
v10t436
v10t440
v10t446
v10t450
200 TON
MOBILE LATTICE
BOOM CRANE
v10t456
200 TON
MOBILE LATTICE
BOOM CRANE
PARTIAL VIERENDEEL
TRUSS ASSEMBLY
v10t460
TOP OUT
STEEL
FRAME
TEMPORARY BRACES
FOR VT-1, VT-2, VT-3
v10t466
v10t470
v10t476
v10t480
POTAIN HDT 80
v10t486
October 2014
POTAIN HDT 80
v10t490
November 2014
POTAIN HDT 80
v10t4a0
Atrium Glass
SCHEDULE SEQUENCE
December 2014
POTAIN HDT 80
v10t4b0
February 2015
CONSTRUCTION
ENTRY POINT
v10t510
March 2015
CONSTRUCTION
ENTRY POINT
v10t520
May 2015
v10t546
July 2015
v10t560
v10t560
v10t570
v10t576
Project Complete
SCHEDULE SEQUENCE
October 2015
v10t900
Project Complete
SCHEDULE SEQUENCE
October 2015
v00t900
SITE LOGISTICS
v10-v12
Field Office
Access Lane
Crane
Site Fence
v01t430
Cornell Office
Subs
Staging
Gate
Excav.
v40t420
Field Office
Fence west of Curb
3-0 Bump Out for Crane
v01t500
Cornell Office
Subs
Staging
Gate
Klarman Hall
v40t500
RISK ASSESSMENT
v10-v12
Risk Assessment
1. Work Adjacent to Historic GSH
Safe Egress
Noise / Dust
Risk Assessment
2. Building Excavation
Underpinning
Start as Early as possible
Prepare for Unknowns
Mass Excavation
Start over Winter Break
Rock Excavation
No Blasting within 20
Vibration Expectations
Existing Condition
EXCAVATION SECTIONS
Today
EAST AVENUE
833
813
v70t000
Excavation to Rock
EXCAVATION SECTIONS
February 2014
CRANE
833
Bank Retention
800 - 803-9
Underpinning
v70t416
Pit Excavation
EXCAVATION SECTIONS
April 2014
CRANE
833
800 - 803-9
v70t436
Existing Condition
EXCAVATION SECTIONS
Today
EAST AVENUE
833
GOLDWIN SMITH HALL
813
v71t000
Excavation to Rock
EXCAVATION SECTIONS
April 2014
CRANE
833
800-0
Bank Retention
Dewatering
775-9
Underpinning
v71t436
Existing Condition
EXCAVATION SECTIONS
Today
VAULT
STORM
SEWER
STORM
SEWER
813
v72t000
Pit Excavation
EXCAVATION SECTIONS
April 2014
800-0
SOUTH 792-1
(DEEPEST AT 782-1)
NORTH 788-7
(DEEPEST AT 775-9)
Underpinning
v72t436
Risk Assessment
3. Traffic Control
Crosswalk
Possibly Adjust Location of Crosswalks for Visibility
ENTRY
GATE
Truck Route
SITE LOGISTICS
During Construction
PLAN VIEW
Route 2
Route 1
v09t456
During Construction
Risk Assessment
4. LEED Platinum Certification
Risk Assessment
4. LEED Platinum Certification
Construction Requirements
Regional Materials
Recycled Materials
Waste Recycling
Indoor Air Quality
Risk Assessment
5. Schedule
Monthly Updates
Subcontractor Buy In
Impact Mitigation
Prompt Recovery Plans
Risk Assessment
6. BIM Coordination
Challenge: Coordinate concrete, steel, fire
protection, plumbing, HVAC & electrical trades.
Non-traditional chase stack.
Risk Assessment
7. Stone Cladding
Installation
Handling & Hoisting Inside Building
Risk Assessment
8. Enclosure Coordination
Scope
Carefully Define Scope with Other Trades &
Gartner
Envelope Commissioning
Risk Assessment
9. Site Constraints
Risk Assessment
10. Hoisting & Material Handling
Risk Assessment
10. Hoisting & Material Handling
KLARMAN HALL
Risk Assessment
Assumed Enabling Work
Questions