Beruflich Dokumente
Kultur Dokumente
A COMPANY OF
George Hintzenweg 85
Postbus 8520
Rotterdam 3009 AM
The Netherlands
+31 (0)10 443 36 66
Telephone
Fax
info@rotterdam.royalhaskoning.com
www.royalhaskoning.com
Arnhem 09122561
Document title
Drafted by
Checked by
Date/initials check
Approved by
Date/initials approval
G. Bosman
A. Woods
23/06/2009
H. Altink
24/06/2009
E-mail
Internet
CoC
CONTENTS
Page
1
INTRODUCTION
INSTRUCTIONS
3.1
Harbour construction stages
3.1.1
Harbour construction stages
3.2
Engineering instructions
3.2.1
Specific Instructions for Engineering of the Breakwater
3.2.2
Specific Instructions for Engineering of Berth 4
3.3
Procurement instructions
3.3.1
General
3.3.2
Expediting
3.3.3
Logistics
3.3.4
Spare parts
3.3.5
Surplus Equipment and Materials
3.3.6
Material Controls
3.4
Cost Control Instructions
3.5
Construction and Commissioning Instructions
3.5.1
Specific Instructions for the Construction of Berth 4
3.5.2
Specific Instructions for Dredging
3.6
Preliminary Program and Execution Plan
3.6.1
Completion of works
5
5
5
5
5
5
6
6
7
8
8
8
9
10
10
10
11
13
13
-i-
9R4944Q0/0426/902503/Rott/Rev0
23 June 2009
INTRODUCTION
This document describes the Contract Program and Execution Plan for the
Works of the new Azzawiya Oil Harbour. This document is for information
only and supports the Volume I Invitation to Bidder.
The relation of this document to the complete set of Bid Documents is given
below:
BID DOCUMENTS AZZAWIYA OIL HARBOUR:
VOLUME I - INVITATION TO BIDDER
VOLUME II - OWNER'S REQUIREMENTS
Exhibit A Scope of Works
Exhibit B Compensation of Payment
Exhibit C1 Performance Specifications and Design Criteria
Exhibit C2 Technical Data and Specifications
Exhibit D Drawings
Exhibit E Contract Program and Execution Plan (this document)
Exhibit F Coordination Procedures
Exhibit G Guide to Safety Regulations in the ARC Refinery Facilities
VOLUME III - SITE INFORMATION
9R4944Q0/0426/902503/Rott/Rev0
-1-
23 June 2009
2.1
9R4944Q0/0426/902503/Rott/Rev0
-2-
23 June 2009
The analysis shall also address the timing of handing over of working areas
from the Contractor.
Activity number
Description of work
Area of work to be performed
Duration (workdays)
Code number referring to applicable specification section
Early start date (calendar)
Late start date (calendar)
Early finish date (calendar)
Late finish date (calendar)
Total float (workdays)
Estimate crew and gang sizes size.
Logic diagrams shall be based on precedence of work item logic and shall
show activities and milestones. Each activity shall display the activity
number, description duration in work and total float. Blank spaces shall be
provided for recording of actual start and finish dates. The critical path shall
be clearly marked.
Material procurement items and sequences shall not be displayed on the
logic diagrams, but shall be handled as outlined below.
Once the initial CPM Programme has been approved, it shall not be
changed, amended or varied without the approval of the Engineer. The
Contractor shall record the actual starts and finishes and remaining durations
and, using this data, shall update the computer analysis.
The updated mathematical analysis shall be accompanied by a narrative
report and shall be used by the Engineer as a basis for evaluating any
request by the Contractor to change, amend or vary the CPM Programme.
Revisions to the schedule logic shall be provided by the Contractor on the
occurrence of any of the following events:
A change in work sequence instituted by the Contractor.
The initial CPM Programme has been delayed by more than thirty (30)
calendar days.
An instruction is given by the Engineer which will significantly affect the
progress of the Works.
As necessary in order to accommodate the Work carried out by other
contractors.
9R4944Q0/0426/902503/Rott/Rev0
-3-
23 June 2009
The Contractor shall perform the Work in accordance with the approved
Programme. If any Work is found not to be on schedule during any regular
review of the Works the Contractor shall immediately advise the Engineer in
writing of action proposed to bring the Works up to schedule and shall submit
a revised Programme indicating such action, together with a typed list of such
revisions. Correction and updating of the Programme will be done as often as
necessary until the Works are on schedule.
Float shall be utilised so as to complete the Works on time. Any existing float
shall be used to the maximum extent possible to offset unexpected delays to
the Works.
In the event of the Contractor failing to submit a CPM Programme or
submitting a CPM Programme which is not in compliance with the
requirements of this Clause the Engineer shall be entitled to employ and pay
other persons to carry out the same. All expenses consequent thereon or
incidental thereto shall be recoverable from the Contractor by the Owner, or
may be deducted by the Owner from any monies due or which may become
due to the Contractor.
2.2
9R4944Q0/0426/902503/Rott/Rev0
-4-
23 June 2009
INSTRUCTIONS
3.1
3.1.1
3.2
Engineering instructions
3.2.1
3.2.2
9R4944Q0/0426/902503/Rott/Rev0
-5-
23 June 2009
3.3
Procurement instructions
3.3.1
General
3.3.1.1
The Contractor shall provide all personnel and be solely responsible for all
Procurement activities associated with delivery of the Work, ensuring that all
enquiry and purchase requisitions are processed correctly and on schedule.
3.3.1.2
3.3.1.3
3.3.1.4
3.3.1.5
The Contractor shall be responsible for the provision of all first fill material,
oils, chemicals, catalysts, refrigerants, etc, as required and agreed by the
Owner, and for their continued replenishment if necessary up to hand over of
the Work.
3.3.1.6
3.3.1.7
9R4944Q0/0426/902503/Rott/Rev0
-6-
23 June 2009
3.3.1.8
The Contractor shall plan all cargo loads to minimize risk of loss for any
single component of the Work.
3.3.1.9
3.3.1.10 The Owner reserves the right to periodically audit the Contractors
procurement process to ensure compliance with agreed procedures.
3.3.1.11 The Contractor shall maintain all records of all materials procured and all
tests carried out, for information and provide these to the Owner upon
request, and in the Handover dossier. Procured surplus materials shall be
removed by the Contractor at the finish of the works, unless the Owner
requests in writing to purchase these surplus materials.
3.3.1.12 The Contractor shall handle all procured materials with proper care, and
comply fully with the guidelines set by the manufacturer, with regards to
storing, stacking, lifting and preservation prior to use.
3.3.2
Expediting
3.3.2.1
9R4944Q0/0426/902503/Rott/Rev0
-7-
23 June 2009
3.3.3
Logistics
3.3.3.1
3.3.3.2
3.3.3.3
3.3.3.4
The Contractor shall be responsible for inspecting all shipments at the time of
off loading, at Site or port of entry, giving adequate notification to the Owner
for participation in the inspection.
3.3.3.5
3.3.4
Spare parts
3.3.4.1
3.3.5
3.3.5.1
3.3.5.2
3.3.5.3
9R4944Q0/0426/902503/Rott/Rev0
-8-
23 June 2009
3.3.6
Material Controls
General
3.3.6.1
The Contractor shall submit procedures within thirty (30) Days of the
Effective Date for material control, and implement them throughout all stages
of the Contract. The Contractor shall use computerized systems for material
receipt, issue allocation and stock control. The system shall have the ability
to trace an item from origin to issue.
3.3.6.2
Import and receive all items delivered to the Site, unload, unpack,
inspect, store and protect same.
(b)
Ensure that all Materials are used correctly and no Materials are
substituted without prior Approval.
(c)
(d)
(e)
(f)
(g)
(h)
Implement a Surveillance
Subcontractors.
and
Inspection
System
for
Storage
3.3.6.3
9R4944Q0/0426/902503/Rott/Rev0
-9-
23 June 2009
3.3.6.5
3.4
3.5
3.5.1
9R4944Q0/0426/902503/Rott/Rev0
- 10 -
23 June 2009
Place the piles for the first part of the access trestle (no
superstructure yet) as a preparation for the second stage;
o Stage 2:
- Construct the access trestle to berths 5 and 6;
- Install the electrical equipment at the dolphins at jetty 4;
- Install the piping for Berth 4 on the access trestle and following
remove the piping on top of the breakwater;
- Remove the temporary road- and pipe bridge connecting the
turning platform with the breakwater;
3.5.2
9R4944Q0/0426/902503/Rott/Rev0
- 11 -
23 June 2009
Area
Construction stage 1
Construction stage 2
NA
Berth 5
Berth 4
NA **
NA
NA
Berth 6
inner
Quay
NA
Full
walls
* These areas have been partly dredged during construction stage 1. As the
design vessel of construction stage 2 for these areas is more significant
than that of construction stage 1, these areas need to be expanded and
deepened.
** Harbour area D has already been fully dredged during construction stage
1.
9R4944Q0/0426/902503/Rott/Rev0
- 12 -
23 June 2009
3.6
3.6.1
Completion of works
The Works (construction stage 1 and 2) shall be completed within 36 months
after the Effective Date.
Construction stage 1 shall be completed within 20 months after the Effective
Date.
The programme and execution plan are to compiled and issued in
accordance with the Owners Requirements. (see Volume 1 Invitation to
Bidder)
=o=o=o=
9R4944Q0/0426/902503/Rott/Rev0
- 13 -
23 June 2009