Beruflich Dokumente
Kultur Dokumente
: 3776/GC13112800
CONTRACT TITLE: -
DOCUMENT TITLE :
ENGINEERING CONSULTANT:
COWI
DOHA, QATAR
DOHA, QATAR
18-Feb-15
DATE
REV.
NO.
DOCUMENT NO:
3776
DGEN
14
ASBA
MOSA
GTJ
PREPARED
CHECKED
APPD.
0004
SHT
01
OF
23
APPD.
Q.P.
REV
TABLE OF CONTENTS
1
SCOPE OF WORK
REFERENCE DRAWINGS
TECHNICAL SPECIFICATIONS
DOCUMENTATIONS
16
18
EXAMINATION
19
EXECUTION
20
Rev # 0
Page 2 of 23
SCOPE OF WORK
This Specification document covers the technical requirements for the design, manufacture, test and
commissioning of Building Management System (BMS) equipment, which shall be supplied in the
Dukhan Field Area.
The proposed Building Management System shall monitor & control the A/C (Split Unit / Package
Unit), Fire & Gas Control Panel, PA/GA Control Panel, LV Switchgear, UPS Status, Temperature &
Humidity of Telecom Equipment Room, Exhaust Fans. The system shall send the corresponding
signals to the Proposed BMS Server in Dukhan Township Substation 1, where the BMS Server shall
be integrated with the SCADA System at high level (software) to receive all BMS Alarms / Signals for
Monitoring at SCADA Workstations.
The contractor shall provide BMS server hardware and management software. The proposed BMS
server shall be located in the Existing building (DTS-1). It will be the contractors responsibility to
seamlessly integrate the BMS system with the existing SCADA System. There will be no workstations
in either side (proposed buildings & DTS-1) in the design. The system installed in the four buildings
shall work in standalone modes, even when there is no network connectivity with the Server in the
DTS-1 building.
The BMS shall be configured with an open, non-proprietary communications protocol, such as
BACnet at all management level components, integration control panels, and plant controllers utilizing
the QP Corporate LAN for data transfer and communication. The proposed BMS Controllers (Direct
Digital Controller) shall be mounted on the wall in Telecom Equipment Room. The Direct Digital
controllers shall connect to IT LAN Switch through Ethernet CAT-6 Cable to transfer data to Proposed
BMS Server (at DTS-1) through QP Corporate IT Converged LAN. The proposed BMS Server shall
generate and send the SMS to the concern QP Engineer in case of Power Supply Failure. The proposed
BMS Controllers (DDCs) shall either have setting display screen to configure and monitor the Input
Data or it can be configured through portable operator terminal and shall be functioned stand-alone
without having Workstation or Server in the Telecom Equipment Room.
The provision of a fully functioning BMS System that shall undertake the monitoring and control of
the unmanned potable water pumping stations which shall include but shall not be limited to the
following monitoring and control functions:
The monitoring and control of the air-condensing units, fan coil units, extract
fans and other miscellaneous fans used for the distribution of airflow as detailed
in the points schedule, relevant control schematic and MEP specifications.
The monitoring of the Building fire alarm system. The fire alarm system shall
interface to the BMS through volt free contacts. Common trouble, alarm and
power status are to be monitored by the BMS.
The monitoring of the Facility UPS. The UPS functions shall be monitored by a
controller that shall interface to BMS through a BACnet/IP to third party
gateway.
Monitoring of Building Electrical equipment including LV Switchgear.
Rev # 0
Page 3 of 23
Monitor and control other points as described in the data points schedule,
control schematic, specifications and the mechanical and electrical drawings and
specifications.
The BMS shall be a turnkey installation and shall include the integration of the building services
systems as detailed in these specifications. The BMS shall comprise, at minimum, the following
components:
All interlocking and control relays, equipment enclosures and other components,
materials and services required for a completed and fully operational turnkey
BMS installation meeting these specifications.
Fully networked
Real time
Distributed processing
All data shall be available as BACnet objects at the Management level network
The BMS shall be configured to ensure reliability of systems operation and control of critical
functions/systems. In general, all monitoring and control of separate systems shall be achieved via
single control panels. Critical inputs of a system shall be wired directly to the controlling panel.
Where required, dedicated control panels shall be provided and shall not share any point monitoring or
control with other systems.
All installation work requirements shall be agreed and approved by QP Engineer on site.
Rev # 0
Page 4 of 23
The design / manufacture of the devices shall, unless otherwise specified, confirm to the latest edition
of the following Codes, Standards, Specifications and Regulations.
2.1
The equipment shall confirm in design, materials and performance with the requirements of following
QP and international standards listed below.
Standards list is provided as a guide only and does not in any relieve the vendor of the requirement to
comply fully with another appropriate standards. It shall be noted that the standards used shall be those
ruling on the tender issue date.
In the event of conflict, the order of precedence shall be:
This specification
QP's Standards
International Codes/Standard
Any conflict detected by the BMS system integrator, between the above codes will be
noticed to QP together with the resolution as selected by the Vendor according to the
above order of precedence. Any instances of non-compliance must be notified by the
BMS system integrator to QP and their approval obtained prior to implementation of the
work.
2.1.1
2.1.2
UL 50 & 486A
IEC 60849
BS 6701:2010
UL 864
Rev # 0
Page 5 of 23
BS 6259:1997
2.2
ABBREVIATIONS
A/C
Air Conditioning
ANSI
ASHRAE
BS
British Standard
BMS
DDC
DTS-1
DOMB
FAS
HMI
IEC
I/O
Input / Output
LAN
LON
ODBC
OEM
PCI
QP
Qatar Petroleum
TCP/IP
UPS
VFC
VFD
VSD
Rev # 0
Page 6 of 23
BACnet
- This term is used to imply that BACnet devices (i.e. the BMS controllers
and Servers) only communicate in BACnet protocol and do not require a
gateway for protocol conversion.
2.3
DEFINITIONS
REFERENCE DRAWINGS
The following project documentation shall be read with and form part of this
specification..
3776-KAHM-9-KC-0003 (Khatiyah Main Potable Water Pump Station BMS System Schematic Diagram)
Rev # 0
Page 7 of 23
3776-KAHM-9-KC-0009 (Khatiyah Main Potable Water Pump Station - BMS System Layout)
3776-UBAB-9-KC-0003 (Umm Bab Potable Water Pump Station - BMS System Schematic Diagram)
3776-UBAB-9-KA-0001 (Umm Bab Potable Water Pump Station - BMS System Data
Points Schedule)
3776-UBAB-9-KC-0008 (Umm Bab Potable Water Pump Station - BMS System Block
Diagram)
3776-UBAB-9-KC-0009 (Umm Bab Potable Water Pump Station - BMS System Layout)
3776-FHSP-9-KC-0003 (Fahahil SP Potable Water Pump Station - BMS System Schematic Diagram)
Rev # 0
Page 8 of 23
TECHNICAL SPECIFICATIONS
BMS Controllers (DDCs) shall be provided inside the Telecom Equipment Room in all
three new proposed PS buildings and New Chlorination Dioxide Dosing Building at
Jabel Tank Farm and shall be linked to the Proposed BMS server located in DTS-1
through QP IT Converged LAN.
The new proposed BMS shall be interfaced with the existing SCADA System
(Implemented under LC-10101900) at DTS-1 Building at high level (software) to
receive all BMS Alarms / Signals for Monitoring at SCADA Workstations. The
approved specialist shall undertake to carry out mapping of BACnet objects as detailed
elsewhere.
All field equipment shall have minimum ingress protection of IP65 and control room
equipment with a minimum of IP42.
Rev # 0
Page 9 of 23
o
o
o
o
o
o
o
detailed. The contractor shall also detail the location of controllers, the specific
point connection numbers, and wiring details for all additional unused point, both
analogue and digital and inputs and outputs.
If applicable, Damper end switches shall verify damper blade position and not
damper motor position.
All reports generated by BMS including summary, or status report shall be
downloadable to a usable format such as Lotus, Excel, standard graphics packages
or other state of the art software available at the time system is commissioned.
The BMS system shall be designed for industrial environments where advanced
technology coupled with very high system availability is demanded.
The equipment shall be of solid-state type, multi-microprocessor based, modular /
expandable and programmable.
BMS system shall be controlled by special software to enable easy configuration
and self-diagnostics. A user friendly set-up and checking routine shall provide
system management and programming through interfaces.
It shall be contractors responsibility to provide the necessary up gradation or
additional equipment, reconfiguration of existing SCADA Server to add the new
devices, licenses required for all new devices etc. to make BMS System in working
condition with the coordination of LC10101900 Contractor and QP Engineer. The
contractor shall also supply, install, test and commission new proposed BMS Server.
All proposed BMS system equipment and their installation must be compliance with
ASHRAE Standards.
The system integrator shall ensure the newly proposed system is completely
interconnected to the existing network.
The BMS System components in potable water pumping stations shall consist of :
BMS Server
BMS Controller
Damper Actuator
Temperature & Humidity Sensors
Differential Pressure Switch
Fire Alarm Interface
Auxiliary Control Devices
Telecommunication Cable (Hard-wire)
4.1
BMS SERVER
The proposed BMS Server should have the following features:
Rev # 0
Page 10 of 23
Real Time Energy Management: Energy logs, demand limiting, optimum start,
tenant activity and billing provide valuable insight and control into energy planning
and consumption.
Energy Dashboard: Energy consumption and other vital building data displayed
visually for sharing with SCADA and should support LEED and other sustainability
initiatives.
Users and Groups: Can create custom start displays for individual users or groups of
users; restrict access to an authorized role or devices on a campus without having to
use multiple server; quickly change group membership on the fly by adding and
subtracting individual users to a group.
SQL Server Scalability: Enable users to utilize third-party reporting software such
SQL Server or Crystal Reports etc.
Display Capability: Unlimited 3D, animated custom data displays and resolution can
be customized to suit any requirement and easily updated for equipment additions,
moves and changes dependent only on hard disk space and graphics hardware.
Rev # 0
Page 11 of 23
4.2
Alarms: Alarms display regardless of currently running application. Dial out alarms
to remote sites or modems. Customize alarm handing based on alarm type.
Optimum Start: Self-tuning optimum start algorithm adjusts equipment start time
based on environmental factors, achieving optimum space conditions for occupancy.
Auto Archiving: Automatically auto-archive trend logs, energy logs, user activity
and alarm history.
Job Merge: Restore Utility automatically merges jobs when adding new devices,
displays, buildings etc.
The proposed BMS Server shall be used for database as well as application
software.
4.3
BMS CONTROLLERS
The BMS controller (DDC) shall have the following features:
Rev # 0
Page 12 of 23
4.4
The device shall be programmable and capable of extensive measuring, control and
monitoring functions.
It shall support modular architecture with distributed I/O Modules to accommodate
Input / Output points.
Energy management programs such as optimum start/stop, load reset, duty cycling,
night purge, distributed demand control and others must be resident on DDC.
In no circumstances shall a multiple DDCs be employed to control a single piece of
equipment, if applicable.
There shall be Ethernet Interface to connect it with Centralized Fire & Gas
Monitoring System in DTS-1 Building at Dukhan QP Site.
Analogue inputs shall have a minimum resolution of 24 bits. DDC outputs shall be
binary for On-Off control, and true variable voltage (0 12c) for driving analogue
devices.
DDC shall provide a trend logging feature which can trend and store a minimum of
25 different data point simultaneously.
DDC shall have LEDs for continuous indication of all bus communications, power,
and operational status.
DDCs shall be provided where shown and specified with capacity to accommodate
input/output (I/O) points required for the application plus 25% spare points.
16 universal inputs with 12-bit resolution. Input 0 can be used for a BACtalk.
All inputs accept thermistor.
8 triac outputs rated 24V AC @ 0.25A with HOA.
8 analog outputs are driven by precision D/A Converter.
On broad, battery backed real-time clock, support schedules, trendlogs and timed
automation functions.
Rev # 0
Page 13 of 23
4.5
It shall be used for Monitoring filter, fan, fire damper, or air flow status of air
handling system.
Switching point easy adjustable with scale in Pascal
Direction of M20x1.5 conduit entry can be rotated in steps of 120 deg.
CE Approval according to low-voltage directive 2006/95/EC
Switch according to VDE 0630
EC Gas Appliance Directive 90/396/EEC
ROHS 2002/95/EC
Maxi. Operating Pressure should be 10 kPa
Pressure Media shall be Air, Non-flammable Gases and Non-aggressive gases.
Pressure Connections shall be two plastic tubes.
Switching Capacity shall be 1.5 A (0.4) / 250V AC
Electrical Connections shall be AMP connectors, or Screw terminals
Conduit Entry shall be M20 x 1.5
Protection Class IP 54
Mounting lugs shall be integrated in bottom housing
Medium Temp range is -20 to +85 C
Membrane Material is Silicone
Rev # 0
Page 14 of 23
4.6
DAMPER ACTUATOR
4.7
APPLICATIONS
Volume control dampers, mounted directly to the drive shaft or remotely (with the
use of accessory hardware)
Quarter turn rotary valves, such as ball or butterfly valves mounted directly to the
drive shaft
Liner stroke globe or cage valves mounted with linkages to provide linear actuation.
Proposed Actuation shall be used within heating, ventilating, and air-conditioning
(HVAC) systems. And should drive a variety of quarter turn, final control elements
requiring spring return fail-safe operation.
4.8
DATA POINTS SCHEDULE
BMS at a minimum shall monitor / control the following points:
EQUIPMENT MONITORING SIGNALS DETAILS
Sr.No
QTY
BMS CONTROLLER - 1
INPUT
Analog
Digital
(AI)
(DI)
1.1
1.2
OUTPUT
Analog
Digital
(AO)
(DO)
Rev # 0
Page 15 of 23
1.3
2.1
2.2
2.3
3.1
Filter Status
3.2
3.3
3.4
3.5
3.6
3.7
3.8
1
Y
Y
Y
Y
3.9
Space Temperature
3.10
4.1
Room Temperature
4.2
1
Y
Y
4.3
Humidity Level
5.1
Fire Alarm
5.2
6.1
System Healthy
6.2
Power Failure
Exhaust Fan (Battery Room)
7.1
7.2
7.3
7.4
H2 Sensor Status
7.5
7.6
Y
1
Y
Y
Y
Y
DOCUMENTATIONS
The following are the list of documentation required as minimum from contractor under this project.
Rev # 0
Page 16 of 23
5.1
MATERIAL SUBMITTAL
Material submittal shall include the following as minimum:
System Architecture as proposed with specific reference to interoperability,
describing locations and types of all controllers, workstations and server for Building
Management System.
Schedule of all equipment with model number, names of manufacturers and country
of origin.
Product data sheets highlighting the selected model of proposed equipment.
Product data sheets of all components, including BMS Controllers, BMS Server, all
Field Devices etc. and enclosures with dimensions shall be submitted.
Brief description of system operation, functions and control sequences.
Schedule of all equipment with model number, names of manufacturers and country
of origin
Software provider's license agreement stating limits on use, copying, and transferring
software.
Copy of contract specifications complete with clause wise compliance statement.
Pre-qualifications of the specialist system integrator and the proposed manufacturer,
including list of projects where system Integrator has implemented products from the
same manufacturer.
5.2
WORKSHOP DRAWINGS
The Contractor shall submit layout drawings complete with cable sizing, cable routing, containment
sizing, and location of equipment, power requirements and data ports for system components and
installation details of door hardware for QP approval, prior to proceeding with works on site.
Drawings shall also indicate requirements of back boxes, pull boxes, access panels, data, power etc.
The above information shall be provided to the MEP contractor on time as per the project programed
for providing containment and builder's works, and to the door suppliers for manufacturing doors with
all provisions as required by the specialist.
5.3
AS-BUILT DRAWINGS
Submit number of sets of final as-built drawings as indicated in the contract documents including the
above items marked up with labels of each component.
Rev # 0
Page 17 of 23
5.4
5.5
Descriptive data of all operating, user and application software including complete
operators manuals, programming manuals, and alphanumeric point name convention
sheet shall be provided.
Provide final documentation to serve the diverse needs of personnel concerned with
operation, procurement, installation and maintenance.
Operation & Maintenance manuals shall be complete with preventive maintenance
schedules, procedures and troubleshooting procedures.
TRAINING MANUAL
The Contractor shall submit at-least three weeks prior to training the complete training manual along
training schedule, training agenda covering training mode, duration, number of trainees in each session
etc.
The Contractor shall submit CV's of trainers, brief description of the installed system, preventive and
breakdown maintenance procedures for the training.
The Contractor shall also arrange the following trainings for QP Staff :
Operator Training
Admin Training
Maintenance Training
6
6.1
The manufacturer shall be fully qualified to complete the work mentioned in this specification and
drawings. Contractor to ensure that qualified manufacturer is selected to perform the work.
The system shall be engineered, commissioned and serviced by the manufacturer or manufacturer's
authorized systems integrator employing factory trained personnel for commissioning and after sales
support.
Materials and equipment shall be the catalogued products of manufacturers regularly engaged in
production of access control equipment and the products proposed shall be the latest versions
commercially available at the time of the bid.
The manufacturer shall be ISO-9002 and ISO 9001 certified for Quality Assurance in Production,
Installation and Servicing.
The systems integrator shall be an authorized partner to the manufacturer and the partnership shall be
at least two year old. The manufacturer systems integrator combination shall have successfully
implemented at least three projects of similar complexity in the State of Qatar.
Rev # 0
Page 18 of 23
The specialist shall obtain and submit a written undertaking from the manufacturer that the spare parts
of the system proposed will be made available upon request for at least 10 years from the date of
substantial completion. In addition, the manufacturer shall undertake to ensure forward compatibility
of the proposed equipment for at least 15 years.
6.2
The Contractor shall clearly state limitations of the proposed system in terms of
adding additional capacity. Particular attention should be given to the number of
additional slots (or blades) before which additional chassis would be required.
At the time of final system acceptance, all Access Switches shall have a minimum
of 25% reserve capacity, with the capability to double the capacity by simply adding
more switches.
The Contractor shall provide the spare parts 25% at a minimum and furnish a bill of
materials, catalogue numbers, unit prices, and a list of local distribution sources for
replacement parts. Required spares shall be on site at the time of final system
acceptance. The parts are to be inventoried at the beginning of the warranty period
and accounted for at the end of the warranty and service period. Any spare
parts unused at the end of the warranty and service period shall become
property of the QP.
EXAMINATION
Rev # 0
Page 19 of 23
EXECUTION
8.1
SUPERVISION
All works associated with implementation of the security system shall be carried out under the direct
supervision of a representative of the approved specialist systems integrator. Installations shall be
carried out by skilled technicians.
8.2
INSTALLATION
All installation activities shall be performed in a neat and professional manner in accordance with all
applicable local and national codes. Additionally, the Contractor and all subsequent Sub-Contractors
employed to satisfy the requirements of these specifications shall obtain, or satisfy, the following prior
to installation:
1.
2.
3.
Contractor shall install and inspect all hardware required in this specification in
Doc. No. 3776-DGEN-9-14-0004
Rev # 0
Page 20 of 23
Underwriters
Laboratories
(UL)
listing
for
restricted
access
installations in business and customer premises applications. This listing is
required by the National Electric Code for customer premise installations
2.
System installation and construction methods shall conform to the requirements of the QP IT
Corporate Standards.
Where undefined by codes and standards, Contractor shall apply a safety factor of at least two (2)
times the rated load to all fastenings and supports of system components.
Contractor shall install all system components including furnished equipment, and appurtenances in
accordance with the manufacturer's instructions, and shall furnish all cables, connectors, terminators,
interconnections, services, and adjustments required for a complete and operable system.
Rack Mounted Equipment:
1.
As a general practice, Contractor shall run power cables, control cables, and high
level cables on the left side of an equipment rack as viewed from the rear
2.
The Contractor shall run other cables on the right side of an equipment rack, as
viewed from the rear
3.
Contractor shall install all custom and packaged software in the development and production
environments.
Contractor shall provide a migration plan for all new and updated software to be migrated
from within the development environment to the production environment.
Final hardware selected and installation of hardware shall be submitted for review by the Project
Engineer. Additionally, the Contractor shall review the cabinets and equipment room to ensure
ventilation requirements are met or recommend modifications.
The contractor shall facilitate, configure, document and test all network connections required by
other systems or other facilities not in contract that require access to the network specified herein.
Contractor shall place materials only in those locations that have been previously authorized.
Any other locations shall be authorized, in writing, by the Engineer.
Rev # 0
Page 21 of 23
Contractor shall provide all tools, applications and test equipment required to install, verify,
and test the installation and to determine that it meets the specifications. The Contractor shall
furnish all necessary materials required to implement and to achieve the required work performance.
8.3
WORKSHOP DRAWINGS
Detailed engineering shall be the carried out by a factory trained engineer working with the approved
specialist systems integrator. Workshop drawings shall detail all cable types, conduits, backbox /power
requirements, mounting details etc. Workshop drawings submitted for QP approval shall be duly
signed and stamped by the specialist systems integrator. Detailed system schematic diagram showing
cable sizes and types, exact locations of devices, server, workstations etc. shall be submitted along
with the workshop drawings. Detailed lay out of the security control room complete with equipment
console and furniture shall be submitted separately for QP approval.
8.4
COORDINATION
The supervisor of installation shall be fully responsible for coordination with specialists integrators of
other systems to which the system has an interface or integration.
8.5
LABELING
A labeling scheme shall be submitted for approval of QP. All cables and devices shall be labeled to the
approved scheme.
8.6
CONTAINMENT
All wires and cable shall be installed in GI conduits or metallic cable trays. Sizing of containment shall
be carried out during detailed engineering to be carried out by the specialist. Containment shall be
sized such that a 25% spare capacity is available for any modifications to the system after handing
over.
8.7
GROUNDING
Each piece of electronic equipment shall be properly grounded before energizing. All wire shields
shall be grounded at the hub end only, not at the remote or device end. Ground system components &
conductor & cable shields to eliminate shock hazard & to minimize ground loops, common-mode
returns, noise pickup, cross talk, & other impairments.
8.8
All tests shall be carried out according to a detailed procedure duly approved by QP. The tests shall be
carried out in phases.
Cables are to be tested for any damage occurred during transportation to site and/ or during the course
of pulling-in and laying.
Pre-testing: Upon completing installation of the system, align, adjust and balance
the system and perform complete pre-testing. Determine, through the pre-testing, the
conformance of the system to the requirements of the drawings and specifications.
Correct deficiencies observed in pre-testing. Replace malfunctioning or damaged
Rev # 0
Page 22 of 23
8.9
items with new & retest until satisfactory performance & conditions are achieved.
Prepare forms for systematic recording of acceptance test results.
Report on Pre-testing: After pre-testing is complete, provide a letter certifying the
installation is complete and fully operable, including the names and titles of the
witness to the preliminary tests.
Final test notice: Provide a 10-day minimum notice in writing when the system is
ready for final acceptance testing.
Resetting: Correct deficiencies indicated by tests and completely retest work
affected by such deficiencies. Verify by the system test that the total system meets
the specifications and complies with the applicable standards.
TRAINING
Engage a factory-authorized service representative, whose credentials are approved by QP, to explain
programming and operation of system and to train Employer's maintenance personnel on procedures
and schedules for maintaining, programming, operating, adjusting, troubleshooting, and servicing
system.
Training shall be carried out to an approved training manual Separate training shall be provided on the
hardware and software. Each training shall have both class room session and hands on session.
Contractor shall allow for 6 trainees each in both the trainings.
Rev # 0
Page 23 of 23