Beruflich Dokumente
Kultur Dokumente
3
4
5
6
7
8
BETWEEN
9
10
11
(Claimant)
12
13
V.
14
15
CONSTRUCTION COMPANY
16
(Respondent)
17
18
I.
19
20
21
corporation organized and duly existing under Philippine laws engaged in sale
22
23
24
corporation organized and duly existing under Philippine laws and is engaged on
25
26
3. In October 2012, PEC entered into a contract with CC engaging the latter to
27
design, construct, commission, test complete and hand over the power station in
28
Pampanga.
29
30
31
32
33
PEC claimed that there were many technical design and construction defects in
34
35
36
37
38
39
40
41
by
arbitration
administered
by
the
Hong
Kong
42
43
44
45
46
47
48
49
50
51
filed a Notice of Arbitration with the Hong Kong International Arbitration Centre
52
53
(HKIAC).
9. On November 18, 2013 CC commenced its own arbitration proceedings against
54
PEC and submitted its Request for Arbitration to the Construction Industry
55
56
57
58
59
proceedings.
11. On November 25, 2013, the Manila Regional Trial Court granted CCs application
60
61
31.2 This clause and the parties agreement to arbitrate herein shall
62
63
64
II.
65
In response to the Notice of Arbitration, counsel for the defense respectfully submits
66
its objection on the jurisdiction of HKIAC for the following reasons, to wit:
67
68
69
70
wherein
71
72
12. Generally, when parties enter into a contract indicating therein terms and
73
74
governs the relationship between the parties, such that if theres any arbitration
75
agreement, the rules stated in the contract subject to the laws from which the
76
under
Philippine
law,
CIAC
has
77
13. This agreement however, is subject to limitations set by the national laws which
78
has jurisdiction over the parties. While we respect the competence of the
79
80
81
14. It must be noted that the issue in the case at bar involved construction disputes
82
83
84
15. The CIAC was created through Executive Order No. 1008 (E.O. 1008), in
85
86
87
88
89
90
the national labor force and is a leading contributor to the gross national product. 1
91
16. Basic as a hornbook principle is that jurisdiction is conferred by law and cannot
92
93
94
diminished by the stipulation, act or omission of the parties, as long as the parties
95
96
arbitration clause in the construction contract. 2 The parties upon agreeing that
97
98
divesting CIAC of its power to resolve and adjudicate disputes arising from
99
construction contracts. This cannot be permitted. It must also be noted that the
100
parties have agreed that the substantive law governing their contract is Philippine
101
law.
102
103
104
105
106
107
108
109
110
111
17. It bears stressing that the above-cited provision tells us that 1) any disputes
112
arising from or connected with construction in the Philippines are within the
113
original and exclusive jurisdiction of CIAC 2) that the only requirement to for the
114
CIAC to acquire jurisdiction is that the parties must agree to submit their dispute
115
to voluntary arbitration.
116
18. By vesting in CIAC original and exclusive jurisdiction over construction disputes
117
118
Hence, we reiterate that the exclusivity clause of the law precludes HKIAC from
119
assuming jurisdiction.
120
121
19. Moreover, under Philippine law, the exclusive jurisdiction of CIAC is further
bolstered by Sec 34 of RA 9285:
122
123
124
125
126
127
128
129
130
those between or among parties to, or who are otherwise bound by,
131
132
133
134
construction project.
135
136
137
138
20. The basic objective of arbitration is to provide a speedy and inexpensive method
139
of settling disputes by allowing the parties to avoid the formalities, delay, expense
140
141
litigation which goes through the entire hierarchy of courts. 4 Both the claimant
142
and the respondent are Philippine based companies. Hence, it is not only
143
practical but also in accordance with the objective of voluntary arbitration that in
144
145
146
expensive, US courts have found such agreements unconscionable and for that
147
148
149
foreign venue which makes it prohibitively expensive. In such case, the court
44 Alternative Dispute Resolution Act of 2004 Annotated, Atty. Custodia O. Parlade, 2004 p
5492-493
150
may compel arbitration but under the domestic arbitration law and in a more
151
152
22. Assuming arguendo that the HKIAC has jurisdiction, it only serves as an
153
alternative forum to which if a party elected to submit their dispute before the
154
155
23. As a matter of fact, the jurisdiction of CIAC was enunciated in the Philippine
156
Supreme Court, Rather, it is plain and clear that as long as the parties agree to
157
158
their agreement will fall within the jurisdiction of the CIAC, such that, even if they
159
specifically choose another forum, the parties will not be precluded from
160
electing to submit their disputed before the CIAC because this right has
161
been vested upon each party by law, i.e. E.O. No. 1008. (China Chang Jiang
162
163
164
165
166
167
168
24. Under clause 31.10, it is stated that to the extent permitted by applicable laws or
169
170
65 Ibid p 502
171
Resolution Act of 20014 and other laws shall not be applicable to the agreement
172
and is thereby irrevocably waived by the parties. These are the very substantive
173
174
31.3 PEC and CC hereby expressly agree that, to the fullest extent
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
Alternative
191
192
193
194
31.10
Dispute
Resolution
Act
of
2004,
relating
to
195
196
197
198
199
200
201
submit
202
203
204
rule that when laws or rules are clear, it is incumbent on the court
205
206
207
208
209
210
211
facto vested the CIAC with jurisdiction. This rule applies, regardless
212
213
214
215
216
217
218
an
existing
or
future
controversy
to
CIAC
219
220
221
xxxx
222
223
224
225
226
227
228
229
230
231
232
26. If the parties have expressly agreed that the substantive law of the Philippines
233
shall govern, they shall not be permitted to divest the laws specifically mandated
234
to govern them.
235
purpose of establishing order and when they fail in this purpose they become the
236
237
238
24. In light of the foregoing, given that the claims of the parties shall be resolved
239
by the CIAC, respondent CC prays to the honorable tribunal to dismiss the claim
240
and respect the anti-suit injunction issued by Manila Regional Trial Court on
241
242
25. Equity dictates that where the proceeding is oppressive and vexatious, an
243
244
245
must be respected.
246
26. In fact, pursuant to Cap 609 Sec 45(2) of Arbitration Ordinance, the
247
248
249
250
Court
251
252
253
interim measure.
may,
in
relation
to
any
arbitral
254
255
256
basis. Broadly speaking, the court will grant an anti-suit injunction when it is just
257
258
jurisdiction will be exercised with caution (Airbus Industrie CIE v Patel &
259
Ors [1999] 1 AC 119, applied in China Reit Ltd v Su Ping & Others [2007] HKEC
260
576).
261
262
263
27. According to Margaret L. Moses in her book, The Principles and Practice of
264
265
is stated that Although traditionally an arbitrator might not have been expected
266
to take into account the law of the enforcing jurisdiction when rendering an
267
award, increasingly, this is changing with regard to regulatory areas that fall
268
269
270
271
272
273
parties appearing before them, and have not generally assumed duty to enforce
274
the public interest, the duty to render an enforceable award in case involving
275
276
tribunal that does not consider the public interest in ways expected under
277
the enacted statutes, at issue in the arbitration risks offending the public
278
279
These decisions indicate that courts, xxx expect an arbitrator to have obligations
280
28. It cannot be denied that a contract involving the construction of a power station is
281
282
283
apply mandatory laws, in this case, the E.O. 1008, because public interest so
284
requires.
285
29. The so called equity clauses mandate that the arbitrators shall decided
286
287
288
Relief sought
289
2901. Finally, it is submitted that jurisdiction is conferred by law and not by the will of the
291
parties. It is the law that imposes upon the parties the limits on which it can be
292
2932. WHEREFORE, we pray that the tribunal immediately dismiss the arbitration
294
proceedings, resolve the question as to its jurisdiction and recognize the anti-suit
295
296
297DATED: 30 August 2015
298
299
300
76 Law and Practice of International Commercial Arbitration, Alan Redfern et. Al, 2004. Pp 1408141
301
Rm
302
303
210,
AUF
Professional
School,
Mac-Arthur