Beruflich Dokumente
Kultur Dokumente
CAPITAL ESTIMATE
1.1.
Cost Index
Most cost data which are available for immediate use in a preliminary or
predesign estimate are based on conditions at some time in the past. Because price
may changes considerably with time due to changes in economic conditions, some
method can be used for updating cost data applicable at a past date to costs that are
representative of conditions at a later time. This can be done by using cost index.
Cost index is numerical values that reflect historical change in engineering
costs. The cost index numbers are dimensionless, and reflect relative price change in
either individual cost items such labor, material, utilities; or groups of costs such
consumer prices, producer prices. Indexes can be used to update historical costs with
the basic ratio relationship as follows;
C2 =C1
I2
I1
()
where,
C1
C2
I1
I2
is gotten from the CEPCI Online. However, the available data for 2015 is only for the
range year between 2004-2013. The Table 1.1 below shows the data for cost index
from 2004 to 2013.
Table 1.0.1. Chemical Engineerings Plant Cost Index
Year
2004
2005
2006
2007
2008
CEPCI
444.2
468.2
499.6
525.4
575.4
Year
2009
2010
2011
2012
2013
CEPCI
521.9
550.8
585.7
584.6
567.3
Using the data above, we can projected annual cost index in year of 2018.
Projections made by the cost growth index, based on data annually. First, we can plot
it as Figure 1.1 below. Then , we get the equation y = 14.4 x 28,389. So, for
estimate annual cost index in 2018, we can use that equation.
700.0
600.0
500.0
400.0
CEPCI
300.0
200.0
100.0
0.0
2002
2004
2006
2008
2010
2012
2014
Year
Figure 1.0.1. Chemical Engineerings Plant Cost Index Graphic
(Source: CPCEI Online, 2015)
By extrapolating the data and graphic, we can get a cost index value of 670.2 on
2020, as stated in Table 1.2 below:
Year
2014
2015
2016
2017
2018
CEPCI
612.6
627.0
641.4
655.8
670.2
1.2.
Direct Cost
Direct cost is the cost that is experience depreciation in the equipments. Direct
is consist of total bare modul cost, bulk material cost (piping, valve, electrical,
instrumentation, installation etc), site development cost, building cost and offsite
facilities cost.
1.2.1. Total Bare Modul Cost
To obtain an estimate of the capital cost of a chemical plant, the costs
associated with major plant equipment must be known. The calculation of total bare
module cost is begun with the calculation of purchased equipment cost. FOB (Free
On Board) is the bases cost of the purchased equipment cost. This is based on the
parameter of each equipment. The parameters and the formula we can see in Process
and Product Design Principles by Seider exactly in the Table 16.32 or based on
current price quote from a suitable vendor.
Analyses of the total installed costs of equipment in a number of typical
chemical plants indicate that the cost of the purchased equipment varies from 65 to 80
percent of the installed cost depending upon the complexity of the equipment and the
type of plant in which the equipment is installed. In other case, we can use bare
modul factor on the FOB purchase cost of the process equipment that is shown in
Table 1.3 to estimate total installation cost of process equipment. When these cost are
added to the purchase cost, Guthrie call the result the bare module cost instead of the
installed cost.
Using the design specification for all equipment, the purchase cost can be
determined, and later converted into 2018 purchase cost using the cost index. The
overall calculation is summarized on Table 1.4.
No
A
1
2
B
1
C
1
2
3
D
1
2
3
E
1
2
3
4
5
Equipment
Equipment Name
Code
Filter
F-101
Coarse Strainer
F-102
Multi Media Filter
Deoxygenation Tower
V-101
Deoxygenation Tower
Deaeration Vacuum Package
M-101
Ejector
P-102
Vacuum Pump
V-102
Deoxygenation Separator
Centrifugal Pump
P-101
Seawater Lift Pump
P-103
Booster Pump
P-104
Seawater Injection Pump
Reciprocating Pump
Oxygen Scavenger
P-105
Dosing Pump
P-106
Nitrate Dosing Pump
P-107
Biocide Dosing Pump
Corrosion Inhibitor
P-108
Dosing Pump
Hypochlorite Dosing
P-109
Pump
Qty.
Price/Unit
Total
Price
Bare Module
Factor
CTbm in
2018
Reference
2
2
$51,100
$36,000
$102,000
$72,000
2.32
2.32
$403,200
$284,100
Seider, 2003
$46,900
$46,900
4.16
$331,800
Seider, 2003
1
2
1
$5,600
$133,500
$3,600
$5,690
$267,000
$3,600
3.30
2.15
4.16
$18,500
$574,100
$25,500
Seider, 2003
1
1
1
$23,500
$17,900
$167,000
$23,500
$17,900
$167,000
3.30
3.30
3.30
$77,600
$59,100
$551,100
Seider, 2003
$8,700
$9,700
$8,700
$8,700
$9,700
$8,700
3.30
3.30
3.30
$28,700
$32,000
$28,700
$6,000
$6,000
3.30
$19,800
$3,400
$3,400
3.30
$11,200
1
1
1
1
1
Seider, 2003
No
F
Equipmen
Equipment Name
t Code
Chemical Injection Tank
1 T-101
2 T-102
3 T-103
4 T-104
1
1
Biocide Tank
5 T-105
Hypochlorite Tank
G
Hypochlorite Generator
1 CH-101
Qty.
Hypochlorite Generator
1
1
Bare Module
Factor
CTbm in 2018
$39,000
$39,00
0
1.41
$113,300
$47,600
$47,60
0
1.41
$138,300
$39,200
$39,20
0
1.41
$113,900
$44,800
$44,80
0
1.41
$130,100
$68,000
$68,00
0
1.41
$197,500
$55,000
$110,0
00
2.00
$220,000
Price/Unit
Total
Price
$4,358,500
Reference
Wallas, 1990
Alibaba, 2015
No
1
Controller
Pressure Control
Pressure Control
Valve
Level Control
Level Control
Valve
Flow Rate Control
Check Valve
Backwash Valve
Sludge Disposal
Valve
ESDV
Priority Panel
Portable Smoke
Detector
9
10
11
12
Note
Qty.
Pressure
5
Transmitter
Pressure
5
Indicator
2"
2
6"
3
Level
1
Transmitter
Level Indicator
5
Price/Unit
Total Price
$101
$510
$51
$260
$326
$1,223
$650
$3,670
$122
$120
$39
$200
$1,223
$1,220
$120
$840
$51
$360
4
3
4
2
12
$326
$1,223
$290
$710
$609
$1,300
$3,670
$1,160
$1,420
$7,310
6"
$609
$3,050
6"
2
2
$4,974
$7,260
$9,950
$14,520
$1,852
$5,560
6"
Flow Rate
Transmitter
Flow Rate
Indicator
1.5 "
6"
1.5"
6"
6"
Total
$55,800
The cost for piping covers pipe, fitting, supports, and other terms involved
in the complete erection of all piping used directly in the process. The cost of
piping depending upon the size of pipe or fitting and length of pipe. Calculation
for piping and fitting cost is shown in Tabel 1.6 and 1.7.
Table 1.0.6. Piping Cost
Size
(in)
1.5
6
10
Length
Wall
(in)
Thickness (in)
0.21
59.06
0.86
236.22
1.51
393.70
Total
Mass
(lb)
34
2,213
10,791
Mass
Price/ton
(kg)
15
$ 665
996
$ 686
4,856
$ 697
Total
Price
$10
$680
$3,390
$4,100
Type
Elbow 90o
Tee
Bend
Size (in)
1.5
6
10
6
10
1.5
6
10
Total
Qty.
35
15
8
4
2
12
6
4
Price/ unit
$98
$184
$227
$22
$24
$85
$153
$188
Total Price
$3,410
$2,750
$1,810
$90
$50
$1,020
$920
$750
$10,800
Requirement
Building Lamp
Outdoor Lamp
Panel Distribution Lighting
Transformation, metering
and protection system
UPS + Battery
LV Switchboard
Cathodic Protection
Qty.
Total
10
8
1
Unit
Unit
Unit
Lot
Price/Unit
$20
$20
$1,707
Total Price
$200
$200
$1,700
Lot
$36,321
$36,300
1
1
1
Lot
Lot
Lot
$88,850
$62,500
$25,500
$88,900
$62,500
$25,500
$215,300
In seawater injection plant, is used multi media filter to filter the solid
seawater. So we can estimate media filter that is used in multi media filter. The
type of media filter is antrachite, sand and garnet with volume that is shown in
Table 1.9. Media filter cost has been calculated and it shown in Tabel 1.9 with
volume and height in column that is gotten in sizing assignment.
Table 1.0.9. Media Filter Cost
Type
Media
Antrachite
Sand
Garnet
Height
(m)
0.2
0.5
0.2
Volume
Density
3
(m )
(kg/m3)
1.41
1,600
3.53
2,650
1.41
4,200
Total
Qty.
2
2
2
Price per
ton
$190
$80
$200
Total
Price
$430
$700
$1,200
$2,300
The other of bulk material cost that is used in seawater injection plant is
safety equipment such as APAR, safety sign and personal protective equipment.
And also, the installation cost like water installation, electrical installation and
hydrant installation is put in bulk material cost. Calculation for safety eqquipment
cost and installation cost is shown in Tabel 1.10 and 1.11.
Table 1.0.10. Safety Equipement Cost
Type
2
6
10
Price/ unit
$1,704
$370
$200
Total Price
$3,410
$2,220
$2,000
$148
$1,180
Qty.
APAR 25 Kg
APAR 6 Kg
Safety Sign
PPE standard Oil & Gas (Safety Shoes,
Safety Helm, Safety Glass, Ear Plug)
Total
$8,800
Installation Cost
Water Installation
Electricity Installation
Hydrants Installation
Total
$8,500
$6,500
$4,500
$19,500
bare module cost for grass plant root and equivalent 4-6 % of the total bare
module cost for brown plant root. In seawater injection plant, site development is
consist of prepare the steel platform for building modular deck. Cost of site
preparation of our plant can be seen at Table 1.12.
Table 1.0.12. Site Development Cost
Type
Floor 1
First
Floor 2
Area
Floor 3
Second Floor 1
Area
Floor 2
mass (kg)
10,219
10,219
8,942
3,194
3,194
USD/ton
3,850
3,850
3,850
3,850
3,850
Total Price
$39,300
$39,300
$34,400
$12,300
$12,300
$137,600
Utility Cost
2,694.54 kW
156.74 GPM
203 $/kW
58 $/GPM
$547,000
$9,100
Process Water
Air Instrument Compressor
Package
2.22 GPM
247 $/GPM
1
Lot
Total
$500
$25,000
$581,600
1.3.
Indirect Cost
Indirect cost is the cost that is not include depreciation in the investation or
Additional Cost
Equipment
Office Desk
Office Chair
Air Conditioner
Qty.
5
5
5
Price / Unit
$111
$67
$370
Total Price
$600
$300
$1,900
Locker
Computers
White Board
Cupboards
Telephone
Photocopy Machine
Fax Machine, Scanner and Printer
Total
1
5
5
5
5
1
2
$259
$630
$56
$150
$74
$1,000
$370
$300
$3,200
$300
$800
$400
$1,000
$700
$9,500
1.5.
Working Capital
Working capital is needed to cover operating cost that required for early
operation of the plant. Includes cash cost of inventories, net accounts receivable,
spare parts or supplies, and cash-on-hand. The working capital for an industrial
plant consists of the total amount of money invested in raw materials and supplies
carried in stock, finished products in stock and semifinished products in the
process of being manufactured, accounts receivable, cash kept on hand for
monthly payment of operating expenses, such as salaries, wages, and raw-material
purchases, accounts payable, and taxes payable. In general, it will be found to be
amount equal to 15 % of the total capital investment cost (C TCI) or or 17.6 % of
total permanent investment cost (CTPI). The calculation of working capital cost is
shown in Tabel 1.15.
1.6.
and working capital cost (CWC). However, total permanent investment (CTPI) is
total of total depreciable capital (CTDC) and additional cost like royalties and start
up cost. And also total depreciable capital (CTDC) is total of total direct cost (total
bare module, site development, buliding, and offsite facility cost) and total
indirect cost (engineering, contruction, contingency cost and contractor fee). The
calculation of total capital investment (CTCI) is shown in Table 1.15.
Type Cost
Kind of Cost
Additional
Cost
Working
Capital
Symbol
Cost
Note
CTBM
CBulk
Csite
CBuild
Coffsite
$3,358,500
$316,600
$137,600
$0
$749,500
Calculated
Calculated
Calculated
(no buliding office, etc)
Calculated
CDPI
$4,562,200
CTDC
$6,201,600
Royalties Cost
Plant Start Up Cost
Supporting Facilities Cost
Total Permanent Investment
Working Capital
Croyal
Cstartup
Csupport
CTPI
CWC
$124,100
$620,500
$9,500
$6,945,700
$1,222,700
(8% CDPI)
(10% CDPI)
(15% CDPI)
(3 % CDPI)
(CTDC = CDPI + Ceng + Ccontruction + Ccontingency
+ C contractor)
(2% CTDC)
(10% CTDC)
Calculated
(CTPI = CTDC + Croyal + Cstart up)
(CWC = 17.6 % CTPI)
CTCI
$8,183,400
Ceng
Ccontruction
Ccontingency
Ccontractor
$365,000
$456,200
$684,300
$136,900
1.7.
Figure 1.2, direct cost with pencentage of 56 % is the highest cost in capital cost.
The other cost like indirect cost, additional cost and working capital cost have
percentage value of 20 %, 9 % and 15 %.
Direct cost and Indirect cost breakdown is shown in Figure 1.3 and Figure
1.4. Based on Figure 1.3, Total bare modul cost with pencentage of 74 % is the
highest cost in direct cost. Based on Figure 1.4, contingency cost with pencentage
of 42 % is the highest cost in indirect cost.