Beruflich Dokumente
Kultur Dokumente
Abstract
Introduction
Based on the size of the dams, different hazard evaluations
have to be carried out in Austria. For example, for dams
taller than 15 m or dams with a volume of more than
500.000 m, flood wave propagations have to be
accomplished. In this case study, a dam-break flood analysis,
according to the ICOLD Bulletin 111, for a dam with the
height of 10 m and with a volume of 36.000m is carried out
due to this dams hazard potential.
The dam is used as an equalizing reservoir. The catchment
area is very small; thereby the only inflow to the dam is the
headrace tunnel, which has the same capacity as the outflow
(pressure tunnel turbines) or even the spillway. During an
inspection of the reservoir a bypass is used to operate the
hydropower plant. The dam is an embankment dam with
impervious coating on the upstream side of the dam.
140
discharge [m/s]
120
100000
100
80000
80
60000
60
40000
40
20000
20
0
0
-0,5
-0,4
-0,3
-0,2
-0,1
0,0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1,0
time [h]
Author
Froehlich
Costa
Molinaro
Peak value
213 m/s
208 m/s
234 m/s
Acknowledgements
Figure 3: Water flowing down on the triangulated terrain
model endangered area
References
Results
The result of the present study is the chronology of the flood
wave propagation with water depths and velocities. The
arrival times of the flood wave are nearly the same for all
scenarios. Within the first 15 minutes, very high velocities
occur mostly in inhabited areas. After 15 minutes, due to the
terrain slope, the velocities and the speed of the flood wave
propagation decrease.
After 6 hours of simulation, most of the water out of the dam
(106.000 m) is stored in the flooded area (approx. 3.000.000
m, 1-2 % with basements, 30.000-60.000 m) or transported
through the sewer system out of the area (capacity 2-3 m/s,
40.000-65.000 m). Due to the arguments mentioned above
the calculation is aborted after 6 hours.
Based on the results of the flood wave propagation, the
hazard/emergency planning for this dam on the owners side
and for the municipality involved is adapted.
Conclusion
The presented study was based on the ICOLD Bulletin 111
[1], which is very good guideline for dam break analyses.
For small dams the formulas mentioned in [1] lead to high
peak value of the dam failure hydrograph. The time spread
up to the peak is also estimated too long for small dams.
Furthermore, it is difficult to take care about the impervious
coating on the upstream side of the dam in the used software
because this material has a very high cohesion. At least in
the 2d numerical model of the flood wave propagation the
amount of stored water in basements or the out flown water
[1]
[2]
[3]