I.
LEARNING COMPETENCIES
At the end of the class, students are expected to:
A. Perform how to make a Multiple Wrapped Cable Splice.
B. Understand the importance of Multiple Wrapped Cable splice in electrical work.
II.
LEARNING CONTENT
A. Topic: Basic Splicing: Multiple Wrapped Cable Splice
B. References: Competency-Based Learning Material in Electricity , DepEd 2008, p. 25
C. Instructional Materials:
1. Visual aids
2. Electrical Tools & Stranded Wire #14
D. Strategies: Discussion, Demonstration
E. Skills: Splicing
F. Values: Appreciation, Patience, Hard work
III.
LEARNING STRATEGIES
Teachers Activity
A. Preparatory Activities
a) Prayer
Please stand up for our prayer. May I call on Ms.
______ to lead the prayer.
b) Greetings
Good afternoon class! How was your day?
Students Activity
B. Collecting of Assignments
Last meeting I have given you an assignment right?
Please pass it forward at count of 5. 1,2,3,4,5!
Yes maam.
D. Motivation
The class will be divided into two groups. We will play
a game. Are you familiar of the game Charades?
In this game, a representative from each group has to
"act out" a word without speaking, while their group
members try to guess what the word is. The group
who have guess the answer in a shortest period of
time will be announce as winner. Each group is only
given two minutes to guess the answer. Am I
understood?
Lets begin..
Let us give a hand to Group___ for winning this game
activity.
Based from our activity, have you come up an idea
what would be our lesson for today?
E. Presentation of Objectives
But before that, let me introduce to you our objectives
for todays lesson. Everybody please read
Yes, maam.
Yes, maam.
d) Analysis
What is the purpose of Split Cable Tap in electrical
work?
e) Application
The same groupings, perform at least one Plain
Tap and explain the steps on how you do your
output.
EVALUATION
Direction: Perform a Western Union Long Tie splice using the five steps. (10pts)
The students output will be evaluated based on the following:
CRITERIA
Execution of the proper procedure
1) Prepare stranded wire #14 as our main wire. Unskinned
the wire for about 5 inches and clean leaving 1 inch on
both ends of the wire with insulation.
2) The
Prepare
a wire
#14main
as our
wire and
unskinned
for
3)
strands
of the
wiretap
is divided
in half
by forcing
the screw driver through the center of the bared portion
of the main wire.
4) The strands of the tap wire is cleaned and fanning out
the strands so that they can be pushed around the space
in the main wire.
5) A space about 2 inches should be left between the main
POINTS
Allotted Gaine
d
5 pts.
4 pts.
Speed
TOTAL
1 pt.
10 pts.
V.
ASSIGNMENT
Note: Refer your answer in page 24 of the Competency-Based Learning Material in Electricity,.
In a sheet of paper, answer the following:
1. Identify the different types of forms used in electrical job.