Beruflich Dokumente
Kultur Dokumente
EFFICIENT ENERGY OF
TENNESSEE, LLC
Plaintiff,
)
)
)
v.
)
)
----
)
)
BAJA CONSTRUCTION COMPANY, INC.
COMPANY,
)
)
Defendants.
COMPLAINT
1.
2.
Baja is a California Corporation with its principal place of business at 223 Foster
3.
1
3396929.1
4.
substantial part of the events or omissions giving rise to the claims occurred in Wichita, Kansas.
5.
1s complete diversity of citizenship between Plaintiff and Defendants and the amount in
controversy exceeds $75,000.
6.
On or about September 27, 2013, EETN entered into an agreement with the
United States Department of Veteran's Affairs to serve as the prime contractor for the Tum-Key
Solar PV project at the Robert J. Dole Medical Center (the "Project"), a facility operated by the
U.S. Department of Veterans Affairs ("VA").
7.
On or about June 15, 2014, EETN entered into a subcontract agreement with Baja
(the "Subcontract"), that required Baja to design, fabricate, and install parking canopies for the
Project. A true and correct copy of the Subcontract is attached hereto as Exhibit A.
8.
After execution of the Subcontract, EETN paid Baja one hundred and thirty-one
thousand two hundred thirty-three dollars and sixty-one cents ($131,233.61 ), an amount equal to
ten percent of the Subcontract amount.
9.
The Subcontract required Baja, within ten days of the execution of the
2
3396929.1
10.
provided a performance bond (the "Performance Bond") in favor of EETN. A true and correct
copy of the Performance Bond is attached hereto as Exhibit B.
11.
The Subcontract requires timely completion of all work and makes Baja liable for
any damages resulting from a delay by Baja in performing the work. See Ex. A, at 4.
12.
under the Subcontract and its failure to correct such non-performance within five working days
following written notice from EETN constitutes a default under the Subcontract. See Ex. A, at
17. Upon default, EETN was permitted to terminate the Subcontract and complete Baja's work,
13.
14.
Engineering Consultants, P.A. ("PEC"), to review the design prepared by Baja. PEC confirmed
several deficiencies in Baja's work, including deviations from the applicable building code.
These observations were shared with Baja.
15.
On August 26, 2014, EETN provided written notice to Baja that it was in default
because its design was deficient and its work was behind schedule.
16.
On September 15, 2014, EETN noted that Baja's response to the observations of
3
3396929.1
material breach of the Subcontract. As a result, EETN was forced to terminate the Subcontract
and secure a replacement subcontractor to complete the work of Baja.
COUNT I
17.
BREACH OF CONTRACT
18.
performed its
Subcontract.
19.
Baja failed to fulfill its contractual obligations and failed to complete its work in
20.
Baja engaged in actions that resulted in delay and increased costs to EETN.
21.
The acts and conduct of Baja constitute a material breach of the Subcontract.
22.
amount not less than one hundred and eighty-one thousand four hundred thirty-eight dollars and
sixty-two cents
($181,438.62).
COUNT II
23.
24.
EETN timely notified Westchester of its claims against the Performance Bond,
satisfied all conditions under the Performance Bond, and made demand for Westchester's full
performance of its obligations under the Performance Bond.
4
3396929.1
25.
Despite demand, Westchester has refused to pay EETN for damages caused by its
principal, Baja.
Bond for which Westchester is liable to EETN in an amount not less than one hundred and
eighty-one thousand four hundred thirty-eight dollars and sixty-two cents ($181,438.62).
26.
27.
28.
Despite demand, Westchester has refused without just cause or excuse to pay the
full amount of EETN's performance bond claim. EETN has incurred and will continue to incur
substantial damages for the prosecution of this action, including but not limited to attorneys'
fees, and is entitled to judgment for those fees and expenses.
1.
That this Court grant Judgment in EETN's favor and against Defendants in an
amount not less than One Hundred and Eighty-One Thousand Four Hundred Thirty-Eight
Dollars and 62/100 ($181,438.62), plus pre-judgment and post-judgment interest at the highest
rate allowed by law;
2.
That this Court award reasonable attorneys' fees to EETN pursuant to K.S.A.
40-256;
5
3396929.l
3.
4.
That EETN be awarded such further relief as this Court deems appropriate.
Respectfully Submitted,
Dated: December
j_, 2015
By:
Pursuant to D. Kan. Rule 40.2, EETN designates Wichita, Kansas as the place of trial.
6
3396929.l