Beruflich Dokumente
Kultur Dokumente
Document review
Date
Name
Drawing number
Date
Checked
Approved
Status of approval
A
Approved
AN
Approved except Noted
RR
Returned for correction and Resubmission
The approval of the drawings will not exonerate the Contractor from any
responsibility in connection with the works
po:Koenig
2
1
Ind
2013-08-05
2013-05-25
Date
E. BLACHE
E. BLACHE
Prepared
N. KOENIG
JL. PEREZ
Checked
A. ROUSSIN
N. KOENIG
Reviewed
OBS
OBS
Status
CONCRETE WORKS
PREFABRICATION ANALYSIS
Originator
Issuer
Type
Type
Color
Black
EGYPTIAN FRENCH
NEW ASSIUT BARRAGE
TECHNICAL
DOCUMENTS
JOINT VENTURE
NUMBERING SYSTEM
\
\
Originator
Originator
Scale
Scale
Folio
Folio
N/A
None
Div Type
Type
Div
Element
Section
Pages
Pages
A4
A4
Doc
1/19
1/19
Number
Number
Ind
Ind
L1 1J JN OC 00 00 Q0 00 00 17 A2
Table of Index
Page
10
11
12
13
14
15
16
17
18
19
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
2/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
List of Contents
1
Abbreviations ...................................................................................................................................................... 4
Scope ................................................................................................................................................................... 5
4.1
4.2
4.3
4.4
fabrication storage............................................................................................................................................ 10
5.1
5.2
5.3
5.4
6.1
Location ............................................................................................................................................................. 13
6.2
Characteristics .................................................................................................................................................. 13
6.3
6.4
7.1
7.2
7.3
7.4
8.1
8.2
8.3
8.4
Conclusion......................................................................................................................................................... 19
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
3/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
1
NL
NL
NL
PH
PH
SW
SW
ABBREVIATIONS
DS
MP
US
EP
WP
EP
WP
Navigation Locks,
Navigation Locks,
Navigation Locks,
Powerhouse,
Powerhouse,
Sluiceway,
Sluiceway,
Downstream Head
Middle Part
Upstream Head
East pier
West pier
East pier
West pier
REFERENCE DOCUMENTS
General:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
Concrete works:
(10) 1JR C00 5002-1: Concrete works, precast slabs forming table
(11) 1JR C05 5003-2: Navigation Locks, precast fill-empty channels mould (standard)
(12) 1JR C05 9101-1: Navigation Locks, precast slabs, fill/empty gallery, layout and principles
(13) 1JR C05 9102-1: Navigation Locks, precast slabs, ballast room, layout and principles
(14) 1JR C05 9201-1: Navigation Locks, precast slabs, fill/empty gallery, schedule
Electrical galleries:
(15) 1JD K05 0109-C: Guide drawing, Navigation Locks, plan view level +54.00, from axis F to axis K
(16) 1JD K05 0110-C: Guide drawing, Navigation Locks, plan view level +54.00, from axis K to axis O
(17) 1JD K05 0111-C: Guide drawing, Navigation Locks, plan view level +54.00, from axis O to axis S
Precast stairs:
(18)
(19)
(20)
(21)
(22)
(23)
(24)
Planning:
(25)
1JD K03 0167-A: Preliminary guide drawing, Powerhouse, stair cases, axes 6-7A, 12-13A
1JD K03 0168-A: Preliminary guide drawing, Powerhouse, stair cases, axes 6-7R, 12-13R
1JD K03 0171-A: Preliminary guide drawing, Powerhouse, precast stairs, details
1JD K05 0170-B: Guide drawing, Navigation Locks, stair cases G17, G20
1JD K05 0171-B: Guide drawing, Navigation Locks, stair cases G18, G19
1JD K05 0172-B: Guide drawing, Navigation Locks, stair cases O17, O20
1JD K05 0173-B: Guide drawing, Navigation Locks, precast stairs, details
1JP J00 0003-A: Working programme, revision (A) dated on 15th July 2013
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
4/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
SCOPE
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
5/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
PRECAST SLABS
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
6/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
7/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
8/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
Above element:
Precast slabs
Th: 12cm
Total
Navigation Locks
Upstream
Downstream
Middle part
552
533
1291
m
m
m
650
305
0
m
m
m
1202
838
1291
m
m
m
0
0
m
m
1854
305
m
m
1854
305
m
m
0
0
0
m
m
m
1967
0
5082
m
m
m
1967
0
7458
m
m
m
Powerhouse
Intermediate piers
Main structure
Sluiceway
Abutment pier axis
Standard piers and bays
Total
Equipment capacity:
Production assumption:
Lifting assumption:
Installation assumption:
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
9/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
Storage assumption:
4.4
Thickness
Dimension
7 cm
12 cm
35m
1.56m
Precast slabs
Storage
Precast slab
superposition
stored
7 elements
105 m
6 elements
54 m
Ratio
(m/m)
3
1.9
Storage area
35 m
28 m
FABRICATION STORAGE
8000
7000
6000
5000
4000
Sluiceway
Powerhouse
Navigation locks
3000
2000
1000
Prefabrication rate:
Storage:
Storage period:
Needed storage area:
to minimise storage (
)
145 m/week from November 2013
30 m/week
from July 2014
2 months
6.5 months
800 m
up to July 2014
up to July 2015
up to July 2014
up to July 2015
If first concrete structures start on the 21th August 2013 as per working programme, prefabrication should start middle
of November 2013 and first installation of precast slabs will be on the middle of December 2013.
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
10/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
11/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
G17-Q17
+ 53.45
1.35m
215m
1.90m
294m
539m
G20-Q20
+53.45
1.35m
17.55m (span: 0.50m) and 173m (span: 1.35m)
1.90m
245m
Equipment capacity:
Production assumption:
Lifting assumption:
Installation assumption:
Storage assumption:
Thickness
Dimension
7 cm
12 cm
35m
1.56m
Precast slabs
Storage
Precast slab
superposition
stored
7 elements
105 m
6 elements
54 m
Ratio
(m/m)
3
1.9
Storage area
35 m
28 m
145 m/ week
Storage:
Storage period:
Needed storage area:
6 weeks
200 m
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
12/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
6.1 LOCATION
One technical gallery is present in Power House.
6.2 CHARACTERISTICS
Location:
Precast slab level:
Span:
Gallery length
Gallery height
Precast slab surface
Equipment capacity:
Production assumption:
Lifting assumption:
Installation assumption:
Storage assumption:
6.4 FABRICATION
Thickness
Dimension
7 cm
12 cm
35m
1.56m
Precast slabs
Storage
Precast slab
superposition
stored
7 elements
105 m
6 elements
54 m
Ratio
(m/m)
3
1.9
Storage area
35 m
28 m
AND
STORAGE
Prefabrication rate:
Storage:
Storage period:
Needed storage area:
145 m/ week
2 weeks
25 m
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
13/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
PRECAST CHANNELS
96 elements with:
80 elements done with standard mould (
)
16 elements done with mould and extension (
24 units
48 units
24 units
Beginning of March
Beginning of May
Middle of July
Fabrication assumptions:
Equipment:
Production assumption:
Lifting assumption:
Installation assumption:
Storage assumption:
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
14/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
90
80
70
60
50
40
30
20
10
0
Oct-13
Nov-13
Jan-14
Mar-14
Apr-14
Jun-14
Jul-14
Sep-14
Nov-14
Programme of installation
Prefabrication:
Prefabrication rate:
Prefabrication period:
Starting of prefabrication:
Storage:
Maximum storage period:
Maximum precast channels stored:
Needed storage area:
3 channels / week
32 weeks ~ 7months
Mid of November
45 elements have to be produce before the beginning of period installation
(14 weeks before)
6 months
45 elements
200 m
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
15/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
PRECAST STAIRS
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
16/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
34 units with:
o 16 units in Navigation Locks
Precast stair type PCS 9:
Precast stair type PCS 10:
Precast stair type PCS 10A:
Precast stair type PCS 11:
Precast stair type PCS 11A:
o 18 units in Power house
First flight of stairs:
Precast stair type PCS 7:
Precast stair type PCS 7A:
Precast stair type PCS 8:
Precast stair type PCS 10:
Precast stair type PCS 12:
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Type
2
4
2
2
4
4
Folio
None
Div
2
4
2
5
3
Element
Pages
A4
17/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
Production assumption:
Lifting assumption:
Installation assumption:
Storage assumption:
Storage:
Maximum storage period:
15 months
Maximum precast stairs stored: 16 units
Needed storage area:
150 m
35
30
25
20
15
10
Programme of installation
Issuer
Type
Color
CONCRETE WORKS
PREFABRICATION ANALYSIS
Scale
Originator
Folio
None
Div
Type
Element
Pages
A4
18/19
Number
Ind
1 J N C 0 0 0 0 0 7 2
CONCLUSION
2013
Prefabrication programme
Precast slabs
Prefabrication
Storage
Installation in situ
Electrical galleries (NL)
Prefabrication
Storage
Installation in situ
Technical gallery (PW)
Prefabrication
Storage
Installation in situ
Channels
Prefabrication
Storage
Installation in situ
Precast stairs
Prefabrication
Storage
Installation in situ
10
11
2014
12
2015
8
10
11
12
10
11
12
3 channels/week
() peak : 100m
discontinuous
Recommendations:
- Storage area peak:
- To be considered:
Issuer
Type
Scale
Color
PREFABRICATION ANALYSIS
145 m/week
() peak : 100m
continuous
CONCRETE WORKS
145 m/week
() peak : 100m
continuous
3 stairs/week
() peak : 150m
discontinuous
Originator
Folio
None
Div
Type
Element
Pages
A4
19/19
Number
Ind
1 J N C 0 0 0 0 0 7 2