Beruflich Dokumente
Kultur Dokumente
Volume I
FOR THE APPOINTMENT OF
SYSTEM INTEGRATOR
For
Smart Grid Pilot Project
AT JEEDIMETLA INDUSTRIAL AREA
TWO STAGE BIDDING PROCEDURE
HYDERABAD
Volume-I
Conditions of
Contract
Single Stage Two Part Bidding
Procedure
Page 2 of 223
Description
work
of EMD
(inRs.)
CGM
(P)/Smart
Grid/No.01
/2015-16,
Dt.: 01.07.2015
Implementation of
Smart Grid Pilot
Project in Jeedimetla
Industrial
Area,
Rangereddy District
in
Greater
Hyderabad
50,00,000
(Rupees
fifty lakhs 13.00 Hrs.
only)
3. (a) All the interested Bidders may visit www.eprocurement.gov.in to view and
download the Bid documents from 1.07.2015 at 16.00 Hrs. to 22.07.2015 at 15.00 Hrs.
(b) Request for sending Bid documents by post will not be entertained.
4. Those who are interested to submit Bids will have to register in the above mentioned
site.
Guidelines for E-Tendering
E-tendering Notice
The TSSPDCL is opting for e-tendering for implementation of Smart Grid Pilot Project in
Jeedimetla Industrial Area, Rangareddy District in Greater Hyderabad, Telangana State.
Bid. No. CGM (P)/Smart Grid/No.01/2015-16, Dt.01 -07-2015
Implementation of Smart Grid Pilot Project in Jeedimetla Industrial Area, Rangareddy District in Greater
Hyderabad, Telangana State.
Sl.No.
Description of Item
Date
Time
1.
2.
3.
01-07-2015
22-07-2015
23-07-2015
16-00 Hrs.
15-00 Hrs.
12-00 Hrs.
4.
24-07-2015
13-00 Hrs.
5.
24-07-2015
15-00 Hrs.
6.
07-08-2015
12-00 Hrs.
TSSPDCL
Bid. No. CGM (P)/Smart Grid/No.01/2015-16, Dt.01 -07-2015
Notice Inviting Tender Details
1
2
BID No :
Name of the work
3
4
5
6
Work Completion
Type of Tender
Bid category
Bid Security (INR)
7
8
Bid Validity
Bid Document
Calendar Event
16-00 Hrs.
22-07-2015
15-00 Hrs.
23-07-2015
12-00 Hrs.
24-07-2015
13-00 Hrs.
24-07-2015
15-00 Hrs.
07-08-2015
12-00 Hrs.
Time
participating
Bidder
also
has
to
Page 5 of 223
pay
11
12
(a)
12
(b)
13
14
Officer Inviting
Bids/Contact
person
Address / E-mail ID
Contact Details
/ Telephone,
Fax No.
Eligibility& Qualifying
Criteria
Procedure for
Bid
Submission
shall
be
submitted
online
on
www.eprocurement.gov.in
platform
The participating Bidders should register themselves
free of cost on e-procurement platform in the
website www.eprocurement.gov.in.
ii) Bidders can log-in to e-procurement platform in
Secure mode only by signing with the Digital
certificates.
(iii) The Bidders who are desirous of participating in
e-procurement shall submit their technical Bids,
price Bids as per the standard formats available at
the e-market place.
(iv) The Bidders should scan and upload the copies of
all the following documents in support of technical &
price Bids in proof of qualification requirement duly
signing on all the statements, documents &
certificates uploaded by him, owning responsibility
for their correctness/authenticity:
Documents to be uploaded on-line as part
Technical Bid proposal is given below in Table-A.
of
15
General Terms
and Conditions
Table-A
S.No
1. Check list-Attachment-13
2. Copy of Demand draft / Bank guarantee towards bid security- Attachment14
3. Integrity Pact- Attachment-32
4. Undertaking for having testing facilities in India- Attachment-31
5. Summary of Audited Financial Statements- Attachment-22
6. Consortium Agreement-Attachment-17
7. Power of attorney authorising lead partner on behalf of construction
Power of Attorney authorizing an Individual Designated Representative for
8. the Consortium- Attachment-19
9. Work Completion Schedule- Attachment-07
Additional Information (1. Bankers certificate on credit facility, 2.
10 Litigation / Arbitration history, 3. Detail of works on hand.)Attachment-12
.
11 Bill of Quantity (un-priced)- Attachment-30
Technical experience certificates as per clause 2.4.3 of RfP Vol-1 and
12 Sl.no.1 of Table-A.
.
13
Certificate of incorporation / Registration14 Proof of certificate for SEICMM level 3/ISO 9001 : 2008 or of higher level
15 BID FORM FOR Technical BID UNDER SINGLE STAGE BIDDING- Attachment.
01
16
Deviations and Exceptions to the Provisions- Attachment-05
Letter of Consent by Consortium Member reviewing each element of the
17 Bid.- Attachment- 20
.18 Format of covering letter by lead consortium member for submission of
bid- Attachment-16
19 Format of submission of financial bid (for reference only) -Attachment-26
20 Compliance statement- Attachment-36.
21 Declaration on origin of systems and equipment- Attachment-37
Table-B
Successful bidder has to submit hard copies of documents before issue of LOI for further
evaluation
S.
No.
1.
DESCRIPTION
Letter of Manufacturer's Authorization of Supply and Support-
2.
3.
4.
5.
6.
7.
8.
9.
10. Smart Grid Implementation elements (refer clause 2.11.1 of RfP Vol-1)
11. Curriculum Vitae of experts and support team- Attachment-35
12. Copies of test certificates
13. Copy of service tax registration
14. Copy of PAN allotted by IT department
Automation components, IT Systems (hardware) and AMR/AMI
compatible meters (5% of indicated quantities of BOQ shall be supplied
15. as per clause 2.4.5 (copy of work orders / end user certificates are to
be attached)
CHIEF GENERAL MANAGER/ PROJECTS
th
TSSPDCL, Corporate Office, 4 Floor,
Corporate Office, Mint Compound,
Hyderabad-500063
Page 9 of 223
CONTENTS
SECTION 1: INTRODUCTION.......................................................................... 15
1.1
1.2
1.3
SECTION-3:
SECTION-4:
A.
4.1
4.2
B.
4.3
4.4
4.5
4.6
C.
4.7
4.8
4.9
4.10
D.
4.11
4.12
E.
4.13
4.14
4.15
4.16
4.17
4.18
4.19
4.20
F.
4.21
4.22
4.23
4.24
4.25
G.
4.26
4.27
4.28
4.29
4.30
4.31
H.
4.32
4.33
4.36
4.37
4.38
4.39
SECTION-5:
5.4
SECTION-8:
8.1
8.2
8.3
8.4
8.5
SECTION-9:
SECTION-1
INVITATION FOR THE
BIDS
SECTION 1:
1.1
INTRODUCTION
1.2
THE OPPORTUNITY
TSSPDCL intends to develop Smart Grid elements in to its Distribution
System &Process and has selected works to be executed under the current
Program through SGIA.
The SGIA shall be capable of carrying as is study, designing, developing,
supply, integration,
training, functional and performance testing,
commissioning and performance evaluation of the pilot project.
1.3
Content
Section 1
Introduction
Section 2
Section 3
Section 4
Section 5
Section 6
Section 7
Scope of Work
Section 8
Section 9
Evaluation Methodology
SECTION-2
INSTRUCTIONS TO
BIDDERS (ITB)
SECTION 2:
2.1
INSTRUCTIONS TO BIDDERS
PREAMBLE
This section of the Bidding
Documents provides the information
necessary for bidders to prepare responsive bids, in accordance with the
requirements of the TSSPDCL. It also provides information on bid
submission, opening and contract award.
All matters arising out of the provisions of this Section 2 and the
Section 3 of the Bidding Documents, shall be governed by and
interpreted in accordance with laws of the Telangana State in the
jurisdiction of Telangana State Courts of state capital (Hyderabad) in all
matters arising under this Contract.
2.2
2.2.1
INTRODUCTION
BACKGROUND
The electric power utility industry in India has been undergoing significant
transformation of its operating landscape, driven primarily by rising energy
demands of a fast growing economy, market operations and regulatory
mandates. Significant developments are executed for the addition of new
generation facilities and the expansion of existing transmission corridors.
However, the distribution infrastructures/systems have grown in an
improper manner resulting in not adequately meeting the societal needs.
In recent years, there have been initiatives toward improving the power
distribution efficiency through reform activities like APDRP/RestructuredAPDRP. Central Government and some State Governments have
implemented such reforms, allowing some DISCOMS to achieve profitability,
while most of the sectors are still struggling for survival. Therefore, there is
a most pressing need to modernize the power distribution Grid using full
digital technology-the integration of Information and communication
technology (ICT) with corresponding power infrastructures in the
distribution sector in India.
Global energy scenario is witnessing key changes in terms of shift of
focus towards green energy and Sustainable growth and SMARTGRID is
getting evolved. In line with that outlook Ministry of Power, Government of
India has taken up the initiative for establishing Smart Grid in India. The
broad scopes of these initiatives are:
Functionality
AMI for Residential
AMI for Industrial
Peak Load Management
Outage Management
Power Quality
All eligible payments under the contract(s) for the package for which this
Invitation for Bids is issued shall be made by the TSSPDCL.
2.2.3
2.2.4
The Employer is Chief General Manager (Projects), TSSPDCL, Mint compound,
Hyderabad.
2.3
ELIGIBILITY CONDITIONS
This invitation for bids, issued by the TSSPDCL is open to all firms
including company (ies), government owned enterprises registered and
incorporated in India as per companies act, 1956.
Bids may be submitted by
i.
A single individual firm that on its own meets all the qualification requirements.
ii. A consortium of up to five firms as partners with legal binding for this
2.4.3TECHNICAL EXPERIENCE
a. The bidder or the consortium shall have previous experience in the
design, supply, installation, testing and commissioning of the Smart Grid
works involving AMI/AMR implementation for a minimum of 500
consumers/Distribution Transformer Metering in the last seven (7) years
for power utilities in India or Abroad by parent Company/subsidiary/holding
company/technical collaborator as on date of technical bid opening.
(and)
b. The bidder or the consortium shall have previous experience in the
design, supply, installation, testing and commissioning of power utility
automation involving any one of the following functionalities in the last
seven (7) years in India or Abroad by parent Company/subsidiary/holding
company/technical collaborator as on date of technical bid opening with a
value of not less than Rs. 3 Crores (INR).
1. Outage Management-Please refer clause 3.5 of RfP Vol-II for details
of objective and scope.
2. SCADA /Distribution Management-Please refer clause 3.5 of RfP
Vol-II for details of objective and scope.
3. System Peak Load Management- Please refer clause 3.6 of RfP
Vol-II for details of objective and scope.
4. Power Quality- Please refer clause 3.7 of RfP Vol-II for details of objective and
scope.
(or)
c. The bidder on its own or any Consortium member or associate partner
can be a System integrator with installation and commissioning
experience. The System integrator should have completed at least one
project of value not less than Rs.3 Crores, involving Utility application
software, Hardware, Communication system or network automation in the
last seven (7) years in India or abroad.
The lead partner of the consortium is fully responsible and liable to
TSSPDCL for the deliverable from associate partner.
d. Deleted
e. The Two projects mentioned in ITB 2.4.3.(a) and (b or c) should be in
successful operation continuously for at least one (1) year during the last
seven(7) years as on the date of bid opening.
Proof: Experience certificates and/or Acceptance reports and Work Order
and/or LoA from the owners/client for completion of work done, in support
of the qualifying requirements, clearly establishing the start and end date
of the project, scope of work and worth of project, on client letterhead.
necessary to replace any of the core team members, the SGIA shall
provide replacement to person of equivalent or better qualifications.
Such replacement will be subject to approval of the TSSPDCL.
b) The bidder or Consortium shall have Credit Facilities of not less than 10 % of
minimum annual turnover indicated above.
The bidder shall enclose turnover statement of last five financial years from
2009-10 onwards certified by Charted Accountant and statement of Credit
Facilities from bankers.In case bidder is a holding company, annual turnover&
Credit Facilities referred to in clause 2.4.4 (a) & (b) above shall be of that
of holding company only (i.e. excluding its subsidiary /group companies ). In
case Bidder is a subsidiary of holding company, annual turnover & Credit
Facilities referred to in clause 2.4.4 (a) & (b) above shall be of that
subsidiary company only (i.e. excluding its holding company).
2.4.5Qualification Requirements for Each Supplier
In the case of a Bidder who offers to supply and/or install systems and
equipment under the contract that the Bidder did not manufacture or
otherwise produce and/or install, the Bidder shall (i) have the financial and
other capabilities necessary to perform the contract meets the minimum
criteria listed for an individual Bidder for that item. (ii) have been duly
authorized by the manufacturer or producer of the related systems and
equipment or component as per Performa in Attachments of section 6 to
supply and/or install that item in the India; and (iii) be responsible for
ensuring that the manufacturer or producer complies with the requirements
of ITB Sub-Clause 2.5.2., wherever components/subsystems are procured
such organizations/OEMs/agencies shall fulfil the qualifying requirements as
given under.
Automati
on
compone
nts
Ring Main Unit
(RMU),
Autorecloser,
Sectionaliser
IT
systems and
Hardware supplier
At
least
5%
of
indicated
quantities in BoQ in last 7 years
shall be supplied by the bidder
or sub-vendor.
For smart meter sub-vendors,
they
should have
supplied
AMI/AMR
compatible
meters
equivalent
to
5%
of
the
Smart Meter
quantity
of
smart
indicated in BoQ.
meter
concluding
agreement.
the
2.5
2.5.1 For the purposes of these Bidding Documents, the words facilities,
systems and equipment, installation services, Clause GCC4.1 (P, X &
S) shall be construed in accordance with the respective definitions given to
them in the General Conditions of Contract.
2.5.2 All systems and equipment to be supplied and installed and services
carried out under the contract shall have their origin in any country
barring those countries against whom sanction for conducting business is
imposed by Government of India and barring those firms with whom
business is banned by the TSSPDCL. The Declaration form as per format
given in section 6 shall be submitted by bidder.
2.5.3 For purposes of this clause, origin means the place where the systems
and equipment or component parts thereof are designed, manufactured,
assembled and purchased.
2.5.4 The origin of the systems, equipment, and services may be distinct from
the nationality of the Bidder.
2.6
COST OF BIDDING
The Bidder shall bear all costs associated with the preparation and
submission of its bid including post-bid discussions, technical and other
presentations etc., and the TSSPDCL will in no case be responsible or liable
for these costs, regardless of the conduct or outcome of the bidding
process.
2.7
2.7.1 The facilities required, bidding procedures, contract terms and technical
requirements are prescribed in the Bidding Documents. The Bidding
Documents comprise of the following and shall include amendments, if
any, thereto:
Volume -I: Conditions of Contract
Section 1: Introduction
Section 2: Instructions to Bidders
(ITB) Section 3: Bid Data Sheet
(BDS)
Section 4: General Conditions of
Contract (GCC) Section 5: Special
Conditions of Contract (SCC) Section
6: Sample Forms and Procedures (FP)
Section 7: Scope of Work
Section 1: General
Information Section 2:
General Requirement Section
3: Functional Requirements
Section 4: Training
Requirements Section 5:
Project Management
Section 6: Quality assurance and
Testing Section 7:Project Evaluation
Section 8: Documentation
Section 9: Technical Specifications
Volume-III: Price Schedule (to be uploaded only in the e-procurement plotform under appropriate section by the bidder)
2.7.2 The Bidder is expected to examine all instructions, forms, terms,
specifications and other information in the Bidding Documents. Failure to
furnish all information required by the Bidding Documents or submission of
a bid not substantially responsive to the Bidding Documents in every
respect will be at the Bidders risk and may result in rejection of its bid.
2.7.3
2.9
2.9.1 At any time prior to the deadline for submission of bids, the TSSPDCL
may, for any reason, whether at its own initiative, or in response to a
clarification requested by a prospective Bidder, or as a result of the
clarifications sought by the prospective bidders during the pre-bid meeting
the TSSPDCL may issue an amendment to the Bidding Documents modifying,
inter alia and as needed, the evaluation criteria or other sections of the
Instructions to Bidders, General Conditions of Contract the Special
Conditions of Contract, and the Technical Specifications with the objective of
improving competition without compromising essential project objectives .
2.9.2 The amendment will be notified in writing or by cable to all prospective
bidders who have purchased the Bidding Documents and will be binding on
them. Bidders are required to immediately acknowledge receipt of any
such amendment, and it will be assumed that the information contained
therein will have been taken into account by the Bidder in its bid.
2.9.3 In order to afford reasonable time to the prospective Bidders to take
the amendment into account in preparing their bid, the TSSPDCL may, at
its discretion if necessary, extend the deadline for the submission of bids,
in such cases; the TSSPDCL will notify all bidders through E-Mail & upload
in e-procurement platform and TSSPDCLs website.
2.10
LANGUAGE OF BID
The bid prepared by the Bidder and all correspondence and documents
exchanged by the Bidder and the TSSPDCL related to the bid shall be
written in the English language, provided that any printed literature
furnished by the Bidder may be written in another language, as long as
such literature is accompanied by English translation of its pertinent
passages, in which case, for purposes of interpretation of the bid, the
English translation shall govern.
2.11
2.11.1The bid shall be completed and signed by the Bidder, together with all
Attachments identified in ITB Sub-Clause2.11.2 below.
Bidders are to submit the un-priced schedule of Smart Grid Pilot Project
Implementation elements with suitable and feasible technology which
include the following Details:
1. Details of Project Implementation Plan, GIS Mapping of consumer and
Automation Equipment along with Blue print for Implementation.
Each Bidder shall submit with their Part-1: Technical Bid, the following
attachments and supporting documents on-line:
a) Attachment 19: Power of Attorney
A power of attorney, duly notarized, indicating that the person(s)
signing the bid has(ve) the authority to sign the bid and thus that the
bid is binding upon the Bidder during the full period of its validity, in
accordance with ITB Clause 2.3.
b) Attachment 2: Bidders Eligibility and Qualifications
Documentary evidence establishing that the Bidder is eligible to bid in
accordance with ITB Clause 2.3 and is qualified to perform the
contract in accordance with ITB clause 2.4. The documentary
evidence of the Bidders eligibility to bid shall establish to the
TSSPDCLs satisfaction that the Bidder, at the time of submission of its
bid, is eligible as defined in ITB Clause 2.3.
The documentary evidence of the Bidders qualifications to perform
the contract, if its bid is accepted, shall establish to the TSSPDCLs
satisfaction that the Bidder has the financial, technical, production,
procurement, shipping, installation and other capabilities necessary
iv.
v.
vi.
vii.
V.
and shall be returned by the Bidder in two (2) originals along with the
Techno - Commercial Part in a separate envelope, duly superscripted with
Integrity Pact. The Bidder shall submit the Integrity Pact on a non-judicial
stamp paper of Rs. 100/-.
If the Bidder is a partnership firm or a consortium, the Integrity Pact shall
be signed by all the partners or consortium members.
Bidders failure to submit the Integrity Pact duly signed along with the
Bid shall lead to outright rejection of the Bid.
k) Attachment 11: Information for E-payment, PF details etc.
l) Attachment 12: Credit Facilities Available
(i) Certificate from their Banker(s) (as per prescribed formats in Form 12,
Section-6: Sample Forms and Procedures) indicating various fund
based/non fund based limits sanctioned to the Bidder and the extent
of utilization as on date. Such certificate should have been issued not
earlier than three months prior to the date of bid opening. Wherever
necessary the TSSPDCL may make queries with the Bidders Bankers.
(ii) Detailed information on any litigation or arbitration arising out of
contracts completed or under execution by it over the last five years.
A consistent history of awards involving litigation against the Bidder or
any partner of JV may result in rejection of Bid.
(iii) Any other information which the Bidder intends to furnish.
m) Schedule 1: Bill of Quantity (BOQ) (un-priced)
n) Other enclosures required to be submitted as per Technical Specification.
Note: The Central /State PSUs are exempted from furnishing of
certificate from bankers indicating credit facilities mentioned
above.
2.12 BID FORM
The Bidder shall complete the technical Bid Form furnished in the Bidding
Documents in the manner and detail indicated therein and submit the same
with its bid.
All amendments / clarifications shall be binding on the bidders and the
bidder shall give due consideration while preparation and submitting of the
bids. Such amendments / clarifications invariably be enclosed as a part of
the bid.
2.13
2.13.1
The Bidder shall prepare an original and two numbers of copies/sets
of the bid, clearly marking each one as: Part-1 Technical Bid
Original, Part-1 Technical Bid Copy No. 1, Part-1 Technical Bid
2.14.1
The Bidder shall seal the original and each copy of the Part-1
Technical Bid in separate envelopes, duly marking the envelopes as Part-1
Technical Bid Original and Part-1 Technical Bid Copy No. [Number]. The
envelopes shall be sealed in an outer envelope.
2.14.2
the Bidders identity, the TSSPDCL will not guarantee the anonymity of the
bid submission, but this disclosure will not constitute grounds for bid
rejection.
2.15.1
All volumes of bid as per clause 2.11 must be uploaded in the eprocurement platform on or before due date and the bidder shall also
submit hard copies of all the uploaded statements, certificates, documents
along with original BG/DD in respect of bid security at the address
specified under ITB sub-clause2.8.1 and no later than the time and date
stated in the BDS. Hard copies received after deadline will be rejected and
returned to the Bidder. In the event of the specified date for the submission
of hard copies being declared a holiday for the TSSPDCL, the bids will be
received up to the appointed time on the next working day. Hard copies of
bid documents once received shall not be returned except otherwise
provided in the Bidding Documents.
2.15.2
The TSSPDCL may, at its discretion, extend this deadline for
submission of bids by amending the Bidding Documents in accordance with
ITB Sub-Clause 2.9 for the reasons specified therein, or at any time prior
to opening of bids, in which case all rights and obligations of TSSPDCL
and bidders will thereafter be subject to the deadline as extended.
2.16
2.16.1
The Bidder may modify or withdraw its bids after submission,
provided that modification or written notice of withdrawal is received by
the TSSPDCL prior to the deadline prescribed in BDS for bid submission.
2.16.2
The bidders modifications shall be prepared, sealed, marked and dispatched as
follows
a. The bidders shall provide an original and two numbers of copies of any
modifications to the bid, clearly identified as such in two inner
envelopes duly marked bid -original and copies. The inner envelope is
sealed in an outer envelope, which shall be duly marked bid
modifications.
2.17.1
The TSSPDCL will open the Technical bids in public, including
withdrawals and modifications made pursuant to ITB Clause 2.16, in the
presence of bidders designated representatives who choose to attend, at
the time, date, and location stipulated in the BDS. The bidders
representatives who are present shall sign in a register evidencing their
attendance. In the event of the specified date for the submission of bids
being declared a holiday for the TSSPDCL, the bids will be received upto
the appointed time on the next working day.
2.17.2
a) Envelopes marked Withdrawal shall be opened first and the name of
the Bidder shall be read out. Bids for which an acceptable notice of
withdrawal has been submitted pursuant to ITB Clause 2.16 shall be
returned unopened.
b) For all other Bids, the bidders names, the presence of bid security,
and any such other details as the TSSPDCL may consider appropriate,
will be announced by the TSSPDCLat the opening. Subsequently, all
envelopes marked Modification shall be opened and the
submissions therein read out in appropriate detail. No bid shall be
rejected at bid opening except for late bids pursuant to ITB Clause
2.15 and bids not accompanied with bid security or the bid security is
found to be prima facie unacceptable. Such bids shall be returned to
the Bidder unopened. However, opening of bid accompanied with the
bid security shall not be construed to imply its acceptability which
shall be examined in detail pursuant to ITB Clause 2.17.5.
2.17.3
The TSSPDCL shall prepare minutes of the bid opening in the form
of Bid Opening Statement, including the information disclosed to those
present in accordance with ITB Sub-Clause 2.17.2(b).
2.17.4
Bids not opened and read out at bid opening shall not be
considered further for evaluation, irrespective of the circumstances and
shall be returned to the Bidder unopened.
2.17.5
2.18.1
Prior to the detailed evaluation, the TSSPDCL will determine
whether each bid is of acceptable quality, is complete, is substantially
responsive to the Bidding Documents and has properly incorporated all
the modifications listed in the Changes Required Pursuant to technical
related corrigenda. For purposes of this determination, a substantially
responsive bid is one that conforms to all the terms, conditions and
specifications of the Bidding Documents and the Changes Required
Pursuant to corrigendums without material deviations, objections,
conditionality or reservations.
2.18.2
The TSSPDCL will carry out a detailed evaluation of the bids in order
to determine whether the technical aspects are substantially responsive to
the requirements set forth in the Bidding Documents. In order to reach
such a determination, the TSSPDCL will examine the information supplied
by the bidders, pursuant to ITB Clause 2.11, and other requirements in
the Bidding Documents, taking into account the following factors:
(b)
(a)
Overall completeness and compliance with the Technical
Specifications and Drawings; the technical merits of alternatives
standards and deviations from the Technical Specifications; suitability
of the facilities offered in relation to the environmental and climatic
conditions prevailing at the site; quality, function and operation of any
process control concept included in the bid.
Achievement of specified performance criteria by the facilities.
(c)
Compliance with the time schedule called for in the corresponding
attachments/Forms of Contract Agreement and any alternative time
schedules offered by bidders, as evidenced by a milestone schedule
provided in the bid.
(d)
Type, quantity, and long-term availability of spare parts and maintenance
services.
(e)
Any other relevant technical factors that the TSSPDCL deems
necessary or prudent to take into consideration.
(f) Any deviations to the commercial and contractual provisions
stipulated in the Bidding Documents.
(g)
Details furnished by the bidder in response to the requirements
specified in Volume-II of the Bidding Documents.
(h)
Prior to proceeding to open the price bid, the TSSPDCL will
determine to its satisfaction that no circumstances, in particular the
Bidders contract work in hand, future commitments and current
litigation, have arisen or intervened that would change the
TSSPDCLs opinion as to whether the Bidder determined as having
submitted the lowest evaluated technical bid is still qualified to
satisfactorily perform the contract.
2.18.3
The TSSPDCL may request the Bidder to withdraw any of the deviations listed in
ATTACHMENT
-5 to the bid, at the price shown for the deviation in ATTACHMENT- 5 to
the bid.The bidder shall withdraw the deviations listed in ATTACHMENT-5 at
the cost of withdrawal stated by him in the bid. In case the bidder does not
withdraw the deviations proposed by him, if any, at the cost of withdrawal
stated by him in the bid, his bid will be rejected and his bid security
forfeited.
2.18.4Deleted
2.18.5 The following factors will be considered in technical evaluation in the
manner and to the extent indicated in ITB sub-clause 2.18.6 and in the
technical specifications.
a] Compliance with the time schedule called for in the corresponding
Appendix to the Form of Contract Agreement and evidenced as needed in
a milestone schedule provided in the bid;
b]The functional guarantee of the facilities shall be applied as per the
provision of Technical Specification, Volume-II of the Bidding Documents.
c] The performance of the equipment offered shall conform to the
guaranteed performance or efficiency of the Equipments in response to
the Technical Specifications. Equipment offered shall have minimum
performance specified in Technical Specification to be considered
responsive. Bids offering Equipment with a performance less than the
specified may be rejected.
2.18.6.
Pursuant to ITB Sub-Clause 2.18.5, the following evaluation methods will be
followed:a]Time schedule (program of performance). The Time for Completion for
successful Completion of Jeedimetla smart grid pilot project implementation
shall be 18 (Eighteen) months from the date of Notification of Award. The
systems and equipment covered by this bidding shall have the Taking
Over by the TSSPDCL after successful Completion within the period
specified above. Bidders are required to base their prices on the time
schedule given in Form of Contract Agreement (Time Schedule) or No credit
will be given to earlier completion. Bids offering completion beyond the
specified period will be rejected.
b]Functional
Guarantees
of
facilities.
Bidders
shall
the
state
the
functional
QUALIFICATION
2.19.1
The TSSPDCL will ascertain to its satisfaction whether bidders
determined as having submitted responsive Part-1 Technical Bid are
qualified, as per the Qualification Requirement specified in ITB Clause 2.4
to satisfactorily perform the contract. The TSSPDCL shall be the sole judge
in this regard and the TSSPDCLs interpretation of the Qualification
Requirement shall be final and binding.
2.19.2
The determination will take into account the Bidders financial,
technical capabilities including
production
capabilities
and
past
performance. It will be based upon an examination of the documentary
evidence of the Bidders qualifications submitted by the Bidder, pursuant to
ITB Sub-Clause 2.11.2(b), as well as such other information as the
TSSPDCL deems necessary and appropriate.
2.19.3
The TSSPDCL may waive any minor informality, nonconformity or
irregularity in a bid that does not constitute a material deviation, affecting
the capacity and capability of the Bidder to perform the Contract.
Bidder would be required to comply with all other requirements of the
Bidding Documents except for those deviations which are accepted by the
TSSPDCL.
2.20
PRICE SCHEDULES
The Bidder shall UPLOAD the Vol 3(Part-2) Price Bid and the appropriate
Price Schedules furnished in the Bidding Documents in the manner and
detail indicated therein, following the requirements of ITB Clauses 2.21and
2.22.
2.21
BID PRICES
2.21.1
Un-less otherwise specified in the Technical Specifications, bidders
shall quote for the entire facilities on a single responsibility basis such
that the total bid price covers all the Contractors obligations mentioned
2.21.4
Discount(s)/rebate(s) offered by the bidder shall be indicated as a
percentage of price component(s). Bidder shall also indicate in his bid, the
price component(s) on which the discount is to be applied.
2.21.5
Prices quoted by the bidder shall be fixed during the bidders
Performance of the contract and not subject to variation on any account,
except statuary variation pursuant to ITB clause 2.21. A bid submitted
with the adjustable price quotation will be treated as non-responsive and
rejected.
2.21.6
The Bidder is responsible to quote correct rates taxes and duties payable.
While submitting their bids, bidders will clearly indicate the rates of
Excise Duty, sales Tax and any other levies payable.
In case the bidder assumes a lower rate of statuary levies than the
correct prevailing rates, payment will be regulated as per the rates
quoted. If the statutory levies assumed by the bidder are later found to
be higher than the actual/correct rates prevailing at the time of the
bidding, payment will be limited to the actual rates prevailing only.
2.21.7
STATUTORY VARIATION
Sl.No.
Description of Service
Percentage
Percentage
of
of
service
tax service
tax
payable by the payable by the
person
person
providing
receiving
In respect of services
50%
50%
provided or agreed to be
provided in service portion
execution
of
works
contract
BID CURRENCIES
Prices shall be quoted in Indian Rupees Only.
2.23
BID SECURITY
2.23.1
The Bidder shall furnish, as part of its
bid, a bid security in the amount and currency as stipulated in the BDS.
The bid security must be submitted.
2.23.2
The Bid security shall be a demand guarantee in one of the following forms
1. Unconditional Bank Guarantee in favourof pay officer/TSSPDCL issued
by Nationalized Bank/Scheduled Bank.
2. Bank Demand draft in favour of Pay officer/TSSPDCL /Hyderabad
payable at Hyderabad. drawn on any Nationalized/Scheduled Bank.
The bid security shall, at the bidders option, be submitted for the
amounts as stipulated in BDS. The format of the bank guarantee shall be
in accordance with the form of bid security included in the Bidding
Documents. Bid security shall remain valid for a period of thirty (30) days
beyond the original bid validity period, and beyond any extension
subsequently requested under ITB Sub-clause 2.24.
2.23.3
Any bid not accompanied by an acceptable bid security shall be
rejected by the TSSPDCL and shall be returned unopened.
2.23.4
The bid securities of unsuccessful bidders will be returned as
promptly as possible, but not later than twenty-eight (28) days after the
expiration of the bid validity period.
2.23.5
The successful Bidder shall be required to keep its bid security
valid for a sufficient period till the performance security (ies) pursuant to
ITB Clause 2.36 are furnished to the satisfaction of the TSSPDCL. The bid
security of the successful Bidder will be returned when the Bidder has
signed the Contract Agreement, pursuant to ITB Clause 2.35, and has
furnished the required performance security, pursuant to ITB Clause 2.36.
2.23.6
(c)
(d)
limit
(i) to sign the Contract Agreement, in accordance with ITB Clause 2.35, or
(ii)
to furnish the required performance security(ies), in
accordance with ITB Clause 2.36and/or to keep the bid
security valid as per the requirement of ITB Sub- Clause
2.23.5.
2.23.7
2.24
2.24.1
Bids shall remain valid for the period of six months after the date of
opening of bids prescribed by the TSSPDCL, pursuant to ITB Sub-Clause
2.15.1. A bid valid for a shorter period shall be rejected by the TSSPDCL
as being nonresponsive.
2.24.2
In exceptional circumstance, the TSSPDCL may solicit the Bidders
consent to an extension of the bid validity period. The request and
responses thereto shall be made in writing or by cable. If a Bidder accepts
to prolong the period of validity, the bid security shall also be suitably
extended. A Bidder may refuse the request without forfeiting its bid security.
A Bidder granting the request will not be required or permitted to modify its
bid.
2.25
LATE BIDS
Any bid received by the TSSPDCL after the bid submission deadline
prescribed by the TSSPDCL, pursuant to ITB Clause 2.15, will be rejected
and returned unopened to the Bidder.
2.26
2.27
2.27.1
The TSSPDCL will examine the price bids to determine whether
they are complete, whether any computational errors have been made.
The TSSPDCL may, at its discretion, ask the Bidder for a clarification of its
bid. The request for clarification and the response shall be in writing, and
no change in the price or substance of the bid shall be sought, offered or
permitted.
2.27.2
Arithmetical errors will be rectified on the following basis. If there
is a discrepancy between the unit price and the total price, which is
obtained by multiplying the unit price and quantity, or between subtotals
and the total price, the unit or subtotal price shall prevail, and the total
price shall be corrected. However, in case of items quoted without
indicating any quantity or the items for which the quantities are to be
estimated by the Bidder, the total price quoted against such items shall
prevail. If there is a discrepancy between words and figures, the amount
in words will prevail. The subtotal, total price or the total bid price,
irrespective of the discrepancy between the amount indicated in words or
figures shall be rectified in line with the procedure explained above. If the
Bidder does not accept the correction of errors, its bid will be rejected and
the amount of Bid Security forfeited.
The prices of all such item(s) against which the Bidder has not quoted
rates/amount (viz., items left blank or against which -is indicated) in the
Price Schedules will be deemed to have been included in other item(s).
If the discount(s)/rebate(s) offered by the Bidder is a percentage discount
and the price component(s) on which the said discount is not indicated in
the bid, the same shall be considered on the total bid price [i.e.
proportionately on each price component], in the event of award. However,
if lump-sum discount is offered, the same shall be considered in full on the
Ex-works price component (by proportionately reducing Ex-works price of
individual items), in case of award. Further, Conditional discounts/rebates, if
any, offered by the bidder shall not be taken into consideration for
evaluation. It shall, however, be considered in case of award.
In respect of taxes, duties and other levies indicated by the Bidder in the
Bid, the applicable rate and amount thereof shall be ascertained by the
TSSPDCL based on which, if required, necessary rectification and
arithmetical correction shall be carried out by the TSSPDCL for the purpose
of evaluation. The rate and amount so ascertained by the TSSPDCL shall
prevail.
The Bidder should ensure that the prices furnished in various price
schedules are consistent with each other. In case of any inconsistency in
5to its bid and that does not prejudice or affect the relative ranking of any
Bidder as a result of the technical and commercial evaluation, pursuant to
ITBClauses 2.29.
2.27.3.1
Regarding deviations, conditionality or reservations introduced in
the bid, which will be reviewed to conduct a determination of substantial
responsiveness of the Bidders bid as stated in ITB Clause 2.18.1, the
order of precedence of these documents to address contradictions, if any,
in the contents of the bid, shall be as follows:
I.
Covering Letter
II.
Bid Form
III.
Attachment-5
IV.
Price Schedule(un-priced)
V.
2.29
2.29.1
The comparison shall be on the Grand total (sum of Schedules A
H) in Price bid Volume III.The grand total price shall include the
applicable taxes, duties and other levies.
2.29.2
Deleted
2.29.3Deleted
2.29.4Bid prices quoted by bidders and rectified as per ITB Sub Clause 2.27.2shall
remain unaltered.
2.30
PURCHASE/DOMESTIC PREFERENCE
2.30.1
No purchase preference is applicable for the Systems and
equipment to be supplied under the Contract.
2.30.2
No margin of domestic preference will be allowed in evaluation and comparison of
bids.
2.31 CONTACTING THE TSSPDCL
2.31.1
From the time of bid opening to the time of contract award, TSSPDCL may
ask the bidders to produce clarifications on bid submitted which may not result in
material deviations.
2.31.2 Any effort by a Bidder to influence the TSSPDCL in the TSSPDCLs bid
evaluation, bid comparison or contract award decisions may result in
rejection of the Bidders bid. The TSSPDCL shall be the sole judge in this
regard.
2.32 AWARD CRITERIA
2.32.1 Subject to ITBClause 2.33, the TSSPDCL will award the contract to the
successful Bidder (also referred to as the L1 Bidder) whose bid has been
determined to be substantially responsive and fulfills the evaluation
criteria to be the lowest evaluated bid, further provided that the Bidder is
determined to be qualified, as per the Qualification Requirement specified
in ITB clause 2.4 to perform the contract satisfactorily. This shall, however,
be subject to assessment that may be carried out, if required, by the
TSSPDCL as per the provisions of ITB Clause2.4.The TSSPDCL shall be the
sole judge in this regard.
The TSSPDCL reserves the right to waive minor deviations if they do not
materially affect the capability of the Bidder to perform the contract.
2.32.2 The TSSPDCL reserves the right to vary the quantity of any of the
items and/or delete any items altogether at the time of Award of Contract.
However, evaluation will be carried out as per the quantity of items
stipulated in Bill of Quantity.
2.32.3 The mode of contracting with the successful bidder will be as per
stipulation outlined in Clause GCC 4.2.1 and briefly indicated below:
2.32.3.1
2.33
TSSPDCLS RIGHT TO ACCEPT ANY BID AND TO REJECT ANY OR ALL BIDS
The TSSPDCL reserves the right to accept or reject any bid, and to annul
the bidding process and reject all bids at any time prior to award of
contract, without thereby incurring any liability to the affected Bidder or
bidders or any obligation to inform the affected Bidder or bidders of the
grounds for the TSSPDCLs action.
2.34
NOTIFICATION OF AWARD
2.34.1
Prior to the expiration of the period of bid validity, the TSSPDCL
will notify the successful Bidder in writing, that its bid has been accepted.
The notification of award will constitute the formation of the contract.
2.34.2
The TSSPDCL shall publish the results on its website, identifying
the bid and Specification numbers and the following information: (i) name
of each Bidder who submitted a Bid; (ii) bid prices as read out at bid
opening; (iii) name and evaluated prices of each Bid that was evaluated;
(iv) name of bidders whose bids were rejected and the reasons for their
rejection; and (v) name of the winning Bidder, and the price it offered,
as well as the duration and summary scope of the contract awarded.
2.34.3
Upon the successful Bidders furnishing of the performance
security pursuant to ITB Clause 2.36, the TSSPDCL will promptly discharge
the bid securities, pursuant to ITB Sub-Clause 2.23.4
&2.23.5.
2.35
2.35.1
At the same time as the TSSPDCL notifies the successful Bidder that
its bid has been accepted, the TSSPDCL in consultation with the Bidder will
prepare the Contract Agreement as provided in the Bidding Documents,
incorporating all agreements between the parties.
2.35.2
The Contract Agreement shall be prepared within twenty-eight (28)
days of the Notification of Award and the successful Bidder and the
TSSPDCL shall sign and date the Contract Agreement immediately
thereafter.
The Priced listing incorporating the above details has to be submitted as per
bid to the employer before the execution of Contract Agreement by the
successful Bidder after receiving Letter of Award.
2.36
PERFORMANCE SECURITY
2.36.1
Within 28 days of receipt of Letter of Acceptance, the successful
bidder shall deliver to the employer a performance security in any of the
form given below, for due performance of the contract , for an amount
equivalent to 10% of the contract price.
The 2 Nos. separate performance guarantees shall be delivered in favor of
pay officer/ TSSPDCL/ Hyderabad for
i.
ii.
One no. bank guarantee for an amount of 10% of agreement value for
systems and equipment valid for 78 months with validity up to 90 days
beyond the above period as per the proforma given in section-6,
ATTACHMENT NO.: 28.
For Remaining Value (works/ services):
One no. bank guarantee for an amount of 10% of agreement value for 30
months with validity up to 90 days beyond the above period as per the
proforma given in section-6, ATTACHMENT NO.:28
(Or)
Two Nos. bank drafts
officer/ TSSPDCL
(DDs)
with
the
above
values,
in
favour
of
ISSUING BANKS
pay
2.37
2.37.1
It is the TSSPDCLs policy that requires the Bidders, suppliers and
contractors and their vendors under the contracts to observe the highest
standard of ethics during the procurement and execution of such
contracts. In pursuance of this policy, the TSSPDCL:
(a)
defines, for the purpose of this provision, the terms set forth below as follows:
(i) corrupt practice is the offering, giving, receiving or soliciting,
directly or indirectly, of anything of value to influence
improperly the actions of another party;
(ii) fraudulent practice is any act or omission, including a
misrepresentation, that knowingly or recklessly misleads or
attempts to mislead, a party to obtain a financial or other
benefit or to avoid an obligation;
(iii) Collusive practice is an arrangement between two or more
parties designed to achieve an improper purpose, including
influencing improperly the actions of another party;
(iv) Coercive practice is impairing or harming, or threatening to
impair or harm, directly or indirectly, any party or the property
of the party to influence improperly the actions of a party;
(v) Obstructive practice is
(aa) deliberately destroying, falsifying, altering or concealing of
evidence material to the investigation or making false
statements to investigators in order to materially impede a
TSSPDCLs investigation into allegations of a corrupt,
fraudulent,
coercive
or
collusive
practice;
and/or
threatening, harassing or intimidating any party to prevent
it from disclosing its knowledge of matters relevant to the
investigation or from pursuing the investigation;
Or
(bb) acts intended to materially impede the exercise of the
TSSPDCLs inspection and audit rights.
(b)
will reject a proposal for award if it determines that the bidder
recommended for award has, directly or through an agent, engaged in
corrupt, fraudulent, collusive, coercive or obstructive practices in
competing for the contract in question;
(c)
will sanction a firm or individual, including declaring ineligible,
either indefinitely or for a stated period of time, to be awarded a
contract if it at any time determines that the firm has, directly or
(d)will have the right to require that the provision be included in Bidding
Documents and in contracts, requiring Bidders, suppliers, and
contractors and their sub-contractors to permit the TSSPDCL to
inspect their accounts and records and other documents relating to
bid submission and contract performance and to have them audited
by auditors appointed by the TSSPDCL.
2.38
PAYMENT SCHEDULE
Payment Milestones
%of payment
against each
item
30
30
5
5
30
b. 30
Installation,
Testing
and
commissioning smart
utility as per
Bill of
quantities.
meters, DCU
c. 30
After
and
Successful
modems. completion of End to End test at site.
d. After successful
of Field performance test 5
completion
e. Final payment after operational Acceptance(on
successful
30 completion of system availability tests)
and proof of submission of the required number
of reproducible ,O & Manuals , Spares & test
equipment, approved drawings, data sheets, test
reports and user manuals etc.
4.
b.
50
50
Quarterly
Quarterly
10
Quarterly
11
Quarterly
6.
Page 54 of 223
ITB Clause
Ref. No.
1.
ITB 2.2.3
ITB 2.8.1
ITB 2.14.2
ITB
2.16.3(a)
ITB 2.17.1
ITB 2.23
ITB 2.23.2
10
ITB 2.26.1
3
4
5
12-00Hrs.
Technical Bid Opening date and time 24.07.2015, 1500Hrs.
Corporate
TSSPDCL, Mint
Compound,
Hyderabad.
Amount
of Office,
Bid Security:<Rs.
50, 00,
000/->(Fifty
Lakhs)
SECTION-4
GENERAL CONDITIONS OF
CONTRACT (GCC)
4.1
DEFINITIONS
The following words and expressions shall have the meanings hereby
assigned to them:
(a)
Arbitrator means the person or persons appointed by agreement
between the TSSPDCL and the Contractor to make a decision on or to
settle any dispute or difference between the TSSPDCL and the
Contractor referred to him or her by the parties pursuant to GCC SubClause 4.37(Arbitration) hereof.
(b)
Associate means a party who has been conjoined by the
Contractor to independently execute a pre-selected part of facilities
of the contract and grant him the associated contractual rights and
obligations, without diluting the overall responsibility of the contractor
in respect of the Facilities under the contract.
(c)
Collaborator or Parent Company means the firms/corporations
who have provided technological support to the manufacturer for
establishing production line for the specific Equipment.
(d)
Commissioning means operation of the Facilities or any part
thereof, if any, as per GCC Sub-Clause 4.1(e) by the Contractor as
specified in the Technical Specifications, which operation is to be
carried out by the Contractor as provided in GCC Clause
4.20(Commissioning), for the purpose of Trial Operation (GCC Clause
4.20).
(e)
Completion means that the Facilities or a specific part thereof
have been completed operationally and structurally and put in a tight
and clean condition and that all works in respect of pre-commissioning
of the Facilities or a specific part thereof has been completed
(wherever
required,
as
per
Technical
Specifications)
and
Commissioning followed by Trial Operation has been completed,
as provided in GCC Clause 4.20 (Completion of Facilities) hereof.
(f) Contract means the Contract Agreement entered into between the
TSSPDCL and the Contractor together with the Contract Documents
referred to therein.
(g)
Contract Documents means the documents listed in GCC Clause
4.2.2of Contract Agreement (including any amendments thereto).
(h)
Contract Price means the sum specified in Contract Data,
subject to such additions or deductions there from, as may be made
pursuant to the Contract. For the purpose of Liquidated Damages and
Contract Performance Guarantee, the Contract Price means the sum
specified in Contract Data.
(i) Contractor means the firms whose bid to perform the Contract has
been accepted by the TSSPDCL and is named in the Contract
Agreement, and includes the legal successors or permitted assigns of
the Contractor.
(j) Contractors Equipment means all systems , facilities, equipment,
machinery, tools, apparatus, appliances or things of every kind
required in or for installation, completion and maintenance of
Facilities that are to be provided by the Contractor, but does not
include Systems and equipment, or other things intended to form or
forming part of the Facilities.
(k)
Contractors Representative means any person nominated by the
Contractor and approved by the TSSPDCL in the manner provided in
GCC Sub-Clause
4.13.2 (Contractors Representative and
Construction Manager) hereof to perform the duties delegated by the
Contractor.
(l) Day means calendar day of the Gregorian calendar.
(m) The contractors are responsible for the quality of works executed
till the expiry of defect liability period, which is prescribed as one
year.
The defect liability period should be reckoned only after
installation/commissioning taking over of entire project by TSSPDCL.
During which the Contractor is responsible for defects with respect to
the Facilities (or the relevant part thereof) as provided in GCC Clause
4.22 (Defect Liability) hereof.
(n)
Effective Date means the date of Notification of Award from
which the Time for Completion shall be determined.
(o)
Facilities means the Systems and equipment to be supplied and
installed, as well as all the Installation Services to be carried out by the
Contractor under the Contract.
(P) GCC means the General Conditions of Contract hereof.
(q)
Guarantee Test(s) means the test(s) specified in the Technical
Specifications to be carried out to ascertain whether the Facilities or a
specified part thereof is able to attain the Functional Guarantees
specified in the Technical Specifications in accordance with the
provisions of GCC Clause 4.20 (Guarantee Test) hereof during/after
successful Commissioning followed by Trial - Operation.
Pre-commissioning,
commissioning,
maintenance, the
provision
and maintenance manuals, training, etc.
(s)
operations,
of operations
INTERPRETATION
CONTRACT
4.2.1.1
under:
4.2.1.2
The award of two separate Contracts shall not in any way dilute
the responsibility of the Contractor for the successful completion of the
facilities as per Specification and a breach in one Contract shall
automatically be construed as a breach of the other Contract(s) which will
confer a right on the TSSPDCL to terminate the other Contract(s) also at
the risk and the cost of the Contractor.
4.2.1.3
The Contract will be signed in two originals and the Contractor
shall be provided with one signed original and the rest will be retained by
the TSSPDCL.
4.2.1.4
The Contractor shall provide free of cost to the TSSPDCL all the
engineering data, drawing and descriptive materials submitted with the
bid, in at least two (2) copies to form a part of the Contract immediately
after Notification of Award.
4.2.1.5
Subsequent to signing of the Contract, the Contractor at his own
cost shall provide the TSSPDCL with ONE original and Nine (9) true copies
of Contract Agreement within fifteen (15) days after signing of the
Contract.
4.2.2CONTRACT DOCUMENTS
All documents forming part of the Contract (and all parts thereof) are
intended to be correlative, complementary and mutually explanatory,
subject to clause GCC Sub-clause4.2.6 (Order of Precedence) of the
Contract Agreement. The Contract shall be read as a whole.
4.2.3LANGUAGE
The ruling language of the Contract and the language for communications shall be
English.
4.2.4SINGULAR AND PLURAL
The singular shall include the plural and the plural the singular, except
where the context otherwise requires.
4.2.5HEADINGS
The headings and marginal notes in the General Conditions of Contract are
included for ease of reference, and shall neither constitute a part of the
Contract nor affect its interpretation.
4.2.6ENTIRE AGREEMENT
The documents forming the contract shall be interpreted in the following order of
priority:
1.
Agreement
2. Letter of acceptance, notice to proceed with the work.
3. Contractors (Bidder) Bid form
4. Amendments/pre-bid decisions if any
5. Contract data
6. Conditions of contract (i) General (ii) special
7. Specifications
8. Drawings
9. Price bid where quantities and their estimated values are
mentioned 10.Any other listed in the contract and
forming part of the contract
11.PERT chart: the works shall be executed as per the pert chart subject
to the approval of the employer
4.2.7AMENDMENT
4.2.8INDEPENDENT CONTRACTOR
The Contractor shall be an independent contractor performing the Contract.
The Contract does not create any agency, partnership, joint venture or
other joint relationship between the parties hereto.
Subject to the provisions of the Contract, the Contractor shall be solely
responsible for the manner in which the Contract is performed. All
employees, representatives or vendors engaged by the Contractor in
connection with the performance of the Contract to complete the project
as per scope of pilot and scope of work shall be under the complete
control of the Contractor and shall not be deemed to be employees of the
TSSPDCL, and nothing contained in the Contract or in any supply/ service
relationship awarded by the Contractor shall be construed to create any
contractual relationship between any such employees, representatives or
vendors and the TSSPDCL.
4.2.9 If the Contractor is a joint venture of two or more firms, all such firms
shall be jointly and severally bound to the TSSPDCL for the fulfillment of
the provisions of the Contract and shall designate one of such firms to act
as a leader with authority to bind the joint venture. The composition or
the constitution of the joint venture shall not be altered without the prior
written consent of the TSSPDCL.
4.2.10Non-Waiver
4.2.10.1
Subject to GCC Sub-Clause 4.2.10.2 below, no relaxation,
forbearance, delay or indulgence by either party in enforcing any of the
terms and conditions of the Contract or the granting of time by either
party to the other shall prejudice, affect or restrict the rights of that party
under the Contract, nor shall any waiver by either party of any breach of
Contract operate as waiver of any subsequent or continuing breach of
Contract.
4.2.10.2
Any waiver of a partys rights,
Contract must be in writing, must
authorized representative of the party
specify the right and the extent to which
4.2.11Severability
If any provision or condition of the Contract is prohibited or rendered invalid
or unenforceable, such prohibition, invalidity or unenforceability shall not
affect the validity or enforceability of any other provisions and conditions of
the Contract.
4.2.12Country of Origin
Origin means the place where the materials, equipment and other
supplies for the Facilities are mined, grown, produced or manufactured,
and from which the services are provided. Systems and equipment are
produced when, through manufacturing, processing or substantial
4.3
SCOPE OF FACILITIES
4.3.2 The supply of Mandatory Spares Parts, if any, shall be included in the
Contract. Beside the aforesaid Mandatory Spares parts, the Contractor
shall ensure the availability of spare parts required for the operation and
maintenance of the Facilities by the TSSPDCL for a minimum
4.4.1 The Contractor shall commence work on the Facilities from the Effective
Date of Contract and without prejudice to GCC Sub-Clause4.21.2 hereof,
the Contractor shall thereafter proceed with the Facilities in accordance
CONTRACTOR RESPONSIBILITIES
TSSPDCLSRESPONSIBILITIES
4.6.1 The TSSPDCL shall ensure the accuracy of all information and/or data to
be supplied by the TSSPDCL as described in the corresponding Section-7
reasonably required for the proper execution of the Contract, including all
requisite rights of way, as specified in the corresponding section -7 (Scope
of Works) to the Contract Agreement. The TSSPDCL shall give full
possession of an accord all rights of access thereto on or before the date(s)
specified in that section.
4.6.3 If requested by the Contractor, the TSSPDCL shall use its best endeavors
to assist the Contractor in obtaining in a timely and expeditious manner
all permits, approvals and/or licenses necessary for the execution of the
Contract from all local, state or national government authorities or
public service undertakings that such authorities or undertakings require
the Contractor or the personnel of the Contractor as the case may be, to
obtain.
4.6.4 The TSSPDCL shall be responsible for the continued operation of the
Facilities after Taking Over, in accordance with GCC Sub-Clause4.20.1.5.
However, the Contractor shall be responsible for Maintenance during
Defect Liability Period and during AMC thereafter in accordance with
provisions of Technical Specifications.
4.6.5
All costs and expenses involved in the performance of the obligations under this
GCC Clause
4.6
C.
PAYMENT
4.7 CONTRACT PRICE
4.7.1
4.7.2 The Contract Price shall be subject to adjustment in accordance with the
provisions of Price Adjustment to the Contract Agreement. The Contract
Price shall be increased or reduced on account of variation in quantity in
accordance with Clause4.32 of GCC.
4.7.3 Subject to GCC Sub-Clauses 4.5.2 and 4.6.1 hereof, the Contractor
shall be deemed to have satisfied itself as to the correctness and
sufficiency of the Contract Price, which shall, except as otherwise provided
for in the Contract, cover all its obligations under the Contract.
4.7.4
SECURITIES
ISSUANCE OF SECURITIES
The Contractor shall provide the securities specified below in favor of the
TSSPDCL at the times, and in the amount, manner and form specified
below.
4.10.1
For CIF Contract, the Contractor shall be entirely responsible for
payment of all taxes, stamp duties, license fees and other such levies
imposed out-side India.
In case of Contract for domestic supplies and services, the Contractor shall
be entirely responsible for payment of all taxes, duties, license fees and
other such levies legally payable/incurred until delivery of the contracted
supplies to the TSSPDCL.
If it is statutory requirement to make deductions towards such taxes and
duties or any other applicable taxes and duties, the same shall be made
by the TSSPDCL and a certificate for the same shall be issued to the
Contractor.
4.10.2
The Contractor shall be solely responsible for the taxes that may be
levied on the Contractor's persons or on earnings of any of his employees
and shall hold the TSSPDCL indemnified and harmless against any claims
that may be made against the TSSPDCL. The TSSPDCL does not
take any responsibility whatsoever regarding taxes under Indian Income Tax
Act, for the Contractor or his personnel. If it is obligatory under the
provisions of the Indian Income Tax Act, deduction of Income Tax at source
shall be made by the TSSPDCL.
4.10.3
or CIF Contract:
4.10.5
Sales Tax/VAT on Works Contract, Turnover Tax or any other
similar taxes under the Sales Tax/VAT Act for services to be performed in
India, as applicable is included in Contract Price and TSSPDCL would not
bear any liability on this account. TSSPDCL shall, however, deduct such
taxes at source as per the rules and issue Tax Deduction at Source (TDS)
Certificate to the Contractor.
4.10.6
For the purpose of the Contract, it is agreed that the Contract Price
specified in Contract Price and Terms of Payment of the Contract
Agreement is based on the taxes, duties, levies and charges prevailing at
the date seven (07) days prior to the last date of bid submission
(hereinafter called Tax in this GCC Sub-clause4.10.7). If any rates of
Tax are increased or decreased, a new Tax is introduced, an existing Tax
is abolished, or any change in interpretation or application of any Tax
occurs in the course of the performance of the Contract, which was or will
be assessed on the Contractor in connection with performance of the
Contract, an equitable adjustment of the Contract price shall be made to
fully take into account any such change by addition to the Contract price or
deduction there from, as the case may be, in accordance with GCC Clause
4.32 (Changes in Laws and Regulations) hereof. However, these
adjustments would be restricted to direct transactions between the
TSSPDCL and the Contractor for which the taxes and duties are
reimbursable by the TSSPDCL as per the Contract. These adjustments shall
not be applicable on procurement of raw materials, intermediary
components etc by the Contractor and also not applicable on the bought
out items dispatched directly from sub-vendors works to site.
In respect of raw materials, intermediary components etc. and bought out
items, neither the TSSPDCL nor the Contractor shall be entitled to any claim
arising due to increase or decrease in the rate of Tax, introduction of a new
Tax or abolition of an existing Tax in the course of the performance of the
Contract.
Service Tax: The service tax of 12.36% on the labour charges was already
incorporated in the labour portion of the schedules. The services of works
contract have been brought under the partial reverse charge mechanism
for payment service tax vide notification No.30/2012 Dt: 20- 06-2012. The
extent of service tax payable by the provider and the service recipient is
specified as below.
Sl.No Description of Service
.
Percentage
of
service
tax
payable
by
the
person
providing
the services.
Percentage of
service
tax
payable by the
person
receiving
the
services
50%
INTELLECTUAL PROPERTY
4.11
COPY RIGHT
4.11.1
The copyright in all drawings, documents and other materials
containing data and information furnished to the TSSPDCL by the
Contractor herein shall remain vested in the Contractor or, if they are
furnished to the TSSPDCL directly or through the Contractor by any
third party, including supplies of materials, the copyright in such materials
shall remain vested in such third party.
The TSSPDCL shall however be free to reproduce all drawings, documents
and other material furnished to the TSSPDCL for the purpose of the
Contract including, if required, for operation and maintenance.
4.11.2
The copyright in all drawings, documents and other materials
containing data and information furnished to the Contractor by the
TSSPDCL herein shall remain vested in the TSSPDCL.
4.12
CONFIDENTIAL INFORMATION
4.12.1
The TSSPDCL and the Contractor shall keep confidential and shall
not, without the written consent of the other party hereto, divulge to any
third party any documents, data or other information furnished directly or
indirectly by the other party hereto in connection with the Contract,
whether such information has been furnished prior to, during or following
termination of the Contract. Notwithstanding the above, the Contractor
may furnish to its personnel/ agencies engaged such documents, data
and other information it receives from the TSSPDCL to the extent required
for the personnel/agencies engaged to perform its work under the
Contract, in which event the Contractor shall obtain from such personnel/
agencies engaged an undertaking of confidentiality similar to that
imposed on the Contractor under this GCC Clause 4.12.
4.12.2
The TSSPDCL shall not use such documents, data and other
information received from the Contractor for any purpose other than the
operation and maintenance of the Facilities. Similarly, the Contractor shall
not use such documents, data and other information received from the
TSSPDCL for any purpose other than the design, procurement of Systems
and equipment, construction or such other work and services as are
required for the performance of the Contract.
4.12.3
The obligation of a party under GCC Sub-Clauses 4.12.1 and
4.12.2 above, however, shall not apply to that information which
a. Now or hereafter enters the public domain through no fault of that party
b. can be proven to have been possessed by that party at the time of
disclosure and which was not previously obtained, directly or indirectly,
from the other party hereto
c. Otherwise lawfully becomes available to that party from a third
party that has no obligation of confidentiality.
4.12.4
The above provisions of this GCC Clause 4.12 shall not in any
way modify any undertaking of confidentiality given by either of the parties
hereto prior to the date of the Contract in respect of the Facilities or any
part thereof.
4.12.5
The provisions of this GCC Clause 4.12 shall survive termination,
for whatever reason, of the Contract.
E.
4.13
REPRESENTATIVES
4.13.1
If the Project Manager is not named in the Contract, then within
fourteen (14) days of the Effective Date, the TSSPDCL shall appoint and
notify the Contractor in writing of the name of the Project Manager. The
TSSPDCL may from time to time appoint some other person as the project
Manager in place of the person previously so appointed, and shall give a
notice of the name of such other person to the Contractor without delay.
The TSSPDCL shall take all reasonable care to see that no such appointment
is made at such a time or in such a manner as to impede the progress of
work on the Facilities. The Project Manager shall represent and act for the
TSSPDCL at all times during the currency of the Contract. All notices,
instructions, orders, certificates, approvals and all other communications
under the Contract shall be given by the Project Manager, except as herein
otherwise provided.
All notices, instructions, information and other communications given by
the Contractor to the TSSPDCL under the Contract shall be given to the
Project Manager, except as herein otherwise provided.
4.13.2
4.13.2.1
If the Contractors Representative is not named in the Contract,
then within fourteen (14) days of the Effective Date, the Contractor shall
appoint the Contractors Representative and shall request the TSSPDCL
in writing to approve the person so appointed. If the TSSPDCL makes no
objection to the appointment within fourteen (14) days, the Contractors
4.13.2.2
The Contractors Representative shall represent and act for the
Contractor at all times during the currency of the Contract and shall
give to the Project Manager all the Contractors notices, instructions,
information and all other communications under the Contract. All notices,
instructions, information and all other communications given by the
TSSPDCL or the Project Manager to the Contractor under the Contract
shall be given to the Contractors Representative or, in its absence, its
deputy, except as herein otherwise provided. The Contractor shall not
revoke the appointment of the Contractors Representative without the
TSSPDCLs prior written consent, which shall not be unreasonably
withheld. If the TSSPDCL consents thereto, the Contractor shall appoint
some other person as the Contractors Representative, pursuant to the
procedure set out in GCC Sub-Clause4.13.2.1.
4.13.2.3
The Contractors Representative may, subject to the approval of
the TSSPDCL (which shall not be unreasonably withheld), at any time
delegate to any person any of the powers, functions and authorities
vested in him or her. Any such delegation may be revoked at any time.
Any such delegation or revocation shall be subject to a prior notice
signed by the Contractors Representative, and shall specify the powers,
functions and authorities thereby delegated or revoked. No such
delegation or revocation shall take effect unless and until a copy thereof
has been delivered to the TSSPDCL and the Project Manager. Any act
or exercise by any person of powers, functions and authorities so
delegated to him or her in accordance with this GCC SubClause4.13.2.3 shall be deemed to be an act or exercise by the
Contractors Representative.
4.13.2.3
Notwithstanding anything stated in GCC Sub-Clause4.13.1 and
4.13.2.1 above, for the purpose of execution of Contract, the TSSPDCL
and the Contractor shall finalize and agree to a Contract Co-ordination
Procedure and all the communication under the Contract shall be in
accordance with such Contract Coordination Procedure.
4.13.2.4
From the commencement of installation of the Facilities at the Site
until Operational Acceptance, the Contractor's Representative shall
appoint a suitable person as the construction manager, (hereinafter
referred to as "the Construction Manager"). The Construction Manager
shall supervise all work done at the Site by the Contractor and shall be
present at the Site through-out normal working hours except when on
leave, sick or absent for reasons connected with the proper performance
of the Contract. Whenever the Construction Manager is absent from the
Site, a suitable person shall be appointed to act as his or her deputy.
4.13.2.5
The TSSPDCL may by notice to the Contractor object to any
representative or person employed by the Contractor in the execution of
the Contract who, in the reasonable opinion of the TSSPDCL, may
behave inappropriately, may be incompetent or negligent, or may
commit a serious breach of the Site regulations provided under GCC
Sub-Clause4.18. The TSSPDCL shall provide evidence of the same,
whereupon the Contractor shall remove such person from the Facilities.
4.13.2.6
If any representative or person employed by the Contractor is
removed in accordance with GCC Sub-Clause4.13.2.5, the Contractor
shall, where required, promptly appoint a replacement.
4.14
4.14.1
WORK PROGRAM
CONTRACTORS ORGANIZATION
The Contractor shall supply to the TSSPDCL and the Project Manager a
chart showing the proposed organization to be established by the
Contractor for carrying out work on the Facilities. The chart shall include the
identities of the key personnel together with the curricula vitae of such key
personnel to be employed within twenty-one (21) days of the Effective Date.
The Contractor shall promptly inform the TSSPDCL and the Project Manager
in writing of any revision or alteration of such an organization chart.
4.14.2
PROGRAM OF PERFORMANCE
Within the time stated in the Contract Data, the contractor shall submit
the revised work completion schedule to the Project Manager for approval.
The Contractor shall update and revise the program ( in addition to Vol II
Section-5) as and when appropriate or when required by the Project
Manager, but without modification in the Times for Completion under GCC
Sub-Clause4.4.2 and any extension granted in accordance with GCC
Clause 4.33, and shall submit all such revisions to the Project Manager.
4.14.3
PROGRESS REPORT
The Contractor shall monitor progress of all the activities specified in the
program referred to in GCC Sub-Clause4.14.2 above, and supply a
progress report to the Project Manager every month.
The progress report shall be in a form acceptable to the Project Manager and
shall indicate: (a) percentage completion achieved compared with the
planned percentage completion for each activity; and (b) where any
activity is behind the program, giving comments and likely consequences
and stating the corrective action being taken.
4.14.4
PROGRESS OF PERFORMANCE
If at any time the Contractors actual progress falls behind the program
referred to in GCC Sub- Clause4.14.2, or it becomes apparent that it will
so fall behind, the Contractor shall, at the request of the TSSPDCL or the
Project Manager, prepare and submit to the Project Manager a revised
program, taking into account the prevailing circumstances, and shall notify
the Project Manager of the steps being taken to expedite progress so as
to attain Completion of the Facilities within the Time for Completion
under GCC Sub-Clause4.4.2, any extension thereof entitled under GCC
Sub-Clause4.33, or any extended period as may otherwise be agreed upon
between the TSSPDCL and the Contractor.
4.14.5
WORK PROCEDURES
SUBCONTRACTING
The Subcontracting of any/or part of the work covering this subject contract is not
permitted.
4.16
4.17.1
Subject to GCC Sub-Clause4.10.2, the Contractor shall
manufacture or procure and transport all the Systems and equipment
(including Hardware & Software also) in an expeditious and orderly
manner to the Site.
4.17.1.1
The bidder shall be responsible for all the deliverables under the
contract and shall have the authority to conduct all businesses for and on
behalf of any and all the members of consortium/joint venture during the
bidding process and, in the event the bidder is awarded the Contract,
during contract execution period.
4.17.2TSSPDCL-Supplied Systems, Equipment, and Materials
If the corresponding section-7 Scope of Works to the Contract Agreement
provides that the TSSPDCL shall furnish any specific items of machinery,
equipment or materials to the Contractor, the following provisions shall
apply:
4.17.2.1
The TSSPDCL shall, at its own risk and expense, transport each
item to the place on or near the Site as agreed upon by the parties and
make such item available to the Contractor at the time specified in the
program furnished by the Contractor, pursuant to GCC Sub-Clause4.14,
unless otherwise mutually agreed.
4.17.2.2
The equipment & materials to be furnished by the TSSPDCL shall
be supplied to the Contractor at the depots established by the Contractor
or the TSSPDCL. The Lorry Receipts for
4.17.3.1
The Contractor shall at its own risk and expense transport all the
Systems and equipment and the Contractors Equipment to the Site by
the mode of transport that the Contractor judges most suitable under all
the circumstances.
4.17.3.2
The contractor shall ensure safe delivery of supplies to TSSPDCL
through registered transport operators. The contractor is responsible for
arrangement of statuary transit documents for smooth and safe passage
at check posts as well as for any loss or damage during transit.
4.17.3.3
Upon dispatch of each shipment of the Systems and equipment
and the Contractors Equipment, the Contractor shall notify the TSSPDCL
by telex, facsimile or Electronic Data Interchange (EDI) of the description
of the Systems and equipment and of the Contractors Equipment, the
point and means of dispatch, and the estimated time and point of arrival
in the country where the Site is located, if applicable, and at the Site.
The Contractor shall furnish the TSSPDCL with relevant shipping
documents to be agreed upon between the parties.
4.17.3.4
The Contractor shall be responsible for obtaining, if necessary,
approvals from the authorities for transportation of the Systems and
equipment and the Contractors Equipment to the Site. The TSSPDCL shall
use its best endeavors in a timely and expeditious manner to assist the
Contractor in obtaining such approvals, if requested by the Contractor. The
Contractor shall indemnify and hold harmless the TSSPDCL from and
against any claim for damage to roads, bridges or any other traffic
facilities that may be caused by the transport of the Systems and
equipment and the Contractors Equipment to the Site.
4.17.3.5
Customs Clearance
The Contractor shall, at its own expense, handle all imported Systems
and equipment and Contractor's Equipment at the point(s) of import and
shall handle any formalities for customs clearance including liabilities for
port charges if any, provided that if applicable laws or regulations
require any application or act to be made by or in the name of the
TSSPDCL, the TSSPDCL shall take all necessary steps to comply with such
laws or regulations.
4.17.4
Delivery and
Documents
4.17.4.1Delivery
Documents
Upon shipment, the Contractor shall notify the TSSPDCL with full details of
the dispatch and shall furnish the supporting documents.
4.17.4.2Packing
4.17.4.2.2 The packing, marking and documentation within and outside the
packages shall comply strictly with such special requirements as shall
be expressly provided for in the Contract and, subject to any
subsequent instruction ordered by the TSSPDCL consistent with the
requirements of the Contract.
4.18
INSTALLATION
4.18.1Setting Out/Supervision/Labour
4.18.1.1
Bench Mark: The Contractor shall be responsible for the true and
proper setting-out of the Facilities in relation to bench marks, reference
marks and lines provided to it in writing by or on behalf of the TSSPDCL.
If, at any time during the progress of installation of the Facilities, any
error shall appear in the position, level or alignment of the Facilities,
the Contractor shall forthwith notify the Project Manager of such error
and, at its own expense, immediately rectify such error to the reasonable
satisfaction of the Project Manager. If such error is based on incorrect
data provided in writing by or on behalf of the TSSPDCL, the expense of
rectifying the same shall be borne by the TSSPDCL.
4.18.1.2
Contractors Supervision: The Contractor shall give or provide
all necessary superintendence during the installation of the Facilities,
and the Construction Manager or its deputy shall be constantly on the
Site to provide full-time superintendence of the installation. The
Contractor shall provide and employ only technical personnel who are
skilled and experienced in their respective callings and supervisory staff
who are competent to adequately supervise the work at hand.
4.18.1.3
Labour:
(a)
The Contractor shall provide and employ on the Site in the
installation of the Facilities such skilled, semi-skilled and unskilled
labour as is necessary for the proper and timely execution of the
Contract. The Contractor is encouraged to use local labour that has the
necessary skills.
(b)Unless otherwise provided in the Contract, the Contractor at its own
expense shall be responsible for the recruitment, transportation,
accommodation and catering of all labour, local or expatriate, required
for the execution of the Contract and for all payments in connection
therewith.
(c) The Contractor shall at all times during the progress of the Contract
use its best endeavors to prevent any unlawful, riotous or disorderly
4.18.3.1.1 During continuance of the contract, the Contractor and the agencies
involved for execution of works shall abide at all times by all applicable
existing labour enactments and rules made there under, regulations
notifications and byelaws of the State or Central Government or local
authority and any other labour law (including rules), regulations bye
laws that may be passed or notification that may be issued under any
labour law in future either by the State or the Central Government or the
local authority. The employees of the Contractor and the Sub-contractor
4.18.6Site Clearance
4.18.6.1
Site Clearance in Course of Performance: In the course of
carrying out the Contract, the Contractor shall keep the Site reasonably
free from all unnecessary obstruction, store or remove any surplus
materials, clear away any wreckage, rubbish or temporary works from
the Site, and remove any Contractors Equipment no longer required for
execution of the Contract.
4.18.6.2
Clearance of Site after Completion: After Completion of all parts of
the Facilities, the Contractor shall clear away and remove all wreckage,
rubbish and debris of any kind from the Site, and shall leave the Site and
Facilities clean and safe.
4.18.7Watching and Lighting
The Contractor shall provide and maintain at its own expense all lighting,
fencing, and watching when and where necessary for the proper
execution and the protection of the Facilities, or for the safety of the
owners and occupiers of adjacent property and for the safety of the
public.
4.18.8Work at Night and on Holidays
4.18.8.1
Unless otherwise provided in the Contract, no work shall be
carried out during the night and on public holidays of the country
where the Site is located without prior written consent of the TSSPDCL,
except where work is necessary or required to ensure safety of the
Facilities or for the protection of life, or to prevent loss or damage to
property, when the Contractor shall immediately advise the Project
Manager, provided that provisions of this GCC-Clause4.18 shall not
apply to any work which is customarily carried out by rotary or doubleshifts.
4.18.8.2
Notwithstanding GCC Clauses 4.18 if and when
considers it necessary to carry out work at night or on
so as to meet the Time for Completion and requests
consent thereto, the TSSPDCL shall not unreasonably
consent.
4.19
the Contractor
public holidays
the TSSPDCLs
withhold such
4.19.1
The Contractor shall at its own expense carry out at the place of
manufacture and/or on the Site all such tests and/or inspections of the
Systems and equipment and any part of the Facilities as are specified in
the Contract.
4.19.2
The TSSPDCL and the Project Manager or their designated
representatives shall be entitled to attend the aforesaid test and/or
inspection, provided that the TSSPDCL shall bear all costs and expenses
incurred in connection with such attendance including, but not limited to,
all traveling and board and lodging expenses.
4.19.3
Whenever the Contractor is ready to carry out any such test and/or
inspection, the Contractor shall give four weeks advance notice of such test
and/or inspection and of the place and time thereof to the Project Manager.
The Contractor shall obtain from any relevant third party or manufacturer
any necessary permission or consent to enable the TSSPDCL and the
Project Manager (or their designated representatives) to attend the test
and/or inspection.
4.19.4
The Contractor shall provide the Project Manager with a certified
report of the results of any such test and/or inspection.
4.19.5
The Project Manager may require the Contractor to carry out any
test and/or inspection not required by the Contract, provided that the
Contractors reasonable costs and expenses incurred in the carrying out of
such test and/or inspection shall be paid to the contractor on production
of supplementary bill and recommendation of project manager on
approval of CGM (projects) .Further, if such test and/or inspection impedes
the progress of work on the Facilities and/or the Contractors performance
of its other obligations under the Contract, due allowance shall be
considered by TSSPDCL in respect of the Time for Completion and the other
obligations so affected.
4.19.6
If any Systems and equipment or any part of the Facilities
covered in the contract or in pursuant of clause 4.19, fails to pass any
test and/or inspection, the Contractor at his own cost shall either rectify
or replace such Systems and equipment or part of the Facilities and shall
repeat the test and/or inspection at his own cost, upon giving a notice
under GCC Clause4.19. In such case the cost to be incurred by contractor
to carry out any test pursuant to clause GCC Clause4.19 will not be paid
by TSSPDCL.
4.19.7
If any dispute or difference of opinion shall arise between the
parties in connection with or arising out of the test and/or inspection of the
Systems and equipment or part of the Facilities that cannot be settled
between the parties within a reasonable period of time, it may be
referred to an Arbitrator for determination in accordance with GCC
Clause4.37.
4.19.8
The Contractor shall afford the TSSPDCL and the Project Manager,
at the TSSPDCLs expense, access at any reasonable time to any place
where the Systems and equipment are being manufactured or the
Facilities are being installed, in order to inspect the progress and the
manner of manufacture or
installation, provided that the Project
Manager shall give the Contractor a reasonable prior notice.
4.19.9
The Contractor agrees that neither the execution of a test and/or
inspection of Systems and equipment or any part of the Facilities, nor the
attendance by the TSSPDCL or the Project Manager, nor the issue of any
test certificate pursuant to GCC Clause4.19, shall release the Contractor
from any other responsibilities under the Contract.
4.19.10
No part of the Facilities or foundations shall be covered up on the
Site without the Contractor carrying out any test and/or inspection
required under the Contract. The Contractor shall give a reasonable
notice to the Project Manager whenever any such part of
4.20.1.1
Physical Completion
4.20.1.1.1 As soon as the Facilities or any part thereof has, in the opinion of
the Contractor, been completed operationally and structurally and put
in a tight and clean condition as specified in the Technical
Specifications, excluding minor items not materially affecting the
operation or safety of the Facilities, the Contractor shall so notify the
TSSPDCL in writing.
4.20.1.2
Pre-Commissioning
4.20.1.2.1 Within seven (7) days after receipt of the notice from the
Contractor under GCC Clause4.20, the Project Manager shall deploy
the operating and maintenance personnel for Pre-commissioning of the
Facilities or any part thereof.
4.20.1.2.2 As soon as reasonably practicable after the department personnel
have been deployed by the TSSPDCL the Contractor shall commence
Pre-commissioning of the Facilities or the relevant part thereof, in
presence of the TSSPDCLs representatives, as per procedures
detailed in Technical manual provided by the contractor.
4.20.1.2.3 As soon as all works in respect of Pre-commissioning are
successfully completed and, in the opinion of the Contractor, the
4.20.1.2.10 As and when, after the period of suspension under GCC Clause
4.20, the Contractor is notified by the Project Manager that the
Facilities are ready for Pre-commissioning, the Contractor shall proceed
without delay in performing all activities and obligations under the
Contract.
4.20.1.3
Commissioning
Trial Operation
4.20.1.5
Taking Over
4.20.2.1.3 The Project Manager shall within twenty-one (21) days after
receipt of the Contractor's notice, issue an Operational Acceptance
Certificate.
4.20.2.1.4 Upon Operational Acceptance, pursuant to GCCClause 4.20, the
Project Manager shall issue
to
the
Contractor
Operational
Acceptance Certificate as a proof of the final
4.21
4.21.1
The Contractor guarantees that it shall attain Completion of the
Facilities (or a part for which a separate time for completion is specified in
the contract data) within the Time for Completion specified in the contract
data pursuant to GCCSub-Clause 4.4.2, or within such extended time to
which the Contractor shall be entitled under GCCClause 4.33 hereof.
4.21.2
LIQUIDATED DAMAGES:
If the Contractor fails to comply with the Time for Completion in
accordance with Clause GCC4.21 for the whole of the facilities, (or a part
for which a separate time for completion is agreed) then the Contractor
shall pay to the TSSPDCL a sum equivalent to half percent (0.5%) of the
Contract Price as liquidated damages for such default and not as a
penalty, without prejudice to the TSSPDCL's other remedies under the
Contract, for each week or part thereof which shall elapse between the
relevant Time for Completion and the date stated in Taking Over
Certificate of the whole of the Works (or a part for which a separate time for
completion is agreed) subject to the limit of five percent (5%) of
Contract Price. The TSSPDCL may, without prejudice to any other method
of recovery, deduct the amount of such damages from any monies due or
to become due to the Contractor. The payment or deduction of such
damages shall not relieve the Contractor from his obligation to complete
the Works, or from any other of his obligations and liabilities under the
Contract.
4.21.3
No bonus will be given for earlier Completion of the Facilities or part thereof.
4.22
DEFECT LIABILITY
4.22.1
The Contractor warrants that the Facilities or any part thereof shall
be free from defects in the design, engineering, materials and
workmanship of the Systems and equipment supplied and of the work
executed.
4.22.2
The Defect Liability Period shall be twelve (12) months from the date of
Taking Over
/Completion of Facilities (or any part thereof).
If during the Defect Liability Period any defect should be found in the
design, engineering, materials and workmanship of the Systems and
equipment (includes hardware and software) supplied or of the work
executed by the Contractor, the Contractor shall promptly, in consultation
and agreement with the TSSPDCL regarding appropriate remedying of the
defects, and at its cost, repair, replace or otherwise make good (as the
Contractor shall, at its discretion, determine) such defect as well as any
damage to the Facilities caused by such defect. The Contractor shall not
be responsible for the repair, replacement or making good of any defector
of any damage to the Facilities arising out of or resulting from any of
the following causes:
(a)improper operation or maintenance of the Facilities by the TSSPDCL
(b)operation of the Facilities outside specifications provided in the Contract
(c) normal wear and tear.
4.22.3
The Contractors obligations under this GCCClause 4.22 shall not apply to
(a)any materials that are supplied by the TSSPDCL under GCCClause
4.17, are normally consumed in operation, or have a normal life
shorter than the Defect Liability Period stated herein
(b)any designs, specifications or other data designed, supplied or
specified by or on behalf of the TSSPDCL or any matters for which
the Contractor has disclaimed responsibility herein
(c) any other materials supplied or any other work executed by or on
behalf of the TSSPDCL, except for the work executed by the TSSPDCL
under GCCClause 4.22.
4.22.4
The TSSPDCL shall give the Contractor a notice stating the nature
of any such defect together with all available evidence thereof, promptly
following the discovery thereof. The TSSPDCL shall afford all reasonable
opportunity for the Contractor to inspect any such defect.
4.22.5
The TSSPDCL shall afford the Contractor all necessary access to
the Facilities and the Site to enable the Contractor to perform its
obligations under this GCCClause 4.22. The Contractor may, with the
consent of the TSSPDCL, remove from the Site any Systems and
equipment or any part of the Facilities that are defective if the nature of
the defect, and/or any damage to
where such defects are the result of the gross negligence, fraud, criminal
or willful action of the Contractor.
4.
4.23.1
Bidder shall confirm the guaranteed performance or efficiency of
the System/Equipment in response to the Technical Specifications and
ATTACHMENTs-8 of section 6.
4.23.2
If the guarantees specified in ATTACHMENT 8 (Guarantees,
Liquidated Damages for Non Performance) to the Contract Agreement
are not established, then the TSSPDCL shall, at its discretion either
(a)reject the equipment/system, or
(b)accept the equipment/system after rectification/updation
confirmation of guaranteed technical particulars.
and
4.23.3
In case the TSSPDCL exercises its option as per GCC Clause 4.23,
the Contractor shall at its cost and expense make such changes,
modifications and/or additions to the equipment or any part thereof as may
be necessary to meet the specified guarantees. The Contractor shall notify
the TSSPDCL upon completion of the necessary changes, modifications
and/or additions, and shall request the TSSPDCL to repeat the Test until
the level of the specified guarantee has been met.
4.23.4
After TSSPDCL accept the equipment/system in pursuant to GCC
Clause 4.23 the Contractor shall have no further liability whatsoever to
the TSSPDCL in respect thereof.
4.24
PATENT INDEMNITY
4.24.1
The Contractor shall, subject to the TSSPDCLs compliance with
GCC Clause 4.24, indemnify and hold harmless the TSSPDCL and its
employees and officers from and against any and all suits, actions or
administrative proceedings, claims, demands, losses, damages, costs,
and expenses of whatsoever nature, including attorneys fees and
expenses, which the
4.25
LIMITATION OF LIABILITY
Except in cases of gross negligence or willful misconduct,
(a)the Contractor and the TSSPDCL shall not be liable to the other party
for any indirect or consequential loss or damage, loss of use, loss of
production, or loss of profits or interest costs, provided that this
exclusion shall not apply to any obligation of the Contractor to pay
liquidated damages to the TSSPDCL and
RISK DISTRIBUTION
4.26
TRANSFER OF OWNERSHIP
4.26.1
Ownership of all systems / equipment including spare parts shall
be transferred to TSSPDCL after successful completion of all deliverables
and demonstration of all functions as envisaged under the project as per
GCC Clause 4.20.
4.26.2
From the dispatch of system/ equipment till handover to project
manager after commissioning, the risk of Ownership shall remain with the
contractor.
4.26.3 Ownership of any Systems and equipment in excess of the requirements
for the Facilities shall revert to the Contractor upon Completion of the
Facilities or at such earlier time when the TSSPDCL and the
Contractoragree that the Systems and equipment in question are no longer
required for the Facilities provided quantity of any Systems and equipment
specifically stipulated in the Contract shall be the property of the TSSPDCL
whether or not incorporated in the Facilities.
4.26.4
Notwithstanding the transfer of ownership of the Systems and
equipment, the responsibility for care and custody thereof together with
the risk of loss or damage thereto shall remain with the Contractor
pursuant to GCCClause 4.27 (Care of Facilities) hereof until Completion of
the Facilities and Taking Over pursuant to GCCClause 4.20or the part
thereof, if any, as per GCCSub-Clause 4.1.1(e) in which such Systems
and equipment are incorporated.
4.27
CARE OF FACILITIES
The Contractor shall be responsible for the care and custody of the
Facilities or any part thereof until the date of Taking Over Certificate
pursuant to GCCClause 4.20 or, where the Contract provides for
Completion of the Facilities in parts, until the date of Completion of the
relevant part, and shall make good at its own cost any loss or damage that
may occur to the Facilities or the relevant part thereof from any cause
whatsoever during such period. The Contractor shall also be responsible
for any loss or damage to the Facilities caused by the Contractor in the
course of any work carried out, pursuant to GCC Clause4.22.
Notwithstanding the foregoing, the Contractor shall not be liable for any
loss or damage to the Facilities or that part thereof caused by any use or
occupation by the TSSPDCL or any third party authorized by the TSSPDCL
of any part of the Facilities.
4.28
LOSS OF
TO
OR DAMAGE
TO PROPERTY;
WORKERS; INDEMNIFICATION
ACCIDENT OR INJURY
4.28.1
The Contractor shall indemnify and hold harmless the TSSPDCL and
its employees and officers from and against any and all suits, actions or
administrative proceedings, claims, demands, losses, damages, costs, and
expenses of whatsoever nature, including attorneys fees and expenses,
in respect of the death or injury of any person or loss of or damage to any
property (other than the Facilities whether accepted or not), arising in
connection with the supply and installation of the Facilities and by reason
of the negligence of the Contractor , or their employees, officers or agents,
except any injury, death or property damage caused by the negligence of
the TSSPDCL, its contractors, employees, officers or agents.
4.28.2
If any proceedings are brought or any claim is made against the
TSSPDCL that might subject the Contractor to liability under GCC Clause
4.28, the TSSPDCL shall promptly give the Contractor a notice thereof and
the Contractor may at its own expense and in the TSSPDCLs name
conduct such proceedings or claim and any negotiations for the settlement
of any such proceedings or claim.
If the Contractor fails to notify the TSSPDCL within twenty-eight (28) days
after receipt of such notice that it intends to conduct any such
proceedings or claim, then the TSSPDCL shall be free to conduct the
same on its own behalf. Unless the Contractor has so failed to notify the
TSSPDCL within the twenty-eight (28) day period, the TSSPDCL shall make
no admission that may be prejudicial to the defense of any such
proceedings or claim.
The TSSPDCL shall, at the Contractors request, afford all available
assistance to the Contractor in conducting such proceedings or claim,
and shall be reimbursed by the Contractor for all reasonable expenses
incurred in so doing.
4.28.3
Notwithstanding anything in this Contract to the contrary, it is
agreed that neither the Contractor nor the TSSPDCL shall be liable to the
other party for loss of production, loss of profit, loss of use or any other
indirect or consequential damages.
4.29
INSURANCE
4.29.1
The Contractor shall at its expense take out and maintain in effect,
or cause to be taken out and maintained in effect, during the
performance of the Contract, the insurances set forth below. The identity
of the insurers and the form of the policies shall be subject to the
(III)
Third Party Liability cover with cross Liability within
Geographical limits of India as on Add-on cover to the
basic EAR(Erection All Risk) cover:
The third party liability add-on cover shall cover bodily injury or
death suffered by third parties (including the TSSPDCLs
personnel) and loss of or damage to
FORCE MAJEURE
4.31.1
Force Majeure shall mean any event beyond the reasonable
control of the TSSPDCL or of the Contractor, as the case may be, and
which is unavoidable notwithstanding the reasonable care of the party
affected, and shall include, without limitation, the following:
Act of GOD, Act of Govt. fires, epidemics, quarantine restrictions, strikes,
lockouts freight embargoes.
(a) War, hostilities or warlike operations (whether war be declared or
not), invasion, act of foreign enemy and civil war,
(b) Rebellion, revolution, insurrection, mutiny, usurpation of
government, conspiracy, riot and civil commotion,
(c) Earthquake, landslide, volcanic activity, flood or cyclone, or other
inclement weather condition, nuclear and pressure waves or other
natural or physical disaster and strikes,
4.31.2
Neither party shall be considered to be in default or in breach of
his obligations under the Contract to the extent that performance of such
obligation is prevented by any circumstances of Force majeure, which
arises after date of Notification of Award.
4.31.3
If either party is prevented, hindered or delayed from or in
performing any of its obligations under the Contract by an event of Force
Majeure, then it shall notify the other in writing of the occurrence of such
event and the circumstances thereof within fourteen (14) days after the
occurrence of such event.
4.31.4
The party who has given such notice shall be excused from the
performance or punctual performance of its obligations under the
Contract for so long as the relevant event of Force Majeure continues and
to the extent that such partys performance is prevented, hindered or
delayed. The Time for Completion shall be extended in accordance with GCC
Clause 4.33.
4.32.1
H.
4.32
4.32.1.1
Subject to GCC Clause 4.32, the TSSPDCL shall have the right to
propose, and subsequently require, that the Project Manager order the
Contractor from time to time during the performance of the Contract to
make any change, modification, addition or deletion to, in or from the
Facilities (hereinafter called Change), provided that such Change falls
within the general scope of the Facilities and does not constitute
unrelated work and that it is technically practicable, taking into account
both the state of advancement of the Facilities and the technical
compatibility of the Change envisaged with the nature of the Facilities as
specified in the Contract.
4.32.1.2
The Contractor may from time to time during its performance of
the Contract propose to the TSSPDCL (with a copy to the Project
Manager) any Change that the Contractor considers necessary or
desirable to improve the quality, efficiency or safety of the Facilities.
The TSSPDCL may at its discretion approve or reject any Change
proposed by the Contractor without any change in contract price.
4.32.1.3
Changes made necessary because of any default of the Contractor
in the performance of its obligations under the Contract shall be not be
deemed to be a Change, and such change shall not result in any
adjustment of the Contract Price or the Time for Completion.
4.32.1.4
The procedure on how to proceed with and execute Changes is
specified in GCC Clause 4.32.
4.32.2
4.32.2.1
The pricing of any Change shall, as far as practicable, be
calculated in accordance with the rates and prices included in the
Contract. If such rates and prices are inequitable, the parties thereto
shall agree on specific rates for the valuation of the Change on
mutual agreement with 28 days from date of such change proposed by
TSSPDCL. If change not finalized on mutual concern it is presumed that
the change proposed is withdrawn.
4.32.2.2
The Contract Price for (i) the items for which quantities have been
indicated as lump sum or lot or set and/or (ii) where the quantities are
to be estimated by the Contractor shall remain constant unless there is
change made in the Scope of Work by TSSPDCL. The quantities and unit
prices (i) subsequently arrived while approving the Bill of Quantities
JMSG RFP VOLUME-I
payment shall be made over and above the lump sum Contract Price. In
case quantities of these items supplied at site are in excess of that
required for successful completion of scope of work, such additional
quantities shall be the property of the Contractor and they shall be
allowed to take back the same from the site for which no deduction from
the lump sum Contract Price shall be made. Further, in case actual
requirement of quantities for successful completion of scope of work is
less than the quantities identified in the approved BOQ /billing breakup
and/or estimated by the Contractor, the lump sum contract price shall
remain unchanged and no deduction shall be made from the lump sum
price due to such reduction of quantities.
It shall be the responsibility of the Contractor to pay all statutory taxes,
duties and levies to the concerned authorities for such surplus material
which would otherwise have been, lawfully payable in case of nondeemed export contracts.
Set/Lot/Lump sum shall be governed as per the requirement of the
corresponding item description read in conjunction with relevant
provisions of Technical Specifications and the Billing breakup referred to
above shall be issued by the TSSPDCL based on Contractors request,
if and as may be required during the currency of the Contract.
4.32.2.3
If before or during the preparation of the Change Proposal it
becomes apparent that the aggregate effect of compliance therewith
and with all other Change Orders that have already become binding
upon the Contractor under this GCC Clause 4.32 would be to
increase or decrease the Contract Price as originally set forth in Contract
Price and Terms of Payment of the Contract Agreement. The percentage
of increase for change orders shall not exceed 10 % of the contract
valve. The TSSPDCL and the Contractor shall mutually agree on specific
rates for valuation of the Change beyond the above set limit.
4.32.2.4
If rates and prices of any change are not available in the Contract,
the parties thereto shall agree on specific rates for the valuation of the
change and all matters therein related to the change. Based on the
same, the TSSPDCL shall, if it intends to proceed with the Change,
issue the Contractor with a Change Order.
4.32.2.5
The TSSPDCL shall issue the Contractor with a Change Order
pursuant to GCC Clause 4.32 by way of amendment to the Contract or
in any other manner deemed appropriate. Even if the TSSPDCL and the
Contractor cannot reach agreement on the price for the Change, an
equitable adjustment to the Time for Completion, or any other matters
related to the Change Proposal, the TSSPDCL may nevertheless instruct
JMSG RFP VOLUME-I
If the parties cannot reach agreement within sixty (60) days from the
date of issue of the Pending Agreement Change Order, then the matter
may be referred to the CGM (Projects) and CGM (Finance) to resolve the
issue.
4.32.3
4.32.3.1
If the Contractor proposes a Change pursuant to GCC Clause
4.32, the Contractor shall submit to the Project Manager a written
Request for Change Proposal, giving reasons for the proposed Change
and which shall include the following:
(a)
(b)
(c)
(d)
(e)
4.33
4.33.1
The Time(s) for Completion specified in the SCC shall be extended if
the Contractor is delayed or impeded in the performance of any of its
obligations under the Contract by reason of any of the following:
(a) any Change in the Facilities as provided in GCC Clause 4.32
(b) any occurrence of Force Majeure as provided in GCC Clause 4.31
(c) any changes in laws and regulations as provided in GCC Clause 4.30or
d) any other matter specifically mentioned in the Contractby such
period as shall be fair and reasonable in all the circumstances and
as shall fairly reflect the delay or impediment sustained by the
Contractor.
4.33.2
Except where otherwise specifically provided in the Contract, the
Contractor shall submit to the Project Manager a notice of a claim for an
extension of the Time for Completion, together with particulars of the event
or circumstance justifying such extension as soon as reasonably
practicable after the commencement of such event or circumstance. As
soon as reasonably practicable after receipt of such notice and supporting
particulars of the claim, the TSSPDCL and the Contractor shall agree
upon the period of such extension. In the event that the Contractor
does not accept the TSSPDCLs estimate of a fair and reasonable time
extension, the Contractor shall be entitled to refer the matter to
Arbitration, pursuant to GCC Clause 4.37.
4.33.3
The Contractor shall at all times use its reasonable efforts to
minimize any delay in the performance of its obligations under the
Contract.
4.34
4.34.1
TERMINATION
Termination for TSSPDCLs Convenience
4.34.1.1
The TSSPDCL may at any time terminate the Contract for any
reason by giving a 30 days prior notice to the Contractor a notice of
termination that refers to this GCC Clause 4.34.
4.34.1.2
Upon receipt of the notice of termination under GCC Clause 4.34,
the Contractor shall either immediately or upon the date specified in the
notice of termination
(a) cease all further work, except for such work as the TSSPDCL may
specify in the notice of termination for the sole purpose of
protecting that part of the Facilities already executed, or any work
required to leave the Site in a clean and safe condition
(b) terminate all contracts, except those to be assigned to the
TSSPDCL pursuant to paragraph (d) (ii) below
(c) remove all Contractors Equipment from the Site, repatriate the
Contractors personnel from the Site, remove from the Site any
wreckage, rubbish and debris of any kind, and leave the whole of
the Site in a clean and safe condition
(d) In addition, the Contractor, subject to the payment specified in GCC Clause
4.34, shall
(i)
(ii)
(a) the Contract Price, properly attributable to the parts of the Facilities
executed by the Contractor as of the date of termination
4.34.2
4.34.2.1
The TSSPDCL, without prejudice to any other rights or remedies it
may possess, may terminate the Contract forthwith in the following
circumstances by giving a notice of termination and its reasons therefor
to the Contractor, referring to this GCC Clause 4.34:
(a) if the Contractor becomes bankrupt or insolvent, has a receiving
order issued against it, compounds with its creditors, or, if the
Contractor is a corporation, a resolution is passed or order is made
for its winding up (other than a voluntary liquidation for the
purposes of amalgamation or reconstruction), a receiver is
appointed over any part of its undertaking or assets, or if the
Contractor takes or suffers any other analogous action in
consequence of debt
(b) if the Contractor assigns or transfers the Contract or any right or
interest therein in violation of the provision of GCC Clause 4.35.
(c) if the Contractor, in the judgment of the TSSPDCL has engaged in
corrupt or fraudulent practices as mentioned in under GCC Clause
4.37 in competing for or in executing the Contract.
d)
If the Contractor
4.34.2.2
Upon receipt of the notice of termination under GCC SubClauses 4.34, the Contractor shall, either immediately or upon such
date as is specified in the notice of termination,
(1) cease all further work, except for such work as the TSSPDCL
may specify in the notice of termination for the sole purpose of
protecting that part of the Facilities already executed, or any work
required to leave the Site in a clean and safe condition
(2) deliver to the TSSPDCL the parts of the Facilities executed by the
Contractor up to the date of termination
(4) deliver to the TSSPDCL all drawings, specifications and other
documents prepared by the Contractor as of the date of
termination in connection with the Facilities.
4.34.2.4
The TSSPDCL may enter upon the Site, expel the Contractor, and
complete the Facilities itself or by employing any third party. The
TSSPDCL may, to the exclusion of any right of the Contractor over the
same, take over and use with the payment of a fair rental rate to the
Contractor, with all the maintenance costs to the account of the
TSSPDCL and with an indemnification by the TSSPDCL for all liability
including damage or injury to persons arising out of the TSSPDCLs use
of such equipment, any Contractors Equipment owned by the
Contractor and on the Site in connection with the Facilities for such
reasonable period as the TSSPDCL considers expedient for the supply and
installation of the Facilities.
Upon completion of the Facilities or at such earlier date as the TSSPDCL
thinks appropriate, the TSSPDCL shall give notice to the Contractor that
such Contractors Equipment will be returned to the Contractor at or
near the Site and shall return such Contractors Equipment to the
Contractor in accordance with such notice. The Contractor shall
thereafter without delay and at its cost remove or arrange removal of the
same from the Site.
4.34.2.5
Subject to GCC Sub-Clause 4.34, the Contractor shall be
entitled to be paid the Contract Price attributable to the Facilities
executed as of the date of termination, the value of any unused or
partially used Systems and equipment on the Site, and the costs, if any,
incurred in protecting the Facilities and in leaving the Site in a clean and
safe condition pursuant to paragraph (a) of GCC Sub-Clause 4.34. Any
sums due to the TSSPDCL from the Contractor accruing prior to the date
of termination shall be deducted from the amount to be paid to the
Contractor under this Contract.
4.34.2.6
If the TSSPDCL completes the Facilities, the cost of completing the
Facilities by the TSSPDCL shall be determined.
If the sum that the Contractor is entitled to be paid, pursuant to GCC
Sub-Clause 4.34, plus the reasonable costs incurred by the TSSPDCL
in completing the Facilities, exceeds the Contract Price for the entire
Facilities if entire Facilities have been completed by the
TSSPDCL or the price for part of the Facilities if part of the Facilities have
been completed by the TSSPDCL, the Contractor shall be liable for such
excess.
If such excess is greater than the sums due to the Contractor under GCC
Sub-Clause 4.34, the Contractor shall pay the balance to the TSSPDCL,
and if such excess is less than the sums due the Contractor under GCC
Sub-Clause 4.34, the TSSPDCL shall pay the balance to the Contractor.
For facilitating such recovery from contractor the TSSPDCL shall claim the
Bank Guarantees of the Contractor available with the TSSPDCL and
retain such other payments due to the Contractor under the Contract in
question or any other Contract that the TSSPDCL may have with the
Contractor.
The TSSPDCL and the Contractor shall agree, in writing, on the
computation described above and the manner in which any sums shall be
paid.
4.34.3 In this GCC Clause 4.34, the expression Facilities executed shall include
all work executed, Installation Services provided, and all Systems and
equipment acquired (or subject to a legally binding obligation to
purchase) by the Contractor and used or intended to be used for the
purpose of the Facilities, up to and including the date of termination.
4.34.4 In this GCC Clause 4.34, in calculating any monies due from the
TSSPDCL to the Contractor, account shall be taken of any sum previously
paid by the TSSPDCL to the Contractor under the Contract, including any
advance payment paid pursuant to the corresponding Appendix (Terms
and Procedures of Payment) to the Contract Agreement.
4.35
ASSIGNMENT
Neither the TSSPDCL nor the Contractor shall, without the express prior
written consent of the other party (which consent shall not be
unreasonably withheld), assign to any third party the Contract or any part
thereof, or any right, benefit, obligation or interest therein or there
under, except that the Contractor shall be entitled to assign either
absolutely or by way of charge any monies due and payable to it or that
may become due and payable to it under the Contract.
I.
RESOLUTION OF DISPUTES
4.36
SETTLEMENT OF DISPUTES
4.36.1
If any dispute of any kind whatsoever shall arise between the
TSSPDCL and the Contractor in connection with or arising out of the
Contract, including without prejudice to the generality of the foregoing, any
4.36.2
If the parties fail to resolve such a dispute or difference by mutual
consultation at the execution site level, then the dispute shall be referred
by the Contractor to the Project Manager, who, within a period of thirty
(30) days after being requested by Contractor to do so, shall give written
notice of his decision.
4.36.2.1
The decision/instruction of the Project Manager shall be deemed to
have been accepted by the Contractor unless notified by the Contractor
of his intention to refer the matter for Arbitration within thirty (30) days
of such decision/instruction.
4.36.2.2
In the event the Project Manager fails to notify his decision as
aforesaid within thirty (30) days, the Contractor, if he intends to go for
Arbitration, shall notify his intention to the Project Manager within 30
days of expiry of the first mentioned period of thirty days failing which it
shall be deemed that there are no dispute or difference between the
TSSPDCL and the Contractor.
4.36.3
In case of dispute or difference between the TSSPDCL and the
Contractor, if the TSSPDCL intends to go for Arbitration, he shall notify
such intention to the Contractor.
4.37
ARBITRATION
The arbitration shall be conducted in accordance with the arbitration
procedure published by the institution named and in the place shown in the
Contract data.
4.38
obstructive practice is
(aa)
or
(bb) acts intended to materially impede the exercise of the
TSSPDCLs inspection and audit rights.
In persuasions of its policy, the TSSPDCL will sanction a firm or
individual, including declaring ineligible, either indefinitely or for a
stated period of time, to be awarded a contract if it at any time
determines that the firm has, directly or through an agent, engaged in
corrupt, fraudulent, collusive, coercive or obstructive practices in
competing for, or in executing, a contract.
4.39
RETENTION:
The employer shall retain from each payment due to the contractor the
proportion stated in the contract Data until completion of whole of works.
On completion of the whole of the works half the total amount retained is
paid to the contractor and half when the defects liability period has passed
and the engineer has certified that all defects notified by the engineer to
the contractor before the end of this period have been corrected, and after
100% verification of the quality, quality and unauthorized services by the
concerned ADE
On completion of the whole works, the contractor may substitute retention
money with an on demand bank guarantee.
Schedule-A:
Refer 2.38.2 (Progressive /Milestone based payment)
SECTION-5
SPECIAL CONDITIONS OF CONTRACT
(SCC)
DESCRIPTION
The Contractor shall, at all times during the continuance of the contract,
comply fully with all existing Acts, regulations and bye laws including all
statutory amendments and reenactments of State or Central Government
and other local authorities and any other enactments, notifications and
acts that may be passed in future either by the State or the Central
government or local authority, including Indian Workmens Compensation
Act 1923, Contract Labour (Regulation and Abolition) Act 1970, the Child
Labour Prohibition and Regulation Act 1986, and Equal Remuneration Act
1976, Factories Act, Minimum Wages Act 1948, Provident Fund Regulations,
Employees Provident Fund Act 1952, EPF Act 1996 and related acts passed
from time to time. Schemes made under the Same Act the Buildings and
other construction workers (Regulation of Employment and condition of
Service) Act 1996, the Cess Act 1996 and also applicable Labour
Regulations, Health and Sanitary Arrangement for Workmen, Insurance and
other benefits and shall keep Employer indemnified in case any action is
commenced by Competent authorities for contravention by the Contractor.
If the Employer is caused to pay or reimburse, such amounts as may be
necessary to cause or observe, or for non-observance of the provisions
stipulated above on the part of the Contractor, the TSSPDCL shall have
the right to deduct from any amounts due to the Contractor, his amount of
Performance Security or recover from the Contractor personally any sum
required or estimated to be required for making good the loss or damage
suffered by the TSSPDCL, responsibility in connection with the employees
of the contractor, who shall, in no case, be treated as the employees of the
Employer at any point of time.
5.1.2 Notices
1. All Certificates, notices or written orders to be given by the Employer
to the Contractor under the terms of the contract shall be served by
sending by post to or delivering the same to Contractors principal
place of business, or such other address or person as nominated for
this purpose by contractor
2. All notices to be given to the Employer under the terms of the
Contract shall be served by sending by post or delivering the same
to the respective addressee nominated for that purpose.
3. The Employers address is
Chief General Manager/ Projects/ TSSPDCL,
4th Floor, Corporate
Office, Mint Compound,
Hyderabad-63.
5.1.3 Working Hours
Before commencement of work, the contractor shall inform in writing, the
normal working hours for his staff and workers. These hours shall be as far
as possible in consonance with the Employers working hours for better
coordination.
All the staff and workers should positively leave the site premises after
these hours, except for authorized watch and ward personnel, approved by
the Employer.
5.2
5.3
ACCIDENTS
The Employer will not be responsible for any damages or compensation
payable inconsequence of an accident or injuries to any of the
Contractors personnel or any third party.
The contractor shall insure at his cost-against any such eventuality as per
rules in force and submit the documentary evidence of the Insurance Policy
taken, positively prior to commencement of work at site and should keep
policy valid by paying premium and other changes will handing over of the
plant.
authority as lay down by the existing rules and regulations and inform the
Employer regarding the same.
5.4
Clause deleted
5.5
INDEMNITIES
5.5.1The contractor is liable for and shall indemnify the TSSPDCL against
losses, expenses and claims for loss or damage to physical property,
personal injury and death caused by his own acts or omissions.
5.5.2The contractor claiming indemnity is to take all reasonable steps to mitigate
lower damage will occur.
5.5.3The contractor shall indemnify the TSSPDCL against claims to
damages caused by the movements of his equipment or temporary
works.
5.5.4The Contractor shall submit an Indemnity Bond to the TSSPDCL
incorporating the above points before taking up the execution of the work.
5.6
TRANSPORT ARRANGEMENT
The contractor shall make the transport arrangement at his cost for his
staff and workers to site.
5.7
LICENSE
The successful bidder shall submit the A grade license issued by CEIG Govt.
Of Telangana state for the agencies engaged in executing the related
workswithin the 60 days from the date of LOI or before starting the field
execution works whichever is earlier
5.8
materials,
Tools
and
Tackles
after
5.9
SAFETY PRECAUTIONS
All the safety measures to avoid accidents shall be followed strictly in
accordance with the safety rules and regulation laid down by the
government authorities.
The Contractor shall take all safety precautions and shall provide proper
scaffolding, life-belts, ladder shock proof helmets, etc. to avoid accidents
and to ensure safety, of not only his personnel but also the safety of the
staff and workers sat the same site.
The contractor shall take necessary precautions to ensure that no part of
the building/structure damage or disfigured due to negligence on his part
while carrying out the work. In case of excess damage, the same shall be
made good by the contractor immediately at his own cost.
Re-commissioning on energized equipment shall be carried out with
proper safety permits issued by the Purchaser/Competent authorities.
When required to work at heights or at hazardous location areas, the
contractor shall carryout the same with utmost care and all safety
precautions.
5.10
FIRE PRECAUTIONS
The contractor shall strictly instruct his site staff and workers to abide by
the regulations in force at the site regarding all precautions to be taken to
avoid fire hazards.
5.11
5.12
SITE DISCIPLINE
Strict discipline shall be observed by all the contractors personnel inside
the premises of the site. The contractor and his personnel shall abide by
all the rules and regulations of the Employer, Disciplinary action shall be
taken against the Contractor/his personnel and their services liable to be
terminated, if found quarrelling/ violating the rules.
5.13
power supply will be provided at one point at the nearest switch room. The
power consumption charges will have to be borne by the Contractor.
However, non-availability of the Crane does not leave the contractor off his
responsibilities.
5.14
5.15
INCOME TAX
a. Deductions will be made towards Income Tax at source by the
TSSPDCL as directed by Income Tax Department.
b. The Contractors staff, personnel and labour will be liable to pay
personnel income taxes in India in respect of such of their salaries
and wages as are chargeable under the laws and regulations for the
time being in force, and the contractor shall perform such duties in
regard to such deductions there of as may be imposed on him by
such laws and regulations and also refer GCC 4.10.2.
5.16
LABOUR
The contractor shall, unless otherwise provided in the contract, make his
own arrangements, for the engagements of all staff and labour, local, or
other, and for their payment, housing, feeding and transport.
The contractor shall, if required by the engineer, deliver to the engineer a
return in detail, in such form and at such intervals as the engineer may
prescribe showing the staff and the numbers of the several classes of
labour from time to time employed by the contractor on the site and such
information respecting contractors equipment as the engineer may require.
5.17
performance security. The Employer/ project manager shall also have right
to recover from the Contractor any sum required or estimated to be required
for making good the loss or damage suffered by the Employer.
II.
III.
j. Industrial Disputes Act 1947: - The Act lays down the machinery
and procedure for resolution of Industrial disputes, in what situations
or lock-out becomes illegal and what are the requirements of laying
off or retrenching the employees or closing down the establishments.
k. Industrial Employment (Standing Orders) Act 1946: - It is
applicable to all establishments employing 100 or more workmen
(employment size reduced by some of the States and Central
government to 50). The Act provides for laying down rules
governing the conditions of employment by the Employment on
matters provided in the Act and get the same certified by the
designated Authority.
l. Trade Union Act 1926: - The Act lays down the procedure for
registration of trade unions of workmen and employers. The Trade
Unions registered under the Act have been given certain immunities
from civil and criminal liabilities.
m.
Child Labour (prohibition & Regulation) Act 1986: - The Act
prohibits employment of children below 14 years of age in certain
occupations and process and provides for regulation of employment
of children in all other occupations and processes. Employment of
Child Labour is prohibited in Building and Construction Industry.
n. Inter-State Migrant Workmens (Regulation of Employment &
Conditions of Service) Act 1979: - The Act is applicable to an
establishment which employs 5 or more inter- state migrant workmen
through an intermediary (who has recruited workmen in one state
for employment in the establishment situated in another state). The
Inter State migrant workmen, in an establishment to which this Act
becomes applicable, are required to be provided certain facilities
such as housing, medical aid, traveling expenses from home up to the
establishment and back, etc.
o. The Building and Other Construction Workers (Regulation of
Employment and Conditions of Service) Act 1996 and the Cess
Act of 1996: All the establishments who carry on any building or
other construction work and employs 10 or more workers are covered
under this Act. All such establishments are required to pay cess at the
rate not exceeding 2% of the cost of construction as may be modified
by the Government. The Employer of the establishment is required to
provide safety measures at the building or construction work and
other welfare measures, such as Canteens, First- Aid facilities,
Ambulance, Housing accommodations for workers near the work place
etc. The Employer to whom the Act applies has to obtain a
registration certificate from the Registering Officer appointed by the
Government.
p. Factories Act 1948: - The Act lays down the procedure for
approval at plans before setting up a factory, health and safety
5.18
PROTECTION OF ENVIRONMENT
The Contractor shall take all reasonable steps to protect the environment
on and off the Site and to avoid damage or nuisance to persons or to
property of the public or others resulting from pollution, noise or other
causes arising as consequence of his methods of operation.
During continuance of the Contract, the Contractor and his Sub-contractors
shall abide at all times by all existing enactments on environmental
protection and rules made thereunder, regulations, notifications and byelaws of the State or Central Government, or local authorities and any other
law, bye-law, regulations that may be passed or notification that may be
issued in this respect in future by the State or Central Government or the
local authority.
Salient features of some of the major laws that are applicable are given below:
The Water (Prevention and Control of Pollution) Act, 1974, this provides for
the prevention and control of water pollution and the maintaining and
restoring of wholesomeness of water. Pollution means such contamination
of water or such alteration of the physical, chemical or biological
properties of water or such discharge of any sewage or trade effluent or of
any other liquid, gaseous or solid substance into water (whether directly or
indirectly) as may, or is likely to, create a nuisance or render such water
harmful or injurious to public health or safety, or to domestic, commercial,
industrial, agricultural or other legitimate uses, or to the life and health of
animals or systems s or of aquatic organisms.
The Air (Prevention and Control of Pollution) Act, 1981, this provides for
prevention, control and abatement of air pollution. Air Pollution means
the presence in the atmosphere of any air pollutant, which means any
solid, liquid or gaseous substance (including noise) present in the
atmosphere in such concentration as may be or tend to be injurious to
human beings or other living creatures or systems s or property or
environment.
The Environment (Protection) Act, 1986, this provides for the protection and
improvement of environment and for matters connected therewith, and the
prevention of hazards to human beings, other living creatures, systems s
and property. Environment includes water, air and land and the interrelationship which exists among and between water, air and land, and
human beings, other living creatures, systems s, micro-organism and
property.
The Public Liability Insurance Act, 1991, This provides for public liability
insurance for the purpose of providing immediate relief to the persons
affected by accident occurring while handling hazardous substances and
for matters connected herewith or incidental thereto. Hazardous
substance means any substance or preparation which is defined
as
hazardous substance under Environment (Protection) Act, 1986, and
exceeding such quantity as may be specified by notification by the Central
Government.
5.20
5.20.1
SAFETY PRECAUTIONS
The Contractor shall observe all applicable regulations regarding safety on the Site.
Unless otherwise agreed, the Contractor shall, from the commencement of
work on Site until Taking Over, provide:
5. 20.4 Periodical examinations and all tests for all lifting/hoisting equipment
& tackles shall be carried-out in accordance with the relevant provisions of
Factories Act 1948, Indian Electricity Act 1910 and associated Laws/Rules
in force from time to time. A register of such examinations and tests shall
be properly maintained by the Contractor and will be promptly produced
as and when desired by the Project Manager or by the person authorized by
him.
5.20.5
The Contractor shall provide suitable safety equipment of
prescribed standard to all employees and workmen according to the need,
as may be directed by the Project Manager
who will also have right to examine these safety equipment to determine
their suitability, reliability, acceptability and adaptability.
5.20.6
The Contractor shall provide safe working conditions to all workmen
and employees at the Site including safe means of access, railings, stairs,
ladders, scaffoldings etc. The scaffoldings shall be erected under the
control and supervision of an experienced and competent person. For
erection, good and standard quality of material only shall be used by the
Contractor.
5.20.7
The Contractor shall not interfere or disturb electric fuses, wiring
and other electrical equipment belonging to the TSSPDCL or other
Contractors under any circumstances, whatsoever, unless expressly
permitted in writing by TSSPDCL to handle such fuses, wiring or electrical
equipment
5.20.8
Before the Contractor connects any electrical appliances to any plug
or socket belonging to the other Contractor or TSSPDCL, he shall:
a. Satisfy the Project Manager that the appliance is in good working condition;
b. Inform the Project Manager of the maximum current rating, voltage
and phases of the appliances;
c. Obtain permission of the Project Manager detailing the sockets to
which the appliances may be connected.
5.20.9
The Project Manager will not grant permission to connect until he is satisfied that;
5.20.12
The Contractors shall employ necessary number of qualified, full
time electricians/electrical supervisors to maintain his temporary electrical
installation.
5.20.13
The Contractor employing more than 250 workmen whether
temporary, casual, probationer, regular or permanent or on contract, shall
employ at least one full time officer exclusively as safety officer to
supervise safety aspects of the equipment and workmen, who will
coordinate with the Project Safety Officer. In case of work being carried
out through Sub- Contractors, the Sub-Contractors workmen/employees
will also be considered as the Contractors employees/workmen for the
above purpose.
The name and address of such Safety Officers of the Contractor will be
promptly informed in writing to Project Manager with a copy to Safety
Officer-In charge before he starts work or immediately after any change of
the incumbent is made during currency of the Contract.
5.20.14
In case any accident occurs during the construction/ erection or
other associated activities undertaken by the Contractor thereby
causing any minor or major or fatal injury to his employees due to any
reason, whatsoever, it shall be the responsibility of the Contractor to
promptly inform the same to the Project Manager in prescribed form
and also to all the authorities envisaged under the applicable laws.
5.20.15
The Project Manager shall have the right at his sole discretion to
stop the work, if in his opinion the work is being carried out in such a way
that it may cause accidents and endanger the safety of the persons
and/or property, and/or equipment. In such cases, the Contractor shall be
informed in writing about the nature of hazards and possible
injury/accident and he shall comply to remove shortcomings promptly.
The Contractor after stopping the specific work can, if felt necessary,
appeal against the order of stoppage of work to the Project Manager
within 3 days of such stoppage of work and decision of the Project
Manager in this respect shall be conclusive and binding on the Contractor.
5.20.16
The
Contractor
shall
not
be
entitled
for
any
damages/compensation for stoppage of work due to safety reasons as
provided in SCC Sub-Clause 5.20.15 above and the period of such
stoppage of work will not be taken as an extension of time for completion
of work and will not be the ground for waiver of levy of liquidated
damages.
5.20.17
It is mandatory for the Contractor to observe during the
execution of the works, requirements of Safety Rules which would
generally include but not limited to following:
Safety Rules
a) Each employee shall be provided with initial indoctrination regarding
safety by the Contractor, so as to enable him to conduct his work in a
safe manner.
take
for the safety of personnel or the Contractor does not prevent hazardous
conditions which cause injury to his own employees or employees of other
Contractors or TSSPDCLs employees or any other person who are at Site or
adjacent thereto, then the Contractor shall be responsible for payment
of a sum as indicated below to be deposited with the TSSPDCL, which
will be passed on by the TSSPDCL to such person or next to kith and kin of
the deceased:
a.
b.
5.20.21
Permanent disablement shall have same meaning as indicated in
Workmens Compensation Act. The amount to be deposited with
TSSPDCL and passed on to the person mentioned above shall be in
addition to the compensation payable under the relevant provisions of the
Workmens Compensation Act and rules framed there under or any other
applicable laws as applicable from time to time. In case the Contractor
does not deposit the above mentioned amount with TSSPDCL, such
amount shall be recovered by TSSPDCL from any monies due or becoming
due to the Contractor under the contract or any other on-going contract.
5.20.22
The Contractor shall also submit Safety Plan as per proforma
specified in Section Sample Forms and Procedures of the Bidding
Documents along with all the requisite documents mentioned therein
and as per check-list contained therein to the Engineer In-Charge for its
approval within 60 days of award of Contract.
5.21
ARBITRATION
5.21.1
All disputes or differences in respect of which the decision, if
any, of the Project Manager and/or the Head of the Implementing
Authority has not become final or binding as aforesaid shall be settled by
arbitration in the manner provided herein below:
5.21.2 The arbitration shall be conducted by three arbitrators, one each to be
nominated by the Contractor and the TSSPDCL and the third to be
appointed by both the arbitrators in accordance with the Indian Arbitration
Act. If either of the parties fails to appoint its arbitrator within sixty (60)
days after receipt of a notice from the other party invoking the Arbitration
clause, the arbitrator appointed by the party invoking the arbitration clause
shall become the sole arbitrator to conduct the arbitration.
5.21.3 The language of the arbitration proceedings and that of the documents
and communications between the parties shall be English. The arbitration
shall be conducted in accordance with the provisions of the Indian
Arbitration and Conciliation Act, 1996 or any statutory modification
thereof. The venue of arbitration shall be the state capital of the employer.
5.21.4 The decision of the majority of the arbitrators shall be final and binding
upon the parties. In the event of any of the aforesaid arbitrators dying,
neglecting, resigning or being unable to act for any reason, it will be lawful
CONTRACT DATA
Contract price is Rs
(GCC 4.1(h))
Effective Date
(GCC
(GCC
4.1(ee))
Sl.
No
1.
Activities
Jeedimetla Smart Grid
project
Implementation
(GCC 4.8.1)
Work completion schedule (to be attached as Schedule B) Also refer Annexure 4, Volume
II
(GCC 4.4.1)
The contractor shall submit the revised work completion schedule for the Smart
Grid Pilot Project at Jeedimetla within 15 days of date of award of contract (LOA).
(GCC 4.14.2)
Sl.No Activity
.
M M
M M M M
6 7
(GCC 4.14.1)
The defect liability period is 12 months from the date of taking over /completion
of facilities (or any part thereof) (GCC 4.22.2)
The name and identification number of the contact is bid No.-Bid. No.
CGM(P)/Smart Grid/No.1
/2015-16, Dt. 29-06-2015
(Insert name and number as including in the invitation for bids (or prequalification, if
any))
The works consist of
under the project).
(GCC 1. (n))
The intended completion date for the whole of the works is 18 months
comply with the work completion schedule.
(GCC 4.4.1)
The language of contract data is English.
(GCC 2.3)
(GCC 4.2.14)
(GCC
(GCC
4.39)
Arbitration will take place in accordance with Indian Arbitration conciliation act 1996 at
Hyderabad,
A.P only.
(GCC4.39)
The proportion of payments retained (retention money) shall be 6 % from
each bill subject to a maximum of 5 % of contract valve.
(GCC 4.41)
The liquidated damages for whole of the works are @ Rs.0.5 % per week of delay
or part thereof on the balance contract amount.
(GCC 4.21.2)
The maximum amount of liquidated damages for the whole of the works is 5 % of final
contract price.
(GCC4.21.2)
No bonus is intended to be paid.
(GCC 4.21.3)
SECTION-6
SAMPLE
FORMS/ATTACHMENTS/PROFORMA/
APPENDIX/ANNEXURE & PROCEDURES
SECTION-6:
SAMPLE
FORMS/ATTACHMENTS/PROFORMA/APPENDIX/ANNEXURE
& PROCEDURES
ATTACHMENT-1:
(Specification No.
To
The Chief General Manager (Projects),
Having examined the Bidding Documents, including Amendment Nos. (Insert Numbers)
dated
........................, the receipt of which is hereby acknowledged, we the
undersigned, offer to design, manufacture, test, deliver, install and
commission (including carrying out Trial Operation, Performance &
Guarantee Test as per provision of Technical Specification) the Facilities
under the above-named package in full conformity with the said Bidding
Documents.
2.
and
the price Bid shall be deemed to include and account for the full scope as
aforesaid, including overheads and profit.
3.3 We declare that as specified in the ITB Clause 2.21.5, Volume-I of the
Bidding Documents, prices to be quoted by us in the Price Schedules in
price Bid shall be on FIRM price basis during the execution of Contract.
4. TAXES AND DUTIES
4.1 We confirm that except as otherwise specifically provided our Bid Prices in
Bid shall include all taxes, duties including VAT, octroi, labourcess, service
tax and all local taxes, levies and charges as may be assessed on us, our
Vendors or their employees by all municipal, state or national government
authorities in connection with the Facilities, in and outside of India.
4.2 We confirm that we shall also get registered with the concerned Sales Tax
Authorities, in all the states where the project is located.
4.3 We confirm that no Sales Tax/VAT in any form shall be payable by you for the
bought out items which shall be dispatched directly by us under the First
Contract (as referred in Para4.5 below) to the project site. However, you
will issue requisite Sales Tax declaration/Vatable forms in respect of such
bought out items, on production of documentary evidence of registration
with the concerned Sales Tax Authorities.
4.4 Statuary Variations: We have noted and agree that
Any variation up or down in taxes and duties, new levies introduced
after bid submission and during contract agreement period will be to
the account of TSSPDCL.
Any Difference that accrues due to change of above taxes and duties
will be granted with the approval of chief general manager (projects)
and chief General Manager (Finance) on production of documentary
evidence.
Beyond date of scheduled contract agreement period any increase
in statuary levies shall be to the account of the bidder. However any
decrease in the statuary levies during the scheduled contract period
agreement shall be to the advantage of TSSPDCL.
TSSPDCL shall not bare any liability in respect of personnel taxes,
corporate taxes of the consortium and their vendors and service tax
VAT in respect of agents.
4.5 CONSTRUCTION OF THE CONTRACT
We declare that we have studied GCC Sub-Clause 4.2.1 relating to
mode of contracting for Domestic Bidders and we are making this proposal
with a stipulation that you shall award us two separate Contracts viz. First
Contract for ex-works supply of all equipment and materials including
mandatory spares and Second Contract for providing all the services
i.e. inland transportation for de2.livery at site, unloading, storage,
handling at site, installation, testing and commissioning including Trial
Operation in respect of all the equipment supplied under
the First Contract and other services specified in the Contract Documents.
We declare that the award of two contracts will not in any way dilute our
responsibility for successful operation of systems /equipment and
fulfilment of all obligations as per Bidding Documents and that both the
Contracts will have a cross-fall breach clause i.e. a breach in one contract
will automatically be classified as a breach of other contract which will
confer on you the right to terminate the other Contract at our risk and cost.
4.6
We have read the provisions of following clauses and confirm that the
specified stipulations of these clauses are acceptable to us:
(a)
ITB 2.23
Bid Security
(b)
GCC 4.2.14
Governing Law
(c)
GCC 4.8
Terms of Payment
(d)
GCC 4.9.3
Performance Security
(e)
GCC 4.10
(f)
GCC 4.21
(g)
GCC 4.22
Completion Time
Guarantee
Defect Liability
(h)
GCC 4.24
Patent Indemnity
(i)
GCC 4.25
Limitation of Liability
(j)
GCC 4.36
Settlement of Disputes
(k)
GCC 4.37
Arbitration
OR
@ We have read the provisions of following clauses and confirm that the
specified stipulations of these clauses are acceptable to us except for the
deviations as listed in Attachment-5. The cost of withdrawal of deviations
from above mentioned critical provisions, if remained unresolved during
Bid evaluation, shall be indicated in our (Price) Bid.
(a)
ITB 2.23
Bid Security
(b)
GCC 4.2.14
Governing Law
(c)
GCC 4.8
Terms of Payment
(d)
GCC 4.9.3
Performance
Security
(e)
GCC 4.10
(f)
GCC 4.21
(g)
GCC 4.22
Defect Liability
(h)
GCC 4.24
Patent Indemnity
(i)
GCC 4.25
Limitation of Liability
(j)
GCC 4.36
Settlement of Disputes
(k)
GCC 4.37
Arbitration
(l)
4.12
Name
and
address
of agent
Purpose of
Commission
gratuity
or
20
. Thanking you,
we remain,
Yours faithfully,
(Signature)..................................
(Printed Name)............................
(Designation)...............................
(Common Seal)...........................
Date:
Place:
Business Address:
Country of
Incorporation:
(State or Province to be
indicated) Name of the
To:
(Signature)...................................................
Place:...................
(Printed Name)...........................................
(Designation)................
..............................
(Common Seal)
ATTACHMENT-3:
To: <TSSPDCL
Unit
Quantity
(Signature)...................................................
Place:...................
(Printed
Name)..........................................
(Designation)................
..............................
(Common Seal)
ATTACHMENT-4:
To: <TSSPDCL
Item Description
No.
Quantity proposed
to be
bought/vendor
1.
2.
3.
4.
5.
Date:....................
(Signature)...................................................
Place:...................
(Printed Name).........................................
(Designation)......................................
(Common Seal)
.
ATTACHMENT-5:
To: <TSSPDCL
Provision
Status as per
as per the
technical
bidding
specifications(de
document
viation or
Contract, Vol.-I
Detailed
description of
deviation or
exception
Reas
on
for
the
Date:....................
Place:...................
(Signature)...............................................
(Printed Name)...................................
(Designation).....................................
(Common Seal)..................................
To: <TSSPDCL
Sl. No.
Specification,
Answer
Date:....................
(Signature)...................................................
Place:...................
(Printed
Name)........................................
(Designation)....................................
(Common Seal)............................
..
ATTACHMENT-7:
Dear Sir,
We hereby declare that the following Work Completion Schedule shall be followed
by us in furnishing and installation of the subject Package i.e., Jeedimetla Smart
Grid project Implementation for the period commencing from the effective date
of Contract to us:( to be linked with work schedule)
Sl.
No.
Description Work
b)
completion
Equipment Design and Specification
a)commencement
b)
completion
Procurement of raw
materials
commencement
b)
completion
Type
Tests
commencem
ent
b)
completion
Manufacturing
a)commencement
b)
completion
Factory Test
a)commencement
b)
completion
completion
Establishment of Site
Office
commencement
b)
completion
Installation
at Site
a)commencement
b)
10
completion
11
completion
Trial Operation
a)commencement
b)
completion
Date:....................
(Signature)........................................................
Place:...................
.
(Printed Name)........................................
(Designation)...............
..............................
(Common Seal)...
..........................................
ATTACHMENT-8:
GUARANTEE DECLARATION
To:
<TSSPDCL
Address
Dear Sir
We conform that the equipment offered shall have minimum performance
specified in Technical Specification. The guaranteed performance or efficiency of
the systems and equipment offered are enclosed. We further guarantee the
performance/efficiency of the equipment in response to the Technical
Specifications.
Date:....................
..
Place:...................
(Signature).................................................
(Printed Name)...........................................
.
(Designation)..............
..............................
(Common Seal)..
..........................................
>
ATTACHMENT-9:
INFORMATION
EMPLOYEES OF TSSPDCL
ORGANIZATION(AYL) or deviation
REGARDING EXIN
OUR
To:
<TSSPDCL
Address
Dear Sir,
We hereby furnish the details of ex-employees of TSSPDCL who had retired/
resigned at the level of General Manager and above from the TSSPDCL and
subsequently have been employed by us:
Sl.No.Name of the
person
With Designation in
Date of Retirement/
resignation from
designation in our
TSSPDCL
TSSPDCL
Organization
1.
2.
3.
..
..
Date:....................
..
(Signature).................................................
Place:...................
(Printed Name)...........................................
.
(Designation)............................................
(Common Seal)..............
.......................
Note: The information in similar format should be furnished for each partner of
joint venture in case of joint venture bid.
ATTACHMENT-10:
ACCOUNTABILITY(AYL)
DECLARATION
REGARDING
SOCIAL
To: <TSSPDCL
Date:....................
..
(Signature).................................................
Place:...................
(Printed Name)...........................................
.
(Designation)..............
..............................
(Common Seal)..
..........................................
To: <TSSPDCL
2.
Registered Office:
Branch Office:
Correspondence
3.
Deleted
4.
5.
6.
7.
8.
9.
10.
11.
12.
Telephone No(s).
Address
Landline(
s):
13.
Mobile(s)
:Name
Emailof the
Bank: Address
of Branch:
Account No.:
Type of
Account: [ ]
Saving
14.
15.
[ ] Current
(Signature).................................................
Place:...................
(Printed Name)...........................................
.
(Designation)..............
..............................
(Common Seal).........................................
ATTACHMENT-12:
ADDITIONAL INFORMATION(AYL)
Jeedimetla smart grid
project implementation
To: <TSSPDCL
1.0
1.1 In accordance with 1.0, certificate(s) from banker as per requisite format,
indicating various fund based/non fund based limits sanctioned to the
bidder and the extent of utilization as on date is/are enclosed, as per the
following details:
1.2 The Bidder should accordingly also provide the following information/documents:
(i)
Details of Banker:
Name of Banker
Address of Banker
Telephone No.
Contact Name and
Title
Fax No.
E-mail ID
(ii) As per Para 1.0, Authorization Letter(s) from the bidder addressed to
the Banker(s), authorizing TSSPDCL to seek queries about the bidder
with the Banker(s) and advising the Banker(s) to reply the same
promptly, is/are enclosed as per following details:
Sl.
No.
Letter Ref.
Date
Addressed to
(name of the
Bank)
Name
of
client, Details
of Award for
cause
of Contract
or against
litigation/arbitration
the bidder
and
date
and
matter
in
Disput
ed
amoun
t
Details of
Contract
Value of outstanding
work (in INR)
Estimated completion
date
DOCUMENT
Attach
ed?
(Yes/
Reference
to
documents
uploaded
Softcopy/
hard copy
/both
and
AYL
Company/subsidiary/holding
company/technical collaborator as
on date of technical bid opening
with a value of not less than Rs. 3
Crores (INR).
1.Outage Management
2.SCADA /Distribution Management
3.System Peak Load Management
4.Power Quality
Or
The bidder on its own or any
Consortium member or associate
partner can be a System integrator
with installation and commissioning
experience. The System integrator
should have completed at least one
project of value not less than Rs.3
Crores, involving utility application
software,
hardware,
and
communication system or electric
distribution network automation in
the last seven (7) years in India or
abroad.
The lead partner of the consortium
is fully responsible and liable to
TSSPDCL for the deliverable from
associate partner.
Letter
of
Consent
by
each
Consortium
Member
reviewing
9
each element of the Bid as per
Attachment-20
Company Profile document with
evidence of fields of competence
10. and office location for
each
Consortium Member.
11 List of all Clients served by each
Member of the ConsortiumAttachment-21.
12 Financial Turnover statement along
with Audited Financial Statements
distinctly indicating the revenue
heads
and
turnover
for the
Financial Years2009-10, 2010-11,
2011-12 and 2012-13,2013-14 for
each member of the ConsortiumAttachment-22.
13 Details
of liquid assets given by the
banker
14 Certificate by the Company Human
Resources
Head
or
Company
Secretary indicating the number of
skilled
manpower for relevant
technical skill set, individually for
each
Consortium
MemberAttachment- 24
15 Curriculum Vitae of all personnel
indicated of this RFP-Attachment-35
AYL
16. Work
completion schedule as
per Attachment-07
P1DI
17
P1DI
18
19
20
AYL &P1DI
P1DI $AYL
AYL
AYL
AYL
P1DI
21
22
Integrity Pact-Attachment-32
23
24
AYL
26
Note: Bidders are requested to fill up the above table (last three columns).
Bidders' are requested not to enclose more than four reference projects
executed/under execution to claim qualifying requirements. It may please be
noted that supporting document shall indicate clearly the scope of work, cost
of project, start & completion dates (supportive documents may include all or
in any combination - work order, agreement, end user certificate with contact
details and indicating requested information for claiming qualifying criteria as
per RFP). Also bidder's need to indicate the enclosed best two project reference
details in column no-4 (primary and secondary) among the enclosed four
projects /works against Sl. No.5
(Sign and Seal of Bidder)
ATTACHMENT-14:
[To be on non-judicial stamp paper of Rupees One Hundred Only (INR 100/-) or
appropriate value as per Stamp Act relevant to place of execution, duly signed on
each page.
Reference No. . Bank Guarantee No. ... Dated: .
.
To:
Dear
Sir,
WHEREAS . *Insert name of the Lead Consortium Member+ with
address . *Insert address of the Lead Consortium Member+ having its
registered office at . *Insert address of the Lead Consortium Member+
(hereinafter, the Bidder) wishes to participate in Tender No. (the RFP)
issued by .. (hereinafter, the Beneficiary) for Appointment of Smart Grid
Implementing Agency for Implementation of Smart Grid Pilot Project. And
WHEREAS a Bank Guarantee for Rupees ..Only (INR ../-) valid till .. is
required to be submitted by the Bidder along with the RFP.
We,. *Insert name of the Bank and address of the Branch giving the
Bank Guarantee+ having our registered office at . *Insert address of
the registered office of the Bank+ hereby give this Bank Guarantee No.
. *Insert Bank Guarantee number+ dated . *Insert the date of
the Bank Guarantee], and hereby agree unequivocally and unconditionally to
pay immediately on demand in writing from the Beneficiary any officer
authorized by it in this behalf any amount not exceeding Rupees to the
said Beneficiary on behalf of the Bidder.
We . *Insert name of the Bank+ also agree that withdrawal of the Bid
or part thereof by the Bidder within its validity or non-submission of Performance
Security by the Bidder within the stipulated time of the Letter of Award to the
Bidder or any violation to the relevant terms stipulated in the RFP would
constitute a default on the part of the Bidder and that this Bank Guarantee is
liable to be invoked and encashed within its validity by the Beneficiary in
case of any occurrence of a default on the part of the Bidder and that the
encashed amount is liable to be forfeited by the Beneficiary.
JMSG RFP VOLUME-I
Page 152 of 223
This agreement shall be valid and binding on this Bank up to and inclusive of
. *Insert the date of validity of the Bank] and shall not be terminable
by notice or by Guarantor change in the constitution of the Bank or the firm
of the Bidder Or by any reason whatsoever and our liability hereunder shall
not be impaired or discharged by any extension of time or variations or
alternations
*I*nInsesertrt
tthhee
AAuutthhoorriizze
ssigignnaattuurre BBaannk edd
e ooff
kss
SSigignnaatotory
ry] ]
Attested:
. *Signature+ (Notary Public)
Place:
Date: .
[Reference No.]
From:
[Address of the Bidder]
[Telephone No., Fax No.,
Email] [Date]
To:
Sub: Query.
Ref:
Dear Sir,
Please find below our query with respect to the RFP subject to the terms and conditions
therein:
Sl.
No.
Reference
Clause No.
Page No.
Concise
Query
1.
2.
3.
Thanking you,
Sincerely yours,
[Insert Signature
here] [Insert
Name here]
[Insert Designation here]
3. Bid Security
We have enclosed an Bid Security of Rupees .. in the form of a Bank Guarantee
No. .
*Insert Bank Guarantee Number+ (OR Demand Draft) dated .
*Insert date of the Bank Guarantee] as per format of the RFP from .
*Insert name of Bank providing Bid Bond+ and valid up to .
4. No Deviation
We have submitted our Financial Bid strictly as per terms and formats of the
RFP, without any deviations, conditions and without mentioning any
assumptions or notes for the Financial Bid in the said format.
5. Acceptance
We hereby unconditionally and irrevocably agree and accept that the decision
made by TSSPDCL in respect of any matter regarding or arising out of the
RFP shall be binding on us. We hereby expressly waive any and all claims in
respect of Bid process.
7. Contact Person
Details of the contact person representing our Bidding Consortium supported
by the Power of Attorney prescribed in the RFP are furnished as under:
Name:
.
Signature of signing authority
Designation:
.
Company:
.
Address: .
.
.
Mobile:
Phone:
Fax:
.
Email: .
8. We are submitting herewith the Technical Bid containing duly signed formats,
both in electronic and physical forms, (duly attested) as desired by you in the
RFP for your consideration.
9. We are also submitting herewith the Financial Bid in electronic form only, as
per the terms and conditions in the RFP.
10.
It is confirmed that our Bid is consistent with all the requirements of
submission as stated in the RFP and subsequent communications from
TSSPDCL.
11.
The information submitted in our Bid is complete, strictly as per the
requirements stipulated in the RFP and is correct to the best of our
knowledge and understanding. We would be solely responsible for any errors
or omissions in our Bid.
12. We confirm that all the terms and conditions of our Bid are valid for acceptance
for a period of
from the Bid Submission Deadline.
14. We confirm that no order/ ruling has been passed by any Competent
Court or Appropriate Commission against us or any of our Consortium
Members or Associates in the . from the Bid Submission Deadline for
breach of any contract and that the Bid Security submitted by the us or any
of our Consortium Members has not been forfeited, either partly or wholly, in
any bid process in the preceding . from the Bid Submission Deadline.
Thanking you,
Sincerely yours,
[Insert Signature
here] [Insert
Name here]
[To be on non-judicial stamp paper of Rupees One Hundred Only (INR 100/-) or
appropriate value as per Stamp Act relevant to place of execution, duly signed on
each page.]
[The Bidding Consortium should list the name, address of its registered office and
other details of all the Consortium Members above.]
for the purpose of submitting the Bid in response to the RFP and in the event of
selection as Selected Bidder to comply with the requirements as specified in
the RFP and ensure execution of the RFP Documents as may be required to be
entered into with TSSPDCL.
Party 1, Party 2, Party 3,... and Party n are hereinafter collectively referred to as
the Parties and individually as a Party.
WHEREAS Clause ... of the RFP stipulates that the Bidders qualifying on the
strength of a Bidding Consortium shall submit a legally enforceable Consortium
Agreement in a format specified in the RFP, whereby each Consortium Member
undertakes to be liable for its Roles and Responsibilities, provide necessary
guarantees and pay required fees as required as per the provisions of the RFP,
as specified herein.
WHEREAS any capitalized term in this Agreement shall have the meaning
ascribed to such term in the RFP document.
NOW THEREFORE, THIS INDENTURE WITNESSTH AS UNDER:
In consideration of the above premises and agreement all the Parties in this
Consortium do hereby mutually agree as follows:
of
all
the
other Members
of
the
M/s.
instructions for and on behalf of all Members. The Roles and Responsibilities of
all other members shall be as per the Annexure to this Agreement.
3.The Lead Member shall be liable and responsible for ensuring the individual and
collective commitment of each of the Members of the Consortium in discharging
all their respective Roles and Responsibilities. Each Consortium Member further
undertakes to be individually liable for the performance of the Roles and
Responsibilities without in any way limiting the scope of collective liability
envisaged in this Agreement in order to meet the requirements and obligations of
the RFP.
4.In case of any breach of any of the commitment as specified under this
Agreement by any of the Consortium Members, the all Members of the
Consortium and Parties shall be liable to meet the obligations under the RFP.
7.It is hereby agreed that the Lead Consortium Member shall furnish the Bid
Security, as stipulated in the RFP, on behalf of the Bidding Consortium.
Consortium Members respectively from time to time in response to the RFP for
the purposes of the Bid.
a. has been duly executed and delivered on behalf of each Party hereto and
constitutes the legal, valid, binding and enforceable obligation of each such
Party;
b. sets forth the entire understanding of the Parties hereto with respect to the
subject matter hereof; and
c. may not be amended or modified except in writing signed by each of the
Parties and with prior written consent of TSSPDCL.
IN WITNESS WHEREOF, the Parties to the Consortium Agreement have, through
TSSPDCL, executed these presents and affixed common seals of their respective
companies on the Day, Month and Year first mentioned above.
1. Common Seal of
.................................. has
been affixed in my/ our presence
pursuant to Board Resolution dated
.....................
of
the
Authorized
Representative]
1.1. Witness 1
1.2. Witness 2
[Signature of Witness 1]
[Signature of Witness 1]
Designation:
Designation:
n. Common Seal of
.................................. has
been affixed in my/ our presence
pursuant to Board Resolution dated
.....................
n.3. Witness 1
[Designation
n.4. Witness 2 of
[Signature of
[Signature of
Witness 1]
Witness 1]
the
.............................................................. ................................................................
..
Designation:
Designation:
Attested:
. *Signature+ (Notary Public)
Place: .
Date: .
[To be provided by each Consortium Member (other than the Lead Consortium
Member) in favour of the Lead Consortium Member.]
WHEREAS (TSSPDCL) has issued for Tender No. . (the RFP) dated
. for inviting Bids in respect of Appointment of Smart Grid
Implementing Agency for Implementation of Smart Grid Pilot Project (the
Project) on the terms contained in the RFP;
WHEREAS all the Members of the Consortium have agreed under the Consortium
Agreement dated
.. (the Consortium Agreement), entered into between all the Members
and submitted along with the Bid to appoint .. *Insert the name and
address of the Lead Consortium Member] as Lead Consortium Member to
represent all the Members of the Consortium for all matters regarding the RFP
and the Bid;
AND WHEREAS pursuant to the terms of the RFP and the Consortium Agreement,
we, the Members of the Consortium hereby designate M/s .. *Insert
name of the Lead Member+ as the Lead Consortium Member to represent us
in all matters regarding the Bid and the RFP, in the manner stated below:-
registered
office
of
the
Member
3+
,
...,
. *Insert name and address of the
registered office of the Member 4] do hereby constitute, appoint and
authorize *Insert name and registered office address of
the Lead Consortium Member], which is one of the Members of the Consortium,
to act as the Lead Member and our true and lawful attorney, to do in our name
and on our behalf, all such acts, deeds and things necessary in
We, as Members of the Consortium, hereby agree to ratify all acts, deeds and
things done by our said attorney pursuant to this Power of Attorney and that all
acts, deeds and things done by our aforesaid attorney shall be binding on us and
shall always be deemed to have been done by us.
All the terms used herein but not defined shall have the meaning ascribed to
such terms under the RFP.
Signed by the within named . *Insert the name of
the executant Consortium Member] through the hand of Mr. / Ms. / Dr.
. duly authorized by the Board to issue such
Power of Attorney dated this . day of
Accepted
(Signature of Attorney)
[Insert Name, designation and address of the Attorney]
Attested
.
. (Signature of the
executant)
Designation.............
2. .
(Signature) Name
.
Designation.............
Notes:
a. The mode of execution of the power of attorney should be in accordance
with the procedure, if any, laid down by the applicable law and the
charter documents of the executant(s).
b.In the event, power of attorney has been executed outside India, the same
needs to be duly notarized by a notary public of the jurisdiction where it
is executed.
ATTACHMENT-19:
[To be on non-judicial stamp paper of Rupees One Hundred Only (INR 100/-) or
appropriate value as per Stamp Act relevant to place of execution.
Know all men by these presents, we . [Insert
name and address of the registered office of the Lead Consortium Member of
the Bidding Consortium] do hereby constitute, appoint and authorize Mr./Ms.
[Insert name and residential address],
who is presently employed with us and holding the position of
. as our true and lawful attorney, to do in our name
and on our behalf, all such acts, deeds and things necessary in connection
with or incidental to submission of our Bid in response to Tender No.
(the RFP) dated .. for Appointment of Smart Grid
Implementing Agency for Implementation of Smart Grid Pilot Project (the
Project) issued by the .. (TSSPDCL), including signing and submission of
the Bid and all other documents related to the Bid, including but not limited
to undertakings, letters, certificates, acceptances, clarifications, guarantees or
any other document which TSSPDCL may require us to submit. The aforesaid
attorney is further authorized for making representations to TSSPDCL, and
providing information / responses to TSSPDCL, representing us in all matters
before TSSPDCL, and generally dealing with TSSPDCL in all matters in
connection with our Bid till the completion of the bidding process as per the
terms of the RFP.
We hereby agree to ratify all acts, deeds and things done by our said attorney
pursuant to this Power of Attorney and that all acts, deeds and things done by
our aforesaid attorney shall be binding on us and shall always be deemed to
have been done by us.
All the terms used herein but not defined shall have the meaning ascribed to
such terms under the RFP.
Signed by the within named........................................... [Insert the name
of
the
executant
company]
through
the
hand
of
Mr.
. duly authorized by the Board to issue such
Power of Attorney dated this . day of
Accepted
(Signature of Attorney)
[Insert Name, designation and address of the Attorney]
Attested
.
. (Signature of the
executant)
(Name, designation and address of the executant)
.
Signature and stamp of Notary of the place of execution
Common seal of has been affixed in my/our presence pursuant to
Board of Directors Resolution dated
WITNESS:
1. .
(Signature) Name
.
Designation.............
2. .
(Signature) Name
.
Designation...........
.. Notes:
d.The mode of execution of the power of attorney should be in accordance
with the procedure, if any, laid down by the applicable law and the
charter documents of the executant(s).
e.In the event, power of attorney has been executed outside India, the
same needs to be duly notarized by a notary public of the jurisdiction
where it is executed.
[On the letter head of each Member of the Consortium including Lead Member]
[Reference No.]
From
:
[Address of the Lead Consortium
Member] [Telephone No., Fax No., Email]
[Date]
To:
We hereby confirm our concurrence with the RFP including in particular the
Consortium Agreement and the Bid submitted by ................ [Insert name
of the Lead Consortium Member], in response
to the RFP. We confirm that the Bid has been reviewed and each element of
the Bid is agreed to including but not limited to the commitment and obligations
of our Company.
The details of contact person are furnished as
under: Name:
Designation:
Name of the Company:
Address:
Phone Nos. :
Fax
Nos. :
Thanking you,
Yours faithfully,
..
[Signature, Name, Designation of Authorized Signatory of Consortium Member and
Company's Seal]
Business Address:
[Name and address of principal officer]
[Note:
1.
Each Consortium Member shall attach an individual sheet listing out the Clients.
2.It is mandatory to list out all Clients served by the Consortium Member ..
3.The Letter of Award or Work Order corresponding to each Client shall be
attached with this format.]
Sl
.
N
o
Name
of Client
Company
Date of Expecte
d Date
Letter
of
Award/
Work
Order
of
Complet
io n of
Work
(as
1.
2.
3.
per
work
Actual
Brief
Date
of descript
Completio ion of
n of Work
nature
(attach
of Work
completi
on
certifica
te from
Client)
Contac
t
Person
,
design
ati on,
email
and
mobile
from
Client
Compa
Con
fir
m
atta
ch
men
t of
wor
k
orde
r by
initi
2009-10,
2010-11
2011-12
2012-13
2013-14
Indian
The above Turnovers and Net Profits are arrived from our Audit Reports for the
years 2009-10, 2010-11, 2011-12 and 2012-13,2013-14 duly submitted to the
Income Tax Department along with our Audit Reports.
Hence we certify from the records submitted to us. Thanking you,
[Official seal of the Chartered Accountant]
Date: [Date]
Sincerely yours,
......................................................
[Insert Name of the Chartered Accountant]
[Insert address and contact information
of the Chartered Accountant] Place:
[Place]
ATTACHMENT-23:
Sl. Na
No. me
of
Clie
nt
Com
p
any
1.
Date
of
Lett
er of
Awa
rd
/
Wor
k
Ord
er
Expect
ed
date
of
comple
ti on
as per
Work
Order
Actual
Date
of
Compl
et ion
as
certifi
ed by
Client
No.
No.
of
Consu
m ers
catere
d to.
of
nodes
(incl.
meter
s,
DCUs,
repea
te rs,
RTUs,
Wor
k
Ord
er
Valu
e
(In
IN
R)
Confir
m
attach
me nt
of
Work
Order.
Confirm
attachmen
t of
satisfactor
y work
completio
n
certificate
from
Client.
2.
3.
4.
ATTACHMENT-24:
RESOURCE
[Reference No.]
From:
[Address of the Lead Consortium
Member] [Telephone No., Fax No., Email]
[Date]
To:
Dear Sir,
Sl.
No.
Name of Personnel
Qualification
Area of
Expertise
Years
of
Experience
Sincerely yours,
Date: [Date]
Place: [Place]
......................................................
[Insert Name of the Company Secretary]
[Insert address and contact
information of the Company
Secretary
ATTACHMENT-25:
SUPPLY AND
FORMAT
OF
MANUFACTURER'S
AUTHORIZATION
SUPPORT(P1DI)
[Reference No.]
From:
[Address of the Lead Consortium
Member] [Telephone No., Fax No., Email]
[Date]
To:
Dear Sir,
The details of contact person with respect to this Bid are furnished as under:
OF
Name:
Designation:
Phone Nos. :
Fax
Nos. :
E-mail address:
ATTACHMENT-26:
REFERENCE ONLY)
FORMAT
OF
SUBMISSION
OF
FINANCIAL
BID
(FOR
C.Any variation up or down in taxes and duties, or new levies introduced after Bid
submission date and during
contract
agreement
period will be to
theaccount
of
Employer.
D.Beyond the date of schedule contract agreement period any increase in statutory
levies shall be
to the account of the bidder. However any decrease in the statutory levies after
the schedule contract period of the agreement shall be taken into consideration
to the advantage of the Employer only.
E. The details quoted herein shall stand valid at least for .. months from the
date of submission of this Financial Bid and for implementation of Project, if
awarded, as per the timeframe indicated in the RFP. .
Thanking you,
Sincerely yours,
[Insert Signature here]
ATTACHMENT-27:
[To be on non-judicial stamp paper of Rupees One Hundred Only (INR 100/-) or
appropriate value as per Stamp Act relevant to place of execution, duly signed
on each page.
a company
of
2. M/s. ..........................................,
....................and having
a company
incorporated under
the
laws
of
a company
of
4. M/s. ..........................................,
....................and having
a company
of
For TSSPDCL
[Signature of Authorized Representative]
................................................................
[Name of the Authorized
Representative] [Designation of the
Authorized
Representative]
For .
[Name of the Lead
Consortium Member],
[Signature of Authorized Representative]
................................................................
[Name of the Authorized
Representative] [Designation of the
Authorized Representative
.
(Signature) Name
. *Signature+ (Notary Public)
Place: .
Date: .
ATTACHMENT-28:
[To be on non-judicial stamp paper of Rupees One Hundred Only (INR 100/-) or
appropriate value as per Stamp Act relevant to place of execution, duly signed
on each page.
To:
Dear Sir,
WHEREAS . [Insert name of the Lead Consortium Member] with
address . [Insert address of the Lead Consortium Member] having its
registered office at . [Insert address of the Lead Consortium Member]
(hereinafter, the Contractor), subsequent to participation in Tender No.
.. (the RFP) issued by .. (TSSPDCL) (hereinafter,
the Beneficiary) for Appointment of Smart Grid Implementing Agency for
Implementation of Smart Grid Pilot Project, have been issued the Letter of Award
as the Selected Bidder.
And WHEREAS a Bank Guarantee for Rupees . [Insert amount in
words] (.) [Insert amount in figures] valid till. [Insert date two
years from the date of issue of this Performance Guarantee] is required to be
submitted by the Contractor as per the terms and conditions of the RFP.
We, .[Insert name of the Bank and address of the Branch giving the
Bank Guarantee] having our registered office at . [Insert address of the
registered office of the Bank] hereby give this Bank Guarantee No. .
[Insert Bank Guarantee number] dated . [Insert the date of the Bank
Guarantee], and hereby agree unequivocally and unconditionally to pay
immediately on demand in writing from the Beneficiary any officer authorized
by it in this behalf any amount not exceeding Rupees . [Insert
amount in words] (.) [Insert amount in figures] to the said Beneficiary
on behalf of the Contractor.
We . [Insert name of the Bank] also agree that withdrawal of the Bid or
part thereof by the Bidder within its validity or non-submission of Performance
Security by the Bidder within the stipulated time of the Letter of Award to the
Bidder or any violation to the relevant terms stipulated in the RFP would
constitute a default on the part of the Bidder and that this Bank Guarantee is
liable to be invoked and encashed within its validity by the Beneficiary in
case of any occurrence of a default on the part of the Bidder and that the
encashed amount is liable to be forfeited by the Beneficiary.
This agreement shall be valid and binding on this Bank up to and inclusive of
. [Insert the date of validity of the Bank] and shall not be terminable
by notice or by Guarantor change in the constitution of the Bank or the firm
of the Bidder Or by any reason whatsoever and our liability hereunder shall
not be impaired or discharged by any extension of time or variations or
alternations made, given, conceded with or without our knowledge or consent by
or between the Bidder and the Beneficiary.
*Insert signature of
Authorized Signatory]
the
Banks
Attested:
. *Signature+ (Notary Public)
Place: .
Date: .
ATTACHMENT-29:
(among .. (Utility),.. (NBSP) & ..(SGIA )) for providing MPLS VPN based
wide area network services, Internet Bandwidth and GPRS connectivity at
various locations of Projects Area under SMART-GRID Project.
NOTE
a. This agreement is for providing MPLS VPN based wide area network services,
Internet Bandwidth and GPRS connectivity at various locations.
Prior to this agreement Contract agreement between Utility and SGIA has been signed.
The Purchase Order on the same price and work, as quoted by SGIA against the
networking (MPLS VPN based Wide Area Network services, Internet Bandwidth
and GPRS connectivity) and Related Services component of SGIA LOA/PO has
been/is to be signed between Utility and NBSP.
d. SLA format for including in the Utilitys Purchase Order to NBSP is given
at the end of this document.
e. This agreement does not endorse any agreement between NBSP and SGIA
f. The Responsibility Matrix may be modified depending upon specific works.
MODEL AGREEMENT
This Agreement is entered on day of 2010 among (name of
utility) a company incorporated under the Companies Act 1956 and having its
registered office at
AND
.. (name of SGIA), a company incorporated under the Companies
Act
1956
and
having
its
corporate
office
at
.
SELECTED
SGIA
FOR
SMARTGRID PROJECT i.e., Party engaged by .. vide LOI No:
.
and
detailed
order
no.
(herein referred to as the Purchase Order) for
Supply,
installation,
integration,
testing,
commissioning
and
facility
management service of System Integration Project covering software,
hardware, field survey and networking (MPLS VPN based Wide Area Network
services, Internet Bandwidth and GPRS connectivity) and Related Services
incidental thereto as specified in the Scope of Work at Section II of the said
Purchase Order (hereinafter referred to as SGIA or ..(name of SGIA) which
expression shall unless excluded by or repugnant to the meaning or context
thereof be deemed to include its successors and assigns) of the second Part.
AND
.(name of NBSP) a company incorporated under the
Companies
Act
1956
and
having
its
corporate
office
at., being a preferred TELECOM SERVICE
PROVIDER/NETWORK BANDWIDTH SERVICE PROVIDER for the referred SMARTGRID PROJECT
engaged for Providing MPLS VPN based Wide Area Network services, Internet Bandwidth
and GPRS
connectivity incidental thereto as specified in the Scope of Work in the
agreement between (SGIA) and ..(utility) (hereinafter referred to
as ..(NBSP) which expression shall unless excluded by or repugnant
to the meaning or context thereof be deemed to include its successors and
assigns) of the third Part.
(utility), (SGIA) and ..(NBSP) are individually
referred as Party and collectively as Parties.
WHEREAS . (utility), the party of the first part has contracted ..(SGIA),
the second party, for
supply, installation, integration, testing,
commissioning and facility management service of System Integration
Project covering software, hardware, field survey, networking related
services (hereinafter referred to as The Project) vide its RFP No.
..WHEREAS as per the requirements of the
project,
I.
Agreement. Where ...................(NBSP) shall accept the Order form from
..............(Utility),
..................(NBSP) shall provide the Services required by ............(Utility),
and by ..(SGIA)
on behalf of ..............(utility), within a timeframe, quality, security and
agreed with between ..............(utility), .......(NBSP) and ......(SGIA). The
SGIA
provide ..............(NBSP) with a complete network diagram of the set-up along
with the
details of connectivity at the Locations and services will be provisioned to the
..............(Utility) accordingly. It is the responsibility of SGIA, severally and
jointly with
.....(NBSP) of proper network monitoring and network management as per
SLA like
uptime, proper bandwidth etc. and to submit the SLA performance report of
the
......(NBSP) to the ...... (Utility) on monthly/as and when required basis.
ii.
1.APPLICATION
This Agreement details the general terms and conditions for the provision of
the Services to be rendered by (NBSP) *as per PO placed vide./to be
placed by Utility+ and by .(SGIA) *as per PO No. .with ..(Utility)]. Upon
signing the scope, duration and other services to be so rendered under this
Agreement the parties agree to accept and be bound by these terms and
conditions.
3.SERVICE TERM
The term of the Services is SGIA responsibility for .. years (as per SGIA
PO) from the date of commencement of service, and if required, thereafter,
shall be extended from time to time by written consent of the parties. The
Service Commencement Date shall be set forth in accordance with the
Purchase Order placed vide/to be placed by ..............(utility) on ........(NBSP).
4.TERMINATION OF SERVICE
The Termination of this Agreement and Services shall be as per provisions of
Termination clause as appearing in PO No. with .. (SGIA) and/or PO
placed vide/to be placed with . (NBSP).
Responsibility of
Responsibility of
.........(utility)
........(SGIA)
...........(NBSP)
To provide
based Wide
and
MPLS
(SGIA)
and
the
..(utility).
To
disburse
payment to the
(NBSP)
upon
achievement of
the
SLA on the basis of
performance reports/
SLA reports.
To provide safe access
(SGIA)
and..
(NBSP).
and conditions to
services provisioned to
to
use
the
..(SGIA)
(NBSP)s
and the.......(utility)
establishments
and
services
installed
under
this
agreement
for
organizations
other
than .(utility).
Proper
network
employees
or monitoring and network
appointed
personnel management as per SLA
whilst in the premises. like
uptime,
proper
bandwidth
etc.
and
raise
direct
submit SLA report to the To
utility on monthly/as and invoices against the
works/services
when required basis.
performed, as per
To monitor and report the terms of the
any problems
on Purchase Order with
behalf
of
Utility.
..........(NBSP).
To
ensure
To ensure that the . compliance of Indian
(NBSP) comply with all Telecom regulation &
relevant and applicable statutory
provisions
of
the
Contract.
requirements
while
To ensure compliance of
Indian
Telecom
regulation & statutory
requirements
while
performing
the
works/services
under
this agreement.
performing
the
works/services under
this agreement.
To
obtain
and
arrange
for
the
maintenance in full
force and effect of
all
government
To obtain and arrange
approvals,
for the maintenance in
full force and effect of
consents,
licenses,
all
government
authorizations,
approvals,
consents,
declarations, filings,
licenses, authorizations,
and registrations as
6.INVOICE AND PAYMENT
a. ..............(NBSP) shall raise direct invoices against the Requisite Services so
rendered, as per the terms of the Purchase Order placed vide/to be placed
by. (utility) and
..............(utility) shall directly make the payment to ..............(NBSP) based on
the SLA (as per NBSP PO) report and confirmation made by ..............(SGIA).
b. The other terms and conditions shall remain applicable as per .(Utilitys) PO No.
.with .. (SGIA) and/or PO placed vide/to be placed by Utility to .
(NBSP).
7.DISPUTES WITH REGARDS TO INCORRECT INVOICING
Disputes with regard to incorrect Invoicing shall be governed by .(Utilitys) PO No.
.with
.. (SGIA) and/or PO placed vide/to be placed by Utility to . (NBSP).
8.ACCESS TO PREMISES
..............(utility) shall allow or obtain the required permission to enable ..............
(NBSP) employees or authorized personnel, appointed distributors, agents or
subcontractors to enter at all times during the normal working hours of ..............
(utility) into the premises where the Services are provided for periodical
inspection with seven (7) days prior notice, installing, maintaining, replacing and
removing equipment hardware and/or software prior to, during and after the
provision of the Services, as well as to inspect the network and/or to the CPE or
any other equipment used in or in connection with the Services. The ..............
(utility) shall render all assistance in this regard and shall provide safe access
and conditions for ..............(NBSP)s employees or appointed personnel whilst in
the premises.
..............(NBSP)s employees or appointed personnel shall comply with security
and confidentiality policies and procedures while on the ..............(utility)s
premises.
9.NOTICES
Any party may deliver notices to the other by personal delivery or by postal delivery at ..................(utility)
...................
.................. (SGIA)
..................
...................(NBSP)
...
................ Notices shall be deemed
delivered on the date of actual receipt.
JMSG RFP VOLUME-I
10.
ENTIRE UNDERSTANDING
MISCELLANEOUS
b.In the event of any provision of this Agreement being held or becoming invalid,
unenforceable or illegal for any reason, this Agreement shall remain otherwise in
full force apart from the said provision which will be deemed deleted. The
parties shall however attempt to replace the deleted provision with a legally
valid provision that reflects the same purpose of the deleted provision to the
greatest extent possible.
c. Headings used in this Agreement are for the convenience and ease of reference
only, and shall not be relevant to or affect the meaning or interpretation of this
Agreement.
e. Each Party shall obtain and arrange for the maintenance in full force and effect
of all government approvals, consents, licenses, authorizations, declarations,
filings, and registrations as may be necessary and advisable for the
performance of all of the terms and conditions of this Agreement.
12.
APPLICABLE LAW
13.
ARBITRATION
Any disputes which may arise out of this Agreement, and which cannot be
settled in discussions or negotiations between the Parties, shall be referred
to the appropriate management or higher
14.
LIMITATION OF LIABILITY
Address
Address
in the presence of
Signature ..
Name
&
Designation
Address
in the presence of
Signature .. Name
& Designation
Address
The overall SLA for the Services (individually and combined) should be as follows:
a)For first three: 99%uptime or as per PO placed on SGIA,
b)
ATTACHMENT-30:
Any item though not specifically mentioned (in RFP or Price Schedule), but is
required to complete the project works as per RFP in all respects for its safe,
reliable, efficient and trouble free operation shall also be taken to be included,
and the same shall be supplied and installed by the Bidder without any extra cost
unless it is explicitly excluded.
ATTACHMENT-31:
I hereby declare that that <Name of Bidder> has Design /Engineering/Testing facility in
India
as on
since <date>_
ATTACHMENT-32:
INTEGRITY PACT
is entitled also to exclude the Bidder / Contractor from future contract award
processes. The imposition and duration of the exclusion will be determined by
the severity of the transgression. The severity will be determined by the
Beyond this, the Monitor has no right to demand from the parties that they act in
a specific manner, refrain from action or tolerate action.
6. The Monitor will submit a written report to the Chairman of the Board of the
Principal within 8 to 10 weeks from the date of reference or intimation to him by
the Principal and, should the occasion arise, submit proposals for correcting
problematic situations.
ATTACHMENT-33:
Whereas 1. The Supplier has entered in to an agreement with the purchaser (Contract
No.
date
d
for supply
of
Whereas, in accordance with the terms of the said Contract, the Purchaser has
agreed to pay or cause to be paid to the Supplier an Advance Payment in the
amount of [ insert: amount in numbers and words, for each currency of
the Advance Payment ] due to the Supplier as per the terms of the Contract
the Supplier has to provide a Bank Guarantee from a *Nationalized Bank for an
amount of Rs
*(the Guaranteed Amount) for the due performance of
the Suppliers Obligations in accordance with the Contract in favour of the
Purchaser. A copy of the Contract is enclosed with this Bank Guarantee. 3. The
Bank has, at the request of Supplier, agreed to give in favour of the Purchaser
a Guarantee for payment of the Guaranteed Amount in a manner hereinafter
appearing which the Purchase has agreed to accept.
NOW THIS DEED WITNESSETH AS FOLLOWS
4. In pursuance of the said Contract and in consideration of the premises, the
Bank hereby unconditionally and irrevocably, and without any qualification
whatsoever, agrees, covenants, undertakes and guarantees, as primary
obligator and not as surety merely, to make payment to Purchaser on its first
demand without whatsoever any claims, objection, protest or demur and
without any recourse to the Supplier, notwithstanding any intimation or direction
to the contrary or any objection, such sum or sums of money to the extent of
and up to and including the date upon which the Supplier has fully repaid the
amount so advanced to the Purchaser in accordance with the terms of the
Contract and completion of successful site acceptance test. 5. Any such demand
placed on the Bank shall be conclusive as regards the Guaranteed Amount due
and payable by the Bank under this Guarantee. 6. This Guarantee is executed
up to and including up to and including the date upon which the Supplier has
fully repaid the amount so advanced to the Purchaser in accordance
with the terms of the Contract and completion of successful site acceptance test
during which period it is not revocable except with the previous written consent
of Purchaser. 7. Purchaser may, without affecting Banks liabilities and
obligations hereunder, grant time or other indulgence to or compound with
Supplies or enter into any agreement or agree to forbear to enforce any of
the terms and conditions of this Guarantee. 9. This Guarantee shall not be
affected by any change in the constitution of Purchaser or Supplier by merger,
amalgamation or absorption with any other body or corporation or otherwise and
this Guarantee will be available to or enforceable by or against such body or
corporation.
In order to give effect to this Guarantee, Purchase shall be entitled to act as if
the Bank were the principal debtor and the Bank hereby waives all and any of its
rights of suretyship. Any notice by way of request and demand or otherwise
hereunder sent by telex, fax or personally served, or by registered post
addressed as aforesaid to the Bank in [insert: location], India shall be
presumed to have been duly received by the Bank as follows: (i) If personally
served, when served. (ii) If by fax or telex on the second business day after the
transmission.
(iii)
If mailed, upon receipt, or on seventh day after deposit in the mail with
postage prepaid. The Guarantee herein contained is not revocable by notice
during its currency and shall remain in full force until payment has been made
to Purchase by Bank of the Guaranteed Amount payable hereunder.
The liability of the Bank is irrevocable during the currency of this Bank Guarantee
and is restricted to the Guaranteed Amount viz. Rs
_(Rupees
Only). Unless demand or claim under this
Guarantee is received by the Bank in writing within the validity period of this
Guarantee, all the rights of Purchase against the Bank shall be forfeited and
the Bank shall be relieved and discharged of all liabilities hereunder. These
Presents shall be governed by and construed in accordance with the Indian
Law, and the courts in
_alone shall have exclusive jurisdiction in
relation hereto. The Bank hereby declares that it has power to issue this
Guarantee and the undersigned have the full power to approve execution,
delivery and the performance of the Guarantee. Signed, sealed and delivered
by the Bank For
Authorized
Signatories
ATTACHMENT-34:
A.
1.
For Hardware:
Availability
for
each
elements per
quarter
>98%
Severity Levels
Category
Definition
Severity 1
Urgent
Severity 2
Serious
Severity 3
Minor
Severity 4
General/Techni
cal Help
Complete
system
failure,
severe
system
instability, loss or failure of any major subsystem
or system component such as to cause a
significant adverse impact to system availability,
performance, or operational capability
Degradation of services or critical functions
such as to negatively impact system operation.
Failure of any redundant system component such
that the normal redundancy is lost
Non-availability of Man-power at Central system
during working hours, non-availability of spares
Any other system defect, or unexpected
operation
Request
for under
information,
configuration
not covered
severitytechnical
1 or 2
assistance, how to guidance, and enhancement
requests.
Severity-2
Degradation of services or critical functions such as to negatively impact system
operation.
Failure of one Data Server, stoppage of data collections for archiving, at the
respective Central system, and outage of other applications not covered under
severity-1 are included in this category.
Failure of one UPS system, Failure of Battery System and failure of any other
system of Auxiliary Power supply not covered under Severity-1 are included in
this category.
Coverage under this severity would be outages that do not immediately cause
on line data loss but subsequently could result into Severity-1 category outage,
loss of an important subsystem that may affect the day-to-day works and loss of
archived data.
Failure of any redundant system component affecting the critical redundancy
would also be included in this category.
Non-availability of designated contractors Man-power at central system as well
as required inventory of spares specified here will also be covered under this
category.
Severity-3 (Standard support)
The support services included under this category are when the outage or loss
of functionality is neither of an emergency nor priority functionalities as
indicated in severity level 1 or 2 above.
Severity-4 (General Technical Help)
Request for information, technical configuration assistance, how to guidance,
and enhancement requests are included under this category.
2.5. Monitoring and Auditing
Purchaser will review the performance of Supplier against the SLA parameters
each month, or at any periodicity defined in the contract document. The review /
audit report will form basis of any action relating to imposing penalty or breach
of contract. Any such review / audit can be scheduled or unscheduled. The
results will be shared with the Supplier as soon as possible. Purchaser reserves
the right to appoint a third-party auditor to validate the SLA.
2.6.
Reporting Procedures
The Supplier's representative will prepare and distribute SLA performance reports
in an agreed upon format by the 10th working day of subsequent month of
the reporting period. The reports will include "actual versus target" SLA
performance, a variance analysis and discussion of appropriate issues or
significant events. Performance reports will be distributed to the Purchaser's IT
Team.
2.7.
a. General
This process provides an appropriate management structure for the orderly
consideration and resolution of business and operational issues in the event
that quick consensus is not reached between Purchaser and Supplier. It is
expected that this pre-defined process will only be used on an exception basis if
issues are not resolved at lower management levels.
b.
Any changes to the levels of service provided during the term of this agreement
will be requested, documented and negotiated in good faith by both parties.
Either party can request a
change. Changes will be documented as an
addendum to this document and consequently the contract.
b.SLA Change Process
Both the parties may amend this SLA by mutual agreement in accordance.
Changes can be proposed by either party. Normally the forum for negotiating
SLA changes will be Purchaser's monthly review meetings.
c. Version Control
All negotiated SLA changes will require changing the version control number. As
appropriate, minor changes may be accumulated for periodic release (e.g.
every quarter) or for release when a critical threshold of change has occurred.
2.9. Management Escalation Procedures
The purpose of this escalation process is to provide a quick and orderly
method of notifying both parties that an issue is not being successfully
resolved at the lowest possible management level. Implementing this
procedure ensures that purchaser and Supplier management are communicating
at the appropriate levels. Escalation should take place on an exception basis
and only if successful issue resolution cannot be achieved in a reasonable time
frame.
1. All issues would be raised to the project management team, which is completely
responsible for the day to day aspects of the implementation. The project
management team shall classify the issues based on their severity level and
resolve them within appropriate timelines.
2. If project management team is unable to resolve an issue, the issue would be
escalated to Chief General Manager (Projects) with options/ risks detailed for
decision.
3. In case one or both the parties are unsatisfied with the decision of the Purchaser,
the dispute will be resolved as specified in GCC.
2.10. Signature Page
IN WITNESS WHEREOF, the parties hereto have caused this Service Level
Agreement to be executed by their respective authorized representatives as
of the date first written above.
Supplier
Purchaser
(On Behalf of all consortium members
also)
Signature
Signature
Name
Address
Name
Designation
Company
Utility:
Date
Date
ATTACHMENT-35:
1.
Proposed Position:
2.
4.
5.
Education:
3.
Year
6.
7.
8.
9.
Nationali
ty:
Degree/Examination
Institute/Board
Membership
of Professional
Other
Training:
Associations:
Countries of
Work
Experience:
Languages:
Language
10. Employment
Record:
Speaking
Reading
Writing
From
To
Employer
Positions Held
13. Certification:
I, the undersigned, certify that to the best of my knowledge and belief, this
CV correctly describes me, my qualifications, and my experience. I
understand that any wilful misstatement described herein may lead to my
disqualification or dismissal, if engaged.
Signature of Expert
Date:
ATTACHMENT-36:
COMPLIANCE STATEMENT(P1DI)
The bidder shall provide compliance or otherwise to the various supplies and
services that are listed in RFP (Vol-I and Vol-II) and subsequent
amendments/corrigendum.
Module details
ATTACHMENT-37: DECLARATION
EQUIPMENT(P1DI)
ON
ORIGIN
OF
SYSTEMS
AND
To:
<TSSPDCL
Address
Dear Sir
We conform that all systems and equipment offered and services to be carried
out under the contract will not have origin in any countryagainst whom sanction
for conducting business is imposed by Government of India andthose firms with
whom business is banned by the TSSPDCL.
Date:....................
..
Place:...................
(Signature).................................................
(Printed Name)...........................................
.
(Designation)..............
..............................
(Common Seal)..
..........................................
>
SECTION-7
SCOPE OF
WORK
SECTION-8
GUIDELINES FOR TECHNICAL
PROPOSAL
PROJECT EXPERIENCE
Bidder shall provide details of projects of similar nature with application
modules and other subsystems (Field systems, network and communication
Equipments as well as central systems supplied) which have been
successfully completed during the last 5 financial years. In case the system
has already been replaced please do not include the project as part of
description. The details of the same should include with supporting
documents:
FRTUs
Meters
DCUs
FPIs
RTUs
DCs etc
Communication Media and protocols deployed e.g.
PLC
SDH
GPRS
RFMesh
Zigbee
IEC-61850
IEC 60870-5-104 or any other
8.3
FIRM DETAIL
Bidder shall provide details of net-worth and turnover for the past five
audited financial years. Past history of litigation with TSSPDCL/TSSPDCL if
any shall be detailed separately. The experience of the firm in area similar
to the proposed project shall be clearly outlined and supporting document
e.g. LOA etc shall be enclosed.
8.5
COMPLIANCE CHECKLIST
< Part of Section-2: Information to Bidders (ITB)>
SECTION-9
EVALUATION
METHODOLOGY