Beruflich Dokumente
Kultur Dokumente
POWER TRANSFORMER
POWER GENERATION & DISTRIBUTION FACILITY
AT DALEEL FIELD(DALEEL 06-255)
METHOD STATEMENT
FOR
INSTALLATION OF POWER TRANSFORMER
Prepared By
(LTEM)
Reviewed
By
(LTEM)
Approved
by
(LTEM)
Approved
By
(Daleel)
Name
Date
G. Prasanth Kumar
Reddy
5.4.2
011
Devraj Kingsly
5.4.2
011
P.GovindRaj
6.4.2
011
Yousuf Al Harooni
Signature
LIST OF CONTENTS
1. PURPOSE
2. SCOPE
3. DOCUMENT REFERENCE
4. TOOLS AND PLANTS REQUIRED
5. RESPONSIBILITIES
6. PROCEDURE
7. INSPECTION AND TESTING
8. SAFETY
1.0 PURPOSE
The purpose of this method statement is to describe the procedure to be adopted
during installation of Power Transformer.
2.0 SCOPE
This procedure shall be applicable for installation and pre-commissioning of Power
Transformer of EPC of POWER GENERATION DISTRIBUTION SYSTEM at Daleel
Field.
3.0 REFERENCE
1.
2.
3.
4.
5.
Contract documents
General arrangement Drawings
Manufacturers Installation Manual
Vendor Drawing
Operation and Maintenance Manual
Any modification done as per the site condition apart from the \ifc shall be
incorporated in as built drawing.
5.0 RESPONSIBLITY
5.1 QA/QC ENGINEER
a.
b.
c.
d.
e.
Page No 4 of 6
Locations of cables entry for equipments shall be visually inspected with respect to
trenches, switch racks.
Transformer shall be either collected from the stores or other place, or received
directly from manufacturers works.
After receiving the equipments inspect for any abnormalities and damages, If any,
inform LTEM Construction Manager / Stores for necessary action.
The foundation for transformer shall be made ready before installation. Verify the
cable entry for HV, LV and control cables as per approved drawings.
Transformer shall be finally positioned for line and level to the dimensions given in
the drawings.
Care shall be taken in positioning in relation to cable, cable duct and busbar
trunking positions.
Transformer more than 10MVA capacity are supplied with main tank separately.
Radiators and conservators and topping up oil will be supplied in separate
containers/drums.
Once the transformer is on foundation, oil in drums for topping up is tested for its
BDV and the values recorded against drum no. The top, bottom and OLTC sample
is taken and BDV recorded. If the above values are accepted, assembling of
radiators and conservator tank can be started.
It is recommended; the filling of oil shall be through a vacuum filtration plant with
heating facilities and filtered. Oil shall be circulated at least 24 hrs or until oil temp
reaches steady state value.
BDV of oil is verified once the filtration plant is off and the value recorded. Once the
transformer is cooled to ambient temp oil level is adjusted as per manufacturers
recommendation.
Trapped air in the main tank, radiators, OLTC tank is released through the air
release plugs provided. All valves except sampling & drain valves shall be opened.
SAFETY
Ensure that all PPEs are available with the crew involved in the job.
All equipment and tools should be checked before starting of the activity for
suitability and integrity.
Ensure that housekeeping is being carried out before and after work on a daily
basis.