Sie sind auf Seite 1von 6

METHOD STATEMENT FOR INSTALLATION OF

POWER TRANSFORMER
POWER GENERATION & DISTRIBUTION FACILITY
AT DALEEL FIELD(DALEEL 06-255)

Document ref: No.:


LTEM/DP/MS/ELE-09 Rev.0
Page No 1 of 6

METHOD STATEMENT
FOR
INSTALLATION OF POWER TRANSFORMER

Prepared By
(LTEM)
Reviewed
By
(LTEM)
Approved
by
(LTEM)
Approved
By
(Daleel)

Name

Date

G. Prasanth Kumar
Reddy

5.4.2
011

Devraj Kingsly

5.4.2
011

P.GovindRaj

6.4.2
011

Yousuf Al Harooni

Signature

METHOD STATEMENT FOR INSTALLATION OF


POWER TRANSFORMER
POWER GENERATION & DISTRIBUTION FACILITY
AT DALEEL FIELD(DALEEL 06-255)

LIST OF CONTENTS
1. PURPOSE
2. SCOPE
3. DOCUMENT REFERENCE
4. TOOLS AND PLANTS REQUIRED
5. RESPONSIBILITIES
6. PROCEDURE
7. INSPECTION AND TESTING
8. SAFETY

Document ref: No.:


LTEM/DP/MS/ELE-09 Rev.0
Page No 2 of 6

METHOD STATEMENT FOR INSTALLATION OF


POWER TRANSFORMER
POWER GENERATION & DISTRIBUTION FACILITY
AT DALEEL FIELD(DALEEL 06-255)

Document ref: No.:


LTEM/DP/MS/ELE-09 Rev.0
Page No 3 of 6

1.0 PURPOSE
The purpose of this method statement is to describe the procedure to be adopted
during installation of Power Transformer.
2.0 SCOPE
This procedure shall be applicable for installation and pre-commissioning of Power
Transformer of EPC of POWER GENERATION DISTRIBUTION SYSTEM at Daleel
Field.
3.0 REFERENCE
1.
2.
3.
4.
5.

Contract documents
General arrangement Drawings
Manufacturers Installation Manual
Vendor Drawing
Operation and Maintenance Manual
Any modification done as per the site condition apart from the \ifc shall be
incorporated in as built drawing.

4.0 TOOLS AND PLANTS REQUIRED


1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.

Oil Filtration Machine


7 ton truck
50 ton crane
Secondary Injection Kit
BDV testing Kit
Winding Resistance tester
Multimeter FLUKE MAKE
Megger 5000v
Cable jointing tool kit
Tool Box
Crimping Tool &Die Set
Torque Wrench
Compound Gauge
Temperature Gauge.

5.0 RESPONSIBLITY
5.1 QA/QC ENGINEER
a.
b.

Ensure all materials are inspected prior to utilizing at site.


Ensure the availability of required technical documents like approved method
statement, IFC Drawings at work place.

METHOD STATEMENT FOR INSTALLATION OF


POWER TRANSFORMER

Document ref: No.:


LTEM/DP/MS/ELE-09 Rev.0

POWER GENERATION & DISTRIBUTION FACILITY


AT DALEEL FIELD(DALEEL 06-255)

c.
d.
e.

Page No 4 of 6

Responsible for carrying out Stage inspections and surveillance inspections in


accordance with ITP and as per the project requirement.
Ensure the work is done by the qualified person (Ex. Cable Jointer).
Responsible for ensuring the all Testing activities are according to project
requirement.

5.2 ELECTRICAL ENGINEER


Electrical Engineer shall be overall responsible for the safe execution of
complete activity including but not limited to.
a.
b.
c.
d.

Conforming the installation works as per the schedule.


Organizing tools and equipment required for the work.
Assigning work crew.
Conforming the materials handling in safe manner.

5.3 SAFETY SUPERVISOR


The Safety supervisor shall be responsible for safe execution at site.
a. Ensure for effective tool box talk.
b. Ensure all the PPEs are available at site and are using correct PPE.
c. Ensure the first aid box available at site.
d. Ensure the adequate fire extinguishers are available at site.
e. Ensure the required warning signs and boards are available at necessary place
f. Ensure only required people are available at site.
6.0 PROCEDURE POWER TRANSFORMER INSTALLATION
6.1 General Requirements
-

Ensure the Transformer has been inspected and approved by Client.


Transformer installation, testing &commissioning work will be carried out as per the
Client &Vendor recommendation.
Under any circumstances the Power Transformer shall not be forcefully handled.
House Keeping will be done on daily basis.

6.2 Visual Inspection


After receiving the equipments it shall be inspected at store for any abnormalities
and damages. If anything found it shall be reported to Contract Manager/Stores for
necessary action.
-

Locations of cables entry for equipments shall be visually inspected with respect to
trenches, switch racks.

6.3 INSTALLATION OF POWER AND AUXILLARY TRANSFORMER

METHOD STATEMENT FOR INSTALLATION OF


POWER TRANSFORMER
POWER GENERATION & DISTRIBUTION FACILITY
AT DALEEL FIELD(DALEEL 06-255)

Document ref: No.:


LTEM/DP/MS/ELE-09 Rev.0
Page No 5 of 6

Transformer shall be either collected from the stores or other place, or received
directly from manufacturers works.

After receiving the equipments inspect for any abnormalities and damages, If any,
inform LTEM Construction Manager / Stores for necessary action.

The foundation for transformer shall be made ready before installation. Verify the
cable entry for HV, LV and control cables as per approved drawings.

Transformer weighing more than 30 tons is normally installed by specialized


erection contractor. Transformer up to 30 tons is installed by LTEM using the crane
and other lifting facilities.

Transformer shall be positioned centrally on foundation blocks, and clearances shall


be checked.

Transformer shall be finally positioned for line and level to the dimensions given in
the drawings.

Care shall be taken in positioning in relation to cable, cable duct and busbar
trunking positions.

Transformer more than 10MVA capacity are supplied with main tank separately.
Radiators and conservators and topping up oil will be supplied in separate
containers/drums.

Once the transformer is on foundation, oil in drums for topping up is tested for its
BDV and the values recorded against drum no. The top, bottom and OLTC sample
is taken and BDV recorded. If the above values are accepted, assembling of
radiators and conservator tank can be started.

It is recommended; the filling of oil shall be through a vacuum filtration plant with
heating facilities and filtered. Oil shall be circulated at least 24 hrs or until oil temp
reaches steady state value.

BDV of oil is verified once the filtration plant is off and the value recorded. Once the
transformer is cooled to ambient temp oil level is adjusted as per manufacturers
recommendation.

Trapped air in the main tank, radiators, OLTC tank is released through the air
release plugs provided. All valves except sampling & drain valves shall be opened.

HV, LV and Control cabling as applicable and terminations shall be completed as


per approved schedule.

Earthing of transformer body and neutral shall be completed.

METHOD STATEMENT FOR INSTALLATION OF


POWER TRANSFORMER
POWER GENERATION & DISTRIBUTION FACILITY
AT DALEEL FIELD(DALEEL 06-255)

Document ref: No.:


LTEM/DP/MS/ELE-09 Rev.0
Page No 6 of 6

6.4 Verification Documents


- Approved Drawings
7.0

INSPECTION AND TESTING

- Transformer Visual inspection and Storage condition.


- Transformer installation inspection as per Construction Check Sheet for Power and
Auxiliary Transformer Form No.11, 17.
- Transformer Pre-commissioning Tests as per Functional Test Sheet for Power and
Auxiliary Transformer Form No 28, 35, and 36.
8.0
-

SAFETY
Ensure that all PPEs are available with the crew involved in the job.
All equipment and tools should be checked before starting of the activity for
suitability and integrity.
Ensure that housekeeping is being carried out before and after work on a daily
basis.

Das könnte Ihnen auch gefallen