(Assignment)
Submitted by:
Aji Kurnia Dewanta
(12522091)
(12522259)
International Program
INDUSTRIAL ENGINEERING DEPARTMENT
FACULTY OF INDUSTRIAL TECHNOLOGY
ISLAMIC UNIVERSITY OF INDONESIA
2015
CHAPTER I
INTRODUCTION
1.1 Background
Ministry of Communications and Information Technology requested lift facilities building in
their main building. Lift facility needed because to ensure the swiftness and effectiveness from
working in the building. Main building in the office of Ministry of Communications and
Information Technology does not have lift facilities. So, in order to fulfill the need of lift
facilities in their main building, Ministry of Communication and Information Technology held
a project tender throughout inside Ministry Department of Republic of Indonesia. Lembaga
Kebijakan Pengadaan Barang/Jasa Pemerintah (LPSE) is a department in the Ministry of
Republic of Indonesia which is responsible for organizing project tender either the project is
service or non-service. The purpose of the auction is to get a contractor who was really
competent, because in the auction process consists of several stages ranging from prequalification to post-qualification announcement of the winning bidder and knockout. So this
is become an opportunity for our company to bid the tender.
In this case if the company won the auction, it can determine the design concept to be made.
The company also must determine when the project will begin. This relates to determine how
long the workmanship. After that the company needs to determine the resources required. Both
human resources (labor) and material resources. Deep consideration need to determine resource
allocation that needed in the construction. In addition, the cost of wages or salaries of all parties
involved must also be taken into account, the need for the raw materials should be fully
calculated. All of things that related to the costs involved in the project summarized in Budget
Planning Log or Rencana Anggaran Biaya (RAB).
1.2 Activity Theme
In this project, we focus on build lift construction in main building of ministry of
communication and information technology.
1.3 Activity Location
Location of this project is in Jl. Medan Merdeka Barat No. 9 Jakarta Pusat (Kota)
1.4 Purpose Activities
SCHEDULE ACTIVITIES
Schedule Types
1. Initial Meeting
Meeting-Prep
Design Determination
Budgetting Plan
2. Area Sterilization
Discharge Area
Project Boundary Determination
3. Tools Preparation
Tools Mounting
Tools Handling to Poject Area
4. Materials Preparation
Procurement of Material and Furniture
Mounting of Material and Furniture
Material and Furniture Handling
5. Construction Stage
Labor's Briefing
Tools Instalation
Walls Demolition
Floor Demolition
Ceiling Demolition
Lift Instalation
Wall Dcor Instalation
Tiles Instalation
Ceiling Instalation
Tools Discharge
Tools Handling
Cleaning Location
Furniture Instalation
Room's Dcor Instalation
Date
Duration
(Days)
2
2
2
2
7
2
1
2
3
7
10
6
10
7
14
4
7
2
2
2
3
1
Project
Leader
Secretary
Consultant
Treasurer
Field
Leader
Foreman
Labor
CHAPTER II
IMPLEMENTATION
2.1 Implementation Activities
2.1.1 Initial Meeting
In this event the winner began a coordination meeting to discuss all kinds of requirements
necessary for the project. In this stage there are activities as follows:
1. Meeting Prep
In this event the winning bidder did meeting prep. It poses the relevant parties such as
the Head of Project, Project Secretary, Treasurer Responsible Projects and Field. In
which to discuss what kind of projects will be executed.
2. Design Determination
This activity contains parties of the winning bidder and from consultants or interior
designer who has been invited by the winning bidder. The winning bidder entrusted to
the consultant or form design interior designer.
3. Budgeting Plan
At this stage the winning bidder makes RAB (Budget Plan) for the project. In RAB are
necessary costs such as raw material costs, labor costs and other costs which directly or
indirectly.
2.1.2 Area Sterilization
To facilitate processing and maintaining security during the project room or area that will be
the process of the project should be emptied first. Discharging done by project workers. There
are several works such as the following:
1. Discharge Area
2. Project Boundary Determination
2.1.3 Tools Preparation
At this stage the winning bidder has made preparations tools ranging from data collection tool
of what is needed, the quantity as well as how much the price of these tools either purchase or
lease. The activities therein are as follows:
1. Tools Mounting
2. Tools Handling to Project Area
Amount
Unit
Price
Total Price
Orang
25000000.00
IDR
Project Leader
25,000,000.00
2
Consultant
Orang
30000000.00
IDR
30,000,000.00
Secretary
Orang
8500000.00
IDR
8,500,000.00
Treasurer
Orang
8500000.00
IDR
8,500,000.00
Field Leader
Orang
19000000.00
IDR
19,000,000.00
Foreman
Orang
9000000.00
IDR
18,000,000.00
Labor
12
Orang
7000000.00
IDR
84,000,000.00
Laptop
Unit
12500000.00
IDR
12,500,000.00
Cement
60
Sak
57000.00
IDR
3,420,000.00
10
Wall Paint
20
Kaleng
80000.00
IDR
1,600,000.00
11
Metal Paint
10
Kaleng
44000.00
IDR
440,000.00
12
Wood Paint
15
Kaleng
40000.00
IDR
600,000.00
13
Brush
10
Unit
14000.00
IDR
140,000.00
14
Roller
Unit
25000.00
IDR
125,000.00
15
Cement Mixer
Unit
7500000.00
IDR
7,500,000.00
Amount
Unit
Price
Total Price
16
300
Persegi
120000.00
IDR
17
Marble
Sand
20
(M2)
36,000,000.00
IDR
15,000,000.00
18
Rocks
IDR
3,400,000.00
19
Steger
Set
200000.00
IDR
1,200,000.00
20
Bucket
30
Unit
14000.00
IDR
420,000.00
21
Cement Spoon
20
Unit
27000.00
IDR
540,000.00
22
Material Trolley
Unit
1500000.00
IDR
3,000,000.00
23
Ruler
Unit
95000.00
IDR
190,000.00
24
Hose
50
Meter (M1)
14000.00
IDR
700,000.00
25
Wood
100
IDR
1,000,000.00
26
Plafon
300
Lembar
95000.00
IDR
28,500,000.00
27
10
Unit
130000.00
IDR
1,300,000.00
28
Ceiling Lamp
Unit
135000.00
IDR
675,000.00
29
Wall Lamp
20
Unit
75000.00
IDR
1,500,000.00
30
Vase
Unit
30000.00
IDR
150,000.00
31
TV
Unit
3500000.00
IDR
7,000,000.00
Amount
Unit
Price
Total Price
32
Unit
3000000.00
IDR
Rack
6,000,000.00
33
Desk
Unit
3575000.00
IDR
7,150,000.00
34
Table
Unit
800000.00
IDR
3,200,000.00
35
Chair
Unit
1950000.00
IDR
7,800,000.00
36
Sofa
Set
5500000.00
IDR
5,500,000.00
37
Hammer
Unit
134000.00
IDR
804,000.00
38
Small Hammer
Unit
42000.00
IDR
126,000.00
39
Dus
249000.00
IDR
747,000.00
40
Wood Saw
Unit
180000.00
IDR
720,000.00
41
Metal Saw
Unit
4000000.00
IDR
4,000,000.00
42
Bor Machine
Unit
3800000.00
IDR
3,800,000.00
43
Grindstone
Unit
3705000.00
IDR
3,705,000.00
44
Cable
50
Meter (M1)
10000.00
IDR
500,000.00
45
Air Conditioner
Unit
8850000.00
IDR
35,400,000.00
46
Phone
Unit
225000.00
IDR
450,000.00
47
Shovel
Unit
25000.00
IDR
50,000.00
Amount
Unit
Price
Total Price
48
Orang
4500000.00
IDR
Driver
13,500,000.00
49
Truck
Unit
12500000.00
IDR
37,500,000.00
50
Blueprint
Lembar
35000000.00
IDR
140,000,000.00
51
Clock
Unit
75000000.00
IDR
75,000,000.00
52
Book
Set
35000000.00
IDR
35,000,000.00
53
Drum Water
Unit
1500000.00
IDR
3,000,000.00
Total
IDR
703,852,000.00
CHAPTER III
FINANCIAL ANALYSIS
3.1 S-Curve
Cost
1500
1000
500
0
Week 5 Week 7 Week 9 Week
11
Week
13
Week
14
Week
16
Q1
Week
18
Week
20
Week
22
Week
24
Q2
2015