Beruflich Dokumente
Kultur Dokumente
C a p i t a l s
1005/001/012
August 2011
Document Control
Draft
Issue 1
Deborah
Deborah
OConnor
OConnor
Date
Checked
Ken Wade
Ken Wade
22 July 2011
Author
Authorised
Date
1 Summary
This Addendum to the Social and Environmental Assessment (SEA) Qurayyah
Independent Power Plant QIPP1 (June 2011) has been commissioned by ACWA
Power International to assess the environmental and social impacts arising from a
combined 4,000 MW Plant compared with that originally proposed and assessed
i.e. the 1963.5MW Plant. This document should therefore be read in conjunction
with the SEA Report and Technical Appendices for QIPP1 (ref 1005/001/009, June
2011).
Two independent power plants (QIPP1 and QIPP2) of the same size and
configuration had originally been planned for the site, however it was
deemed more feasible to combine the plants into a single facility (QIPP1&2),
thereby
potentially
reducing
the
environmental
impact.
This
revised
assessment has focused on the issues of primary importance associated with the
larger combined Plant, namely the marine dispersion modeling, air quality
modeling and noise modelling predictions. All other social and environmental
issues have low or insignificant additional impacts and are detailed under the
main reference report of the QIPP1 SEA Report (June 2011).
Land-take
The proposed 4,000 MW Plant will reduce the land take on the QIPP2 site by >75%
thereby retaining protected coastal dune habitat within the surrounding
fenceline.
Marine Thermal Modelling
The conclusions of the marine thermal modeling demonstrate that there are
reduced environmental impacts arising from the larger 4,000 MW Plant and
revised intake/outfall configuration compared with the 1963.5MW Plant (ref SEA
Report). The improvements in thermal dispersion results in negligible temperature
rise at the existing QPP and QCC intakes, while the mixing zone areas for the 1
degree C (PME standard) and 3 degree C (World Bank/IFC standard) are
reduced in size, on the seabed.
scenarios for the 4,000 MW Plant is that there is improved thermal dispersion within
a marine site supporting no sensitive marine habitats and is a highly preferred
option compared with the 1963.5MW Plant.
Qurayyah QIPP1&2 (4000MW) Addendum to Social and Environment Assessment
August 2011
concentrations due to emissions from the 4,000 MW facility is less than 1% and
therefore classified as negligible and of insignificant impact.
During maintenance of the gas pipeline or an interruption of the gas supply,
diesel oil would be used as a back-up fuel for up to five successive days
(maximum of 10 days in 1 year). The dispersion model predicts the potential
for exceedance of the 1-hr and 24-hr PME standard and IFC 24-hour mean
guideline value. However, It should be noted that this is a theoretical failure
and worst-case prediction, since it assumes that back-up operation of the
facility is coincidental with periods when meteorological conditions result in
poor dispersion of stack pollutants. Therefore the likelihood of such an
exceedence occurring is very small and is no greater than that predicted for
the 1963.5MW Plant. In mitigation it is recommended that an independent
environmental expert shall undertake air monitoring during any period when
back-up diesel fuel is being used to monitor 24-hour sulphur dioxide GLCs.
Noise Modelling
Noise modelling has been undertaken for the 1963.5MW Plant, although the
larger 4,000MW plant is unlikely to have significantly increased impacts due to
the following:
The noise modelling reported in the SEA has shown that the site will
meet RFP standards without the need for additional acoustic barriers;
Introduction
ACWA Power International has commissioned an addendum to the Social and
Environmental Assessment (SEA) that was prepared for the proposed Qurayyah
Independent Power Plant 1 (QIPP1 1956MW), located 100km south of Dammam,
on the Gulf Coast of Saudi Arabia. This Addendum to the Social and
Environmental Assessment (SEA) Qurayyah Independent Power Plant QIPP1
(June 2011) has been prepared to assess the environmental and social impacts
arising from a combined plant (QIPP1&2). The proposed gas-fired combined
cycle power plant would have a net power generation capacity of 4,000MW.
The combined Qurayyah Independent Power Plant (QIPP1&2) (the Project)
is located in the Qurayyah complex, between the existing SEC Qurayyah
Steam Plant (QPP) in the north and the new SEC Qurayyah combined cycle
plant (QCC) in the south. The combined plant is the third in a series of power
projects at Qurayyah, which is proposed, to meet the future electricity
demands.
This Addendum has also been prepared in accordance with PME (Presidency of
Meteorology and Environment) national environmental regulations, guidance
and standards for Saudi Arabia, the World Bank/IFC (International Finance
Commission) and the Equator Principles. It will be formally submitted to PME and
Recovery Steam Generators (HRSG) and one Steam Turbine (ST) with
generator;
Each HRSG will have its own stack. There will be twelve stacks in total;
Two cooling water intakes have been combined into a single intake
reducing the direct impact on the marine habitats;
The new position of the plant has allowed the intakes to be angled to
reach the -10m contour and the discharges to reach the -3.5m
contour providing improved intake operation and dispersion of the
thermal discharge;
The discharge from the QIPPs for the 1963.5MW plant contributed 32%
to the total heat load in the environment. The contribution from the
combined QIPP1&2 plant results in a decrease to 28% due to the
efficient plant operations. QPP and QCC contribute 35% and 37%
respectively.
This cooling water will be supplied from four submerged intake heads (referenced
as QPPN (north) & QPPS (south) in the report) along four pipelines. The discharge
will be split between two pairs of pipelines and discharge structures, arranged
either side of the intake pipeline. The proposed layout is shown in Figure 1-1. The
intake and discharge pipelines shown in grey are as originally suggested, but it
was apparent that the water depth would be insufficient and therefore an
alternative layout was agreed for testing, as shown by the red lines in Figure 1-2.
The red intake pipelines are angled away from being perpendicular to the shore.
This allows deeper water to be reached and a greater separation of the QIPP1&2
intakes from the QPP discharge, without affecting the design of the land facilities
shown on the plot plan.
Qurayyah QIPP1&2 (4000MW) Addendum to Social and Environment Assessment
August 2011
Figure 1-2 Proposed QIPP1&2 intake and outfall layout (as modelled for this Addendum)
Modelling Scenarios
This combination of discharges was simulated for four combinations of wind,
covering both winter and summer conditions:
Scenario 1: Summer with 11 m/s southeast wind (ref SEA Scenario 2);
Scenario 4: Winter with 5 m/s southeast wind (ref SEA Scenarios 1, 4, 5).
All combinations were run with spring tide thus remaining consistent with
modeling done for the QIPP1 Final SEA. The ambient sea-water temperature
was 35C for summer and 20C for winter.
The model results are presented in several formats to demonstrate the
marginal change, if any, in terms of temperatures at the intakes of each of
the Plants and also the area of the 1 degree C Mixing Zone (PME) and the 3
degree C Mixing Zone (World Bank/IFC) as follows:
The results are analysed to present:
Tidal average temperature contours at surface, mid depth and bed for
QPP, QCC, IPP1 and IPP2;
Tidal average temperature contours at surface, mid depth and bed for
QPP and QCC only (baseline conditions);
Graphs of temperature vs time at the IPP1, IPP2, QPP and QCC intakes
for QPP,QCC, IPP1 and IPP2;
10
Graphs of temperature vs time at the IPP1, IPP2, QPP and QCC intakes
for QPP and QCC only;
Intake location
QPP
QCC
Combined
(400MW)
QIPP1/2
411934 mE,
413745 mE,
2860608 mN
2856965 mN
Intake/Outfall
flow rate
127m3/s
134 m3/s
100 m3/s
Intake/Outfall
Characteristics
Channel
Channel
Piped
Ambient
Temperature
35 oC /20 oC
35 oC /20 oC
35 oC /20 oC
Ambient Salinity
60ppt
60ppt
60ppt
11
Outfall location
412652 mE,
414568 mE,
2859634 mN
2856060 mN
Outfall Salinity
60ppt
60ppt
60ppt
Exit Velocity
n/a
n/a
1.5m/s
Sea -Surface
Mid-Depth
Sea Bed
Depth Average
QIPP1-N
QIPP- S
QPP
QCC
0.0
0.0
0.0
0.0
0.1
0.1
0.0
0.1
1.1
1.2
1.2
1.2
0.8
0.8
0.8
0.8
2.2.1.1 Results
Excess temperatures between 10C and 3 0C are predicted along the stretch
of the coastline extending from the QIPP&2 plant discharge and merging with
the discharge from QPP producing a body of water approximately 6.38km2 in
extent at the surface and 3.19km2 at the sea-bed.
The wind (SE 11m/s) drives the plume towards the shoreline causing the
heated water to mix down through the water column. The time series also
confirms that no significant variation through the water depth is predicted
and that excess temperature varies little at any of the intake locations in this
Qurayyah QIPP1&2 (4000MW) Addendum to Social and Environment Assessment
August 2011
12
scenario.
There are no elevated temperatures at the intakes of QIPP1&2 (0 0C) while
fully mixed waters at QPP and QCC intakes are 1.2oC and 0.8oC respectively.
The average excess temperature for the 4000MW plant (with increased intake
and outfall lengths) is cooler at both the mid-depth and sea-bed (including
depth-average at all intakes than for the QIPP1 (1956MW) plant.
These results suggest that the proposed QIPP1&2 discharges will have no
affect on the intakes at QPP and QCC, and that the temperature increase
(1.2 o C) predicted in this scenario at the QPP intake is due to the recirculation
of the QPP discharge.
Figure 2-1 Predicted Tidal average excess temperature for 4000MW option, summer
with southeast wind of 11m/s- with Combined QIPP1&2
13
2.2.2
14
oC
to the
baseline.
Table 2-3 Predicted tidal average excess temperatures (OC) at the intakes, summer
shamal conditions (NNW wind: 5-15m/s) with Combined QIPP1&2
Sea -Surface
Mid-Depth
Sea Bed
Depth Average
QIPP1-N
QIPP- S
QPP
QCC
1.6
0.2
0.0
0.5
1.6
0.4
0.1
0.6
0.0
0.0
0.0
0.0
2.0
2.1
2.0
2.1
Conclusion
The results from this scenario indicate that the higher flow rates associated
with the 4,000MW plant, in combination with the longer intake and outfalls,
adequately compensate for the increase in power output from the plant
under the NNW 5-15m/s Summer Shamal wind conditions. Under this scenario,
the excess temperatures at QCC and QPP (with and without the combined
IPP1/2) are lower throughout the water depth when compared to the
previous configuration (QIPP1: 1956MW) as described in the SEA report.
15
Figure 2-2 Predicted Tidal average excess temperature for 4000MW option, summer
Shamal condition with Combined QIPP1&2
16
2.2.3
Under calm conditions, the plumes are able to spread offshore as a result of a
combination of buoyant spreading, slight offshore currents at times during the
tide, and offshore momentum of the discharges. This produces a much wider
area of impact at the surface than is predicted for the south-east or Shamal
winds. Despite the absence of wind, there is still a mean current toward the
south-east, and this causes a temperature rise at the QCC intake, which is
mostly attributable to the QPP discharge.
Table 2-4 Predicted tidal average excess temperatures (OC) at the intakes, calm
summer conditions
QIPP1-N
3.8
0.4
0.1
1.1
Sea -Surface
Mid-Depth
Sea Bed
Depth
Average
QIPP- S
3.4
0.6
0.2
1.1
QPP
0.2
0.1
0.1
0.1
QCC
1.5
1.2
0.9
1.2
2.2.3.1 Results
Under summer calm conditions, the modelling shows that the predicted tidal
average excess temperatures reach 3.8
OC
OC
and 3
OC,
17
Figure 2-3 Predicted Tidal average excess temperature for 4000MW option, summer
calm condition with Combined QIPP1&2
18
2.2.4
The south-easterly wind in this scenario is weaker than the wind used in the
summer conditions (Scenario 1). The scenario simulates winter conditions of
an ambient water temperature of 20 o C and a constant wind of 5m/s from
southeast. Although it produces sufficient surface stress to deflect the
discharges toward the northwest the main area of impact remains offshore.
There is little mixing of the warm water down to the bed (at temperatures
more than 1 o C above ambient), except in the immediate vicinity of the
discharges.
Table 2-5 Predicted tidal average excess temperatures (OC) at the intakes, winter
conditions (SE wind: 5m/s) with Combined QIPP1&2
Sea -Surface
Mid-Depth
Sea Bed
Depth Average
QIPP1
2.9
0.6
0.2
1.0
QIPP2
2.5
0.8
0.3
1.0
QPP
0.4
0.3
0.3
0.3
QCC
0.4
0.3
0.3
0.3
2.2.4.1 Results
At QCC and QPP intakes, little temperature variation is predicted through the
water column, and the depth average excess temperature is predicted to be
0.3 o C for both.
At the combined QIPP1&2 intake, average excess temperatures of 2.5 o C are
predicted at times, at the sea surface. The predicted excess temperatures
decrease through the water depth however, and are not predicted to be
greater than 0.3 o C at the seabed. The depth average excess temperature is
predicted to reach about 1.0 o C.
These results suggest that the proposed QIPP1&2 discharges will have little
effect on the intakes at QPP and QCC and the contribution to their own
intakes is 2.2 o C and 1.8 o C.
In the tidal average, the discharge plumes from the combined QIPP1&2 are
Qurayyah QIPP1&2 (4000MW) Addendum to Social and Environment Assessment
August 2011
19
predicted to merge with that from QPP, producing a body of heated water
at excess temperatures between 1oC and 3 oC. At the sea surface, this plume
has an area of 22km2 at the surface, of which QIPP1&2 contributes 6.8km 2
and QPP and QCC contribute 16.7km2.
20
21
22
23
Table 3-1 below identifies the PME ambient air quality standards relevant to
this project.
Table 3-1 PME Air Quality Standards for Ambient Air Quality
Pollutant
Standard (g/m3)
Averaging Period
No of Permitted
Exceedences
Sulphur Dioxide
(SO2)
Particulates
(PM10)
Particulates
(PM10)
730
1-hour
365
24-hour
80
Annual
N/A
660
1-hour
100
Annual
N/A
340
24-hour
80
Annual
N/A
International Finance Corporation World Bank Group, General EHS Guidelines: Environmental. Air Emissions
and Ambient Air Quality, April 2007.
24
Averaging Period
Guideline Value
(g/m3)
Nitrogen Dioxide
Annual
40
1-hour
200
125 (Interim target 1)
Sulphur Dioxide
24-hour
50 (Interim target 2)
20
70 (Interim target 1)
50 (Interim target 2)
Annual
30 (Interim target 3)
20
Particulate Matter (as PM10)
150 (Interim target 1)
100 (Interim target 2)
24-hour
75 (Interim target 3)
50
The potential impact of the proposed facility on local air quality has been
assessed using Breeze AERMOD7 (version 7.3.1), a new generation dispersion
25
Emission Scenarios
For normal natural gas-fired operations at the site, the most significant
pollutants will be nitrogen oxides (NOx as NO2) and particulate matter (as
PM10). In the event of gas supply failure, it is proposed that low-sulphur (<0.5%
S) diesel oil is used as a back-up fuel, which will result in emissions of sulphur
dioxide (SO2), in addition to NOx and PM10.
The source emission parameters used in the dispersion modelling are
presented in Appendix 2.
The following emission scenarios have been assessed:
26
3.4.3
The modelling has been carried out using three years (2007, 2008 and 2009) of
hourly sequential meteorological data in order to take account of interannual variability and reduce the effect of any atypical conditions. Data
from King Fahd International Airport at Dammam (approximately 75 km northnorthwest of the proposed site) has been used for the assessment, which is
the most representative data currently available for the area. The King Fahd
Airport dataset does not include cloud cover; therefore this information has
been obtained from the meteorological observing station at Dhahran Airport,
a Royal Saudi Air Force base in Dammam.
Wind roses for each of these years are presented in Figure 3-1 below; these
show that the prevailing wind directions are from the west, northwest and
north.
Figure 3-1 Wind rose for King Fahd Airport (2009)
3.4.4
Buildings
27
earlier than otherwise would be the case and result in higher ground level
concentrations closer to the stack.
Downwash effects are only significant where building heights are greater
than 30 to 40% of the emission release height. The downwash structures also
need to be sufficiently close for their influence to be significant.
The majority of the structures at the proposed site are open frameworks,
which are unlikely to have a significant impact on wind flow and have
therefore not been included in the dispersion model. The only structure with
the potential to affect dispersion from the stack is the HRSG building, which
has been included as potential downwash structure.
3.4.5
Sensitive Receptors
Receptor
Type
Easting
Northing
Qurayyah
Combined
Cycle
Power Plant (QCC)
Industrial
413074
2857271
Residential
412382
2857271
QCC
supporting
camps and offices
Residential
413137
2857852
Industrial
411848
2860240
Qurayyah
Steam
28
SEC
Camp
Community
Residential
411424
2861261
Residential
410592
2859925
Aramco
Seawater
Treatment Plant
Industrial
410159
2863645
Al-Khaleej
Village
Residential
389289
2886785
Residential
408690
2889743
10
Port and
Facilities
Industrial
414041
2879671
11
Al
Durrat
Development,
Bahrain
Residential
459863
2857018
12
Abqaiq
Residential
368754
2868928
13.
Al Oqair Port
Industrial/
Residential
421268
2836480
Makarim
Industrial
QIPP1
&2
QCC supporting camps and offices
BEMCO Camp and Laydown
QCC
29
3.4.6
Significance Criteria
30
NO2 Concentrations
2007 -2009
2008
2009
IPP1&2
ALL
IPP1&2
ALL
IPP1&2
ALL
Industrial
Receptors (1-7)
Ranges from:
2.4 -10.7
27.1 - 37.1
5.3 14.6
26.7 53.5
2.3 13.7
26.7 - 51.0
Residential
Receptors (813) Ranges
from:
0.33 1.7
8.1 16.7
0.28 - 1.8
6.4- 13.4
0.84- 1.8
6.7- 9.2
Maximum Receptor Concentration (IPP1&2): 14.6 (QCC Supporting camps and Offices)
Maximum Receptor Concentration (ALL): 54.8 (Temporary SEC Community Camp)
Air Quality Standard (PME): 660
Air Quality Guideline (IFC): 200 (as the maximum 1-hour mean)
3.5.1.1 Results
Predicted ground level NO2 concentrations are well within the relevant AQS.
The maximum receptor concentration due to emissions from QIPP1&2 alone
may be summarised as follows:
The
maximum
short-term
(99.7th
percentile
of
1-hour
means)
31
32
3.6
2007
2008
2009
IPP1&2
ALL
IPP1&2
ALL
IPP1&2
ALL
Industrial
Receptors (1-7)
Ranges from:
0.22 0.98
1.4 - 26
0.14- 0.66
2.5 5.6
0.19 -0.86
2.4 -5.3
Residential
Receptors (8-13)
Ranges from:
0.015
0.080
0.16 - 0.33
0.020- 0.071
0.040 1.81
0.021
0.057
0.40- 0.81
Maximum Receptor Concentration (IPP1&2): 1.4 (QCC Supporting Camps and Offices)
Maximum Receptor Concentration (ALL): 5.6 (SEC Cooking and Cleaning Camp)
Air Quality Standard (PME): 340
Air Quality Guideline (IFC): 50 (as the maximum 24-hour mean)
3.6.1.1 Results
Predicted ground level PM 10 concentrations are well within the relevant AQS.
The maximum receptor concentration due to emissions from IPP1&2 alone
may be summarised as follows:
33
(g m-3) QIPP1&2
34
The
ground-level
99.7th
percentile
of
1-hour
mean
NO2
(g m-3)
Receptor
Industrial
Receptors (1-7)
Ranges from:
Residential
Receptors (813) Ranges
from:
2007 -2009
2008
2009
IPP1&2
ALL
IPP1&2
ALL
IPP1&2
ALL
12.2 - 72.3
27.1 - 37.1
12.4 76.8
34.5-106
2.3 13.7
34.1 103
6.4 - 11
12.4 77.2
1.6-9.3
11.4-16.2
11.7-71.5
10.7-15.0
Maximum Receptor Concentration (IPP1&2): 76.6 (QCC Supporting camps and Offices)
Maximum Receptor Concentration (ALL): 106 (QCC Supporting camps and Offices)
Air Quality Standard (PME): 660
Air Quality Guideline (IFC): 200 (as the maximum 1-hour mean)
3.7.1.1 Results
Predicted ground level NO2 concentrations are well within the relevant AQS.
The maximum short-term (99.7th percentile of 1-hour means) receptor
concentration due to emissions from IPP1&2 alone is 11.6% of the PME AQS for
NO2 of 660 g m-3. The maximum NO2 impact occurs at receptor 3 (QCC
supporting camps and offices) for both emissions from IPP1&2 alone and the
cumulative sources. At worst, the predicted short-term NO2 concentration
due to emissions from IPP1&2 represents 90.0% of the total cumulative impact
at QPP (receptor 4).
Predicted cumulative short-term NO2 concentrations are well within the IFC
maximum 1-hour mean guideline value of 200 g m-3. Predicted 99.7th
percentile of hourly mean NO2 concentrations for the most recent year of
Qurayyah QIPP1&2 (4000MW) Addendum to Social and Environment Assessment
August 2011
35
meteorological data (2009) are also presented as contour plots below (for
IPP1&2 and the cumulative scenario respectively).
Plate
(g m-3) ALL
36
3.8
(g m -3)
Receptor
2007
2008
2009
IPP1&2
ALL
IPP1&2
ALL
IPP1&2
ALL
Industrial
Receptors (1-7)
Ranges from:
0.11 0.91
1.4 2.4
0.11-0.99
1.5 - 3.3
0.11 -0.68
1.3-2.9
Residential
Receptors (8-13)
Ranges from:
0.009-0.043
0.21-0.34
0.0068-0.059
0.040 1.81
0.021
0.057
0.0045-0.035
Maximum Receptor Concentration (IPP1&2): 0.99 (QCC Supporting Camps and Offices)
Maximum Receptor Concentration (ALL): 3.3 (QCC Supporting Camps and Offices)
Air Quality Standard (PME): 340
Air Quality Guideline (IFC): 50 (as the maximum 24-hour mean)
3.8.1.1 Results
Predicted ground level PM 10 concentrations are well within the relevant AQS.
The maximum short-term (93.4th percentile of 24-hour means) receptor
concentration due to emissions from QIPP1&2 alone is 0.29% of the PME AQS
for PM10 of 340 g m -3.
At worst, the predicted short-term PM10 concentration due to emissions from
IPP1&2 represents 48.9% of the total cumulative impact. Predicted cumulative
PM10 concentrations are well within the IFC maximum 24-hour mean guideline
value of 50 g m-3.
Predicted 93.4th percentile of 24-hour mean PM 10 concentrations for the most
recent year of meteorological data (2009) are also presented as contour
plots in Plate 3-5, for QIPP1&2 and the cumulative scenario respectively.
37
Plate 3-5 Predicted 93.4th Percentile of 24-Hour Mean PM10 Concentrations (g m-3)
ALL
38
3.9
2007
2008
2009
IPP1&2
ALL
IPP1&2
ALL
IPP1&2
ALL
Industrial
Receptors (1-7)
Ranges from:
41.6 - 183
84.3 242
25.6-258
70.8 - 333
36.6-169
66.1-257
Residential
Receptors (8-13)
Ranges from:
3.0 - 15.5
15.6-44.8
4.0-14.4
13.9-37
4.4-11.5
14.5-17.9
Maximum Receptor Concentration (IPP1&2): 258 (QCC Supporting Camps and Offices)
Maximum Receptor Concentration (ALL): 333 (QCC Supporting Camps and Offices)
Air Quality Standard (PME): 365
Air Quality Guideline (IFC): 20 (as the maximum 24-hour mean)
Table 3-9 Predicted 99.7th Percentile of 1-Hour Mean SO2 Concentrations (g m-3)
Receptor
2007
2008
2009
IPP1&2
ALL
IPP1&2
ALL
IPP1&2
ALL
Industrial
Receptors (1-7)
Ranges from:
76.8 -457
212-499
78.6-486
210-684
74.3-452
209-661
Residential
Receptors (8-13)
Ranges from:
11.7-69.7
55.4111.9
10.0-62.2
7.3-54.9
7.3-62.4
65.4-77.1
Maximum Receptor Concentration (IPP1&2): 486 (QCC Supporting Camps and Offices)
Maximum Receptor Concentration (ALL): 684 (QCC Supporting Camps and Offices)
Air Quality Standard (PME): 730
3.9.1.1 Results
Predicted ground level 99.7th percentile of 24-hour and 1-hour mean SO2
concentrations due to emissions from QIPP1&2 are well within the PME air
Qurayyah QIPP1&2 (4000MW) Addendum to Social and Environment Assessment
August 2011
39
summarised as follows:
The maximum SO2 impact occurs at receptor 3 (QCC supporting camps and
offices) for both emissions from QIPP1&2 alone and the cumulative sources.
The dispersion modelling predicts a widespread exceedence of the 24-hour
IFC guideline. However, the predicted concentrations are worst-case and
would only occur where diesel oil firing occurs during a meteorological event
resulting in poor dispersion from the stacks. It is likely that when the plant is
operating in back-up mode the ground-level concentrations will be
considerably lower than those predicted.
Predicted 99.7th percentile of 24-hour and 1-hour mean SO2 concentrations for
the most recent year of meteorological data (2009) are also presented as
contour plots in Plate 3-6 and Plate 3-7.
Plate 3-6 Predicted 99.7th Percentile of 24-Hour Mean SO2 Concentrations (g m-3) All
40
Plate 3-7 Predicted 99.7th Percentile of 1-Hour Mean SO2 Concentrations (g m-3)
ALL
3.9.2
Mitigation Measures
During commissioning, the stack emissions will be tested for NOx, SOx and
PM10 to ensure that the control systems are operating correctly and that
emission values comply with PME and WB/IFC standards;
In addition the
41
Stack
monitoring
data
collected
during
commissioning
and
the
environmental
auditors
to
verify
the
performance
and
compliance status;
NOx emissions from the plant when burning Gas in turbines will be reduced
to meet the emissions standards specified by the applicable standards by
installing dry low NOx combustion.
Fugitive emissions from the combined QIPP1&2 site during operation will
be controlled by an inspection and maintenance programme that will be
detailed within the Environmental Management System
(equivalent to
42
In the event of gas supply failure at the site, diesel oil will continue to be used
as a back-up fuel for a maximum of five successive days. The dispersion
model predicts for this scenario there is potential for a widespread
exceedence of the 1-hr and 24-hr PME standard and IFC 24-hour mean
guideline value. However, It should be noted that this is a worst-case
prediction since it assumes that back-up operation of the facility is coincident
with periods when meteorological conditions result in poor dispersion of stack
pollutants. The likelihood of these exceedences occurring is small.
43
4 Noise Modelling
Modelling of the noise emissions from each of the Siemens-Westingheure F
class turbines has been derived from measurements at similar combined
cycle power plants over 20 years. Although the noise modelling has been
undertaken for the 1963.5MW Plant, the larger 4,000MW plant is unlikely to
have significantly increased impacts due to the following:
The noise modelling reported in the SEA has shown that the site will meet
RFP standards without the need for additional acoustic barriers;
The results of the baseline noise model for the 1963.5MW QIPP1 Plant for full
load, steady state operation is illustrated in Plot 1. This shows that the 65dBA
sound contour does not extend beyond the plant fence-line indicating that
the facility is likely to comply with the RFP standard without any special or
non-standard acoustic improvements. However, several measures are
proposed to guarantee compliance during operations. It is noted that the
nearest temporary BEMCO camps to the south and west would experience
noise levels of 45- 47 dBA (although they are likely to have been removed
prior to operation of IPP1). The SEC Community Camp 5.5km to the north
would be <45dBA.
Noise modelling of start-up operations has also been undertaken and noise
plots (See Figure 4-1 and Figure 4-2 below) are shown for unattenuated and
attenuated noise conditions. These scenarios demonstrate the need for
mitigation measures, which are detailed in the following section.
The external sound level due to the facility operation at the administrative
building will not cause the sound level inside the control room to exceed the
permissible level of 50dBA (ref: IFC 8-hour exposure in open office and control
room of 45dbA).
44
Figure 4-1 Indicative Modelling Plot for Qurayah IPP1 (Predicted Sound Contours (dBA) of baseline Plant Operating at Full Load (Plot 1))
45
Figure 4-2 Predicted Sound Contours (dBA) of Attenuated Plant During Start-up of QIPP1 (Plot 2)
46
4.1.1
Mitigation measures
Acoustically lag the fuel gas pressure reducing valve bodies and all
above ground downstream piping to avoid excessive noise at the nearby
northern fence line.
Specify all equipment, except the steam turbine and generator, to limit
near field noise to 85dBA at 1m.
set
of
mitigation
recommendations
and
silencer
The HRSG blowdown tanks on all 6 units should be fitted with silencers.
The steam turbine area drain tank should be located inside the ST building
and its atmospheric vent should be fitted with a substantial silencer.
If an SJAE is used for hogging, the system should be located inside the ST
building and its atmospheric vent should be fitted with a substantial
silencer. Use vacuum pumps for hogging, if possible.
Locate the steam turbine bypass valves inside the ST building and not
outside on the exposed pipe racks.
Drag valves are recommended for the HRH, HP, IP and LP vents on each
HSRG at 90 dBA at 1m to avoid excessive noise if these will be regularly
used during normal start-ups. The lead-in lines to these silencers may need
47
48
5 Overall Conclusions
5.1.1
Simulations have been carried out for the combined QIPP1&2, 4000MW plant
for four combinations of season, wind and tide. The results from marine
recirculation modelling indicate that the higher flow rates associated with the
40000MW plant, in combination with the intake and outfall being located at
the -10m and -3.5m contour, adequately compensate for the increase in
power output from the plant under all wind conditions.
The combined QIPP1& 2 plant will have a number of advantages over
separate plants including the following:
Two cooling water intakes have been combined into a single intake
reducing the direct impact on the marine habitats;
The discharge from the QIPPs for the 1963.5MW plant contributed 32%
to the total heat load in the environment. The contribution from the
combined QIPP1&2 plant results in a decrease to 28% due to the
efficient plant operations. QPP and QCC contribute 35% and 37%
respectively.
49
itself. This is due to the relatively large size of the QCC and QPP
discharges, together with the fact that they are shoreline discharges.
Much of the coastal impact is therefore caused by QPP and QCC.
5.1.2
An assessment has been carried out to determine the potential air quality
impacts associated with the proposed combined Qurayyah Independent
Power Plant (QIPP1& 2). The stack point source emissions from the combined
Qurayyah IPP1&2, given the use of gas fuel, will be predominantly NO2, with
relatively small emissions of particulates. Detailed dispersion modelling of
potential emissions from the proposed facility predicts that for normal natural
gas-fired operations at the site, ground-level pollutant concentrations at
sensitive receptors will be well within the relevant PME and IFC air quality
standards and guidelines.
Although the noise modelling has been undertaken for the 1963.5MW Plant,
the larger 4,000MW plant is unlikely to have significantly increased impacts
due to the following:
The noise modelling reported in the SEA has shown that the site will meet
RFP standards without the need for additional acoustic barriers. However
to guarantee compliance of the 4,00Mw Plant, additional measures have
been proposed which are applicable to the 4,000 MW Plant as well.
50
Summing Up
This addendum, read in conjunction with the SEA Report and Technical
Appendices for QIPP1 (ref 1005/001/009, June 2011), complies with the national
(PME) and international standards (IFC/WB) for marine thermal recirculation, air
quality and noise. By combining the two independent power plants (QIPP1&
QIPP2) into a single facility, the environmental impacts (during both the
construction and operational phases) are reduced due to more efficient
plant operations, reduced number of intake and outfall pipelines, reduced
thermal discharge and a decrease in the heat load to the environment. The
land take has also been reduced due to the more efficient layout of the
QIPP1&2 plant, thereby protecting the terrestrial ecology and maintaining
biodiversity in the Qurayyah Complex. The increased number of stacks also
provides better dispersion.
It should be noted that there are however, additional social and economic
benefits resulting from the increased power supply to the Eastern Region of KSA.
51
6 Appendices
Appendix 1: TN-EBR4778-05 - Qurayyah IPP: Thermal recirculation assessment
of Qurayyah IPP1: 4000MW (HR Wallingford); and
Appendix 2: E525 - Air Quality Impact Assessment (Qurayyah Independent
Power Project 1 (4000MW), Qurayyah, Saudi Arabia (Entran Ltd).
52