Sie sind auf Seite 1von 20

POUR CARD FOR PEDESTALS

NAME OF PROJECT
NAME OF BUILDING
FOOTING MARK
S.No.
1
a
b

ACTIVITY
Alignment
Horizontal
Vertical

2 Reinforcement and shuttering


a

Date

Main vertical reinforcement

Laps if any

Rings

Cover Blocks

Shuttering

Diagonal length varification

Top level of Pedestals

Gaps and joints sealed properly


3 Foundation Bolts

Date:

Template

Dia of bolts

Length of bolts

Threaded Length

Projection above top of padestal

Location of bolts

Material of bolts

Verticalness of Bolts

CHECKED BY

4 Concreting Date:
a

Date

Concrete mix M-20

Cement Consumption

c1

Threoratical consumption

c2

Actual consumption

Slump

Cube Strength Test

e(i)

compressive strength in 7 days


Date:
compressive strength in 28 Days
Date:
Curing

f(ii)
5

Pedestals is to be covered with


hessian cloth and curing is to be
carried at least ten days and four
times a day

PEDESTALS

REMARKS

are to be staggered

Good Quality ply shuttering to be used, gaps and


joints are to be sealed properly

POUR CARD FOR PLINTH BEAM/ FLOOR BEAMS

NAME OF PROJECT
NAME OF BUILDING
LOCATION/GRID MARKING

Activity

CHECKED BY

1 Alignment
a

Horizontal

Vertical
2 Shuttering

Date:

Date

Bottom Level

Top Level

Type of Shuttering

Gaps and joints are sealed properly

Reinforcement

Date:

b
c
d

Main R/F at Top


Main R/f at bottom
Extra reinforcement at top of suports

Rings

Laps

f(i)

Bottom Bars

f(ii) Top bars

4 Concreting
a

Date:

concrete mix M-20

cover blocks

Slump

Cube Strength

Cement Consumption

f1

Theoratical consumption

f2

Actual consumption

Date :

f(i)

Compressive Strength in 7 Days


Date:
bf(ii) Compressive Strength in 28 Days
Date:
5
Curing
Concrete surface is to be covered
with hessian cloth and curing is to be
carried at least ten days and four
times a day

ARD FOR PLINTH BEAM/ FLOOR BEAMS

REMARKS

Good Quality ply shuttering to be used, gaps and joints are to be sealed
properly

Are to be Staggered.
Near column support and not in the centre of span
In the centre of span and not near column support

U.G. TANK POUR CARD


NAME OF PROJECT
NAME OF BUILDING
FOOTING MARK

Talbros Automotive Component Ltd.


U.G. Tank
Raft. Drg. No. S-17

Horizontal / Vertical Aligment Checked


Sr. No.
ACTIVITY
1
Alignment
a
Horizontal
b
Vertical
2
a
b
c
3
a
b
c
4
a
b
c
d
e
e1
e2
5
a
6
a
7
a
b
c
d
e
f
f1
f2
g
h
h(i)
h(ii)
8

Exacavation
Date:
Depth
Size
Soling
Date:
Size
Thickness
PCC
Date:
Size
Thickness
Mix Proportion
Cement consumtion
Theoratical consumption
Actual consumption
Reinfrocement
Date:
shuttering
Date:
Concreting
Date:
Cover Block
Concrete grade M-20
Thickness at Toe (t)
Total Thickness ( T)
Cement Consumption
Theoratical consumption
Actual consumption
Slump
Cube Strength
Compressive Strength in 7 Days
Date:
Compressive Strength in 28 Days
Date:
Curing
curing is to be carried at least ten
days and four times a day

CHECKED BY

REMARKS

DAILY ACTIVITY CHART


Name of project
Name of Building /Work
consultants

Contractor

Owner

Planned for
Previous day

Achieved on
previous day

Planned for Today

Previous Day

Today

Safety Measures checked by

S.No.

Activity Description

Reasons for not achiving the target

Manpower Detail
Mason
Carpainter
Bar Binders
Welders
Supervisers
Anyother

1
2
3
4
5
6
7
8

Major Equipments deputed at site


Actual at site
JCB
Tractors
Trolley
Mixer
Vibrates
Welding Machine
Plate Vibrators
Road Roller

Required at Site

Remarks

Project In-charge

Contractor

Remarks

Silt Content in Coarse Sand


S.No.

Date

Total Ht of sand
Taken

height of silt After


pouring water

Height of pure percentage of silt


sand
content

Compaction Test For Earth Filling

Dry Density
W3/V1

Date of
Testing

S.No.
1

a
b
c

Location

Weight of
Volume of empty
core
core cutter
cutter (V1) (W1)
1.005
0.926

Recommended optimum moisture content


Sands / Gravels
8-10%
Silt
15%
Clays
15-20%

Note : - One test for every 500 sqm.

Weight of
core cutter Weight of
including
wet soil
soil (W2)
W3=W2-W1
2.865
1.939

Bulk
density
rd=(W2Weight of Dry
W1)/V1
Soil W3
1.92935323

Maximum Dry Density


Clay
1700 kg/cum
Sand
1950kg/cum
Silty Clay
1850kg/cum
Sandy Clay
2150kg/cum

CUBE TESTING RECORD

S. No.

Date

Location

Size of
cube

Compressive strength after


weight of
7days
cube
(Shall not be
less than
Nos of
strength of
8kg)
cubes taken Total failure load cube

Compressive strength after 28 days

Total failure load

Compressive strength after 28 days

Remarks 7 days
(Comprssive strength
shall not be less than
Authorised 70% of total required
strength of cube person
strength in 28 days

S.N
o.
Date

client rep.

Nos of
bricks
taken(m
in
5bricks
on
10000br Size of
icks
Bricks

Dry weight of
bricks( weight shall
be taken after
drying the bricks
upto 24 hours in
wave oven) W1

weight of weight
bricks( Brick shall
be dipped in water
not less than 24
hours)W2

contracror rep.

Weight
Difference
W3=W2-W1

water absorption
percentage W3/W1*100

EFFLORESCENCE TEST OF BRICKS

S.
N. Date

Nos of Size of
bricks Bricks

client rep.

Date of
testing

total
effloresce
surface
nce area
area of
of brick effloresc
brick (A1)
(A2)
ence %

contracror rep.

category
efflorescenc
e
Remarks

BRICK COMPRESSIVE STRENGTH TEST

S.N
o.
Date

client rep.

Nos
of
brick Size of
s
Bricks

Date of Frog
Curing Dates
filling with
Cement
Finishing
mortar 1:3
Start Date Date

contracror
rep.

Date of Failure of
Testing Load

Compressive
strength of
bricks
Remarks

Das könnte Ihnen auch gefallen