K-259 Upper completion operation Monday,

January 11, 2016


1. P/U & M/U 3 tail pipe assembly with 9-5/8 QHS Schlumberger packer
assembly, and PBR assembly, SSD as per tally No.1 to Joint No. 6 of 3 tubing.

Schlumberger completion engineer should be on Rig floor.

SSD in open position.

Run packer in wellhead carefully.

Lock rotary table all times & do not rotate string

Set Running speed 60 on Amphion.

Drift 3 tubing with 2.74

Clean all joints with water, apply dope on pin end on V-door.

2. R/U SLB Slick line and run 2.74 drift to Glass disk sub @ 182 ft
3. P\U & M\U X-over 4-1/2" V.T By 3-1/2" EUE Pin
4. Continue RIH with 4 tubing, P/U GLMs as per tally.

R/U slick line after Joint No.84 (RIH sequence #85)

Run #1 with 3.8 drift run to XO at 2290 ft

5. Continue RIH with 4 tubing


a. R/U slick line and make

Run # 2 with 3.80 drift run to XO at 4342 ft

5. S/L run and close SSD.

Schlumberger completion engineer should be on Rig floor.

Count remaining tubing on cantilever ( remaining 18 x 4-1/2 tubing ,

6. Connect circulating head and lines and pressure test to 500 psi.
7. Pressure up string slowly to 3000 psi.

8. Slack off 10,000 lb to 15,000 lb increase pressure to 3800-psi hold for 10 minutes to
complete packer setting. Bleed off pressure.
9. Pull test 15 to 20Klbs, to confirm the packer is set.
10.Close the annular, pressure test the annulus to 1000 psi for 10 minutes.
11.Open the BOP. Apply 1000 psi to the tubing and over pull to 65 Klbs to shear the
PBR. Bleed off pressure.
12.

P/U string and Sting out PBR seals

13.

POOH 10 joints (No.27 to No.18 ) & Rack back on derrick

14. P/U & M/U 4-1/2 TRSSSV, control line. Test it with 4500 psi and hold for 15 mins.

15. RIH TRSV with 2x stands of 4-1/2 tubing ( Joints No. 27, 26, 25, 24, 23, 22, 21 )

Strap control line to tubing

Maintain pressure in control line

16. RIH last stand, set slips at Joints No.21 & break between joints No.21 & 20
17. Install tubing hanger

Pass control line and terminate control line after bleeding off pressure, test the control line
with 4500 psi for 15 mins.

18. Continue RIH Joints No.20 & 19 ( Keep 8 ft stick up )


19. R/U Slick line and make the final Drift W/ 3.8 to 300 ft to below TRSV.
20. Drain BOP and make sure lock down pins are out.
21. Lower string and sting in with seal assembly into PBR, align tubing hanger and land in wellhead,
tight lock down pins.
22. Test the annulus to 1500 psi with Tubing open.
23. R/U S/L and install PX plug in TRSV.

24. Pressure test to 500 psi.


25. Install the One-way BPV.
26. N/D BOP.
27. N/U tubing Bonnet and Control line.
28. N/U Production tree as per KJO Procedure and production requirements.
29. Pressure up on Control Line. Open TRSV and maintain 4,500 psi to ensure the TRSV is open.
30. Rig up slick line Lubricator unit and Pressure Test to 1,000 psi.
31. Retrieve one way BPV.
32. R/U S/L and retrieve PX plug.
33. P/T Bonnet & X-mess tree to 3000 psi
34. Slick line retrieve dummy from GLM # 1 at 2078 ft and install Orifice.
35. S/L open SSDV
36. Displace annulas to tbg with diesel.
37. S/L RIH and close SSDV.
38. Test annulas with 1000 psi.
39. S/L RIH with sinker bar and break the Glass Disk. Confirm by passing through it. Run until tubing
end.
40. S/L POOH & R\D slick line unit.
41. Install needle valve and guard on the control line outlet of the tubing bonnet. Secure well.
42. Measure the wellhead, X-Mas tree heights as per drawing given.
43. Clean jacket and confirm Jacket inspection is done to satisfaction of OFD
44. Skid in and secure rig as per procedures for rig move operation.
45. Release the rig to the next well

Work Safe, Good luck !