Beruflich Dokumente
Kultur Dokumente
1.0 INTRODUCTION
1.1
Background
1.2
FORMS REVISED
Old Forms
New Form
Application
1. JKR 203A(Rev.83)
JKR 203(Rev.1/2010)
2. JKR 203(Rev.83)
JKR 203(Rev.1/2010)
3.JKR 203N(Rev.83)
JKR 203N(Rev.1/2010)
4.JKR 203P(Rev.83)
JKR 203P(Rev.1/2010)
Old Forms
New Form
Application
PWD DB(Rev.1/2010)
1.3
NUMBER OF CLAUSES
JKR 203A
Old Form
56
New Form
Rev.2007
Rev.1/2010
78
81
Additonal 22
Clauses (3)
JKR 203
Old Form
56
Change
New Form
Change
Rev.2007
Rev.1/2010
78
81
Additonal 22
Clauses (3)
JKR DB
Old Form
62
New Form
Change
Rev.2007
Rev.1/2010
76
79
Additonal 14
Clauses (3)
JKR 203N
Old Form
37
New Form
Change
Rev.2007
Rev.1/2010
50
50
Additonal 13
Clauses (3)
JKR 203
Old Form
37
New Form
Change
Rev.2007
Rev.1/2010
37
37
No Change
Note: For the JKR 203N, the clause 41.0 in the Rev.2007 Forms has been
deleted and a new Clause 5.0 added in the Rev. 1/2010 Form.
Addendum
to COC
COMPARISON
BETWEEN PWD 203A
(REV. 2007) / PWD 203A (REV. 1/2010)
(CONTD)
PWD 203A (1/2010)
Clause
1.0
Definitions And
Interpretation
2.0
Contract Period
3.0
1.1 : Definitions
1.2 : Interpretation
2.0
Contract Period
Clearly define the contract period, D/Possession and
D/Completion.
3.0
4.0
4.0
S.Os Right to
Take Action
Difference
5.0
S.Os Instruction
5.0
S.Os Instruction
9
Clause
6.0
Contract Sum
Scope of Contract
Difference
7.0
Contract Sum
8.0
Contract Documents
Contract Documents
8.1 : Documents required in 2 sets, one
original with S.O. and contractor
8.2 : S.O will issue instruction regarding any
discrepancies in the contract document.
10
Clause
9.0
Representation,
Warranties and
Undertakings of
the contractor.
10.0
Obligation of the
contractor
10.0
11.0
Inspection of Site
Contractor must visit the site, take note of all risk involved,
access roads, working constraints, etc., especially factors
with cost implication. Information given in document may not
be conclusive, may not relieve the contractor of his
obligation under the contract.
Difference
11.0
Inspection of Site
11
Clause
12.0
13.0
13.0
Performance Bond/
PGB
14.0
Indemnity in
respect of personal
injuries and
damage to
property.
12
14.0
Clause
15.0
Insurance against
personal injuries
and damage to
property.
16.0
Indemnities to the
government in
respect of claims
by work men.
13
Clause
17.0
Employees Social
Security Act 69
18.0
Insurance of work
Insurance of work
- Effect and maintain insurance to cover against
loss and damage by fire, lightning,
-Bear the excess amount as stipulated in Appendix
-Period of cover until completion of the works.
-In case of failure, the Govt may extent the
insurances on behalf of the contractor, the cost of
which shall include 5% (on-cost charges).
-Cancellation of insurance is made 30 days after
receipt of notice by the government.
-Where claims exceed insured amount, the surplus
shall be borne by contractor.
-It stipulates a notification procedure and obligation
the contract to ensure a mandatory procedure is
followed any cancellation process
14
Clause
19.0
Setting out
20.0
21.0
20.0
21.0
15
Clause
22.0
16
Clause
23.0
23.1 : Workmen
Restricted to Msian citizens unless
proven
unavailable. Applies to sub-contractors.
23.2 : Compliance Employment
Act 55 (PERKESO)
23.3 : Days and hours of working
Approval for overtime must be
obtained from S.O. the cost borne
by the contractor.
23.4 : Wages Books and Times Sheets.
23.5 : Default in payment of wages.
17
24.0
Variation
Clause
24.0
Variation
25.0
Valuation of variation
Definition of variation:
A change in the contract Document
arising from the alteration or
modification of the design, quality or
quantity of the Works; including
addition, omission or
substitution/removal from site. There
is a cross reference to sub-clause 22.1
the effect of the SOs approval of the
contractors design.
25.0
Valuation of variation
Contract Rates (of similar character or
similar conditions).
Fair Rates (of differing nature or
differing conditions).
Pro-rata Rates
Day work + 15%
18
Clause
26.0
Bills of Quantities
27.0
Measurement of work
28.0
Payment to contractor
and interim certificate.
27.0
Measurement of work
Outlines the method to be used in measurement of
variation & provisional quantities to be carried out by
contractors agent & S.O. during joint valuations.
28.0
19
Clause
29.0
Adjustment of
Contract Sum
30.0
Fluctuation of price
31.0
32.0
Effect of S.Os
Certificate
30.0
Fluctuation of price
32.0
20
33.0
Clause
33.0
Deduction from
money due to
contractor
34.0
Prime
Cost/Provisional
Sum
35.0
Materials, Goods
and Workmanship
34.0
35.0
21
36.0
Clause
36.0
37.0
Constructional Plant,
Equipment, Vehicle &
Machineries.
37.0
22
38.0
Possession Site
Clause
38.0
Possession Site
23
Clause
39.0
Completion of
Work
40.0
40.0
41.0
Sectional Completion
Involves different Completion Dates for ascertained
portions of work as stipulated in the Appendix where the
EOT, CPC, LAD and DLP will also be considered
separately except Insurances, PB, Final Payment.
Difference
41.0
Sectional
Completion
24
Clause
42.0
Partial Occupation/
taking over by
government.
43.0
25
Clause
44.0
45.0
Investigation by
government and other
persons in case of
accidents, failure or
other event.
46.0
Claims arising from delay (EOT) due to:43.1 : (c) Suspension of Works
(d) S.O. instructions & neighboring
disputes
(e) S.O. instruction under Cl. 5
(f) delay caused by S.O
(h) delay by 3rd party appointed by Govt.
45.0
46.0
26
Clause
Sub-Contract or Assignment
47.0
Sub-Contract or
Assignment
48.0
48.0
Completion
Date
DLP (12 Mths)
CMGD
14 Days
Final list
3 Mths
27
Clause
49.0
Unfulfilled
Obligations
50.0
Suspension of
Works
50.0
Suspension of Works
Difference
28
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010) (CONTD)
Clause
51.0
Clause
51.0
29
Clause
51.0
Events and
Consequences
of Default by
Contractor (contd)
52.0
Termination on National
Interest
Stop Work
Carry out protective work
Remove personnel
Vacate site
Terminate his sub-contractors
Return all plans/documents etc
Pay losses/damages to the Government.
52.0
30
Clause
53.0
54.0
54.0
Payments Upon
Suspension
&Termination On
National Interest
31
Claus
e
55.0
56.0
Surviving Right
(new clause)
Difference
56.0
57.0
57.0
32
Clause
58.0
59.0
60.0
59.0
60.0
33
Claus
e
61.0
Clause
JKR 203A
Rev. 1/2010
61.0
62.0
No Liability of
government to NSC and
NS
63.0
Responsibility of
Contractor to NSC and
NS
64.0
Intellectual Property
Rights
63.0
64.0
Antiquities
All discovery of objects of interest or value during
construction shall be the absolute property of the
Government. Contractor to inform S.O. immediately who
in return will issue instruction as what is to be done.
Contractor will be reimbursed
34
Clause
65.0
Antiquities
66.0
Arbitration
67.0
Notices
Notices
Notices shall be effected by;
i.
Hand delivery or courier,acknowledge
receipt.or
ii.
Leaving notices at the registered
address in the contract or
iii.
Registered post,deemed to have
received, 7 days from date of posting.
Onus on Contractor to inform of any change in
address.
67
Amendments
No amendments to be made to this
agreement unless made by mutual consent
by way of a supplementary agreement.
35
Claus
e
68.0
Clause
68.0
Stamp duty
Safety At Site
Difference
69.0
JKR 203A
Rev. 1/2010
69.0
Advance Payment
Difference
70.0
Severability
73.0
Severability
71.0
Waiver
74.0
Waiver
36
Clause
Clause
72.0
Laws applicable
75.0
Laws applicable
73.0
Successors Bound
76.0
Successors Bound
74.0
77.0
75.0
Technology Transfer
78.0
Technology Transfer
76.0
79.0
80.0
Restriction on imported
materials and
goods
78.0
Time
81.0
Time
37
OTHERS
Appendices
Addendum
Special Provisions
THANK
YOU
39
Clause
Differences
4.0
6.0
10
New sub provision 12.1(a), (b) The provision specified the need of contractor to submit
the Work
Programme to the SO that shows detail activities of wk, methods of
construction proposed to adopt.
'New provision 12.2 (i), (ii) & (iii), It stipulates define periods for the submission and
approval of the programme plus consequences for the SOs default.
(to approve or reject or request further informations to clarify on the Work
Programme submit by the contractor)
'New Provision 12.3, 12.4, 12.5 requires the contractor to resubmit the Work
Programme if request for. The submission to and approval by the SO does
not relieve the contractor of any his responsibilities under the contract.
69
COC Rev. 2007
COC Rev. 1/2010
40
Clause
Differences
22.1 (a)
22.1(b)
A need of contractor to submit the related particulars ie. Dwg, specs, calculation &
other doc. Pertaining to stand alone design.
22.1(c)
Rephrase of clause 22.1 (c) & (d). The contractor shall be fully responsible and
guarantee the Govn. Of the Stand Alone Design, integration, execution of the works,
material and workmanship for the works are independent from any fault, suitable,
functional, safe & compatible with Govn's requirement.
22.2(a)
22.2(b)
'additional term 'imperfection, shrinkage' due to defects in the stand alone design.
22.2(c)
'the Govn. has the right to claim from PB the sum of equal to 5% of the value of the
said part of the works or such part thereof as maybe demanded.
22.2(d)
New clause The contractor need to extend security if the DGB were to expire.
41
Clause
Differences
40.0
40.2
40.3
New Provision related to LAD that is amount of loss which Government will
suffer because of breach of contract by the contractor.
40.4
New Provision which not relieve the contractor from his liabilities and
obligations under the contract even though deduction such LAD has been
made.
The term 'officer named in the appendix' has been replace to SO.
Clause
53.1
Differences
The new term ' unlawful & illegal activities' has been inserted.
53.1 (a) replaced to 53.1
53.1 (a) (i)& (ii) in COC 2007 has been deleted
53.2
53.2 (c)
COC Rev. 2007
COC Rev. 1/2010
55
COC Rev. 2007