Sie sind auf Seite 1von 11

[Project Name:Ring Dryer]

[Company Name: MKS Industrial Solution]


Project Lead: [Mr.S.Sharma]
Start Date: 10/2/2015
[42]

WBS

Tasks

Task
Lead
[Mr. Saurabh Sukla]

Start

End

Engineering & Design

23-Oct-15

2-Nov-15

1.1

Detail Engineering

23-Oct-15

2-Nov-15

PFD(Scope Matrix,Utility Requirement)

23-Oct-15

2-Nov-15

Site layout (Top, Front ,Side,


Elevention View)

24-Oct-15

2-Nov-15

P&ID

25-Oct-15

2-Nov-15

1.2

Fabrication Drawing for Workshop &


Site

23-Oct-15

2-Nov-15

Document sumitted releted to Procurement


Dept

27-Oct-15

28-Nov-15

Equipment Layout& BOQ for Workshop Site

23-Oct-15

Brought for Mechanical & Electrical with


Inspection

25-Oct-15

5-Dec-15

Erection & Comissioning

23-Oct-15

20-Dec-15

Erection Drawing

23-Oct-15

26-Dec-15

BOQ & Erection with Weight wise /Project

25-Oct-15

20-Dec-15

Commisioning Mannual

25-Oct-15

26-Dec-15

Hand - Over Report,Trial& Documentation

25-Oct-15

26-Dec-15

1.3

Duration (Days)
10
10
2
9
9
10
11
2
9
10
2
9
9
9

Design &
23-Oct-15
Engineering & Design
Detail Engineering
PFD(Scope Matrix,Utility Requirement)
Site layout (Top, Front ,Side, Elevention View)
P&ID
Fabrication Drawing for Workshop & Site
Document sumitted releted to Procurement Dept
Equipment Layout& BOQ for Workshop Site
Brought for Mechanical & Electrical with Inspection
Erection & Comissioning
Erection Drawing
BOQ & Erection with Weight wise /Project
Commisioning Mannual
Hand - Over Report,Trial& Documentation

25-Oct-15

27-Oct-15

15

Design & Engineering Department


27-Oct-15

29-Oct-15

31-Oct-15

2-Nov-15

4-Nov-15

4-Nov-15

6-Nov-15

8-Nov-15

[Project Name:Ring Dryer]


[Company Name: MKS Industrial Solution]
Project Lead: [Mr.S.Sharma]
Start Date: 10/27/2015

WBS
2

Tasks
Procurement

Task
Lead
Mr. Jay Om Bhardwaj

End

Duration (Days)

[42]

27-Oct-15

20-Nov-15

24

Start

Perstudy Technical
Clarification

27-Oct-15

3-Nov-15

1.1

Project Estimation List as


Material/Contaractor Part

27-Oct-15

6-Nov-15

10

1.2

Comparative Statement

1.3

Negotation

1.4

Order Releasing

1.5

Follow Up

1.6

Material Workshop to Start up


Work

6-Nov-15

12-Nov-15

Complete metal Workshop

6-Nov-15

20-Nov-15

14

27-Oct-15

16-Nov-15

20

Finance Planing/Billing
planing/Taxes Planing
Inspection & Material
Receving

27-Oct-15

Procurement
Department
6-Nov-15
11-Nov-15
16-Nov-1

1-Nov-15

End Date: 20-Nov-1

Procurement
Perstudy Technical Clarification
Project Estimation List as Material/Contaractor Part

End Date: 03-Nov-15


End Date: 06-Nov-15

Comparative Statement
Negotation
Order Releasing
Follow Up
Material Workshop to Start up Work
Complete metal Workshop
Finance Planing/Billing planing/Taxes Planing
Inspection & Material Receving

End Date: 11-Nov-15

End Date: 20
End Date: 16-Nov-15

partment
11-Nov-15
16-Nov-15

21-Nov-15

26-Nov-15

End Date: 20-Nov-15

Duration (Days)
Start

e: 11-Nov-15
End Date: 20-Nov-15
End Date: 16-Nov-15

[Project Name:Ring Dryer]


[Company Name: MKS Industrial Solution]
Project Lead: [Mr.S.Sharma]
Start Date: 10/27/2015

WBS

Tasks

Task
Lead

Start

End

Duration (Days)

[42]

Fabrication

27-Oct-15

24-Dec-15

60

Planing For Machining & Contractor Work & Site


starting & inspection

27-Oct-15

2-Nov-15

SiteMoblization & Completion of Work

2-Nov-15

24-Dec-15

51

Workshop

Machining

Contractor Finilaziation

Contractor Work Start to Complete

Inspection Plan

Dispatch Plan

Fabrication Department
27-Oct-15

6-Nov-15

16-Nov-15

26-Nov-15

End D

Fabrication

End Date: 02-Nov-15

Planing For Machining & Contractor Work & Site starting & inspection

Start Date: 02-Nov-15

SiteMoblization & Completion of Work

Workshop

Machining

Contractor Finilaziation

Contractor Work Start to Complete

Inspection Plan

Dispatch Plan

End Da

epartment

16-Nov-15

26-Nov-15

6-Dec-15

16-Dec-15 26-Dec-15

End Date: 24-Dec-15

End Date: 24-Dec-15

5-Jan-16

Das könnte Ihnen auch gefallen