Sie sind auf Seite 1von 40

ifj;kstuk vuqoh{k.

k izdks"B
nSfud izxfr izfrosnu
No. : DGM(PMC)/DPR/2016/0026

Date : 12.01.16

Index

/ HIGHLIGHT OF THE DAY

/ Project Zone

A.

/ Coke Zone

B.

/ Mills Zone

C.

/ Steel Zone

D.

.. / OP Zone

E.

.. ... / SP & OHP Zone

F.

$ & / Blast Furnace Zone

G.

/ Power Zone

H.

.. ... / IATRS Zone

I.

Installation of Universal Rail Mill (Pkg.-047)

PDB M2 at ECR-2 & PDB P1 at ECR-3 charged on 11.01.16.


Review meeting held on 11.01.16

Illumination,Earthing & lighting protection system for SMS-3 (Pkg-127)


Review meeting scheduled on 12.01.16

COB-9 Pkg.-5: Electrics & Drive Automation

Installation of Cranes for BOF & CCP (Pkg.-029A) (7Nos 300T + 80 T Cap.)

Instln. Of 10 Nos. Cranes above 100 T capacity (Pkg.-029-A-2)

*, & /Civil services, Township & Mines Zone

J.

2 / Utility Zone

K.
L.

... / SPU Zone

Stage-I approved schemes other than 7.0 MT expansion


Modernization & Expansion of BSP to 7.0 MT

M.

4-( )-...
4 4 ( )

( )

4:
4 - ( )- ;<

. -( )-...

4 -( )-

4 - 4 ( )-

4 -( )- ... & .

4 - 4 ( )-

4 -( )-...3

4 -( )-2

4-( ) BD

4 -( )->?-..&...3

* F .

All project reports available at Project Deptts website: Intranet

Depts Websites

Projects (http://cmmsftp.sail-bhilaisteel.com/projects/index.htm)

ifj;kstuk vuqoh{k.k izdks"B


nSfud izxfr izfrosnu
SN
SCHEME / PACKAGE
A. COKE ZONE
A 1 Coke Oven Battery 11 Proper
(Pkg.-001-SE-01)
A2

Oven Machines & land based


Pushing Emission Control for Battery11 (Pkg. -001-SE-02)
Contract No. TK 2008/279
Consultant MECON

Important activities completed / Highlights

Total

Review meeting scheduled on 13.01.16.


Oven machines put into operation.
PEC system: Eqpt. Erection in progress.

BE (A)
BE ( I )
DE (A)
DE ( I )
TOTAL

124
14
125
244
507
Activity

Submtd.

121
26
97
242
486
Unit

Appd/KFR

90
24
87
230
431
Total vol.

AAN

Comntd

U/S

13
0
0
0
13

18
2
8
8
36

0
0
2
4
6
Cum. Prog.

Jan16

Plan

Review meeting scheduled on 15.01.16.

Processing of Gas from COB#11 in ByProduct Plants - 3 started on 29.09.14.


(Exhauster, ETP, PGC & Decanter running
successfully).
Phase - II
Civil & Structural work in progress.
(Unit 800, 900, DM Plant, Maintenance
bldg.).

Drawings

Total

BE (A)
106
BE I
76
DE (A)
624
DE I
1067
1873
TOTAL
Activity

Submtd.
112
73
681
1224
2090*
Unit

Appd
110
72
667
1214
2063
Total vol.

AAN
2
0
3
0
5

Comntd
0
1
9
9
19
Jan16

Plan

Review meeting held on 17.12.15.

Prog.

Mech. Eqpt. Ordering


T
1776
0
0
1776
Elect. Eqpt. Ordering
T
232
0
0
232
Mech. Eqpt. supply
T
1776
30
0
1746
Elect. Eqpt. supply
T
232
15
0
217
Mech. Eqpt. erection
T
1776
34
0
1683
Elect. Eqpt. Erection
T
232
0
0
139
Part PAC (for all oven machines) issued on 05.12.14 w.e.f 29.09.14.
PAC issued on 26.03.15 w.e.f 23.02.15.
Commissioning Certificate issued on 09.10.15 w.e.f. 17.07.15.

Important activities completed / Highlights

A4

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


PAC issued on 05.12.14 w.e.f 30.09.14.
Commissioning certificate issued on 23.07.15 w.e.f 03.10.14.
Coal charging in Oven started on 29.09.14 & Pushing started on 30.09.14.

Likely completion : Jan16


(Proj. Mgr. Shri U, Bhardwaj, DGM
20184)

Coke Dry Cooling Plant COB-11


(Pkg.-002)
Instln. of By-Product Plant Complex &
its integration with existing facilities
for COB#11 (Pkg. - 003A)
Contract No. TK 2011/344
Consultant MECON
Agency M/s MBE
Contract price - Rs. 353.52 Crs.
Contract signed on: 20.04.11,
Contr. Completion: 19.04.13
Likely completion : Mar16
(Proj. Mgr.- Puneet Sharma, DGM 21776)

Date : 11.01.16

DAILY PROGRESS REPORT

PROGRESS ON DATE

Agency M/s BEC- KBK


Contract price: Rs. 105.61 Crs.
Contract date : 19.09.08,
Contr. Completion : 18.09.10

A3

PROJECT MONITORING CELL

U/S

Review meeting held on 09.11.15.


Review meeting held on 15.12.15.

0
0
2
1
3
Cum. Prog.

Prog.

Earthwork
M3
84000
150
0
82100
Concreting
M3
30200
190
0
29463
Structure supply
T
2250
0
0
2240
Structure erection
T
2250
15
0
2138
Mech. Eqpt. supply
T
8200
0
0
8126
Elect. Eqpt. supply
T
1500
0
0
1480
*- Includes additional drgs. as per
Mech. Eqpt. erection
T
8200
133
32
7595
MECON.
Elect. Eqpt. erection
T
1500
17
8
1451
Part PAC issued on 14.04.15 w.e.f 12.01.15.
Part Commissioning certificate issued on 27.08.15 w.e.f. 20.07.15.
Processing of Gas from COB#11 in By-Product Plant - 3 started on
29.09.14. (Exhauster, ETP, PGC & Decanter running successfully). Ordering
(Mech.-8200 T & Elect.-1500 T) completed.

1/12/2016

Page : 2

SN

SCHEME / PACKAGE

PROGRESS ON DATE

COMMITMENT AS PER LATEST


MOM

OVERALL STATUS AS ON DATE

A 5 Instn. of Phenolic Effluent Treatment


Plant for COB-11 (Pkg. 003C)
Contract No. TK 2010/314
Consultant MECON
Agency UEM
Contract price - Rs. 21.19 Crs.
Contract signed on : 25.06.10,
Contr. Completion: 24.06.11,
Likely completion: Jan16
(Proj. Mgr. - Puneet Sharma, DGM 21776)

Review meeting scheduled on 22.01.16.

Drawings

Total

Submtd.

Appd/KFR

AAN

Comntd

U/S

Road & Drain work in progress.

BE (A)
BE ( I )
DE (A)
DE ( I )
TOTAL
Activity

19
8
120
82
229

19
10
168
75
272*

16
7
144
60
227

0
1
11
10
22

2
2
6
1
11

1
0
7
4
12

A 6 Installation of New Coal Handling


Plant (Pkg. 062)
Contract No. TK 2008/280
Consultant MECON
Agency HEC
Contract price: Rs. 463.8 Crs.
Contract signed on 20.09.08,
Contr. Completion : 19.03.11
Likely completion: Mar16
(Proj. Mgr. K Dikshitulu, DGM, 20403)

15 M3 Concreting completed.
5 T Str. erected.

Unit

Total vol.
Plan

New Silos (CDI - 2 nos. & Boiler - 2 nos.):


Eqpt. erection in progress.
Stacker cum reclaimer 5,6,7:
Eqpt. erection in progress.
Wagon Tippler:
Elect. Eqpt. erection in progress.

Jan16
Prog.

Review meeting held on


24.12.15.

Cum. Prog.

Earthwork
M3
30000
1000
0
22800
Concreting
M3
10050
250
0
9800
*-Includes addition drgs.
Strl. supply
T
190
0
0
190
Strl. Erection
T
190
0
0
190
Mech. Eqpt. Ordering
T
509
50
0
459
Elect. Eqpt. Ordering
T
173
0
0
173
Mech. Eqpt. supply
T
509
50
0
459
Elect. Eqpt. supply
T
173
3
0
170
Mech. Eqpt. erection
T
509
0
0
459
Elect. Eqpt. erection
T
173
10
0
163
Nitrification tank I: Part commissioning activity completed on
29.11.14.Nitrification tank II: Major civil work completed.
Drawings
Total
Submtd
Appd/KFR
AAN
Comntd
U/S
Review meeting held on
145
142
0
2
1
BE (A)
145
07.01.16.
BE I
DE (A)
DE I
TOTAL
Activity

4
661
413
1223

4
661
413
1223

Unit

4
647
409
1202

0
0
0
0

Total vol.

0
6
4
12

Jan16
Plan

0
8
0
9

Cum. Prog.
Prog.

M3
Earthwork
250000
5000
0
242000
M3
Concreting
#52000
125
122
51307
T
Strl. supply
#8145
0
0
7764
T
#- Scope revised.
Strl. Erection
#8145
11
10
7731
T
Mech.Eqpt. ordering
7500
7
0
7493
T
Elect Eqpt. Ordering
2500
0
0
2500
T
Mech. Eqpt. Supply
7500
32
0
6593
T
Elec. Eqpt. Supply
2500
0
0
2478
T
Mech. Eqpt. Erection
7500
0
20
5932
T
Elec. Eqpt. Erection
2500
100
40
1540
Part PAC issued on 19.03.15 (for Dispatcher Building D2, 15 nos. APDs).
SCR- 5, 6, 7: Eqpt. erection in progress
New Silo (CDI - 2 nos. & Boiler - 2 nos.): Eqpt. erection in progress..Wagon
Tippler#4: Mech. Eqpt. erection completed.
SCR-3, 4: Trial run with load completed by 22.07.15.

1/12/2016

Page : 3

SN

A7

SCHEME / PACKAGE
Augmentation of Fuel & Flux Crushing &
Screening Facilities (Pkg. 064)
Contr. No. TK 2011/337
Consultant MECON
Agency M/s EPI
Contract price Rs. 272.65 Crs.
Contract signed on: 15.02.11,
Contr. Completion: 14.12.12,
Likely completion Mar16
(Proj. Mgr.- A P Barnwal, DGM, 20131)

PROGRESS ON DATE

10 M3 Concreting completed.
2 T Str. erected.
CHP Area:
Civil work for LTSS-1, Final crushing
station, Bldg. in progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

BE (A)
BE ( I )
DE (A)
DE ( I )
TOTAL

287
17
375
547
1226*
Activity

Submtd.

256
7
345
468
1076
Unit

Appd/KFR

207
5
278
412
902

AAN

Comntd

31
0
42
1
74

10
2
6
25
43

Plan

Jan16
Prog.

Total vol.

CSP Area :
Emergency coke yard: Eqpt. Erection in
progress.
Civil work for LTSS #2, 3 in progress.

U/S

8
0
19
30
57

Review meeting held on 08.01.16.

Cum. Prog.

M3
Earthwork
95000
3000
1600
87300
M3
Concreting
#18000
500
235
15051
Structure supply
T
7250
250
45
4977
Structure Erection
T
7250
60
18
3570
Mech. Eqpt. ordering
T
2522
186
0
2336
Fuel & Flux area: Civil work for LTSS #4, 5 in Elect Eqpt. Ordering
T
526
0
0
300
progress.
Mech. Eqpt. supply
T
2522
100
0
1693
Elect Eqpt. supply
T
526
30
0
280
Mech. Eqpt. erection
T
2522
30
17
490
Elect Eqpt. erection
T
526
30
0
91
Important activities completed / Highlights
C-line conveyor: Integrated load trial run of new C-line conveyor taken on
07.11.13. CHP area: Civil work for Final crushing station ,LTSS-1 Bldg. in
progress. Coal feeding in Coal Tower started on 27.09.14. 1st Floor Slab of
LTSS#1 cast on 09.10.15.
CSP area: Trial run of Conveyor K11-9B & K11-10B completed.
Emergency coke yard: Eqpt. Erection in progress.
Civil work for LTSS #2, 3 in progress. 1st Floor Slab of LTSS#3 cast on
09.01.16.Fuel & Flux area: Civil work for LTSS #4, 5 in progress.
A 8 Cold repair of Coke Oven Battery no. -9 of CO & CCD (Stage-II approved on 04.08.12) completion: 25 months, Approved cost: Rs. 332.65 Crs. (Consultant CET)
Pkg.-1: Battery Proper
Review meeting scheduled on 19.01.16. Erection of Door frame completed on 02.07.15.
Contract No. TK 2012/ 365 Agency MECON
Temporary Heating in progress.
All 136 nos. WHB assembly erected by 21.07.15..
Contract price - Rs. 150.09 Crs.
TOPR dismantling in progress.
All 136 nos. Buckstay erected by 02.04.15.
Contract signed on : 29.08.12,
Quenching Tower: Civil & Structural work in Erection of temporary tie rods & charging hole completed.
Contr. Completion: 28.08.14,
progress.
Major Refractory erection for Battery proper completed on 13.03.15.
Likely completion Jan16
Cellar:
Eqpt.
Erection
in
progress.
Chimney Heating started on 22.06.15.
(Proj. Mgr. D K Dewangan, DGM,20134)
Wharf: Civil work in progress.
Temporary Heating started on 28.08.15.
TOPR dismantling started on 16.11.15.
Pkg.-4: Instrumentation & Automation
Equipment erection in progress.
All 13 nos. BE drgs. & all 50 nos. DE drgs. Submitted.
Contract No. TK 2012/ 374
Equipment erection in progress.

* - Drg. status reconciled in


Oct.15.
#- Scope revised in Nov15.

Review meeting held on 21.12.15.

Review meeting held on 16.11.15.

Agency M/s Instrumentation Ltd.


Contract price - Rs. 4.43 Crs.
Contract signed : 18.10.12, Contr. Completion:
17.06.14, Likely completion Jan16
(Proj. Mgr. D K Dewangan, DGM,20134)

Pkg.-5: Electrics & Drive Automation


Contract No. TK 2013/376 Agency M/s
Sterling & Wilson Contract price - Rs. 6.93 Crs.
Contract signed : 12.02.13, Contr. Completion:
11.08.14, Likely completion Jan16
(Proj. Mgr. D K Dewangan, DGM,20134)

Review meeting scheduled on 12.01.16.


Equipment erection in progress.

All 21 nos. BE drgs. & 88 out of 89 nos. DE drgs. submitted.


Equipment erection in progress.

1/12/2016

Page : 4

Review meeting held on 11.12.15.

SN

A8

COMMITMENT AS PER LATEST MOM


PROGRESS ON DATE
OVERALL STATUS AS ON DATE
SCHEME / PACKAGE
Cold repair of Coke Oven Battery no. -9 of CO & CCD (Stage-II approved on 04.08.12) Completion: 25 months, Approved cost: Rs. 332.65 Crs. (Consultant CET)
Pkg.-6: Oven Machines
Review meeting scheduled on 18.01.16. All 44 nos. BE drgs. & All 256 nos. DE drgs. Submitted.
Review meeting held on 17.12.15.
Contract No. TK 2012/ 367Agency M/s BEC- CUI Erection of 2nd Guide car in progress.
Erection of Both Charging car ,locos, Pusher car,1st Guide car
Contract price - Rs. 64.08 Crs. & Euro 5000
completed.
Contract signed on : 03.09.12,
Testing of Charging cars, Electric Locos & Erection of 2nd Guide car started on 19.10.15.
Contr. Completion: 02.05.14,
Pusher car in progress.
Likely completion Jan16
(Proj. Mgr. D K Dewangan, DGM,20134)

Pkg.-7: Expert Supervision during erection &


commissioning of 7 MT tall battery

Refractory Expert deputed by M/s CUI at site from 29.07.13.

Contract No. TK 2012/375


Agency M/s CUI Contract
price USD 766800, Contract signed : 07.11.12, Contr.
Completion: 06.02.15, Likely completion Jan16
(Proj. Mgr. D K Dewangan, DGM,20134)

Pkg.-8A:
Replacement
of
Ammonia Review meeting scheduled on 21.01.16.
Saturators # 5 & 6 in ASP #2 of CO&CCD
Erection of 1st saturator is in progress.
Contract No. TK 2012/364 Agency Beekay
Contract price - Rs. 5.40 Crs.
Contract signed on : 22.08.12 Cont Completion: 21.08.14,
Likely completion Jan16
(Proj. Mgr. D K Dewangan, DGM,20134)

Pkg.-8B: Re-tubing of PGC#1-4, Replacement


of ETP#8 in Gas Cleaning Plant #2

Review meeting scheduled on 25.01.16.

Contract No. TK 2012/ 372


Agency Bhilai Techneeds& Technovation
Contract price - Rs. 15.53 Crs.
Contract signed on : 26.09.12,
Contr. Completion: 25.06.14, Likely completion Jan16
(Proj. Mgr. D K Dewangan, DGM,20134)

PGC#1-4:
Illumination work in progress .

Pkg.-8C: Replacement of Circular Tar


Decanter #9 in CCD#2 Contract price - Rs. 2.08 Crs.

All 45 nos. DE drgs. submitted.


Erection of 1st saturator started on 24.02.15.
Major supply of Both Saturators completed.

Review meeting held on 22.12.15.

All 31 nos. BE drgs. and all 78 nos. DE drgs. submitted.


ETP#8: All work completed.
PGC#1-4: Testing completed.

Review meeting held on 18.12.15.

PAC issued on 05.10.15 w.e.f. 06.08.15.

Contract No. TK 2012/ 368 Agency Bengal Tools.


Contract signed on : 05.09.12,
Contr. Completion: 04.12.13,
(Proj. Mgr. D K Dewangan, DGM,20134)

Pkg.-8D: Repl. of Contaminated Water Cooling


Tower of Final Gas Coolers of BRP #2

A9

Contract price - Rs. 1.26 Crs.


Contract signed on : 11.09.12, Agency Koolaqua
Contract No. TK 2012/ 370, Contr. Completion:
10.12.13, (Proj. Mgr. D K Dewangan, DGM,20134)
Replacement of Benzol and Separating Columns
of Old Stream in Benzol Distillation Plant of CCD # 1
Contract no . TK- 2012/369
Consultant CET Agency : M/s Nuberg
Cost : Rs. 3.44 Crs. Contract Signed : 07.09.12
Cont. Completion : 06.09.13
(Proj. Mgr.- P Sharma, DGM -21776)

PAC issued on 24.03.15 w.e.f 18.03.15.


Commissioning certificate issued on 14.08.15 w.e.f. 30.06.15.

Major work completed & put into operation on 24.04.15.


PAC issued on 18.09.15 w.e.f. 24.07.15.

1/12/2016

Page : 5

SN
SCHEME / PACKAGE
B. MILLS ZONE
B 1 Civil works for Bar & Rod Mill
(Pkg-051A-01) (Works Pkg.)

Consultant-MECON
Agency: M/s HSCL
Contract Price: Rs 123.93 Crs.
Contract signed on : 30.12.10
Completion period : 29.08.12
Likely Completion: Jan.16
(Proj. Mgr. A K Singh, AGM) 21014

B2

Structural works for Bar & Rod Mill


(Pkg-051B-01)
Consultant-MECON
Agency: M/s HSCL
Contract price: Rs. 54.26 Crs.
Eff. dt. of Cont. : 07.09.10,
Cont. signed on : 16.09.10
Cont. Completion: 06.05.12
Likely compln: Jan.16
(Proj. Mgr. Ajay Kumar, DGM) 21772

B3

Additional Structural Works of BRM


(Pkg No. 051-B-1A) Consultant MECON

Agency: M/s HSCL

PROGRESS ON DATE

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE

Earthwork for flooring & drain in progress. Concreting for Main Bldg. Column fd/ns (190 nos.) completed on 25.07.14.
Civil work for Chiller Bldg. (Top portion) in Welfare Bldg. RCC work completed on 28.12.13.

26th Review Meeting held


on 14.02.13.

Activity
Unit
Total Scope
Jan.16
Cum. Prog.
progress.
(*- Revised)
Plan
Prog.
Earthwork and Concreting for pump Earthwork
M3
325000 *
30
0
324970
foundation at 0-0 m level in Pump area of Concreting
M3
88125 $
1679
54
86500 #
Pumphouse in progress.
$ - Revised Scope as informed by Zone
Pressure grouting and cleaning of ECR-3 # - RCC Figures reported by Zone after reconciliation
basemen, Brickwork & plaster for Welfare Casting for Chimney, Flue duct & Furnace proper completed.
bldg. & final roof lift for O/h tank above ECRs-1, 2,3 & Furnace ECR RCC work completed.
Work Roll shop RCC work completed on 10.06.14.
23 m up to 25 m in progress.
Finishing & Flooring work in Mill area (AB, Slab at 5.0 m of BC Bay b/w Columns 3 to 23 (Furnace Exit area, Roughing,
BC and CD bay of all Blocks) in progress. Intermediate, Finishing mill & Finishing Block exit area) cast.
Cooling Bed and Bar lineRCC work completed.
3 M3 Concreting completed.

Civil work for all Transformers foundations in all ECRs completed.


RCC work for Product Forming area, Coil Storage area and Cut length
area completed. RCC work for MCC room (Block-1) completed.
RCC for coil evacuation area 98 % comp., balance is cable trench.
RCC work for Rail track parallel to A row of Blocks-3 & 4 completed and for
Drgs. issued:
rail track parallel to D row 99 % completed.
Concreting 88123 M3
Earthwork for Scale pit started on 03.03.15 & completed on 28.05.15.
Slab at 4.3 m in Water Sump area of Pumphouse completed on 11.12.15.
Raft casting for Chiller Bldg comp. on 19.06.15. Slab at 5 M cast on 07.10.15.
Fabrication & erection of strs. incl. Cum. 18425 T steel collected by M/s HSCL for both the pkgs (incl. 967 T for 27th Review Meeting held
sheeting in Axis-X, Y & Z, Blocks-1 to 4 in sheets). Assembly of all 190 columns & 242 Crane Girders (related to Axis X, on 14.02.13.
Y & Z and Blocks-1 to 4) completed. Cum. 186 out of 190 Columns & 237
progress.
out of 242 Crane girders (related to Axis X, Y & Z and Blocks-1 to 4) erected.
2 T Srs. erected.
Erection of roof truss completed except for 4 columns in X, Y & Z axis.
Activity

Unit

(*- Revised)

Strl. Fabrication
Strl. Erection

T
T

Jan.16

Total Scope

8500 *
8500 *

Plan

Cum. Prog.
Prog.

8500
8253

# - Structure erection data


reconciled by Zone on
Scope increased to 13500 T by MECON, awarded in Separate pkg. no. (051-B- 30.11.14.

Status of Drgs.:
DE drgs Approved by MECON 15174 T 1A), further scope increased to 14200 T and further increased to 15500 T.
(combined for both the pkgs.)
Pkg. covers fabrication & erection of structures for Block-3 (partly) and
Block-4 (complete). ie. from Axis- 29 to 47.
Activity

Unit

Total Scope

Jan.16
Plan
Prog.

Cum.
Prog.

Awarded on : 24.11.12,
Contract signed on 15.02.13
Award value: Rs. 47.11 Crs.
Contr. Completion: 23.05.13

Strl. Fabrication

7000 *

200

6393

Likely compln: Jan.16

Strl. Erection

7000 *

500

23

5771.5

(*- Revised)

(Proj. Mgr. Ajay Kumar, DGM) 21772

1/12/2016

Page : 6

SN

B4

PROGRESS ON DATE
SCHEME / PACKAGE
Reheating Furnaces for Bar & Rod Mill Design Engg., ordering, supply &
(Pkg.-049-1)
erection of eqpts. in progress.
Contract No.- TK/2011/335
Rod bending and shuttering for
Consultant - MECON
Concreting of basin of Cooling tower
Agency: M/s Fives Stein, Spain
at 7.4 M level in progress.
Fives Stein, India Beekay
Refractory erection of Furnace Proper
Contract price: Rs. 54.23 Crs.
started on 03.10.15 and erection of
Cont. signed on : 09.02.11
light alumina /alumina bricks in
Cont. Completion: 08.11.12
progress.
Likely compln: Mar.16
1 T Refractory erected.
(Proj. Mgr. J Gopi Krishnan, DGM)
21151

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

Submtd

Appd/KFR

AAN

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

74
211
241
287
813

71
210
227
282
790

67
204
217
272
760

0
0
4
1
5

Unit

Total Scope
(*- Revised)

Plan

Prog.

Cum.
Prog.

324
62*
7*
1048*
195*
190*
1090*
1110*
202*
1280*

30
0.5
8
28
0
0
70
50
300

0
0
0
0
0
0
0
0
13

185
Comp.
6.5
1040
167
Comp.
585
858
82.5
167

Activity

Concreting
Mech. Eqpt. (Imp.)Supply
Elect. Eqpt. (Imp.) Supply
Mech. Eqpt. (Ind.) Supply
Elect. Eqpt. (Ind.) Supply
Refractory (Imp.) Supply
Refractory (Ind.) Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection
Refractory Erection

M3
T
T
T
T
T
T
T
T

Comtd.

4
6
6
9
25
Jan.16

U/S

0
0
0
0
0

18th Review meeting held


on 06.01.16.

# Ordering of all 62 T Mech.


Eqpt. (Imp.) , all 1048 T
Mech. Eqpt. (Indig.), all 195
T Elect. Eqpt. (Indig.) & all 7
T
Elect.
Eqpt.
(Imp.)
completed.
Ordering

of

all

190

Erection of lifting frame assly., Chimney & lateral wall of Furnace completed & of Flue Refactory (Imp.) & all 1090 T
duct 96 % completed Erection of all burners & roof beam of Furnace Proper Refractory
(Indig.)
completed. Alignment of Skid & posts, Charge wall & DA fan completed. Alignment of completed.
all Roller tables & of Furnace actuator without damper completed. All Imported
Refractory received at site on 07.09.15. Pressure testing of indirect cooling water piping
for Furnace comp. on 14.09.15. Erection of Elect.eqpts. restarted on 21.04.15.

B5

Installation of Bar & Rod Mill (Pkg.- Erection and alignment of equipments in
Rolling Mill area, Rolling Mill exit area,
046)
Cooling bed area, Cutting to length
Contract No.- TK/2010/323
area, Product Forming area, Product
Consultant - MECON
Collecting area, Hyd. Cellars, Oil Cellars,
Agency: M/s Danieli & C SpA, Italyetc in progress.
Danieli India, Kolkata - Beekay
Elect. Erection work (on-field cable tray
Contract price: Rs. 406.09 Crs.
work in BC bay, cable laying from
Cont. Signed on : 25.08.10
Switchgear to ECR-1, control cable laying
Cont. Completion : 24.08.12
in Charging area and Mill area, erection
Likely Completion : Mar.16
of MPV panels,etc) in progress.
(Proj. Mgr. - K D Prasad, DGM) 22183
3 nos. Oil filled Transformers of ECR-1

Drawings

Total

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

Submtd

36
231
268
1280
1815

Appd/KFR

36
231
268
1280
1815

Activity

AAN

35
231
268
1279
1813

Unit

0
0
0
0
0

Comntd

1
0
0
1
2

Jan.16
Plan
Prog.

Total
Scope

U/S

0
0
0
0
0
Cum.
Prog.

Mech. Eqpt(Ind.) SupplyM/s Beekay


T
2300*
10
0
2290
Mech. Eqpt. (Ind.) Supply M/S DIL
T
1857
0
0
1069 #
Elect. Eqpt. (Ind.) Supply
T
1650
2
0
1648
Mech. Eqpt. Erection
T
5500*
490
48
3079
charged on 03.12.15, as such cum. 12 out Elect. Eqpt. Erection
T
1824
70
17
1477
of 18 transformers charged.
Charging of Transformers (dry type) in ECR-1 started on 05.09.15, cum. 12 out of
Testing of balance 9 transformers of ECR-1 18 charged. PCC and MCC erection in ECRs-1 & 2 (at 5 m and 16 m) & in ECR-3 (at 0
as well as oil filtration completed.
m) completed. HT cable laying from Switchgear to Primary side of transformers in ECR Charging preparation of balance 6 1 completed. All 18 Transformers of ECR-1, 12 transformers of ECR-2 & 6 Transformers of
transfromers in progress.
ECR-3 erected. Cable tray work in ECRs-1 & 2 and connecting tunnel completed. Bus

2 T Elect. eqpt. erected.

B6

duct erection in all 3 ECRs completed.


Erection of eqpts. of Charging area, Furnace entry & exit area completed.

Diversion of Nallah passing through De-tilting of Nallah bed b/w Manhole 3 Laying/jointing of pipes for manholes nos. 6 to 9 & 12 to 24 completed.
Activity
Unit
Total
Jan.16
& 4 and preparation for PCC in progress.
Universal Rail Mill layout (Pkg-118 S)
Scope
Plan
Prog.
Agency-M/s Kulkarni & Sahu Buildcon
Laying of pipe between manhole-3 & 4 in
Contract price: Rs 9.68 Crs.
Cont. Signed on: 09.02.12
Completion period : 02.06.12
(Proj. Mgr. - A S P Sarma, DGM) 22187

progress, 6 pipes laying done.

Final lift wall casting of Manhole-6 & 7


and slab casting of these manholes in
progress.

M3

Cum.
Prog.

Earthwork
Concreting
Supply of RCC Pipes

M3
RM

42000
9500
2450

0
0
0

0
0
0

39200
5360
1900

Laying/jointing of Pipes

RM

2450

1900

1/12/2016

Page : 7

10th Review meeting held


on 15.12.15.

# - 788 T 1st Fill Oil


Ordering & supply of All
Imported Eqpts.(Mech. 1343 T & Elect. -174 T)
completed.Ordering of All
4157 T Mech Eqpt.(Indig.) &
All 1650 T Elect. Eqpt.(Indig.)
completed.

SN

B7

SCHEME / PACKAGE
Civil works for Universal Rail Mill
(Pkg-052A) (Works Pkg.)
Consultant-MECON
Agency: M/s HSCL
Contract price: Rs. 289.51 Crs.
Eff. dt. of Cont. : 07.09.10,
Cont. signed on : 15.09.10
Cont. Completion: 06.03.12
Likely compln: Jan.16
(Proj. Mgr. A S P Sarma, DGM)
22187

B8

Strl. Works for Universal Rail Mill


(Pkg-052B) (Works Pkg.)
Consultant-MECON
Agency: M/s HSCL
Contract price: Rs 200.02 Crs.
Cont. signed on : 10.12.10
Completion period : 09.08.12
Likely compln: Jan.16
(Proj. Mgr. J P Pandey, DGM)
22171

B9

PROGRESS ON DATE

Concreting for Column fdns. in URM {Areas37, 38, 39, 41, 43}, Drain work parallel to E
row, in progress.
Apron work in Brushing Bldg. & S/s Bldg. of
RWL area in progress.
RCC work for Sceptic tank of Welding & S/s
Bldgs., work for Pre-cast slab for Sceptic tank
Finishing Bldg. & Brushing Bldg. i/p.
Garland Drain in S/s bldg. 90 % completed.
Concreting for railway track for Axis-1 to 20
comp. and in progress for Axis54 to 82.
Civil work for Chiller Bldg. 90 % completed.
Flooring work in various Areas in progress.
200 M3 Concreting completed.
Earthwork
M3
500000*
500000
Drgs. issued:Concreting (#)
M3
230000 $
6000
737
212638 #
Concreting 2,30,000 M3
$ - Revised Scope as informed by Zone # - RCC Figures reported by Zone after reconciliation
Strl. Fabrication for roof truss, supports & lighting Cum. 32270 T steel collected by M/s HSCL. Strl. fabrication for Cols. & CGs for Blks-1 to 7
walkway & erection for Blocks-1 to 7 (roof truss, completed. Assembly of all 342 columns & all 466 Crane Girders completed.
Cum. all 342 columns & 466 Crane girders erected.
girders, lighting walkway, staircase, etc) i/p.
342 Cols (Blk-152 nos,Blk-242 nos, Blk-355 nos, Blk-459 nos,Blk-545 nos,Blk-644 nos,Blk-7-45 nos)
3 T Strs. erected.
Status of Drgs. :-

27th Review Meeting


held on 14.02.13.

26 th Review Meeting
held on 14.02.13.

466 CGs(Blk-1- 70 nos, Blk-2- 54 nos, Blk-3 76 nos, Blk-4- 86 nos,Blk-562 nos,Blk-660 nos &Blk-7-58 nos)

Cum. 492 out of 494 nos. Roof truss erected. 2 no. Long Crane girders at Blk-5 (A row) & 4 no. Long

BE drgs. (Scope) 30000 T (Blk-1-4497 T, Blk-2-3354 T, Blk- Crane girders Blk-7 (B, B row) of 36 m erected. Erection of 58 long trusses (45 m) completed by
3-4441 T,Blk-44415 T,Blk-54271 T, Blk-64500 T, Blk-73600 May.15. 1 no. long Roof girder at AB bay of Block-7 erected.
T, Misc922 T)
Activity
Unit
Total Scope

BE drgs Released by MECON 29898 T


DE drgs Submitted by M/s HSCL - 30336 T
DE drgs Approved by MECON 30336 T
Reheating
Furnaces
for Design Engg., supply and erection of Mech.
Universal Rail Mill (Pkg. 049-3)
and
Elect.
Eqpts.
(cable
laying
Contract no. TK/ 2011 / 346
/glanding/dressing, cable tray support work,
Consultant - MECON
instrumentation work, cable termination,
Agency M/s Gillander Arbuthnot
busduct cleaning,etc) in progress.
(MICCO), Kolkata AndritzBric
Piping work for mixed gas in progress.
MontInc, USA &BricMont, India)
Concreting for column lift at and above 12m
Contract price: Rs. 75.81 Crs.
in Cooling tower area in progress.
Contract Signed on: 13.07.11
Erection of Indigenous refractory in progress.
Cont. Completion: 12.04.13
Erection of eqpts. in Pumphouse started on
Likely Completion : Jan.16
02.02.15 and in progress.
(Proj. Mgr.-T B Kulkarni, AGM)
3 T Mech. eqpt. erected.
21013

Imp. activities completed/ Highlights

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Cum. 321 nos. Main Shop Bldg. fdns of Blocks-1 to 7 cast up to bolt lift (at -1 M level). Civil work for
ECR-1 to 4, 6 including Furnace ECR completed RCC work of ECR-5 comp. on 14.12.15. Brick work &
plaster for ECR- 7 & 8 comp. Eqpt. fdn. of Areas-1 to 19, 24 to 36, 42, 44 to 47 comp & in progress for
Areas-37 to 39,41 & 43. RCC work for MVSWG room and Eqpt fd/n for all 4 CNC Lathe M/cs
completed. Piling work for Drop test area completed. Drain work parallel to D & E row in
progress.Welfare Bldg. Wing -1, 2 & 3 RCC work completed, Finishing work i/p.RCC work of
Cooling Bed-1 (14 to 19) completed on 11.07.14. Raft & wall casting in CB-2 completed Overhead
water tank RCC work completed Furnace Conc. for Furnace proper & Chimney completed Slab
for flue tunnel roof cover cast on 03.03.14.
RWL-: RCC, flooring & rail fixing work for DT, FT &TT completed RCC, finishing & flooring work for all
bldgs.{Brushing Bldg, Grinding & Drilling Bldgs.-7,8,9, Grinding Bldg. 10 Feeding Control Bldg. 6,
Welding Bldg, Finishing, Transfer & S/s Bldgs.} completed. Garland drain & Apron of different bldgs.
of RWL completed and in progress for balance bldg.. (S/s Bldg.).
Jan.16
Activity
Unit
Total Scope
Cum. Prog
Plan
Prog.
(*- Revised)

Structural fabrication
Structural erection
Drawings

Total

50
40
240
954
1284

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

Activity
Concreting (incl. precast slabs)
Elect. Eqpt. (Ind.) Ordering
Mech. Eqpt. (Imp.) Supply
Mech. Eqpt. (Ind.) Supply
Elect. Eqpt. (Imp.) Supply
Elect. Eqpt. (Ind.) Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection
Refractories Erection

Jan.16

Cum.
Prog.

(*- Revised)

Plan

Prog.

T
T

30513 $
30513 $

228
1500

1
67

30286
28607

Submtd.

Appd/KFR

AAN

Comtd.

U/S

50
40
240
934
1264

50
39
233
926
1248

0
1
3
1
5

0
0
3
6
9

0
0
1
1
2

Total Scope
(*-Revised)
475*
170*
171*
1800*
5
170*
1971*
175
1845

Plan
32
2
7
20
0.5
5
236
23
143

Unit
M3
T
T
T
T
T
T
T
T

Jan.16

Prog.
0
0
0
0
0
0
3
1
0

Cum.
Prog.
443
168
164
1780
4.5
165
1738
153
1702

ction of moving ducts, Flue tunnel & Chimney comp. Erection of refractory in Combustion air pipe
started on 19.11.14 & in Furnace Proper started on 19.03.15.Erection of Indigenous refractory in
Chimney area comp. & for flue tunnel 98% completed. Erection of Imported refractory completed
on 17.12.15. LCSS-1 & 3 of ECR along with 2 transformers charged by 18.12.15. No-load trial of
Emergency Pump at Pumphouse taken on 21.12.15. Pumphouse MCC of ECR charged on 19.12.15.
Convertor Transformer at ECR charged on 24.12.15. Mixed gas pipeline from TOP to main header
has been internally tested on 26.12.15. 690 V LT Switchboard at ECR charged on 31.12.15. 2 nos.
VFD panels for CA fan charged on 02.01.16.Cold trial of 2 nos. CA fan taken by 08.01.16. Furnace
MCC at ECR charged on 04.01.16. Cold trial of cum. 7 out of 19 pumps taken by 07.01.16.

1/12/2016

Page : 8

$ - Revised Scope
informed by Zone

as

12th Review meeting held


during 02.04-03.04.15.

Ordering of all 190 T Mech


Eqpt.(Imp.). all 1800 T
Mech Eqpt.(Indig.), all 5 T
Elect.
Eqpt.(Imp.),
completed.
Ordering & supply of all
325 T Imp. Refractory
(Excluding spares) and
1520 T Indig. Refractory
(Excluding
spares)
completed.

SN
SCHEME / PACKAGE
B 10 Installation of Universal Rail Mill
(Pkg.-047)
Contract No. - TK/2010/322
Consultant - MECON
Agency - M/s SMS Meer GmbH,
Germany - SMS Meer India,
Kolkata -ABB, Bangalore
Contract price: Rs. 1177.40 Crs.
Contract Signed on: 23.08.10
Cont. Completion: 22.06.13
Likely Completion : Jan.16
(Proj. Mgr. -B K Dey, DGM) 20008

PROGRESS ON DATE

Erection of Mech. eqpts. in various


areas (Areas- 1 to 12, 14 to 19, 24 to
34) in progress.
Grouting of major eqpts. of Areas -1
to 9 & Area-24 comp. and for Areas
14 to 19 & 20 to 27 in progress.
Erection of Elect. eqpts. (Busduct,
Cable
laying,
cable/panel
termination, cable tray work in
various areas) in progress.
Testing of roller table motors of
Areas-1 to 13 completed.
5 T Mech. eqpt. & 2 T Elect. Eqpt.
erected.
PDB M2 at ECR-2 & PDB P1 at ECR-3
charged on 11.01.16.
Converter transformer (CTR-4) of
ECR-3 charged on 09.01.16.

B 11 Installation of Rail Welding Line for Activities regarding approval of


Long Rails (Pkg.-121)
RDSO in progress.
Contract no. TK/ 2011 / 338
Synchronized trials of Telphers and
Consultant - MECON
trolleys in Delivery Telpher area in
Agency M/s Railtech - Maco Corp
progress.
Contract price: Rs. 263.16 Crs.
Contract Signed on: 18.02.11
Cont. Completion: 17.10.12
Likely Completion : Jan.16
(Proj. Mgr.- M M Gadre, DGM) 21146

Contract price: Rs. 150.42 Crs.


Contract Signed on: 21.01.12
Cont. Completion: 20.07.13
Likely Completion : Mar.16
(Proj. Mgr.- S K Jain, DGM) 21058

Imp. activities completed/ Highlights

B 13 Drop Test Facility for URM

(Pkg.047-01)
Consultant-MECON Price: Rs 97.79 Lakhs
Agency M/s Pragya Eqpts.Pvt. Ltd., Indore
Contract Signed on: 13.09.13 Compln:
12.06.14
Contract no. TK/2013/389

Likely Compln Jan.16


(Proj. Mgr.- B K Dey, DGM) 20008

Total

Submtd.

Appd/KFR

AAN

Comtd.

U/S

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

285
321
685
169

285
320
680
158

264
317
629
151

15
3
32
1

6
0
19
3

0
0
0
3

1460

1443
Unit

1361
Total
Scope
6750*
5800
1808
12550
1971

51

Activity
Mech. Eqpt. (Imp.) Supply
Mech. Eqpt. (Ind.) Supply
Elect. Eqpt. (Ind.) Supply
Mech. Eqpt. erection
Elect. Eqpt. erection

T
T
T
T
T

28
Jan.16

Plan
0
350
23
791
50

Prog.
0
0
0
111
20

Drawings
Basic Engg. (A)
Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

Total

Submtd.

Appd/KFR

AAN

37
12
88
253
390

37
12
88
253
390

34
12
86
251
383

1
0
2
0
3

Unit

Total Scope
*- Revised

Comtd

2
0
0
2
4

Jan.16
Plan
Prog.

6750
5450
1785
7471
1422

U/S

0
0
0
0
0
Cum. Prog.

Mech. Eqpt. Erection


T
3463
20
0
Elect. Eqpt. Erection
T
703*
3
0
Hot trials of Welding M/c no.-1 taken and 1st weld joint of 60 Kg rails (7.5 M) was done on 14.11.14.

3443
700

Drawings

Total

Submtd.

Appd/KFR

AAN

Comtd

U/S

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)

203
48
270
761
1282

203
48
262
756
1269

203
48
262
752
1265

0
0
0
0
0

0
0
0
0
0

0
0
0
4
4

Unit

Total Scope
(*-Revised)

TOTAL
Activity

Mech. (Manufacturing)
Mech. (B/o items) Ordering
Elect. (B/o items) Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection (incl DSL)

T
T
T
T
T
T
T

2636*
464*
1300*
3100*
1300*
3100*
1300*

Jan.16
Plan
Prog.

400
189
100
50
100
50

0
0
0
0
0
0

Table, Rail Transfer Mechanism, Ram & Detail Engg. (A)


Grip Mechanism & of Anvil Block Detail Engg. (I)
approved.
TOTAL

1/12/2016

Page : 9

Ordering of All 6750 T


Mech Eqpt.(Imp.), all
5800
T
Mech
Eqpt.(Indig.) & all 1808 T
Elect. eqpt. (Indig.)& all
163 T Elect. Eqpt.(Imp.)
completed.
Supply of all 163 T Elect.
Eqpt.(Imp.) completed.

8th Review meeting


held on 29.10.13.

Ordering & Supply of All


Eqpt. completed.(Mech.
Imp-438 T, Mech. Indig.3025 T, Elect. Imp-100 T,
Elect. Indig.-603 T )

13th Review meeting held


on 17.01.15.

to
be
commissioned for BRM
1500
17 Cranes, 3 Transfer
275
cars & 21 Electric Hoist.
Completed
Eqpt.
to
be
1652
commissioned for URM
1232.9
24 Cranes & 21 Elect.
1465.8
Hoist)
862.9
Cum. Prog.

Eqpt. erection with Crane-106 in BRM & Crane-413, 416, 418 & 421 in URM i/p. LT mechanism with trolley of Crane-101 & 116 in
BRM & Crane -406 of URM area erected. Crane-105 & 116 has been handed over for erection of eqpts. in BRM area.
Drawings
Total
Submtd.
Appd/KFR
AAN
Comtd
U/s

Drawing list KFR on 05.09.14.


Basic Engg. (A)
GA drgs for civil foundation plan KFR.
GA of Drop Test Area, Feeding Roller Basic Engg. (I)

Review meeting held


on 15.01.14.

3
Cum. Prog.

Erection of eqpts. of Areas- 1 to 12, 14 to 19, 24 to 34, Hyd. Cellars and Oil cellars i/p. Ern. of Housing in all Mill Stands
comp. ECR-1 (LTSS-1, 2, 3 & 13 along with 8 Xmers & Converter Xmer & MCCs 1 to 5, RTDB-1 to 10, LV drive line up-1)
charged except MV drive lineup-1. ECR-2 (MCC-6 to 9, LTSS-4, 5 & 14 with 6 Xmers, RTDB-11 to 17 & LV drive line up-2)
charged except PDB and MV drive lineup-2. 2 out of 5 Crane PDBs charged.MCC -12 & 13 of ECR-3 charged. LTSS-6
to 9 & 8 nos. Xmers of ECR-3 charged. Converter Xmer-3 & LV drive line up-3 of ECR-3 charged on 19.12.15. Cold trial
of Tandem Mill Entry side extension roller table motors taken on 22.12.15. PDB-M3 at ECR-3 charged on 24.12.15.
MCC-10 & 11 at ECR#3 charged by 28.12.15.Converter transformer (CTR-2) at ECR#3 charged on 26.12.15. Converter
Transformer (CTR-5) & PDB P2 at ECR#3 charged on 30.12.15. RTDB-1 to 27 charged except 22 & 23. MCC-14 &15 at
ECR-3 charged by 01.01.16. LTSS#10 & 11 (including 4 nos. Transformers) charged. MCCs-16, 17&18 of ECR-3 charged
by 07.01.16. Crane PDB - 4 & PDB-P3 at ECR-3 charged on 08.01.16.

Activity

B 12 Hoisting and Handling Facilities Equipment erection with Cranein Bar & Rod Mill and Universal 413, 416, 418 & 421 in URM & with
Crane-106 in BRM in progress.
Rail Mill (Pkg. 030)
Supply & erection of equipments
Contract no. TK/ 2012 / 356
ConsultantMECON
(101, 103, 109, 114, 405, 406, etc) in
Agency-M/s HEC Ltd, Ranchi
progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

8
6
6

8
4
0

7
3
0

1
0
0

0
1
0

0
0
0

10

30

12

10

(Eqpt.

1st Review meeting held


on 21.09.15.
Scope of Mech eqpts.
33 T & Elect. eqpts. 2 T
All eqpts. ordered.

SN
SCHEME / PACKAGE
B 14 Illumination System for URM, BRM & RWL

(Pkg-128) Consultant MECON


Contract no. TK/ 2013 / 382
AgencyM/s Traansrect Industries, Raipur
Cont. price: Rs 11.60 Crs.
Contract Signed on: 21.05.13
Contract Completion : 20.02.14
Likely Completion : Feb.16
(Proj. Mgr.- Tirumal Rao, DGM) 20055

PROGRESS ON DATE

Illumination work in BC bay of URM


started on 26.09.13 and in progress.
Illumination work in BC bay of BRM
started on 10.06.14 and in progress.
Illumination work in RWL area in progress.

B 15 CNC Roll Turning Lathes for URM


(Pkg-142-01)
Consultant- MECON
Contract no. TK/ 2013 / 385
Cont. price: Rs 22.84 Crs.
AgencyM/s Hankook-Sanmathi
Contract Signed on: 21.06.13
Contract Completion : 20.06.14
Likely Completion : Jan.16
(Proj. Mgr.- Rakesh Kumar, DGM) 21143

B 16 Air Conditioning System and Ventilation Design Engg., ordering,


supply &
System for BRM, URM & RWL (Pkg.-125-02)
erection of eqpts. in progress.
Consultant-MECON
Fabrication & erection of ducts (ECRs-1, 2
Contract price: Rs 47.92 Crs.
& 3 of BRM & ECRs-1 to 3 & 6 of URM) in
Contract no. TK/ 2013 / 387
progress.
Agency M/s Sterling & Wilson Ltd., Kolkata
Placement of eqpts. in various area of
Contract Signed on: 25.06.13
BRM and URM(Mech. eqpts., Elect.
Contract Completion : 24.09.14
Likely Completion : Feb.16
eqpts. like PDB, insulation work, cable
(Proj. Mgr.- J Gopi Krishnan, DGM) 21151
tray work & cable laying) in progress.
Piping work, welding, alignment, hydro
test and piping insulation work i/p.

Total

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)

20
0
350
71
441

TOTAL

Activity

Elect. Eqpt. (Ind.) Supply


Elect. Eqpt. (Ind.) Erection
Drawings

Total

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL
Activity

B 18 Air Drying Plant for Universal Rail Mill and Air Design Engg. & ordering of eqpts. in
Drying and Filtration Plant for BRM (Pkg. -114A)
progress.
Consultant-MECON
Cont. price: Rs 1.34 Crs.
Agency M/s Mellcon Engineers Pvt. Ltd, New
Delhi
Contract Signed:31.03.15
Contract Compln: 30.11.15

Likely Completion : Mar.16


(Proj. Mgr.- K V S Prakash Rao, DGM) 21374

9
8
15
31
63

Submtd.
20
0
340
67
427
Unit

Appd/KFR

AAN

Comtd

18
0
194
65
277
Total
Scope

2
0
136
0
138

T
T

448
448

30
40

0
0

Submtd.

Appd/KFR

AAN

Comtd

0
0
0
0
0

0
2
0
3
5

9
8
15
31
63
Unit

9
6
15
28
58
Total
Scope

0
0
8
0
8
Jan.16

Plan

U/S
0
0
2
2
4
Cum. Prog.

Prog.

Jan.16
Plan

370
305
U/S
0
0
0
0
0
Cum. Prog.

Prog.

Mech. Eqpt. Erection


T
354
23
0
331
Elect. Eqpt. Erection
T
50
15.3
0
34.7
All Imported Eqpts. (330 T Mech. & 43.5 T Elect.) supplied during 30.07.14-05.08.14. Alignment
work of all 4 nos. CNC lathe machines completed. Cable laying work comp.
Drawings

Total

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL
Activity

31
4
302
47
384

Submtd.
31
4
297
47
379
Unit

Appd/KFR
31
4
203
33
271
Total Revised
Scope

AAN

Comtd

U/S

0
0
79
13
92

0
0
6
1
7

0
0
9
0
9
Cum. Prog.

Jan.16
Plan

Total
14
14
13
62
103

Elect. Eqpt. Supply


Drawings
Basic Engg. (A)
Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

Total
5
0
31
44
80

Submtd.
14
13
12
60
99
Unit

Appd/KFR
13
12
11
58
94
Total
Scope

AAN

Comtd

0
0
0
0
0

1
1
0
1
3
Jan.16

Plan

U/S
0
0
1
1
2
Cum. Prog.

Page : 10

Ordering of all 448 T eqpts.


completed.
8th Review meeting held on
05.05.15.
Ordering & supply of all
Imported Eqpts. (330 T Mech. &
43.5 T Elect.) completed.

Ordering & supply of all


Indigenous eqpts. (24 T
Mech. & 6.5 T Elect.)
completed.
19th Review meeting held on
20.11.15.

All Eqpts. (969 T Mech. & 316 T


Elect.) ordered.

5th Review meeting held on


22.04.15.

Prog.

T
T

420
20

29
10

0
0

391
10

All Eqpts. (420 T Mech. & 20 T


Elect.) ordered.

Submtd.

Appd/KFR

AAN

Comtd

U/S

3
0
21
12
36

2
0
0
0
2

0
0
2
2
4

1st Review meeting held on


21.09.15.

5
0
23
16
44

0
0
0
2
2

Drg. list & datasheets for air filter and air dryer KFR on 17.07.15. GA drgs, P & ID
diagrams, eqpt. list and foundation drawing for air filtration plant and air receiver for
BRM & URM KFR.

1/12/2016

21st Review meeting held on


21.12.15.

Prog.

Mech. Eqpt (Ind.) supply


T
969 #
12
0
957
Elect. Eqpt. (Ind.) Supply
T
316 #
22
0
294
Mech. Eqpt (Ind.) erection
T
969 #
120
0
406
Elect. Eqpt. (Ind.) erection
T
316 #
30
0
191
Mech. eqpts.(VRF, ACs, pipes, GI sheets Chillers, valves, AHUs, FCUs, fans, Airwashers,
louvyers, desert cooler, pipes, plates, humid stats, pkg ACs, Cooling tower, dampers, axial
fan & motor, etc) supplied. Elect. eqpts (Cables, steel supports,cable tray, PDBs, SDBs, etc)
supplied. Testing of all AC and ventilation systems of Rail Welding Line area successfully
comp. on 06.05.15.

B 17 Roll & Repair Shop Equipment for Universal Design Engg., ordering & supply of eqpts. Drawings
Basic Engg. (A)
Rail Mill (Pkg-142-02)
in progress.
Basic Engg. (I)
Contract no. TK/2013/391
Welding rectifier & m/cs, Radial drilling Detail Engg. (A)
Consultant-MECON
m/cs, hack saw, band saw m/cs, lathes, Detail Engg. (I)
Cont. price: Rs 23.90 Crs.
universal milling m/c, Column drilling TOTAL
Agency M/s MACO Corporation, Kolkata
Activity
Contract Signed:26.09.13
m/c, grinding, brazing & welding m/cs,
Contract Compln: 25.09.14
profile redressal m/c, PDBs, etc supplied. Mech. Eqpt Supply
Likely Completion : Jan.16
(Proj. Mgr.- Rakesh Kumar, DGM) 21143

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

C. STEEL ZONE
SN

C1

PROGRESS ON DATE
SCHEME / PACKAGE
Instn. of Desulphurisation Unit at SMS-II (Consultant-CET) Sanction Cost: Rs 83.90 Crs.
Drawings
Pkg.-IV 180T+50T Ladle Crane
Critical Issue
BE (A)
Contract No TK- 2006/221
Supply of Main Trolley.
DE (A)
Consultant-CET
Start erection of eqpt. by M/s DE I
Agency -M/s Jessop
TOTAL
Jessop.
Cost : Rs. 13.18 Crs
Contr. date : 10.03.06
Contr. comp : 09.06.07
Project Mgr- S.K.Jain, DGM- 1058

C2
2.1

CNC Lathe M/c for Segment Repair


Shop

Total

Subm.

40
26
113
179

37
22
68
127

36
17
56
109

1
5
1
7

Unit

Total
vol.

Plan

Activity

Mech. eqpt. supply


Elect. Eqpt. supply
Mech. eqpt. erection
Elect. eqpt. erection

Segment repair & mould repair shop for new slab caster at SMS-II, Consultant-CET
Drawing
Aug. of power supply facility for
BE (A)
segment repair & mould repair shop
Contract no. TK/2010/302
Agency-Hindustan Control & Eqpt., Kolkata
Cost : Rs. 2.63 Crs
Contract signed on : 23.02.10
Cont. Completion : 22.02.11
Likely Compl- Jan16
Proj. Mgr- MP Singh, DGM- 2678

2.2

OVERALL STATUS AS ON DATE

T
T
T
T

Total
15
21
20
56

DE (A)
DE I
TOTAL

Activity

Earthwork
Concrete
Elect. Eqpt. Ord
Elect. Eqpt. Supply
Elect. Eqpt Erection

Submtd.
15
21
19
55

Appd/KFR

AAN

13
19
19
51

Unit

Total Vol.

M3
M3
MT
MT
MT

125
75
32
32
32

Comnt
4
4

Cum. Prog.
Prog.

AAN

U/S
7
7

Jan16

385
52
385
52

Appd/KFR

COMMITMENT AS PER LATEST MOM

206
22
24
7

Comtd.

2
2
0
4

0
0
0
0
Jan16

Plan

Progress

U/S
0
0
0
0

Cum.
Prog

125
75
32
32
32

Testing of PCC panels compl. On 02.08.13 .LT substation- 27Q charged on


16.09.13. PAC given on 14.01.14. Both transformers (of S/S 27Q) charged on
15.03.14.
CNC Lathe erection completed on 10.07.12. PAC issued with effect from
12.07.12. Successful load tials taken.

Contract no . TK/2010/320
Agency- M/s Texllence CNC, Pune
Cost : Rs 87.63 Lakhs
Contract signed : 06.08.10,
Cont. Compl. : 05.08.11
Likely Completion- Jan16
Proj. Mgr K. Rajshekhar, DGM- 0518

2.3

Provision of Roll Cladding facilities &


other Auxiliaries in SRS
Contract no . TK/2010/328
Agency : Welding Alloys , Mumbai
Cost : Rs 1.92 Crs. Contract Signed : 11.11.10
Effective Dt. of contract : 02.11.10
Cont. Completion : 01.11.11
Likely Completion : Jan16
Proj. Mgr K. Rajshekhar, DGM- 0518

2.4

Installation of Machine Tools in


Segment Repair Shop and Mould
repair shop

PAC issued with effect from 02.03.15. Load trials successful on 23.07.15.
Machine is down since Aug15 due to inverted screen problem and
electrical problem of post heat furnace.

All machines under M/s Saha had been erected and commissioned,
except universal tool & Cutter Grinder (1 no.) and Hydraulic press which is
erected but not commissioned. Charging of Oxygen line is balance.

Award No. NTK-5(2919)/12/184


Agency- M/s DK Saha Cost Rs. 47.73 Lakhs.
Date of Award : 06.02.12 Cont. compl. 05.08.12
Likely Completion: Jan16
Proj. Mgr - K. Rajshekhar, DGM - 0518

1/12/2016

Page : 11

Review meeting held on 02.12.15

SN

C3

SCHEME / PACKAGE
BOF Shop Technological Package
(Pkg.-025)
Contract No. TK-2008/285
Consultant MECON
Agency-M/s Siemens VAI
Cost Rs. 1352.10 Crs (Revised)
Contract signed : 24.10.08,
Cont. Completion : Aug.11
Likely Compl: Jun16
(Conv.1-Mar16, Conv.2-May16)

PROGRESS ON DATE

Cable laying in progress.


As on date total 41722 m cable
laying completed out of which 7250
m laid this month.
3 T elect. eqpt erection completed.

OVERALL STATUS AS ON DATE

COMMITMENT AS PER LATEST MOM

Drawing

Total

Subtd.

Appd/KFR

AAN

Comntd

U/S

BE (A)
BE I
DE (A)
DE I
TOTAL

598
282
103
286
1269

597
277
108
279
1261

586
270
102
250
1208

3
1
1
8
13

5
5
5
16
31

3
1
0
5
9

7
0
1
30
38

4
11
9
140
164

0
0
1
8
9

Addl. Drawings

BE (A)
BE I
DE (A)
DE I

Proj. Mgr V.K. Rai, DGM - 0563

TOTAL
Activity

281
226
167
826
1500
Unit

270
215
156
648
1289
Total vol.

Jan16
Plan

Mech. Eqpt. Ord. (Imp)


Mech. Eqpt. Ord. (Indg.)
Elect. Eqpt. Ord. (Imp.)
Elect. Eqpt. Ord. (Indg.)
Refractory Ord.
Mech. Eqpt. Supply (Indg.)
Mech. Eqpt. Supply (Imp.)
Elect. Eqpt. Supply. (Imp.)
Elect. Eqpt. Supply. (Indg.)
Mech. Eqpt. Erection
Elect. Eqpt. Erection
Important activities completed / Highlights

C4

Instln. Of Continuous Casting Plant


Complex (Pkg.-026)
Contract No. TK-2009/289
Consultant MECON
Agency-M/s Siemens VAI
Cost :781.01 Crs
Contract signed on: 18.04.09
Contr. Compln. : 17.12.11
Likely Compl: Jun16
Proj. Mgr - MP Singh, DGM -2678

Review meeting held on 18.11.15

T
T
T
T
T
T
T
T
T
T
T

2426
22055
349
2121
4209
22055
2426
349
2121
2059
1095

Prog.

0
150
0
0
30.4
0
76

10

Cum.
Prog.

2426
21970
349
2107
0
21970
2412
349
2105
2058.5
533

Mechanical test for travel of piston of Gas Holder, to its operating limit
conducted on 18.01.14 along with EMD & SMS-II. Standard leak test of
Gas Holder conducted during 04-07.02.14 along with EMD & SMS-II and
joint inspection recorded for 24, 48 & 72 hrs. Electrical equipment
erection started on 04.11.14.
Erection of JBs, earthing strip and
earthing is in progress.
Cable shifting and dressing in
progress.
As on date total 76110 m cable
laying completed, out of which
8100 m laid this month.
0.5
T
elect.
eqpt
erection
completed.

Drawings
BE (A)
BE I
DE (A)
DE I
TOTAL
Addl. Drawings
BE (A)
BE I
DE (A)
DE I
TOTAL
Activity

Total

Submtd

Appd/KFR

723
108
266
937
2034

722
108
265
908
2003

706
108
258
902
1974

230
496
57
1802
2585
Unit

229
496
57
1795
2577
Total Vol.

Mech. Eqpt. Ord. (Imp.)


Mech. Eqpt. Ord. (Indg.)
Elect. Eqpt. Ord. (Imp.)
Elect. Eqpt. Ord. (Indg.)
Mech. Eqpt. Supply (Imp.)
Mech. Eqpt. Supply (Indg.)
Elect. Eqpt. Supply (Imp.)
Elect. Eqpt. Supply (Indg.)
Refractory Ord.
Elect. Eqpt. erection

T
T
T
T
T
T
T
T
T
T

3299
10791
239
1176
3299
10791
239
1176
2200
971

AAN

Comntd.

16
0
6
1
23

0
0
0
2
2

1
0
0
1
2
Jan16
Plan
Prog

0
0
0
0
50
0
0
0
78.5

3.846

0
0
0
0
0

U/S
0
0
1
3
4
0
0
0
6
6
Cum. Prog.

3294
10682
239
1120
3294
10198
239
1097
0
201.996

Elect. Eqpt erection started on 27.12.14. Cable laying started in Caster-1


on 06.08.15. Transformer testing for Crane sub-station-2 started on
22.12.15.

1/12/2016

Page : 12

Review meeting held on 09-10.12.15

SN

C5

PROGRESS ON DATE
SCHEME / PACKAGE
Instln. Of Secondary Refining Unit for Erection of Storage Bunker is in
SMS-III (Pkg.-025A)
progress.
Cont. No. 2010/303

Consultant MECON
Agency-M/s WISDRI, China
Cost : Rs. 205.56 Crs
Contract signed on 08.03.10,
Cont. Completion : : 22.09.12,
Likely Compl: Jun16
(LF1 & ARS1 - Feb'16,
LF 2 & 3, ARS 2 & 3 - Jun'16,
RH - Jun'16)
Proj. Mgr V.K. Rai, DGM - 0563

OVERALL STATUS AS ON DATE


Total
BE (A)
BE I
DE (A)
DE I
TOTAL

179
173
146
523
1021
Total

BE (A)

BE (I)

DE (A)

DE ( I )
TOTAL

Submtd.
179
173
146
510
1008
Submtd.

3
4
10
75
92

Activity

Unit

Mech. Eqpt.Ord. (Imp.)


Mech. Eqpt. Ord. (Indg.)
Elect. Eqpt. Ord. Imp.)
Elect.Eqpt. Ord. (Indg.)
Tech. Strl Fabrication
Refractory ordering (Imp.)
Refractory ordering (Indig.)
Mech. Eqpt.Supply. (Imp.)
Mech. Eqpt. Supply. (Indg.)
Tech. Strl Supply
Tech. strrl. erection
Elect. Eqpt. supply. (Imp.)
Elect. Eqpt. supply. (Indg.)
Mech. Eqpt. Erection
Elect. Eqpt. Erection

T
T
T
T
T
T
T
T
T
T
T
T
T
T
T

Appd/KFR
176
171
145
489
981
Appd/KFR

COMMITMENT AS PER LATEST MOM

AAN
3
1
1
0
5
AAN

3
3
9
64

0
1
0
2

79

Total
Vol.
1698
1652
303
873
2150
353
480
1698
1652
2150
2150
303
873
3350
1176

Comntd
0
0
0
13
13
Comntd

0
0
1
7

8
Jan16
Progress
Plan

0
0
166
0
0
120
96
0
26
0

0.8

U/S
0
1
0
8
9
U/S

0
0
0
2
2
Cum.
Prog.

1698
1652
303
873
2150
353
0
617
304
691
248.901
208
468
83.99
137.3

Mechanical (imp.) equipment supply started on 27.01.15. Tech. strl


erection started for LF area on 30.03.15. 35 MVA Ladle furnace
transformer supplied in Apr.15. Electrical eqpt. Erection started on
27.05.15. 35 MVA Ladle furnace transformer at LF-1 erected on 27.05.15.
35 MVA Transformer (for LF) received at site on 12.06.15. Mech. eqpt.
Erection started on 25.08.15. 3rd and last 35 MVA trans. Supplied on
03.10.15.

1/12/2016

Page : 13

Review meeting held on 07.12.15

SN

C6

SCHEME / PACKAGE
Instln. of Hot Metal De-sulphurisation
Unit for SMS-III (Pkg.-027)
Contract No. TK-2008/283
Consultant MECON
Agency-M/s ESM USA-Beekay Engg.
Cost Rs. 37.73 Crs
Contract signed: 06.10.08 (Eff. date
06.03.09)
Contr. completion : 05.03.11,
Likely Compl: Mar16
Proj. Mgr -. N.V.Joshi, DGM-0799

PROGRESS ON DATE

Design Engg. in progress.


Strl fabrication under progress.

Total

Submtd

Appd/KFR

AAN

Comtd

U/S

BE (A)

55
61
74
348

55
61
67
322

42
58
55
315

2
0
0
0

10
3
12
6

1
0
0
1

BE I
DE (A)
DE I
TOTAL

538

BE (A)
BE I
DE (A)
DE I
TOTAL

Activity

Mech. Eqpt. Ord. (Imp.)


Mech. Eqpt. Ord. (Indg.)
Elect. Eqpt. Ord. (Imp.)
Elect. Eqpt. Ord. (Indg.)
Structural supply
Structural Erection
Mech Eqpt. Supply (Imp.)
Mech Eqpt. Supply (Indg)
Elect. Eqpt. supply. (Imp.)
Elect. Eqpt. supply. (Indg.)
Mech. Eqpt. Erection
Elect. Eqpt. Erection

C7

Lime Calcinations & Dolomite Plant at


RMP-III (Pkg.-028)
Contract No. TK-2009/298
Consultant-MECON
Agency-M/s Shapoorji Pallonji
Cost : Rs. 263.99 Crs
Contract signed on : 09.12.09,
Cont. Completion : 08.03.12,
Likely Compl : Mar16
(Kiln 1 & Kiln 2 Jan16 ;
Jan'16 ; Kiln 4 - Feb'16 ;
Kiln 5 - Mar'16)

Kiln 3 -

Proj. Mgr MP Singh, DGM- 2678

Important activities completed / Highlights

Handrail & CHQD Plate installation


at WGCS 3 & 4 is in progress.
Kiln 5 - Assembly of Kiln Housing.
CHQD placement in Booster house.
Kiln -2, Flap gate chute erection
under progress.
PMCC -8 , Panel erection.
1 T Elect. Eqpt erected.
4 T strl erected.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Drawings

Total

BE (A)
BE I
DE (A)
DE I
TOTAL

73
95
186
280
634
Activity

Earthwork
Pilling (Scope revised)
Concreting
Refractory ordering
Tech. Structures Supply
Bldg. Structures supply
Structures erection
Mech. Eqpt. Supply. (Imp.)
Mech. Eqpt. Supply. (Indg.)
Elect. Eqpt. supply. (Imp.)
Elect. Eqpt. Supply. (Indg.)
Refractory supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

505
470
Addl. Drawings
3
3
1
1
10
9
14
13

0
0
1
1
Jan16
Plan
Progress

Unit

Total Vol.

T
T
T
T
T
T
T
T
T
T
T
T

15
300
2
60
420
420
15
300
2
60
315
62

5
10

Appd/KFR

AAN

Submtd.
73
95
186
277
631
Unit

M3
Nos.
M3
T
T
T
T
T
T
T
T
T
T
T

72
95
184
277
628
Total vol.

108000
792
21195
4000
8364
2750
11114
21
2047
1.5
1000
4000
2068
1001.5

31

2
0
0
Cum.
Prog.

15
295
2
60
420
0
15
295
2
5.5

5
0
0
0
Comtd

1
0
0
0
0
1
0
1
1
2
Jan16
Plan
Prog.

200
50
25
106
10
9
0
45
24

270
76

18

9.5
7.6
5.5

U/S
0
0
0
0
0
Cum Prog

107302
792
21026
4000
8339
2750
10154
21
2032
1.5
994.5
0
1700.6
720.3

Chilled water line testing done at ECR Building on 03.07.15. No load trial
taken for 2 nos. blowers of Kiln 2 on 13.07.15. No load trial taken for 2 more
blowers of Kiln 2 on 17.07.15. 1 no. & PCC charged at Kiln-1 on 25.07.15. No
load trial taken for 3 nos. blowers of Kiln 1 on 27.07.15. 1 no. transformer (2
MVA) charged for Kiln no.1 on 25.08.15. Total 9 out 12 nos trans. charged.Trial
run taken for vibro feeder of Kiln no.2 on 25.08.15. MCC of Kiln1 & 2 Charged
on 28.08.15. 2 out of 3 nos 200 KVA lighting transformers & MLDB charged on
26.11.15.

1/12/2016

Page : 14

Review meeting held on 10.12.15

Review meeting held on 11.12.15

SN

C8

C9

60 T mech eqpt supplied. (IJ bay


2nd crane aux. trolley)

Contract No. TK-2009/293


Consultant MECON
Agency-M/s HEC
Cost : Rs. 146.10 Crs
Contract signed: 29.06.09,
Contractual Compln : 28.06.11,
Likely Compl: Feb16 (Priority Cranes)
Project Mgr- S.K.Jain, DGM- 1058
Important activities completed / Highlights

Review meeting scheduled on 12.01.16

Instln. Of 10 Nos. Cranes above 100 T


capacity (Pkg.-029-A-2)
Contract no. TK/2011/336
Consultant-MECON
Agency-M/s HEC
Cost Rs. 149.55 Crs
Contract signed: 12.02.11
Contractual Compln : 11.02.13
Likely Compl : Feb16 (Priority Cranes)
Project Mgr- S.K.Jain, DGM- 1058

Important activities completed / Highlights

C 10 Installation of Cranes for BOF & CCP


(Pkg.-029B1) (Consultant- MECON)
(Pkg retendered after RPN)

Activity

Drawing

Plan

Appd/KFR

34
4
53
182
273
Unit
T
T
T
T
T
T
T

Jan16
Progress

Cum. Prog.

Review Meeting held on 21.12.15

AAN

34
4
49
170
257

0
0
0
0
0

Total
vol.
507
494
760
3686
494
760
3686

Plan
9
300
300
100
10

Comntd.
0
0
0
9
9

Jan16
Progress

U/S

Review Meeting held on 21.12.15

0
0
4
3
7
Cum.
Prog.
498
173
760
1540
106
749.3
0

Mech. eqpt. Supply started on 11.01.14. Elect. Eqpt. Supply started on 27.05.14.
Drawing

Total

Submtd.

96
79
316
449

70
70
175
220

940

535

BE (A)
BE I
DE (A)
DE I
Total
Activity

Appd/KFR

60
60
115
202
Unit

Mech. BO item Ordering


Elect. BO item Ordering
Mech. eqpt. Supply
Electrical eqpt. Supply
Mech. eqpt. Erection
Elect. eqpt. Erection

Important activities completed / Highlights

Important activities completed / Highlights

Submtd.

34
4
64
182
284

Mech. BO item Ordering


Elect. BO item Ordering
DSL ordering
Mechanical eqpt. Supply
Electrical eqpt. Supply
DSL Supply
Mech. eqpt. Erection

Proj. Mgr SK Jain, DGM

Agency- M/s Mukand Ltd


Cost :Rs 53.75 Crs
Contract signed: 08.08.12
Contractual Compln : 07.02.14
Likely Compl: Feb16
Project Mgr- S.K.Jain, DGM- 1058

Total

Activity

Review meeting scheduled on 12.01.16


Design engg. in progress.
Equipment ordering in pogress.

Total
vol.

Mech. BO item Ordering


T
553
553
Elect. BO item Ordering
T
599
599
DSL ordering
T
561
561
DSL Supply
T
561
561
Mech Eqpt supply
T
3756
546
3210
Electrical eqpt. supply
T
599
176
423
Mech Eqpt erection
T
3756
300
225
1420
Electrical eqpt. erection
T
599
100
2 Nos. Aux. end girders erected on 13.04.15. EF bay 2nd crane main girder erected
on 28.11.15. EF bay 1st crane E-room and end girder rected on 15.12.15.
IJ bay
crane aux. girder erected on 17.12.15. EF bay 2nd crane aux. girder erected on
st
18.12.15. DE bay 1 crane main girder erected on 06.01.16.

Priority Cranes : Feb16 (Priority Cranes)

Consultant-MECON

Unit

BE (A)
BE I
DE (A)
DE I
TOTAL

Agency M/s Mukand


Contract signed: 19.06.15; Contr. Compln. :
18.12.16; Cost Rs.176.08 Crs.

C 11 Installation of Cranes for BOF & CCP


(Pkg.-029B2)

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE

SCHEME / PACKAGE
Installation of Cranes for BOF & CCP
(Pkg.-029A) (7Nos 300T + 80 T Cap.)

T
T
T
T
T
T

437
Total vol.
3484
233
3484
233
3484
233

AAN

2
0
0
0
2
Plan
300
100
200
50
0
0

Comntd.

0
5
30
0
35
Jan16
Progress

U/S

Review meeting held on 15.12.15

8
5
30
18
61
Cum.
Prog.
1511
10
0
0
0
0

Electrical eqpt ordering started on 18.10.15

Drawing

Total

Submtd.

201
52
210
508
971

201
52
210
505
968

BE (A)
BE I
DE (A)
DE I
Total
Activity

Appd/KFR

Unit

Mech. BO item Ordering


Elect. BO item Ordering
Mech. eqpt. Supply
Electrical eqpt. Supply
Mech. eqpt. Erection
Elect. eqpt. Erection

T
T
T
T
T
T

200
51
205
501
957
Total vol.
704
329
704
329
704
329

AAN
1
0
0
1
2
Plan
10
200
40

Comntd.
0
0
0
0
0
Jan16
Progress
-

U/S
0
1
5
3
9
Cum.
Prog.
704
329
694
329
385
50

Mech equipment started on 01.08.14. Elect. eqpt erection started on 18.08.15.

1/12/2016

Page : 15

Review meeting held on 15.12.15

SN
SCHEME / PACKAGE
C 12 Cast in situ bored piling work in SMS-III
complex (Pkg.-033-A 1)

PROGRESS ON DATE

C 13 Civil works for BOF & CCS (Pkg-033A)

C 16 Augmentation facilities of Material


Handling system in SMS-II (Pkg No.
038-01) Contract no . TK/2011/339
Consultant-MECON
Agency- M/s Anupam Industires
Cost :Rs 8.83 Crs
Contract signed: 15.03.11
Contractual Compln : 14.12.11
Likely Compl: Jan16
Proj. Mgr -V.K.Rai, DGM- 0563
Important activities completed / Highlights

Nos.
Nos.
Nos.

Earth Work
Concreting(PCC)

M3
M3

Concreting(RCC)

M3

Excavation 136 m3 completed.


Concreting -48 m3 completed.

Activity

Jan16

Cum. Prog.

Plan

Prog

8287
7163
15450
239490
3000
2000

Unit

Earth work
Concreting For BOF
-For CCP
Total Concreting

Consultant MECON
Agency-M/s Simplex Infrastructures
Cost : Rs. 330.06 Crs (Revised)
Award Dt. 11.02.13
Contract signed: 28.02.13
Cont. Compl. : 30.04.14.
Likely Completion: Jan16
Proj. Mgr N.V.Joshi, DGM-0799

C 15 Strl. Works for BOF & CCS (Pkg-033B)


Award No. NTK-5(2787)/09/1554
Consultant MECON
Agency-M/s Era Infra Structure
Cost : Rs. 611.66 Crs (Revised)
Contract signed: 30.09.09,
Cont. Completion : 29.09.11
Likely Compl: Feb16
Proj. Mgr Alok Rai, DGM- 0792

Total Vol.

Review meeting held on 09.05.14

8287
7163
15450
239490
3000
733

13320 m3 / 300000 m3 earthwork done & 54680 m3 / 180000 m3


concreting completed. Contract terminated on 09.02.13. Balance work
awarded to M/s Simplex Infrastructures on 11.02.13.

Consultant-MECON
Agency -M/s HSCL
Cost Rs 191.37 Crs (Revised)
Award Dt. 10.02.11. Cont. Signed: 21.02.11
Cont. compl. 20.10.12.

C 14 Balance civil works for BOF & CCP at


BSP Bhilai (Pkg - 033A2)

Unit

Piles for BOF


Piles for CCP
Total Pilling

Award No. PCC/NTK/ 23/10


Consultant-MECON
Agency-M/s Era Infra Structure, Delhi
Cost Rs 84.92 Crs. (Revised)
Contract signed on: 23.01.10,
Cont. Completion : 22.10.10,
Likely Completion: Jan16
Proj. Mgr. N.V.Joshi, DGM-0799

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Activity

Total Vol.

M3
M3
M3
M3

460566
104411
103512
207923*

Jan16

Cum. Prog.

Plan

Prog

3000
873
1451
2824

1466
294
260
554

Review meeting held on 24.11.15

250037
84381
92794
177175

*Scope revised as per MECON (confirmed by Zone on 27.11.15)

RCC work started on 10.04.13


Strl Fabn 50 T for BOF, 10 T for CCP.
Strl Ertn 79 T for BOF, 5 T for CCP.

Activity

Unit

Total Procurement of steel


Structural Fabr -For BOF
-For CCP
Total fabrication
Structural Erection
- For BOF
-For CCP
Total Erection

MT
MT
MT
MT
MT
MT
MT

Total Vol.

106947
57349
42601
99950
57349
42601
99950

Jan16
Plan

Prog

Cum. Prog.

1000
1100
400
1500
1425
1024
2449

0
390
100
490
520
264
784

100500
52452
38419
90871
46447.11
36125.89
82573

Review meeting held on 24.06.14.

89952 T (51231 & 38721) design drawing issued by MECON. 53884 T (BOF) & 42687 T
(CCP) drgs approved by MECON.

Roof Sheeting of H-I bay (Secondary


refining unit) Block 2&3 cmptd. I-J bay
(Casting Bay) Block 2&3 cmptd. J-K bay
(tundish bay) Block 1&2 cmptd. K-L bay
(Segment bay) Block 1&2 cmptd. L-M bay
(Storage bay) & M-N bay (Storage bay)
Block 1&2 cmptd. G-H (Ladle preparation
bay) Block 1 in progress.

Drawing

Review meeting held on 15.12.15.

483/509 column erected.

Total

BE (A)
DE (A)
DE ( I)
TOTAL

*Revised Scope is 99950 T(54500 & 45450)

Submtd

Appd/KFR

AAN

Comntd

U/S

21
27
38
86
Unit

21
27
38
86
Total vol.

0
0
0
0

0
0
0
0

0
0
0
0
Cum.
Prog.

21
27
41
89
Activity

Jan16
Plan

Mech. Eqpt. Ordering


Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

T
T
T
T
T
T

187.3
44.5
187.3
44.5
187.3
44.5

7.3
2.5
17.3
9
50
20

Prog.

180
42
180
42
125
15

All parts of 75/15 T crane erected and load test completed on 04.07.15.

1/12/2016

Page : 16

SN

C 17

SCHEME / PACKAGE
Inter Plant Pipe Conveyor from RMP-3
to RMP-2 (Pkg.-140)

PROGRESS ON DATE
Pipe conveyor started and trial run is

under progress.

Contract no . TK/2011/334
Consultant- MECON
Agency : M/s FL Smidth Pvt. Ltd
Cost- Rs 58.11 Crs
Contract Signed : 04.02.11,
Cont. Completion : 03.05.12
Likely Completion : Jan16

Erection, Testing & Commissioning of


Plant & Equipment of BOF and CCP
complex (Pkg. 131 A)
(Consultant MECON)
Agency-M/s Essar Projects (I) Ltd.
Contract signed: 12.0314;
Contr. Compln. : 11.05.15
Likely Completion : Jun16
( CV1 - Feb'16, CV2 - Jun'16, Converter 1 Mar'16, 2 - May'16,
3 - Jun'16)
Cost: Rs 84.59 Crs.
Proj. Mgr K. Rajsekhar, DGM- 0518

C 19 Pneumatic Sample Transport System


for BOF, CCP & SRU in SMS-III (Pkg.134)

BE (A)
BE I
DE (A)
DE I
TOTAL

Total

Submtd

50
27
145
60
282

50
21
142
53
266

48
19
141
53
261

Unit

Total vol.

Activity

Appd/KFR

AAN

Comntd.

0
0
0
0
0

1
2
0
0
3
Jan16

Plan

U/S

Review meeting held on 28.11.15

1
0
1
0
2
Cum Prog.

Prog.

Earthwork
M3
9700
9700
5000
Concreting
M3
5100
20
Mech. equipment Ord
T
558
558
Elect. equipment Ord
T
200
200
Bldg Strl Fab
T
1600
1600
Bldg Strl Supply
T
1600
1600
Tech. Strl Supply
T
55
55
Strl Erection
T
1655
1654.5
0.5
Mech. Eqpt supply
T
558
556
2
200
Elect. equipment Supply
T
200
Mech. Eqpt erection
T
558
549
9
Electrical Eqpt erection
T
200
198
2
All 133 nos. gallery erection completed on 05.02.15.Electrical eqpt supply completed on
11.03.15. Conveyor belt laying in RMP-2 started on 28.04.15. 2 nos. transformer (2 MVA)
charged at S/S of RMP-2 end on 03.07.15 & 04.07.15. No load trial taken for 2 nos. motors at
tail end on 11.07.15 & another 1 no. on 14.07.15.MCC Panel of RMP-III end charged on
13.07.15. No load coupled trial (motor with gear) of 2 nos motors at head end (RMP-II)
taken on 15.07.15. & no motor at tail end (RMP-III) taken on 16.07.15. Pipe conveyor started
on 21.10.15.

Proj. Mgr MP Singh, DGM- 2678

C 18

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawing

BOF: Primary dedusting ID fan work in


progress. Secondary dedusting raw gas duct
erection in progress. Material handling system
works in progress.Converter 2 & 3 (motor
alignment) work in progress. Dry ESP wok in
progress.
2 T mech eqpt erected. 0 T Elect. Eqpt.
Erected.
CCP:
CK1- Intermediate water room, discharge
hydraulic system, piping erection work in
progress. Torch cutting m/c work in progress.
CV1- Alignment of roller table and cooling
bed is in progress. Erection of coling chamber
casting platform in progress. Segment
storagetack erec. in prog.
Erection of steam exhaust stack of CK1 & CK2
in progress.
1 T mech. Eqpt erected 1 T Elect. Eqpt.
Erected.

Design Engg. in progress.

Activity

Unit

Total vol.

Jan16
Plan

Mech. Eqpt. Erection


BOF
CCP
Elect. Eqpt. erection
BOF
CCP
Refractory
BOF
CCP

Cum Prog
Prog.

Review meeting held on 08.12.15

T
T
T
T
T
T
T
T
T

898
53
34535.6
16019
28
10189.5
707
21293.03
25
5829.5
191
13242.57
30
18
2460.74
1376
5
0
1605.93
674
25
18
854.81
702
15
100
15
10495.21
5700
0
0
0
100
15
15
4795.21
Converter-2- Top cone erected on 30.01.15. Converter-3- Erection of Trunnion
ring assembly completed on 16.02.15. Converter-3 bottom Shell erection
completed on 28.02.15. Finfan Cooler erected at Pump house on 17.03.15.
Converter-2 tilting device installation done on 14.09.15. Converter-1- Cooling
Stack Part1 & 2 positioned at location on 23.11.15. Converter-3- Tilting drive
assembly completed on 08.12.15. Refractory work started in caster area from
21.12.15.

Contract signed with M/s Kerry Engg, Visakhapatnam on 25.06.13.

Consultant- MECON. Agency- M/s Kerry Engg


Cost Rs 2.90 Crs.. Contract Signed on 25.06.13.
Cont.Compl. 24.03.14. Likely cmpn. : Mar16
Proj. Mgr.- Alok Rai, DGM-0792

1/12/2016

Page : 17

Review meeting held on 25.07.15

SCHEME / PACKAGE
SN
C 20 Illumination,Earthing & lighting protection system

for SMS-3 (Pkg-127) (Consultant- MECON);


Agency M/s ETA Engg., Kolkata.
Contract signed: 26.11.14; Contr. Compln. :
25.02.16; Cost Rs.15.47 Crs.
Likely Completion : Mar16
Proj. Mgr MP Singh, DGM- 2678

PROGRESS ON DATE

Design Engg. in progress.


Review meeting held on 11.01.16

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawing

Total

Submtd

Appd/KFR

AAN

BE (A)

Comntd.
2

U/S

BE (I)

DE (A)

13

10

DE I
TOTAL

47
72

35
57
Unit

0
0

12
18

Activity

Elect. Eqpt. Ordering


Elect. Eqpt. Supply
Elect. Eqpt. erection

26
38
Total vol.
299.15

T
T
T

Jan16
Plan
0

299.15

299.15

Review meeting held on 11.01.16

1
1
Cum Prog

Prog.
160
0

Electrical ordering startred from 10.12.15

C 21

Propane storage & handling system (Pkg.032)

Design Engg. in progress.

92
Unit

47
Total vol.

Earthwork
M3
Concreting
M3
Mech. equipment Ord
T
Elect. equipment Ord
T
Mech. equipt supply
T
Bldg Strl Fabrication
T
Mech. Eqpt supply started on 06.01.16

Design Engg. in progress.

Drawing

Total

BE (A)
DE I
TOTAL

Compl.Dt. 28.02.14

Submtd

9
116
96

DE (A)

221
Activity

Likely Completion : Mar16


Proj. Mgr Alok Rai, DGM- 0792

Agency-M/s Unitech Machines Ltd.,Gurgaon


Cost : Rs. 11.64 Crs.
Contract signed: 02.04.13
Cont. Compl. : 01.04.14.
Likely Completion: Mar16
Proj. Mgr V.K.Rai, DGM- 0563

129
Activity

Consultant MECON

Fire Protection System For BOF and CCP


(Pkg. 126-01) Consultant MECON

9
5
21
12

DE I

Agency- M/s Voltas, Jamshedpur.

C 23

Appd/KFR

14
7
46
25

DE (A)
Total

Submtd

19
17
50
43

BE I

Proj. Mgr - N.V.Joshi, DGM-0799

Cost: Rs 39.92 Crs.


Contract Signed on 31.08.12.

Total

BE (A)

Contract no . TK/2011/343
Consultant- MECON
Agency M/s OGPE
Cost : Rs. 9.18 crs
Cont. signed: 19.04.11
Effective Dt. of contract: 16.03.11
Contl. completion: 15.03.12
Likely Completion : Mar16

C 22 Air Conditioning and Ventilation System For


BOF & CCP Complex (Pkg.125-01)

Drawing

Mech. Eqpt. Ordering


Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Mech. Eqpt. erection

Appd/KFR

6
94
78
178

Unit

Total vol.

Comtd.

1
0
4
3
8
Jan16
Plan

3400
1070
300
50
300
50

7
103
85
195

T
T
T
T

AAN

150
250
AAN

2
0
8
2

25

12
Cum Prog

120

Comntd.

1
4
6
11
Jan16

2700
230
290
40
120
0
U/S

BE (A)
BE I
DE (A)
DE I
Total

13
39
48
3
103
Activity

13
36
45
3
97
Unit

Cum Prog

885

Plan
-

175

50

31.67

885

30

480

885

10
30
38
2
80
Total vol.

Prog.
-

696.7
Mech. Eqpt. Ordering
T
5.1
Elect. Eqpt. Ordering
T
696.7
Mech. Eqpt. Supply
T
5.1
Elect. Eqpt. Supply
T
Mech. Eqpt supply started on 05.01.16

1/12/2016

Page : 18

1
0
0
0
1
Jan16
Plan

0
0
0
0

Review meeting held on 08.12.15

0
2
1
3

885

Mech. Eqpt. Supplied started from 16.10.14. Electrical ordering startred from 04.03.15. Mech. Eqpt
erection started on 09.11.15. Piping work started on 29.12.15.
Drawing
Total
Submtd Appd/KFR
AAN
Comtd.
U/S

Review meeting held on 11.12.15

Prog.

30

0
3
0
3

U/S

2
2
13
8

2
5
7
1
15

0
1
0
0
1
Cum Prog

Prog.

340

661.5
4.86
340

Review meeting held on 03.11.15.

SN

SCHEME / PACKAGE
D 1 Installation of Buffer Vessels and
Pressure Reducing & Metering Stn. for
Oxygen, Nitrogen & Argon (Pkg. 075B)
Consultant-MECON,
AgencyM/s Blue Star Ltd, Kolkata & BHPV,
Visakhapatnam
Contract price Rs. 51.39 Crs.
Contract signed: 07.07.12 (Eff. date 06.07.12)
Contr. Completion : 05.07.13
Likely Completion : Jan.16
Proj. Mgr. R.K. Baghel, DGM, 3571

Important activities completed / Highlights

D2 Instn. Of Oxygen Evacuation Facilities


for 2x1250 TPD New Oxygen Plant
Consultant CET
Agency: M/s Bluestar, Kolkata.
Contract value: Rs 29.26 Crs.
Contract Signed : 18.03.11
Cont. Completion : 17.03.13
Likely Completion : Jan.16
Proj. Mgr. R.K. Baghel, DGM, 3571

Important activities completed / Highlights

D3 Augmentation of Propane Storage &


Distribution System for SMS-II
(Consultant-BEDB)
Agency: M/s Gas Projects, Mumbai

Contract value: Rs 73.41 Lakhs


Contract Signed : 12.09.14
Cont. Completion : 11.03.15
Likely Completion: Jan.16
Proj. Mgr. R.K. Baghel, DGM, 3571

PROGRESS ON DATE

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings
BE (A)
DE (A)
DE I

Total
12
91
58
161

Total
Additional drawings
DE (A)
71
DE I
14
Total
85
Activity

Submtd.

Appd/KFR

AAN

12
91
55
158

10
80
45
135

0
8
1
9

2
3
9
14

0
0
0
0

70
9
79
Unit

65
8
73
Total
vol.
14050*
1673*
292*

3
0
3

2
1
3

0
0
0
Cum.
Prog.
13950
1580
260

Earth work
Concreting
Tech. Strl. Fabrication

M3
M3
T

Tech. Strl. Erection


Mech. eqpt. Ordering
Elect. eqpt. Ordering
Mech. eqpt. Supply
Elect. eqpt. Supply
Mech. eqpt. erection
Elect. eqpt. erection

T
T
T
T
T
T
T

292*
1860*
2.2*
1860*
2.2*
1860*
2.2

Comntd.

Jan.16
Plan
100
70
10

Prog.

U/S

30

230

0
0
0
0.2
30
0.3

1860
2.2
1847
1.8
1768
1.7

Review meeting held on 03.09.15

SCOPE REVISED AS PER CHANGE ORDER


SCHEME.

Erection of all 20 Vessels completed by 15.04.14. 2 nos. 100 m3 Argon, 6


nos. Erection & hydraulic testing of all 20 nos. vessels completed on
18.09.15.
Drawings
BE (A)
DE (A)
DE I
Total
Activity

Total
10
138
133
281

Submtd.
10
138
133
281
Unit

Appd/KFR
10
138
133
281
Total
vol.
9500
950
410

AAN

Comntd.

0
0
0
0

0
0
0
0
Jan.16

Plan
-

Prog.

U/S

Review meeting held on 03.09.15.

0
0
0
0
Cum.
Prog.
9500
950
410

Earth work
Concreting
Tech. Strl. Fabrication

M3
M3
T

Tech. Strl. Erection


Mech. eqpt. Supply
Elect. eqpt. Supply
Mech. eqpt. Erection
Elect. eqpt. Erection

410

410

T
T
T
T

561.3
2
561.3
2

561.3
2
561.3
2

All 97 Towers & 19 Bridges supplied & erected by 15.02.14. Structural


fabrication and erection completed by 15.02.14. Civil work completed
by 15.03.14. Equipment supply & erection completed on 14.11.15.
Drawings
BE
DE
Total
Activity

Total
4
9
13

Mech. Eqpt. ordering


Mech. Eqpt. supply
Mech. Eqpt. erection

1/12/2016

Submtd.
4
9
13
Unit
T
T
T

Page : 19

Appd/KFR
4
9
13
Total
vol.
6
6
6

AAN

Comntd.

0
0
0

0
0
0
Jan.16

Plan
-

Prog.
6
6
2

U/S
0
0
0
Cum.
Prog.
6
6
2

Kick-off meeting held on 21.10.14.

SN

E
E1
2.1

SCHEME / PACKAGE

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

SP & OHP Zone


Modernization of SP-II (Pkg.-021) (Consultant MECON)
New Cold Sinter Screening System &
Conveyor SS-1 & SS-2 Conveyor width
Hearth layer feeding arrangement
extension work is in progress.
under Modernization of SP-II (Pkg.-21
Foundation for take-up tower for SS-1 &
A)
SS-2 conveyor is in progress.
Agency: M/s Petro General Engg.
works & M/s Sanmathy
Consultant-MECON
Contract signed: 05.06.10,
Cost: Rs. 22.86 Crs.
Contr. completion: 04.12.11.
Likely Completion: Jan.16

Proj. Mgr. Mr. P. K. Sutaone, DGM


22567.
*- Scope revised
2.2

ESP Based Plant De-dusting system under


Modernization of SP-II (Pkg.21 D)
(Agency- M/s Scintillant Projects)

COMMITMENT AS PER LATEST MOM

Stage-II approved on 06.05.10, Sanctioned Cost Rs. 40.72 Crs.


Drawings

Total

Submtd.

122
6
65
142
335

BE (Appl.)*
BE (Info.)
DE (Appl.) *
DE (Info.) *
TOTAL

Appd/KFR

120
6
64
135
325

Activity
Concreting
Bldg. strs. Erection
Techno. Strs. Erection
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

119
5
58
130
312

M3
T
T
T
T
T
T

Review meeting held on 24.12.14.

Comntd.

0
0
3
1
4

1
1
3
3
8

Jan.15

Total
vol.
*1400
*383
* 461
*267
*20
*267
*20

Unit

AAN

Plan
25
3
82
1
3
68
12

Prog

11

13

U/S

0
0
0
1
1
Cum.
Prog.
1375
380
390
266
17
212
8

Slab cast at +19M level of screen Bldg. on 04.04.15.


RPN issued
23.12.14.

to

M/s

Scintillant

on

Consultant-MECON
Cost: Rs. 7.99 Crs.
Contract signed on: 19.06.10,

Drawings

Total

BE (Appl.)*
BE (Info.)
DE (Appl.) *
DE (Info.) *
TOTAL

Activity

Contr. completion: 18.12.11.

21
2
56
70
149

Unit

Concreting
Techno. Strl erection
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Proj. Mgr. Mr. P. K. Sutaone, DGM


22567.

Submtd

21
2
57
72
152

M3
T
T
T
T

Total
vol.
400
60
19.25
582
19.25

Appd/KFR

AAN

21
2
56
66
145

0
0
0
0
0
Jan.15

Plan
0
0
0
0
0

Comntd
0
0
0
4
4

Prog

U/S
0
0
0
0
0

Cum.
Prog.
350
57
18.75
543
13

RPN issued to M/s Scintillant on 23.12.14.


E2

Revamping of Sinter Cooler of SP-3


Agency - M/s Primetals Technologies India
Pvt. Ltd., Kolkata & M/s Primetals
Technologies, Austria, Consultant-CET,
Cost: Rs. 26.15 Crs. & Euro 626,048.00
Contract signed on: 13.08.15
Contr. completion: 12.12.16
Proj. Mgr. Mr. P. K. Sutaone, DGM 22567.

Design & engg. is in progress.


Dismantling/cutting of sinter cooler
duct of machine No. 1 in progress (80
% Completed).

Drawings

Total
6
6
3
26
41

BE (Appl.)
BE (Info.)
DE (Appl.)
DE (Info.)
TOTAL

Submtd
4
2
0
2
8

Appd/KFR
4
0
0
0
4

AAN
0
2
0
2
4

Comntd
0
0
0
0
0

U/S
0
0
0
0
0

Revised Drawing & equipment list has been submitted by M/s Primetals
on 16.11.15. Site activities inaugurated by GM I/c (Projects) on 19.11.15.

1/12/2016

Page : 20

The following activities have been completed.


Activity Unit
Progress
Earth work M3
870
Bldg. Strl. fabrication
T
8
Bldg. Strl. Erection
T
8
Techno. Strl fabrication
T
60
Mech. Eqpt. Ordering
T
582
Elect. Eqpt. Ordering
T
19.25
Mech. Eqpt. Supplied
T
582

Review Meeting held on 20.11.15.

SN

SCHEME / PACKAGE

E3

Augmentation of OHP Part-A (Pkg.


060)

PROGRESS ON DATE
Commissioning activity in progress.
Defect rectification job in progress.

(Agency M/s HEC)


(Consultant MECON)
Contract signed on: 09.04.08,
Contr. Compl.: 08.04.10
Cost: Rs 184.74 Crs.
(Proj. Manager Mr. R.K. Malve DGM),
57068/22684

Total

BE (Appl.)*
BE (Info.)
DE (Appl.) *
DE (Info.) *
TOTAL

126
22
295
215
658

Activity
Earth work
Concreting
Bldg. Strl. fabrication
Bldg. Strl. Erection
Tech. Strl. Erection
Mech. Eqpt supply
Mech. Eqpt Erection
Elect. Eqpt Erection

*- Scope revised

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Submtd. Appd/KFR
AAN
Comntd
U/S
122
0
4
0
126
22
0
0
0
22
293
0
2
0
295
214
0
1
0
215
658
651
0
7
0
Jan.15
Cum. Prog.
Total
Unit
Plan
Prog.
vol.
M3
*68050
37
68013
M3
*19700
1
19699
T
*3451
1
3450
T
*3451
30
3340
T
*503
3
500
T
* 2600
10
2590
T
* 2600
40
2458
T
*1960
40
1717

The following activities have been completed.


Activity Unit
Progress
Tech. Strl. fabn. T
503
Elect. Eqpt supply

1960

WT No. 5 inaugurated by Chairman on 18.06.13. PAC (part facilities


New Wagon Tippler No. 5 with SAC, belt conveyors J1C1/C2, J3C3/C4,
J3SC3/SC4, J4C3, J4SC3, J5C3 with mobile tripper, STC-3 & TBS, JH-5B,
HTSS-54, LTSS-1&2 & LTSS-3 &4) issued on 27.08.14 w.e.f. 14.07.14. Trial run
of Twin Boom Stacker at load taken on 11.09.15. PAC of bucket wheel
reclaimer issued on 12.08.15 wef 27.07.15. PAC of Conveyor R101 &
R102, Shuttle Conveyor J3-SC1 & J3-SC2, Conveyor J9A-C1, Shuttle
Conveyor J9A-SC1, Junction House JH-9A, Foot Over Bridge & Area
Repair Shop issued on 10.12.2015 w.e.f. 07.11.15.
E4

Augmentation of Raw Material receipt


& handling facilities with New OHP,
Part-B (Pkg. 061)
Agency M/s EPI
Consultant MECON
Contract signed: 30.04.10,
Cost: Rs. 525.86 Crs.
Contr. Completion: 29.04.12.
Likely completion : Feb.16
(Proj. Manager-A.K. Bhatta DGM),
Mob. No. - 22169
*- Quantity revised.

Civil work for Conveyor Z & L - series is


in progress.
Civil work for LT substation Bldgs. are in
progress.
Erection of Bldg. structures is in
progress.
Mech. Eqpt. Erection at Stacker & Reclaimer yard in progress.
Techno. Strs. Erection at Yard area, Zseries conveyor & Track Hopper are in
progress.
Elect. Equipment erections at LTSS Bldg.
No. 1, 2 & 4 are in progress.
Excavation for Junction House L-10 is in
progress.

Drawings
BE (Appl.) *
BE (Info.)
DE (Appl.) *
DE (Info.) *
TOTAL

Total

Submtd

334
25
457
642
1458

297
18
530
496
1341

1/12/2016

Page : 21

Appd/KFR

AAN

Comntd

U/S

15
10
38
1
0
0
96
46
58
8
14
1
97
120
70
Jan.15
Cum.
Activity
Unit
Total vol.
Prog.
Plan
Prog.
Earth work
M3
*375000
1140
372780
Concreting
M3
*100888
1264
157
99664
Bldg. strs. Fabrication
T
*14597
983
11906
Bldg. strs. Erection
T
*14597
1164
139
8618
Techno. Strs. Fabrication
T
*4487
356
3808
Techno. Strs. Erection
T
*4487
687
593
Mech. Eqpt Ordering
T
*3946
296
3650
Elect. Eqpt Ordering
T
*1589
209
1380
Mech. Eqpt Supply
T
*3946
350
3559
Elect. Eqpt Supply
T
*1589
200
1170
Mech. Eqpt Erection
T
*3946
440
5
2917
Elect. Eqpt erection
T
*1589
250
4
161
WT Complex: Rotational drive system flushing jobs of WT completed on 18.06.15. No
load rotational trial of Wagon Tippler (only upto 45 degree) taken on 24.06.15. Long
travel trial run, movement of Boom Conveyor & Luffing of Boom of Stacker No. 4B
conducted on 26.08.15. Trial & Testing of Twin Boom Stacker No. - 5B conducted
successfully on 30.09.15. Trial run of Wagon Tippler with Side Arm Charger (without
wagon) taken on 01.01.16. Erection of 1 span conveyor gallery of conveyor Z12C1/C2 across the Tandula Canal completed on 07.01.16. Excavation for Junction
House L-10 started on 09.01.15.
234
17
330
473
1054

Review meeting held on 14.12.15.

SN

SCHEME / PACKAGE

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

COMMITMENT AS PER LATEST MOM

F. BF ZONE

F1

Installation of BF-8 Capacity 2.8 MT /


Annum, useful vol. 4060 M3 (Pkg.-010)
(Agency M/s Paul wurth /L&T)
Consultant - MECON
Cost: Rs. 1591.32 Crs
Contract signed: 30.08.10,
Contr. completion: 29.12.12
Likely completion: Feb.16
(Proj. Mgr. Mr. B.K. Prasad DGM) 20271
*- Scope revised.

F2
2.1

Drawings
BE (Appl.)*
BE (Info.) *
DE (Appl.) *
DE (Info.) *

Total

517
1204
3026
3507
8254

TOTAL
Activity

Unit

Earth work
M3
Concreting
M3
Bldg. Strs. Fabrication
T
Bldg. Strs. Erection
T
Techno. Strs. Fabrication
T
Techno. Strs. Erection
T
Mech. Eqpt Ordering (Imp.)
T
Mech. Eqpt Ordering (Indig.)
T
Elect. Eqpt Ordering (Imp.)
T
Elect. Eqpt Ordering (Indig.)
T
Refractory Ordering (Imp.)
T
Refractory Ordering (Indig.)
T
Mech. Eqpt Supply (Imp.)
T
Mech. Eqpt Supply (Indig.)
T
Elect. Eqpt Supply (Imp.)
T
Elect. Eqpt Supply (Indig.)
T
Refractory Supply (Imp.)
T
Refractory Supply (Indig.)
T
Mech. Eqpt. Erection
T
Elect. Eqpt. Erection
T
Refractory Erection
T

Submtd

Appd/KFR

501
1159
3024
3449
8133

473
1092
2804
3322
7691

Total vol.

*260000
* 81000
*24785
*24785
*20404
*20404
*4223
*8757
54
*510
*2144
21022
*4223
*8757
54
*510
*2144
21022
*12980
*564
23166

AAN

7
2
85
24
118

Comntd.

Jan.15
Plan

Prog

355
100
186
400
13
30
0
7
50
145
5
500

U/S

21
65
122
91
299

21
4
9

150
21
74

0
0
13
12
25

Likely completion: Jan.16

Combustion Air Fans & Gas Mixing Station


(Pkg-TK-06)
Contract signed on: 13.04.13
Agency: M/s TLT Engg India Pvt. Ltd., Kolkata,
Cost: Rs. 4.72 Crs.
Contr. Completion: 12.07.14

18/19 Civil & 25/27 Mech.).


Drgs status (Evotechs Scope) 50/83
submitted, 31 Appd, 1 AAN, 18
commented.
Erection of Stove shell is in progress.

Front is not available for site activity.

Review meeting held on


16.12.15.

Cum. Prog.

260000
80666
24785
24002
20404
19711
4223
8757
54
510
2144
20622
4210
8706
51
502
2144
20500
12272
552
22178

Leakage testing of cooling water circuit No. 3 of BF-8 completed on 03.10.15. 1 No. 2 MVA Transformer
(57A-1T) 6.6KV/0.433 KV, at Central Contrl Room along with PCC 57-A charged from HTSS - 57, feeder No. 617 on 06.10.15. 2 Nos. 2 MVA Transformer (56J - 1T & 2T) 11 KV / 0.433 KV at GSTS-1 along with PCC 56J
charged from HTSS No. - 56 feeder No. - 12 & 55 on 10.11.15.

Up-gradation of Stoves No. 10, 11 & 12 of Blast Furnace #4 (Proj. Mgr. S.K. Ghosh, DGM) 20274 (Consultant CET), Stage-II approval received on 12.03.13 at a sanction cost of Rs. 70.65 Crs.
Jan.15
HTS design for Achieving Higher Hot Blast
Total issued drgs by CET -152/162 Nos.
Activity
Unit
Total vol.
Cum. Prog.
Plan
Prog
Temperature (Pkg. WP-01)
(52/54 Strl, all 7 Utility, 50/55 Refractory,
Award letter No.: 5(2934)/349,
Date of Award :16.03.13
Agency : Evo Tech, Bhilai Award value Rs. 18.44 Crs,
Contr. Completion: 15.11.14

2.2

Refractory erection at Bustle pipe, Hot Blast


outlet of Stoves & Hot Blast Main is in
progress.
Dry slag pit: Heat resistance concreting at
south side pit No. 1 is to be done.
Erection of expansion joint in Gas-line &
Cooling circuit pipeline at BF Shell in
progress.
Erection of supporting strs at PCI area in
progress.
Testing of cooling water circuit No. 2B is in
progress.
INBA - Erection of structures & equipment
are in progress.
Stock House area Erection of Screens,
under size Chute is in progress.
Laying of cable from HTSS-56 is in progress.
Erection of hydraulic system is in progress.
Erection of vibro feeder at Stock House is in
progress.
Gas duct erection in progress.
Erection of valves at BF gas for stove is in
progress.
Erection of Gas Main at TRT area & motor for
Shuttle conveyor at Stock House is in
progress.
21 M3 Concreting completed.
1 T Bldg. Strs. Erected.
1 T Techno. Strs. Erected.
1 T Mech. Eqpt. Erected.
3 T Refractory erected.

Review
Meeting
15.07.15.

held

on

Earth work
M3
1900
0
200
Concreting
M3
377
75
136
Techno. Strl Fabrication
T
995
60
165
Techno. Strl Erection
T
995
75
165
Pkg. No. SP-02 Stove Refractory Material (18 items) 2210.7T/7274.47T Supplied.
Pkg. No. SP-03: -16.2/48.6T Columns, 17.1/51.3T Girders & 27.9/83.7T Grids supplied.
Pkg. No.SP-04: All 15 Stove Valves, Lubrication & Hydraulic system (1 No. each) supplied.
Pkg. No. SP-05 Expansion joints: - All 5 Nos. Expansion joint supplied. Casting of both CA fan

foundations completed on 16.10.15.


Drawings
Total Submitted
25
25
DE (Appl. Cat.)
25
24
DE (Info. Cat.)
TOTAL
50
49
Activity

Likely completion: Mar.16

Mech. Eqpt Supply


Elect. Eqpt. Supply

Apprd /KFR
23
20
43

Unit

Total vol.

T
T

43.5
22.7

11 No. BE (Appl.) & 3 No. BE (Info). Drgs approved.

1/12/2016

Page : 22

AAN
1
1
2

Commented
0
3
3
Jan.15

Plan
-

Prog

U/S
1
0
1
Cum. Prog.
43.5
22.7

Review Meeting held on


11.04.14.

SN

2.3

SCHEME / PACKAGE

Electrical, Instrumentation & Automation


System (Pkg-TK-07)
Contract signed on: 24.04.13
Agency: L & T, Kolkata, Cost: Rs. 8.36 Crs.
Contr. Completion: 23.12.14

PROGRESS ON DATE
Design
engineering,
equipment
ordering & supply is in progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

BE
DE (Apl. Cat.)
DE (Info. Cat.)
TOTA

14
58
31
103

Likely completion: Jan.16

Submitted

Approved /KFR

AAN

Commented

U/S

14
52
15
81

13
39
5
57

1
5
2
8

0
6
7
13

0
2
1
3

Activity

Unit

Total vol.

T
T

* 64
* 64

Elect. Eqpt. Ordering


Elect. Eqpt Supply

Jan.15

held

on

Review meeting
04.12.15.

held

on

Review Meeting
05.01.15.

held

on

Cum. Prog.

Prog

Plan
0
0

Review meeting
30.10.14.

61.5
57.4

7 Nos. Ventury supplied at site.


F3

Installation of Hot Metal Handling System


For Blast Furnace (Pkg-031)

Site activity held-up by sub-contractor


of M/s AIFL.

Drawings

Total

BE (Appl. Cat.)*

78
110
94
371
653

BE (Info. Cat.)*
DE (Appl. Cat.)*
DE (Info. Cat.)*
TOTAL

Consultant - MECON
(Agency M/s Qinhuangdao Qinye Heavy Ind.
with Associated Industrial Furnace,
Cost: Rs. 108.20 Crs.
Contract signed: 10.09.10,
Contr. completion: 09.05.12
Likely completion: Jan.16
(Proj. Mgr. Mr. B.K. Prasad DGM) 20271

*- Scope revised.

Submitted

Approved /KFR

AAN

Commented

U/S

77
110
88
371
646

62
110
78
368
618

15
0
1
0
16

0
0
9
3
12

0
0
0
0
0

Activity

Unit

Total vol.

Earth work
Concreting
Bldg. Strs. Fabrication
Bldg. Strs. Erection
Techno. Strs. Fabrication
Techno. Strs. Erection
Mech. Eqpt Ordering (Indig.)
Elect. Eqpt Ordering (Indig.)
Mech. Eqpt Supply (Imp.)
Mech. Eqpt Supply (Indig.)
Elect. Eqpt Supply (Imp.)
Elect. Eqpt Supply (Indig.)
Refractory Supply (Imp.)
Refractory supply (Indig.)
Mech. Eqpt. Erection
Elect. Eqpt. Erection

M3
M3
T
T
T
T
T
T
T
T
T
T
T
T
T
T

*12000
*4700
*875
*875
*265
*265
*370
100
2200
*370
25
100
*1474
717
*2570
125

Jan.15

Plan

Cum. Prog.
Prog.

0
55
3
25
6
0
-

10990
4622
875
872
265
190
364
100
2200
295
25
75
1374
168
2308
54

0
2

All imported items 2200 T Mech. Eqpt. & 25 T Elect. Eqpt. Ordered. Refractory ordering
(Imported & Indig.) completed. Erection of all 12 Nos. TLC (Torpedo Ladle Car)
completed by 31.05.15. Rail Laying at TLRS (566 RM completed). Sheeting job (6410
Sq. M out of 7000 Sq. M. completed).

F4

Modification of Stack Cooling system of BF


No. 7.
Consultant CET
Agency M/s Danieli Corus (Netherlands), M/s
Danieli Corus India (New Delhi) & M/s Beekay
Cont. cost: Rs. 11.023 Crs & Euro 28.69 Lakhs.
Contract signed: 16.09.13
Contr. completion: 15.08.14
Likely completion: 28th Feb.16
(Proj. Mgr. Mr. P.K. Ghosh DGM) 21144

*- Scope revised.

Front is not available for site activity.

Drawings
BE (Appl. Cat.)
BE (Info. Cat.)
DE (Info. Cat.)
Total

Total

Submtd

Appd/KFR

6
20
20
46

6
20
20
46

6
20
20
46

Activity

Unit

Refractory Ordering (Indig.)


Refractory Ordering (Imported)
Mech. Eqpt Supply (Indig.)
Mech. Eqpt Supply (Imported)
Elect. Eqpt Supply

T
T
T
T
T

Total vol.

*40
*107.8
61
273
0.17

AAN

Comntd.

U/S

0
0
0
0

0
0
0
0

0
0
0
0
Jan.15

Plan

Prog

0
-

Cum. Prog

0
107.8
61
273
0.17

All 6 Nos. BE (Appl. Cat.), 20 Nos. BE (Info. Cat.) & 20 Nos. DE (Info. Cat.)
Drawings have been approved. All Elect. Eqpt. & Mech. Eqpt. (Indig. &
Imported) ordered & Supplied.

1/12/2016

Page : 23

SN

SCHEME / PACKAGE

F5

Installation of Cast House Defuming system


in Blast Furnace No.7 (Consultant CET)

PROGRESS ON DATE

Design engg. is in progress.

Drawings

BE (Appl. Cat.)
DE (Appl. Cat.)
DE (Info. Cat.)
Total

Agency- M/s Uniseven Engg. & Infrastructure


Pvt Ltd, Kolkata and M/s Soil & Enviro
Industries Pvt Ltd, Kolkata
Cont. cost: Rs. 21.67 Crs
Contract signed: 21.08.15
Contr. completion: 20.08.16
(Proj. Mgr. Mr. P.K. Ghosh DGM) 21144

F6
6.1

OVERALL STATUS AS ON DATE


Approved /
Submitted
AAN
KFR

10
46
62
118

10
9
11
30

5
2
0
7

COMMITMENT AS PER LATEST MOM


Commented

U/S

5
5
5
15

0
2
6
8

0
0
0
0
Jan.15

Activity

Unit

Total vol.

Plan

Review meeting
08.01.16.

held

on

Cum. Prog.
Plan

Mech. Eqpt Ordering


T
450
List of drawing AAN on 04.11.15.

21

21

Stage-II Approved on 16.02.11 at a cost of Rs. 21.27 Crs. (Rev. on 10.09.13) with completion period 14 months(Apr.12)
Rebuilding of Stove No. 18 of BF-6 (Consultant CET)
Total
Submtd
Appd/KFR
AAN
Comntd.
U/S
Electrical,
Instrumentation
&
Supply of balance Electrical equipment Drawings
BE
(Appl.)
20
20
16
1
3
0
Automation (Pkg-5)
(HT, LT Cable and Vacuum Contactor
DE (Appl.)
37
36
31
3
2
0
Agency: Hindustan Controls & Eqpt. P. Ltd.
Panel) is to be done.
DE (Info) *
TOTAL

Contractual cost: Rs. 2.53 Crs.


Contract signed: 18.03.11
Contr. completion: 17.05.12
Likely completion: Jan16
(Proj. Mgr. V.K. Gawande, Sr. Mgr.) 22711

F7

Total

Installation of Dedusting system for


Reversible Shuttle Conveyor area of BF-7
Stock House (Consultant-EDD)

22
79

Activity

20
76

Unit

19
66

Total vol.

0
4

1
6

Jan.15
Plan

0
0

Cum. Prog.
Prog.

Elect. Eqpt Supply


T
24
1.5
22.5
Elect. Eqpt Erection
T
24
2
22
All Elect. Eqpt. Ordered. Trial of Gas Bleeder valve through PLC taken on 23.07.14.

Contract signed with M/s Enviropol Engineers Pvt. Ltd., Noida on Kickoff meeting held on 29.12.15.
08.12.15 at a total price of Rs 1,56,67,039/- with completion period 9
months.

Agency - Enviropol Engg. Pvt Ltd., Noida


Contractual cost: Rs. 1.56 Crs.
Contract signed: 08.12.15.
Contr. completion: 07.09.16
Proj. Mgr. D. Srivastava, DGM

G. POWER ZONE
G 1 Augmentation of MSDSs & Installation MSDS-5:
Lighting jobs in progress.
of MSDS-VII (Pkg.-070)
Charging of outgoing feeders upto reactors
Contract No. TK-2008/282
are in progress (For sections 4 to 9 - 30 feeders
(Consultant-MECON)
are charged including 3 reactors for
(Agency M/s Alstom)
buscouplers).
Cont. signed on : 25.09.08
Control cable laying and termination at MSDS-1
Contr. Completion : 24.09.10
(for 132 KV outgoing feeder to MSDS-4) is in
progress.
Cost: Rs. 216.25 Crs.
PAC issued on 19.03.15 w.e.f. 03.02.15.
Likely completion: Jan.16
(Proj. Mgr. Mr. P. Subba Rao, DGM) 21090

Retrofit job:
At MSDS-II, dismantling of old panels is being
carried out for erection of 132 KV panels of 80
MVA Transformer -1T.
At SS 31 (MSDS-3), door preparation jobs for
retrofit of 6.3 MVA-3 T in progress.

Change
order
for
capacity MSDS-5:
enhancement of MSDS-4 & MSDS-5
Lighting jobs in progress.
under Augmentation of MSDSs -7 (Pkg.
70) Dt. Of issue of change order: 11.10.11,
Contract Price: 4.57 Crs.
Contractual Completion: 10.09.12.

Likely completion: Jan.16

*- Scope revised.

Jan.15
Cum.
Plan
Plan
Progress
Elect. Eqpt. supply
T
2425
1.5
2423.5
Mech. Eqpt. Erection
T
580
3
577
Elect. Eqpt. Erection
T
2425
23.5
2401.5
All 955 Nos. Drawings have been approved. Preliminary Acceptance Certificate
(PAC) for subject contract issued on 19.03.15 w.e.f. 03.02.15.
Retrofit jobs: Door Retrofit job of 11 KV Cubicle-2 (Spare feeder) at MSDS-2
completed on 24.10.15.
MSDS-4: Inauguration of MSDS-4 done by CEO, BSP on 29.10.13.
MSDS-5: 3 Nos. 11 KV feeders charged upto outgoing of reactors (Cubicle No. 103,
110 & 133) at MSDS-5 on 24.11.15. 6.6KV Section-2 connected Neutral Earthing
Transformer at MSDS-5 charged on 26.11.15. Charging of 16 MVA Transformer-2T
done on 08.01.16.
MSDS-7: 132 KV charged cable from MSDS-5to7 Normalised on 06.09.14. SAS Testing
completed.
MSDS-2: 6.6KV Bus Coupler (Cubicle 640) charged on 22.12.15.

Activity

Activity

Concreting
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Unit

Unit

M3
T
T
T
T

Total vol.

Total vol.

640
7.5
40.7
7.5
40.7

Jan.15

Plan

Prog

Cum.
Progress

1.5
1
1.7
1
2

GF, 1st & 2nd floor brick work, Ground floor flooring completed.

1/12/2016

Page : 24

638.5
6.5
39
6.5
38.7

Review
26.06.15.

Meeting

held

on

SN

SCHEME / PACKAGE

G2

Installation of HT Distributed SubStation (Pkg. 071-A)


(Agency M/s ABB)
(Consultant-MECON)
Cont. signed on : 02.09.11
Contr. Completion : 01.05.13
Contract price: Rs. 339.61 Crs.
(Proj. Mgr. P. Subba Rao, DGM) 21090
Likely completion: Jan.16

*- Scope revised.

PROGRESS ON DATE
Auxiliary Eqpt. Erection at SSs - 43, 45, 47,
48, 56, 57, 60, 64, 65, 68, 71, 71A & 73 are
in progress.
Bldg. Structural Fabrication & erection job
is in progress.
6.6 KV Panel testing at SS-63 is in progress.
Incoming cable laying in progress for SS73.
6 M3 Concreting completed.
8 T Bldg. Strs. Fabricated.
5 T Bldg. Strs. Erected.

PAC (Part facility) for HT SS No. 43 &


48 issued on 26.12.14 w.e.f.
01.10.14.

G-3 Instn. of Boiler along with Steam


Turbo-Blower Bldg. (Pkg.- 011-1A)
Consultant-MECON
Agency-M/s Fujian Long King Co. China
/Allied Energy Sys., New Delhi
Cont. price: Rs. 282.28 Crs.
Contract signed: 24.03.12
Contractual Completion: 23.11.13
Likely Completion : Feb.16
(Proj. Mgr. : P. Subba Rao, DGM), 21090

STB building: Aliignment of pipe in STB-2 in


progress.
Feed Pump House cum Electric annex
(FPH cum EA) Column & beams erection
job in progress.
All 3 boilers: Casing, structures, duct work,
pipe lines welding job in progress.
CPRG: Trestles 3-19 erected. PGs & CGs
erected between Tr. Nos 3 to 14.
Boiler-1 & 2: ID Fan/FD Fan foundation
jobs (Total 8 fans) completed.
HVAC
area
Staircase
&
column
shuttering.
0.3 T Structures erected.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Total
127
2
1103
260
1492

Drawings
BE (Appl. Cat.)*
BE (Info. Cat.)*
DE (Appl. Cat.)*
DE (Info. Cat.)*
TOTAL

Activity
Earth work

Submtd. Appd/KFR
127
120
2
1
1069
1014
260
220
1458
1355
Total
Unit
vol.
M3 *133492
M3
*32091
T
*10400

AAN
3
1
26
38
68

Comntd
4
0
29
2
35

Jan.15

Plan

Prog

U/S
0
0
0
0
0
Cum.
Progress

Review
07.09.15.

Meeting

held

on

Review
20.11.15.

meeting

held

on

3000
123894
Concreting
700
82
30647
Building strs. Fabrication
600
69
9010
Building strs. Erection
T
*10400
900
52
7067
Mech. Equipment ordering
T
128
24
104
Electrical eqpt. ordering
T
*6116
41
6075
Mech. Equipment Supply
T
128
10
104
Electrical equipment supply
T
*6116
2
6050
Mech. Equipment Erection
T
128
20
1
46
Electrical Eqpt. Erection
T
*6116
800
42
3110
Total 7638 T Fabricated Strs. Supplied. 3 Nos. 11 KV outgoing feeders
(cubicle No. 25, 31 & 79) at HTSS No. - 64 charged on 03.12.15.
Charging of cubicle 62 (LTSS-7) at SS-70 completed on 10.12.15.
Charging of 11 KV cubicle 32 (1 MVA Transformer in ECR-0) done in SS70 on 15.12.15. Charging of Feeder-14 and Transformer 70I-1T at SS-70
done on 16.12.15. Charging of Incomer-1 of LTSS-7 in ECR-3 through SS70 done on 16.12.15. First time charging of 6.6 KV cubicles No. 612, 616,
629 & 630 (Feeding to 250 KW cooling water pump house) in SS-56
done on 21.12.15.
Drawings

Total

Submtd.

Appd/KFR

AAN

BE (A)
BE I
DE (A)
DE I
Total

241
94
575
442
1352

241
94
575
442
1352

181
69
416
375
1041

7
1
6
5
19

Comntd.

U/S

45
8
18
6
144
9
51
10
258
33
Jan.16
Cum.
Activity
Unit
Total vol.
Prog.
Plan
Prog
18
32098
32500
500
Earth work
M3
29
12267.9
12500
400
Concreting
M3
3879
3916
109.6
Building strs. Fabrication
T
20.3
3787.3
3916
150
Building strs. Erection
T
5200
5402
193
Mech. Eqpt ordering
T
250
515
23
Elect. equipment ordering
T
4406
5402
650
Mech. equipment supply
T
242
515
20
Elect. equipment supply
T
700
1.5
4045
5402
Mech. equipment Erection
T
80
117.5
515
Elect. equipment Erection
T
MV/LV Switchgear building 8 m floor RCC slab cast on 20.05.15. MCC building 12
M slab casting and 3 Nos. column casting done on 12.06.15. STB building 0-0 M
level floor casting done on 27.06.15. MCC control room building 16 M slab casting
done on 17.07.15. CEA Inspection of electrical facilities carried out on 20.9.2015.

1/12/2016

Page : 25

SN

G4

SCHEME / PACKAGE
PROGRESS ON DATE
Instln. of Steam turbine generator, STG area
back pressure turbine generator,
Hydro test for steam pipe lines completed.
Cooling water system & Power
Instrumentation jobs in progress.
Evacuation Sys. (Pkg.- 011-1B)
CWPH: Erection of all 5 pumps completed.
Consultant-MECON
Main header jobs are in progress.
Agency-M/s Triveni Engineering.
Maintenance platform completed.
Contract Price Rs. 170.50 Crs.
Cooling Tower: Crane Load Testing
Contract signed: 19.01.12
completed. Makeup water line work in
Contractual Completion : 18.07.13
progress. Backwash line work is in progress
Likely Completion : Jan.16
in STB building.
(Proj. Mgr. : P. Subba Rao, DGM), 21090
ECR: Erection of cable tray & cable laying
is in progress. Instrumentation jobs in
progress. FDA system is in progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

Submtd.

BE (A)
BE I
DE (A)
DE I
Total

74
37
147
720
978

74
37
147
720
978

Activity

Appd/KFR
74
37
147
710
968

Unit

Earth work
Concreting
Piling
Building strs. Fabrication
Building strs. Erection
Mech. Eqpt ordering
Elect. equipment ordering
Mech. equipment supply
Elect. equipment supply
Mech. equipment Erection
Elect. equipment Erection

AAN

Total vol.

M3
M3
Nos.
T
T
T
T
T
T
T
T

41000
14061
340
1770
1770
1410
500
1410
500
1410
500

Comntd.

0
0
0
2
2

0
0
0
8
8
Jan.16
Plan
Prog
1570
563
0
21
0
0
6
1
1
91
38
23.5

U/S

Review meeting held on 10.09.15.

0
0
0
0
0
Cum.
Prog.
39430
13504
340
1770
1749
1410
500
1406
499
1357
489

Mech Eqpt 1 Condenser, 1 Deaerator, 2 EOT cranes, 1 Turbine & PRDS


station, Ejector erected. Elect eqpt Alternator Reactors, HT reactor
isolator panel, DCS, AVR, Turbine control panel erected. PRDS and
Ejectors erected in BPTG. 25 MW STG rotated successfully on barring
gear on 29.5.2015. Casting of 25 MW SSF Over Head Tank foundations
done on 09.06.15. CEA Inspection of electrical facilities of Pkg 11-01B
carried out on 20.9.2015.
G5

Installation of 3x225 m3/h DM water


Plant for PBS (Pkg.11-1C)
Consultant-MECON
Agency-M/s Technofab Engg Ltd/ M/s ARTES
INGEGNERIA SPA, Italy
Contract Price Rs. 27.70 Crs.
Contract signed: 25.02.12
Contractual Completion : 24.02.13
Likely Completion : Jan.16
(Proj. Mgr. : P. Subba Rao, DGM), 21090

Piping work of CIP tank in progress.

Drawings

Total

Submtd.

BE (A)
BE I
DE (A)
DE I

60
8
220
112
400

60
8
219
112
399

Total

Activity

Appd/KFR
60
8
219
112
399
Unit

Total vol.

AAN
51
7
205
98
361

Comntd.
4
0
4
3
11

Jan.16
Plan
Prog

U/S
4
1
9
10
24
Cum.
Prog.

Earth work
M3
7300
95
7205
Concreting
M3
3000
78
2922
Building strs. Fabrication
T
30
0
30
Building strs. Erection
T
30
0
30
Mech. Equipment ordering
T
650
0
650
Elect. equipment ordering
T
30
0
30
Mech. equipment supply
T
650
8
642
Elect. equipment supply
T
30
0
30
Mech. equipment Erection
T
650
12
638
Elect. equipment Erection
T
30
5
25
Plant is in operation for DM water supply to Coke Oven battery # 11
from stream B & C. Generation of DM water from stream B done for a
continous period of 32.5 Hrs.

1/12/2016

Page : 26

Review meeting held on 03.12.15.

SN

SCHEME / PACKAGE

G6

Installation of Turbo-blower for BF No. 8


(Pkg.-012)
Consultant-MECON
Agency: M/s BHEL
Contract price: Rs. 256.75 Crs.
Contract signed: 11.11.10
Contractual completion:10.02.13
Likely completion: : Jan.16
(Proj. Mgr. : P. Subba Rao, DGM), 21090

PROGRESS ON DATE
Unit#1- cold blast pipe line jobs & oil line
jobs in completion stage. Common cold
blast collector supply to BF#8 - pipe line
erection job is in completion stage.
Unit#3- Condenser surge pipe drain pipe
line modification work completed.
Condenser-Impulse
tubing
jobs
in
progress. Oil flushing in progress. Cold
Blast Line Bellow erection job completed.
Transmitters Governor- Oil tubing at 4.5
mtr under progress. TR.9 all transmitter
gland & termination work under progress
Instrument job & caliberation in progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

BE (A)
BE I
DE (A)
DE I
Total

33
19
37
148
237

Submtd.
33
19
37
148
237

Activity
Earth work
Concreting
Piling
Mech. Eqpt. Ordering
Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Appd/KFR
29
18
26
130
203

Unit

Total vol.

M3
M3
Nos.
T
T
T
T
T
T

4800
1700
88
1590*
347*
1590*
347*
1590*
347*

AAN

Comntd.

1
3
0
1
7
4
0
16
8
24
Jan.16
Plan
Prog
157
40.5
25
29.3
59

U/S

Review meeting held on 30.01.15.

0
0
0
2
2
Cum. Prog.
4643
1659.5
88
1590
347
1565
347
1560.7
288

Mech. Eqpt. Erected -- 3 turbines, 3 blowers, 3 condensers, 3 Hot wells,


3 steam ejectors, 3 gland steam condensers, 3 oil coolers, 3 oil tanks, 3
oil pumps stations. Suction air filter housing erected. CEP-1 & 2 RCC
trench completed.
H IATRS Zone
H-1 Inter Plant Tele-communication System
(Server based) thro fibre optical
network (Pkg-037)
Consultant-MECON,
AgencyM/s Equant Technology Services
Contract price Rs. 10.15 Crs.
Contract signed: 12.07.12.
Contr. completion : 11.01.14
Likely completion : Jan16
(Proj. Mgr. M.V. Subramanyam, DGM), 22557

Cabling work in progress for Phase-2.

Drawings

Total

Submtd.

BE (A)
BE I
DE (A)
DE I
Total

4
11
54
24
93

4
11
54
24
93

Activity

Appd/KFR
4
11
50
18
83

Unit

Total vol.

T
T
T
T

53
53
28
25

Eqpt. Ordering
Eqpt. Supply
Eqpt. Erection Phase-I
Eqpt. Erection Phase-II

AAN

Comntd.

0
0
0
0
0
4
0
4
0
8
Jan.16
Plan
Prog
0.5
8
7

U/S

Review meeting held on 13.10.15.

0
0
0
2
2
Cum. Prog.
53
52.5
25
0

Software configuration at all 3 exchanges completed. UPS and battery


installation work completed by 05.06.15. Sector-9 and Sector-5
exchanges commissioned by 15.06.15.
H-2

Energy monitoring system (Pkg.-075A)

Drawings

Total

Submtd.

Appd/KFR

Consultant-MECON,

BE (A)
BE I
DE (A)
DE I
Total

4
1
22
9
36

4
1
22
9
36

4
1
20
3
28

AgencyM/s Masibus Automation


Contract price Rs. 3.47 Crs.
Contract signed: 30.05.12.
Contr. completion : 29.05.14
Likely completion : Jan.16
(Proj. Mgr. M.V. Subramanyam, DGM), 22557

Activity
Eqpt. Supply
Eqpt. Erection

Unit

Total vol.

T
T

4.9
4.9

AAN

Comntd.

0
0
0
0
2
0
0
6
2
6
Jan.16
Plan
Prog
0.9

U/S
0
0
0
0
0
Cum. Prog.
4.9
4

All 18 nos. RTU connected with Central Energy Monitoring system. UPS
charged on 22.05.14. OPC server installed at OP-II for BOO plant
parameters.

1/12/2016

Page : 27

Review meeting held on 30.10.14.

SN

H-3

SCHEME / PACKAGE
Installation of Hot metal Rail Weigh Bridges
(Pkg-099B) Consultant-MECON,

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

AgencyM/s Sartorius Mechatronics


Contract price Rs. 1.94 Crs.
Contract signed: 14.05.14.
Contr. completion : 13.05.15
Likely completion : Mar16
(Proj. Mgr. M.V. Subramanyam, DGM), 22557

Drawings

Total

BE (A)
BE I
DE (A)
DE I
Total

2
21
13
12
48

Activity
Eqpt. Supply
Eqpt. Erection

Submtd.

Appd/KFR

2
21
13
12
48

AAN

2
19
13
12
46

Unit

Total vol.

T
T

54
54

0
0
0
0
0

Comntd.

U/S

0
2
0
0
2

Jan.16
Plan
Prog
4
-

COMMITMENT AS PER LATEST MOM


Review meeting held on 26.02.15.

0
0
0
0
0

Cum. Prog.
50
0

Site work inaugurated on 02.03.15.


H-4

Installation of Rail & Road Weigh Bridges


(Pkg-099 A) Consultant-MECON,
AgencyM/s ACME Automation
Contract price Rs. 1.72 Crs.
Contract signed: 19.11.14.
Contr. completion : 18.11.15
Likely completion : Jan.16
(Proj. Mgr. M.V. Subramanyam, DGM), 22557

Finsihing work of weigh room for Road


Weigh Bridge 2 is under progress.
Civil work (foundation) for 2 number rail
weigh bridges is under progress.

Drawings

Total

BE (A)
BE I
DE (A)
DE I
Total

9
20
7
10
46

Activity
Earth work
Concreting
Eqpt. Supply
Eqpt. Erection

Submtd.

Appd/KFR

9
20
7
10
46

AAN

9
19
3
10
41

Unit

Total vol.

M3
M3
T
T

178
523
60
60

0
0
0
0
0

Comntd.

U/S

0
0
0
0
0

Jan.16
Plan
Prog

0
1
4
0
5

Review
15.06.15.

meeting

Cum. Prog.
170
300
60
30

100
-

Equipment supplied completed on 31.08.15.Eqpt erection started on


12.10.15. Erection of Road weigh bridge 1 is completed. Placement of
Road weigh bridge 2 is completed.
I. CIVIL SERVICES, TOWNSHIP & MINES ZONE
I-1 Providing a Space frame covering for
School Courtyard at Senior Secondary
School Sector-X of BSP (Consultant-BEDB)

M/S Alumax
responding.

new

Delhi

is

not Party has already submitted soft & hard copy of all drgs to BEDB.

Agency: M/s Alumax, New Delhi


Contract price Rs. 1.42 Crs.
Contract signed: 21.02.14.
Contr. completion: 20.02.15
(Proj. Mgr-: I.N. Wamhne, DGM), 22046

I-2

Appointment
of
consultant
for
development of Aquatic Centre near
Jayanti stadium ConsultantBEDB,
AgencyM/s ARCH-EN DESIGN Lucknow

Award Value Rs. 29.86 Lakhs.


Date of Award: 20.12.12.
Contr. completion: 19.03.14
Likely Completion: 19.03.16

Draft soft copy of specification & Award letter issued on 20.12.12. Draft soft copy of specification & tendor
tendor schedule sent by zone to Arch in schedule sent by zone to Arch in design for finalisation from their side on
design for finalisation from their side on 08.04.15.
08.04.15. Final report is awaited.

(Proj. Mgr-: D.K. Pouria, DGM), 21954

I-3

Construction of RCC Overhead Water Tank


(Capacity 1875 Cum) at Sector -2 in Bhilai
Township for TED
ConsultantBEDB,
Agency M/s Soul Engineers, Bhilai &
M/s Dubey & Goyal Company, Raipur
Contract signed: 12.07.14
Contract Price Rs. 2.92 Crs.
Contr. completion: 11.07.15
Likely Completion: Jan.16
(Proj. Mgr-: I.N. Wamhne, DGM), 22046

Reinforcment & shuttering for bottom


slab of water tank in progress.

Activity

Earth work

Unit

M3

Total vol.

800

Jan.16
Plan

Prog.

Cum. Prog.

500

Concreting
M3
800
50
400
Pipe laying
RM
223
0
Earth work completed on 01.12.14. Concreting work started on 15.01.15. Water
Tank: Plinth beam casting completed. Tie beam at 4 mtr. Level casting completed.
Office bldg: Plinth beam casting completed on 11.04.15. Casting of Lintel beam for
Office bldg. completed on 11.05.15. Casting of slab for Office bldg. completed on
13.06.15. Office bldg. of civil work completed on 07.08.15.

1/12/2016

Page : 28

held

on

SN

SCHEME / PACKAGE

J-1

J. UTILITY ZONE
Aug. of Power Supply facilities for BF
Slag dumps (Electrical Pkg.) (Pkg.-2).
Consultant BEDB

PROGRESS ON DATE

J-2

Agency: Infra-in consulting Pvt. Ltd.


Award value Rs. 18.87 Lakhs.
Date of award: 07.12.11.
Contr. completion : 06.03.14

COMMITMENT AS PER LATEST MOM

7 nos. HT Isolator, all cables, 5 nos. high mast light & GI pipe supplied

Balance Supply: LT & HT panel, Bus duct &


and 2 nos. high mast erections completed. Fabrication of Cable tray
battery charger.

completed. 3 nos. transformers supplied at site on 15.05.14. HT cable


laying completed.

Agency: Hindustan Controls & Eqpt. Ltd.


Award value. Rs. 3.06 Crs,
Date of Award :27.07.11,
Contr. Completion: 26.04.12
(Proj. Mgr. : N.C.Ray, DGM), 21359
Appointment of consultant for secured land
filling facilities for disposal of hazardous
wastes generated in BSP Consultant- BEDB

OVERALL STATUS AS ON DATE

M/s Infra-in consulting Pvt. Ltd has not Presentation of detail project report held on 15.10.12.
applied for further date extension to
complete the work.

(Proj. Mgr.: D.K, Pouriya DGM), 21954

J -3 Relocation of Bhilai Warehouse:


I
Dunnage work Phase-2A (Pkg-02).

Material collected. 25 T Strs. fabricated & erected

Consultant CET
Agency - M/s Sanjay Engr. & Fabricators

Award value Rs. 66.35 Lakhs.


Date of Award: 07.09.12,
Contr. Completion: 06.01.13
Likely completion: Jan.16
(Proj. Mgr.: D.K, Pouriya, DGM), 21954

II

Relocation of Bhilai Warehouse:


Civil & Structural work (Pkg-05).

Activity

Frant not available at site.

Consultant CET,
Agency - M/s BSBK
Award value Rs. 11.10 Crs.
Date of Award: 18.05.10,
Contr. Completion: 17.04.11
(Proj. Mgr. : G. Ravibabu, AGM), 22695

Unit

Total vol.

Earth work
Concreting
Brick work
Plastering
WBM
RCC Pipe Laying

M3
M3
M3
M2
M3
RM

39000
7000
2200
26000
22000
330

Rail track laying

RM

3000

Jan.16
Plan
Prog.
0
0
0
0
0
-

Cum. Prog.
37035
6595
2055
25680
22000
330
3000

Boundary wall: 885/898 columns cast. Pipe laying completed on 10.11.15.

J-4

Gas mixing & Booster Station (Pkg-076).


Consultant-MECON.
Agency-M/s NICCO Corporation,
Cont. Price Rs. 13.62 Crs.
Contract signed: 06.01.12
Contr. Completion : 05.01.13
Likely completion: Jan.16
(Proj. Mgr. : G. Ravi Babu, AGM), 22695

Drawings
BE A
BE I
DE A
DE I
TOTAL

Total

Submtd

15
30
67
56
168

14
30
66
51
161

Appd/KFR
14
29
64
51
158

AAN
0
0
2
0
2

Comntd
0
1
0
0
1

U/S
0
0
0
0
0

All Earth work 3300M3, All Concreting 950M3, All 75T Bldg. strs. fabrication &
erection , All 5T Tech. strs. fabrication & erection, all 270T Mech. eqpt. & 20T
Elect. eqpt. ordering, supply & erection completed, Equipment Erection
completed on 01.10.14. HT & MCC panel charged on 31.03.15. Engg. closer
meeting organized by MECON Ranchi on 10.09.14 to complete the engg.
issue. TOP connection completed on 14.04.15. Blower fan testing completed.

1/12/2016

Page : 29

Review
28.05.14.

meeting

held

on

SN

SCHEME / PACKAGE

J-5

Interplant fuel gas and industrial gases


pipeline for all units (Pkg. 075).
Consultant- MECON
Agency: M/s Tata Projects ltd.

Contract price Rs. 147.16 Crs.


Contract signed: 22.01.11
Contr. completion : 21.04.12

Likely Completion : Jan.16


(Proj. Mgr. Ashok kumar, DGM), 22184

J - 6 External Water Supply system for BOF


& CCP (beyond battery limit) (Pkg. 077-01).
Consultant- MECON
Agency M/s Aireff Detox Ltd.

Contract Price Rs. 113.49 Crs.


Contract signed: 29.06.12,
Contr. completion: 28.09.13
(Proj. Mgr.; Ashok Kumar, DGM), 22184
Likely completion: Jan.16

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

Design engg. in progress.


100 M3 Earth work completed.
6 M3 Concreting completed.
7 T Bldg. strs. fabricated.
4 T Bldg. strs. erected.
16 T Tech. strs. erected.
C-Zone: Civil work of only 2 trestle
foundations is balance.
Pipe ercetion at C zone in progress.
A-Zone: O2 line laying completed.
Welding
work
in
progress
(95%
completed).
N2 line ready for blowing & testing (OP-2
to MSDS4 PRMS).
B-Zone: Earth work & concreting for
trestle foundation in progress.
Shuttering
and
Reinforcement
in
progress.
Trestle, pipe erection in progress.
D-Zone: Earth work & concreting for
trestle foundation & back filing in
progress.
Shuttering
and
Reinforcement
in
progress.
Strl. erection in progress.

Design Engg. in progress.


WTP-1: All 22 nos. piles casting completed.
Sataircase & pump foundation work in
progress.
WTP-3: Thickner-A (BOF): Plinth beam casting
completed.
Thickner-B (BOF): column upto roof level
completed.
Thickner-C (BOF): slab casting completed.
Thickner -A&B (SRU): All footing completed.
SST PH plinth beam casting completed.
WTP-4: Excavation & PCC for SST in progress.
Plinth beam of SST pump house completed.
ECR: 21/22 nos. footing & plinth beam
completed.
WTP-5: All 25 nos. footing completed for MWPH.
80/88 nos. footing completed for common
pump house with emergency overhead tank.
Common pump house earth work in progress.
Casting of raft for emergency overhead tank in
progress.

Drawings

Total

BE (A)
BE I
DE (A)*
DE I*
Total

25
5
440
1878
2348

Activity

Submtd.

Appd/KFR

25
5
440
1878
2348

Unit

22
3
428
1753
2206

Total vol.

AAN

1
0
0
0
1

Comntd

U/S

1
1
0
108
110

1
1
12
17
31

Jan.16

Plan

Prog.

COMMITMENT AS PER LATEST MOM


Review meeting held on 08.07.14.

Cum.
Prog.

*100000
2000
750
96470
*16348
350
106
15944
*7305
300
54
5301
*7305
68
4164
200
10000
9098
0
10000
89
4133
250
37
0
36
3
0
2
37
36
0
3
2
0
37
10
0
3
0.5
0
Mech. & Elect. Eqpt. erection started on 26.09.15. BF gas DN 2200 for COB-11
deblanking & charging has been completed on 03.11.2015.
Zone-A: All 262 nos. trestle & girder erection completed, erection of pipe line
completed. Zone-B: 179 nos. out of 201 nos. foundation bolt lift, 117 nos. Trestle &
72/174 nos. girder erection completed, Erection of Pipe line 26% completed. ZoneC: 114 nos. out of 116 nos. foundation bolt lift & 89 trestle & 67/90 nos. girder
erection completed, Erection of Pipe line 56% completed. Zone-E: All 83 nos.
foundation bolt lift, 82 Trestle & 72 nos. girder erections completed Pipeline erection
95% completed. Zone-D: 155 no. out of 186 nos. bolt lift & 26/186 nos. trestle
erection completed.

Earth work
Concreting
Bldg. Strl. fabrication
Bldg. Strl. erection
Tech. Strl. fabrication
Tech. Strl. erection
Mech. Eqpt. Ordering
Elect. Eqpt. ordering
Mech. Eqpt. supply
Elect. Eqpt. supply
Mech. Eqpt. erection
Elect. Eqpt. erection

Drawings

Total

BE A*
BE I
DE A
DE I
TOTAL

66
23
234
184
507

Activity

M3
M3
T
T
T
T
T
T
T
T
T
T

Submtd

Appd/KFR

66
23
151
75
315

Unit

47
2
36
32
117

Total vol.

AAN

Comntd

U/S

4
0
34
0
38

12
19
58
40
129

3
2
23
3
31

Jan.16
Plan
Prog.
3000
1000
50

Cum. Prog.

*104000
78362
*30000
9435
*2800
*2800
*3000
1970
200
*530
450
10
*3000
54
115
80
*530
20
5
Eqpt. ordering & supply started on 17.02.15. WTP-1: All 22 nos. piles casting
completed. Casting of top slab of PH completed on 28.08.15. WTP-3: Earth work for
thickener started on 09.08.14. WTP-4: Excavation for Secondary settling tank started
on 12.03.15. Plinth beam of SST pump house completed. ECR:21/22 nos. footing &
plinth beam completed. WTP-5: All 25 nos. footing completed for MWPH. 80/88 nos.
footing completed for common pump house with emergency overhead tank.

Earth work
Concreting
Bldg. Strs. Fabrication
Bldg. Strs. Erection
Mech. Eqpt. Ordering
Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply

1/12/2016

Page : 30

M3
M3
T
T
T
T
T
T

Review
27.12.14.

meeting

held

on

SN

SCHEME / PACKAGE

J- 7 External Water System for Mills and Fire


Water Pump houses (Pkg-077-02).
Consultant- MECON
Agency M/s McNally Bharat Engg.,
Kolkata & Southern Cooling Tower,
Kolkata.
Contract Price Rs. 114. 30 Crs.
Contract signed: 22.09.12,
Contr. completion: 21.12.13
Likely completion: Mar.16
(Proj. Mgr.: - N.C.Ray, DGM), 21359

PROGRESS ON DATE

Design Engg. in progress.

Drawings

Total

3 M3 Concreting completed (Pedestle)

BE A
BE I
DE A
DE I
TOTAL

104
24
494
158
780

WTP-3: Cable gallery footing from S/S-68 to


ECR bldg. completed.
WTP-5: Raft concreting started on 13.08.15.
Scale pit 3rd lift of wall & trench concreting
in progress.
WTP-6: Concreting of cold sump slab 80%
Earth work
completed on 19.09.15.
Concreting of secondary settling tank wall Concreting
up to walkway lavel completed.
WTP-7: Concreting of wall for Pump sump &
common sump completed.

Activity

OVERALL STATUS AS ON DATE


Submtd
Appd/KFR
AAN

82
17
296
92
487

63
9
186
60
318
Unit

Total vol.

0
0
14
0
14

COMMITMENT AS PER LATEST MOM


Comntd

18
8
60
23
109

Jan.16
Plan
Prog

U/S

1
0
36
9
46
Cum. Prog.

87420
400
74259
URM
9916
27
8651
M3
350
BRM
9869
6412
Total Concreting
19785
350
27
15063
URM
260
236
Bldg. Strs. Fabtn
MT
20
BRM
260
0
Total Bldg. Strs. Fabtn.
520
236
URM
260
216
Bldg. Strs. Erection
MT
20
BRM
260
0
Total Bldg. Strs. Erection
520
216
URM
450
320
Tech. Strs. Fabtn.
MT
0
BRM
380
200
Total Tech. Strs. Fabtn.
830
0
520
URM
450
263
MT
20
Tech. Strs. Erection
BRM
380
0
Total Tech. Strs. Erection
830
0
263
Mech. Eqpt. Ord. (URM+BRM)
670
340
MT
Elect. Eqpt. Ord. (URM+BRM)
905
500
Total Eqpt. Ordering
1575
840
URM
320
200
Mech. Eqpt. Supply
MT
0
BRM
350
140
Total Mech. Eqpt. Supply
670
0
340
URM
400
260
Elect. Eqpt. Supply
MT
0
BRM
505
225
Total Elect. Eqpt supply
905
485
URM
320
20
180
MT
Mech. Eqpt. Erection
BRM
350
0
Total Mech. Eqpt. Erection
670
180
URM
400
15
250
Elect. Eqpt Erection
MT
BRM
505
0
Total Elect. Eqpt Erection
905
250
Mech. eqpt. erection started on 25.01.15. WTP-1: Civil work of WTP-1 in all respect
up to tie beam at RL 318.40 completed by 30.01.15. WTP-2: Casting of slab at
314m level completed on 10-11.01.15. WTP-3: - Casting of fan deck slab of WTP-3
cooling tower completed on 03.04.15.WTP-4: Casting of slab of pump house at
WTP-4 completed on 10.06.14. WTP-5: Raft concreting started on 13.08.15. PCC
work started on 29.05.15. Scale pit raft concreting completed on 16.07.15. WTP-6:
Concreting of secondary settling tank wall completed on 11.03.15. Hot sump
wall completed. Concreting of cold sump slab 80% completed on 19.09.15.ECR
(WTP-6 BRM area): Casting of slab for ECR completed on 11.06.15. Casting of air
washer slab for ECR completed on 15.09.15. WTP-7: SST completed. Concreting
of ICW Cooling Tower up to fan deck level completed. Casting of pump house
slab completed on 04.09.15. Concreting of slab for ECR bldg. at WTP-7 BRM area
completed.

1/12/2016

M3

Page : 31

Review meeting
05.09.15.

held

on

04-

SN

SCHEME / PACKAGE

J-8

Aug. of Make-up water and drinking water


system (Pkg. 078)

Consultant MECON,
Agency- M/s Vishwa Infrastructure,
Contract Price Rs. 90.04 Crs. + Revised cost
7.89 Lakhs., (Total cost 90.11crs.)
Contract signed: 01.10.11
Contr. Completion : 31.12.12
Likely Completion : Feb.16
(Proj. Mgr. VS Sai, DGM), 21216

PROGRESS ON DATE
Design Engg. in progress.
30 M3 Earth work completed.
4 M3 Concreting completed.
4 T Bldg. strs. fabricated.
2 T Tech. strs. erected.
Intake pump house: (Maroda-2)
ECR: Fixing of door & windows, rolling shutter
are balance.
Makeup water (IW) Pipe Route: Civil work for
pedestal & erection of Tech. pipe line (Dia.
900 mm) in progress.
Bend fabrication for Railway track crossing in
progress (at sheet 2 of 23 near MWPH),
Pipe erection at sheet 2 of 23 Railway track
crossing in progress (near MWPH).
MWPH: R/S for wall in progress.
Drinking water treatment plant:
Earth work for ECR (DWTP) 10/34 foundation
completed.
Trestle erection at Cable gallery from SS-71 to
DWPH in progress.
Concreting for cable gallery foundations
23/25 nos. completed.
Raw water pipe route: (Maroda -2 to DWPH).
1100/1200 Mtr. Pipe laying completed. Pipe
pushing (near intake PH under rail track)
completed & pipe laying in progress. Bend
erection at Raw water pipe route from intake
to DWTP in progress.

J-9

Construction of Railway siding and MGR Sys.


including earthwork, Construction of bridges,
supply of ballast and P-way linking in connection
with modernization of Peripheral Yard (Pkg.-95A)
(Sch.-A) ConsultantRITES,
Agency- M/s Jhajharia & Arcon,

of Railway Electrification work of existing/


proposed Railway Tracks Switching Post (SSP)
including modification of existing 25KV AC, 50 HZ
Single Phase Over-Head Equipment (OHE) (Pkg.
095A, Schedule - C) ConsultantRITES,
Agency- Bright Power Projects Pvt. Ltd., Mumbai

Total

BE A
BE I*
DE A
DE I
TOTAL

34
14
226
61
335

Activity
Earth work
Concreting
Bldg. Strs. fabrication
Bldg. Strs. Erection
Tech. Strs. supply
Tech. Strs. erection
Mech. Eqpt ordering
Elect. Eqpt ordering
Mech. Eqpt Supply
Elect. Eqpt Supply
Mech. eqpt. erection
Elect. Eqpt erection

Submtd

Appd/KFR

34
12
162
43
251

32
11
77
25
145

Unit

Total vol.

M3
M3
MT
MT
MT
MT
MT
MT
MT
MT
MT
MT

*50000
*15000
*1250
*1250
6000
6000
*550
*250
*550
*250
*550
*250

COMMITMENT AS PER LATEST MOM

AAN

Comntd

U/S

0
0
57
0
57

2
1
17
18
38

0
0
8
0
8

Jan.16
Plan

890
240
70
65
25
70
20
10
40
20
30
10

Prog

330
17
42

27

Review meeting held on 16.09.14.

Cum. Prog.

43998
9585
766
637
4622
3117
400
170
400
168
15
5

#Cum. Prog. Reconcioled by zone on 07.10.15. Hydraulic testing of Industrial water pipe 2X DN
200 MS PIPE at URM successfully completed on 09.12.15. Trail run of DN200 Make up water pipe
line up to URM -C1 done on 24.11.15. DWTP: Casting of Dirty Back wash water compartment
completed. Casting of Drinking water treatment plant Pump House slab completed on 10.09.14.
MWPH: Laying of DN 900mm pipe near Boria gate completed on 07.12.13. Intake PH: Erection of
gangway completed. Casting of top slab of IWPH completed on 12.01.15. ECR: casting of slab
completed on 15.09.14. Mech. & Elect. eqpt. supply started on 08.04.14. MCC panel for IWPH
supplied on 09.09.14. Mech. eqpt. erection started on 13.08.15. Elect. eqpt. erection started on
02.12.15.

Earth work at MGR & MOR line in progress.

Activity
Earth work
Concreting
Supply of Ballast
Dismtlg. of existing track
Laying of railway track

Award value Rs. 79.38 Crs.


Date of Award - 29.06.11.
Contract signed : 03.08.11
Contr. Completion : 28.12.12
Likely Completion : Jan.16
(Proj. Mgr.: D.K, Pouriya DGM), 21954

J-10 Design, Supply, Erection,Testing & Commissioning

OVERALL STATUS AS ON DATE


Drawings

Unit

Total vol.

M3
M3
M3
RM
TM

1080000
6130
103500
8000
41500

Jan.16
Plan
Prog
0
0
0
0
0

Cum. Prog.

Review meeting held on 23.09.14

912600
3661
75230
1400
24925

WT-5 - Main line (Western side) track connectivity completed & loco testing
completed on 29.04.13. 5 nos. out of 7 nos. Bridge deck slab completed.

Contract signed on 01.08.2015. Award letter issued to at a total cost of


Rs. 18,83,63,711.62 on 06.07.15 with completion period of 24 months.

Award value Rs. 18.83 Crs.


Date of Award 06.07.15.
Contr. Completion : 05.07.17
(Proj. Mgr.: D.K, Pouriya DGM), 21954

J-11 Railway track works for plant internal yard

Activity

(Pkg.-95B).

ConsultantMECON
Agency -M/s ISC projects Pvt. Ltd. Bhusawal
Contract Price Rs. 76.08 Crs. (4th revision)
Contract signed 18.08.10
Contr. completion; 17.02.13
(Proj. Mgr.; D.K, Pouriya DGM), 21954

Likely Completion : Mar.16

Earth work
Concreting
Supply of Ballast
Dismtlg. of existing track
Laying of railway track

Unit

M3
M3
M3
RM
RM

Total vol.

Jan.16
Plan

Prog

Cum. Prog.

150000
0
147835
5800
0
5458
79000
0
61000*
13500
0
11761
*37300
0
15500*
Track no. 18 near high line linking completed on 22.10.13. Line no. 41: track laying of
dump car line, Boiler coal line & escape engine line completed by 23.05.14.

1/12/2016

Page : 32

Review meeting held on 24.12.14.

SN

SCHEME / PACKAGE

J-12 Balance Railway track works for plant internal


yards at BSP, Bhilai (Pkg.-095B1)

ConsultantMECON
Agency -M/s Jhajharia Nirman Ltd.
Award value Rs. 16.91 Crs.
Date of award: 17.10.2015
Contract signed: 02.11.15.
Contr. completion; 17.07.2016
(Proj. Mgr.; D.K, Pouriya DGM), 21954

J-13 Road works & road culvert over Tandula


canal (Pkg-100-2)
Consultant MECON,
Agency: M/s HSCL
Award value Rs. 12.50 Crs.
Date of Award: 25.02.10,
Contlr. Completion : 24.02.11
Likely Completion : -------(Proj. Mgr. : S.S. Prasad, Mgr.), 22708

J-14 Construction of Fly Over at 3 locations &


road network (Pkg.-111-01)
Consultant MECON
Agency: M/s SP Singla Construction,
Contract Price Rs. 74.06 Crs. (Addition
sanction on 21.10.13 Rs. 8.03028 Lakhs)
Contract signed on 14.07.10
Contr. completion: 13.07.12.
Likely completion: Jan.16
(Proj. Mgr.- Ashok Kumar, DGM), 22184

J-15 Electrical enabling works at TDS-I & new


LT Substation near Boria Stores (Pkg.113)
Consultant MECON,
Agency M/s ABB
Contract price Rs. 26.18 Crs
Contract signed on : 01.05.08,
Contr. completion: 31.03.09
(Proj. Mgr. : N.C.Ray, DGM), 21359

PROGRESS ON DATE

Earth work for Track formation is in


Activity
progress.
Earth
work
600 M3 Earth work completed.
Suplly of Ballast
65 M3 Concreting completed.

M/s HSCL has not applied for Further


date extension to complete the work.
Road No. - 8 (URM area) at not
available at site.

Unit

OVERALL STATUS AS ON DATE


Jan.16
Total vol.
Plan
Prog

COMMITMENT AS PER LATEST MOM


Cum. Prog.

M3
137464
15000
5300
20900
M3
26000
4200
4200
Track Dismantling
TM
2336
Rail track Laying
TM
20500
1000
91
1791
Bhoomi poojan held on 19.10.2015. Earth work started on 07.11.15.Track
laying started on 28.11.15. Rail track Connectivity line from RSM to URM
1400 TM laying completed.
Jan.16
Activity
Unit
Total vol.
Cum. Prog.
Plan
Prog
Earth work
M3
210277*
10000
162575
Concreting
M3
4100
0
3979
Sub grade
M3
60200
1090
59110
Road carpeting
M2
72450*
0
49259

Review meeting held on 25.09.14.

Road carpeting behind PRO completed on 01.07.14. Survey for 8A, 8B & 8C
completed.

ROB No. 2: Road widening work from Drawings


CEZ to Boria road T junction in BE (A)
BE (I)
progress.
DE (A)

From Boria gate road T junction to TOTAL


Boria gate circle one side WMM
Activity
progress.
ROB No.- 3: Work of both side RE wall is
under progress.

Total

Submtd

28
2
95
125

17
2
52

Appd/KFR

AAN

13
2
47

71

62

2
0
3

Jan.16

Total
vol.

Unit

Comntd

2
0
2

U/S

Review meeting held on 18.10.14.

0
0
0

0
Cum. Prog.

Plan
Prog.
Piles
Nos.
344
0
127
Earth work
M3
260000
0
58600
Concreting
M3
26000
100
6
16392
Elect. Eqpt. ordering
T
33.8
0
9
Elect. Eqpt. supply
T
33.8
0
9
Elect. Eqpt. Erection
T
33.8
0
6
Bldg. Structural fabn.
T
28
0
10
Bldg. Strl. erection
T
28
0
8
Road WMM
M2
65000
0
15550
Road Carpeting (BM)
RM
4450
0
2350
F.O. No.-2: CEZ to Boria road T junction both side WMM completed. Road
widening work from junction to Boria gate in progress. F.O. No.-3: GAD submitted on
29.07.14. 11 nos. pier caps & 2 nos. abutment cap completed. Casting of 10th deck
slab completed by 30.05.15. F.O. No.-1: GAD approved from railway. Approval of
GAD awaited from NHAI.
Drawings
Total
Submtd.
Appd/KFR
AAN
Comntd
U/S

M/S ABB has submitted letter on


15.06.15
to
issue
commissioning BE (A)
BE I
certificate.

14
3
66
93

14
3
71
101
189

DE (A)
DE I
TOTAL

9
3
48
85

1/12/2016

Page : 33

Unit

145

0
0
2
7

0
0
0
0

22
9
0
Jan.16
Cum. Prog.
Plan
Prog
Earth work
M3
1284
1284
Concreting
M3
877
877
Elect. Eqpt. Supply
T
1185
1185
Elect. Eqpt. Erection
T
1185
1185
HM Tower: 18/19 nos. high mast tower charged by 29.03.13. 29/32 nos. CSS erection
completed by 08.02.14. Erection completed on 01.07.14
Activity

176

5
0
16
1

Total vol.

Review meeting held on 27.09.14

SN

SCHEME / PACKAGE

J-16 Installation of fire fighting system for


transformer installed in TDS-1 (Pkg.113A) Consultant MECON,

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

Design engg. is in progress.

COMMITMENT AS PER LATEST MOM

Communication protocol issued on 04.11.14. List of drawing & Billing Kick off meeting held on 14.11.14.
schedule approved, Power od attorney submitted. Land allotted for
stores at TDS-1. QAP approved on 15.12.15.

Agency M/s Vendere sales service Pvt. Ltd.


Contract price Rs. 44.82 Lakhs
Contract signed on : 29.10.14
Contr. completion: 28.04.15
Likely Completion: Apr. 16
(Proj. Mgr. : G.S. Wadhwa, Mgr), 21484

J-17 Data network and Intranet Services


(Pkg-117A).

Activity

Diversion/Piping of Outlet No-7, 14, 15


16 & 17 (Pkg.-118G).

Outlet no. 15: Concreting of manhole


top wall in progress.

Consultant- MECON,
Agency M/s Kulkarni & Sahu,
Award value of Rs. 9.39 Crs.
Date of award: 03.11.10,
Contr. Completion: 02.11.11
Likely Completion: Feb.16
(Proj. Mgr. : S.S. Prasad, Mgr), 22708

J-19

Recycling of Waste Water from Outlet-B


(Comprising of Outlet 8, 9 & 10) (Pkg-1)
for WMD. Consultant- BEDB,
Agency M/s Otto Projects Pvt. Ltd., Kolkata
Contract price Rs. 6.25 Crs.
Contract signed on: 17.10.14,
Contr. Completion: 16.01.16
(Proj. Mgr. : J.M. Palaiya DGM), 22577

J-20

Relocation of refractory storage shed from


near SP-3 to Boria Storage Complex (Pkg118P). Consultant- MECON,
Agency: M/s Hitesh Bhai Patel,

Award value Rs. 1.45 Crs.


Date of award: 07.01.12,
Contr. Completion: 06.07.12
Likely Completion : Feb.16
(Proj. Mgr. : Ashok D. Thawre, AGM), 21967

J-21

Civil & Strl. for Relocation of Mech. Repair


Shop & Quenching Car repair shop. (Pkg.
119-01)
Consultant- MECON, Agency; HSCL
Award value Rs. 3.797 Crs,
Dt. of Award : 19.08.09
Contr. Completion: 18.08.10
(Proj. Mgr. : D.K, Pouria, DGM), 21954

Total vol.

Jan.16
Plan
Prog
-

Cum. Prog.

1000
Earth work
M3
15.8
Elect. Eqpt. ordering
T
15.8
Elect. Eqpt. supply
T
15.8
Elect. Eqpt. Erection
T
Cable laying job completed. All work completed on 30.09.2014.
All work completed on 31.12.15.

Consultant- MECON
Agency- M/s HCL Info systems
Contract price Rs. 0.8137 Crs
Contract signed on : 30.04.11
Contr. Completion by : 29.08.11
(Proj. Mgr. : N.C.Ray, DGM), 21359

J-18

Unit

Activity

Unit

Total vol.

Earth work
Concreting
RCC Pipe laying

M3
M3
RM

129500
12110
1150

Jan.16
Plan
Prog
8000
400
0

11

1000
15.8
15.8
15.8

Cum. Prog.
63480
4900
1029

Outlet # 14 (850RM): 375 RM completed. Outlet # 15 (350RM): 320 RM pipe


laying completed by 16.04.14. All 9 nos. man holes completed. Outlet # 16:
All 70 RM pipe laying completed by 13.02.14.

M/s Otto Projects Pvt. Ltd., Kolkata has


not started the site activities as per the
schedule submitted by them. They
have not finalised the civil contractors.

Kick off meeting held on 31.10.14. Site organisation chart submitted on


08.12.14. QAP approvesd on 08.12.14. Name plate & numbering system, List
of drawing & document, list of equipment, P&I diagram approved
on13.01.15. Layout Plan, GA & cross section of plant submitted on 10.01.15.
Pert Network submitted on 29.01.15. L-2 Network submitted on 03.02.15.

Strl. erection completed.


Activity
Brick work in progress.
Earth
work
Erection of tie rod for sheeting in
Concreting
progress.
Strl. Fabrication
Strl. Erection

Unit

Total vol.

M3
M3
T
T

3700
1313
230
230

Jan.16
Plan
Prog
200
200
0

Cum. Prog.

Kick off meeting held on 31.10.14.

3125
450
230
230

Strs. erected started on 27.01.14 & completed on 20.11.15.

M/s HSCL has not applied for Further date


extension to complete the work due to
M/S HCEPL (Pkg.119-02) has not
completed the Elect. job.
Balance work:
Track connection from SS-21L to Q/Car
repair shop including RCC inspection pit.

Activity

Unit

Total vol.

Concreting
M3
2800
Brick work
M3
650
Road carpeting
M2
1800
Railway track laying
RM
150
Road carpeting completed on 21.12.11.

1/12/2016

Page : 34

Jan.16
Plan
Prog
0
0
0

Cum. Prog.
1740
606
1800
0

SN

SCHEME / PACKAGE

J-22

Elect. Power & Ventilation Facilities for


Mechanical Repair Shop & Quenching Car
Repair Shop (Pkg.119-02)

PROGRESS ON DATE

Electrical
progress.

Equipment

erection

in

Technological & Services for Relocation of


Mech. Repair Shop for CO&CCD (Pkg.
119-03)

M/s GAME has not applied for further Drawings


date extension to complete the work. BE (A)
BE I
DE (A)
TOTAL

Consultant MECON,
Agency: M/s GAME
Contract price Rs. 1.75 Crs.,
Contract signed on :13.10.09,
Contr. Completion : 12.04.10,
(Proj. Mgr. : D.K, Pouria, DGM), 21954

J-24

J-25

Dismantling of existing bldg./shed in old


administrative bldg complex, stockyard &
CMO for construction of Universal Rail Mill &
new CMO yard (Pkg.-120G)
ConsultantMECON, Agency-M/s Radha Constn.
Amount to be paid to BSP Rs. 1.71Crs.
Date of Award: 16.08.10,
Contr. Completion: 15.11.10
(Proj. Mgr. : G. Ravibabu, AGM), 22695
Relocation
of
printing
press
from
Old
Administrative bldg. to CEZ area (Pkg.-120N)
Consultant-MECON,

Agency M/s Sadani Enterprises,

COMMITMENT AS PER LATEST MOM


Cum. Prog.

48
Elect. Eqpt. Supply
72.1
0
31
Elect. Eqpt. Erection
T
All 200 M3 Earth work, 150 M3 Concreting & 72.1 T Elect. Eqpt. Ordered.
2 nos. PDB supplied. PDB erected at MRS.

Consultant-MECON,
Agency- M/s Hindustan Controls & Eqpt,
Contract price Rs. 2.519 Crs).
Contract signed on: 09.01.10,
Contr. Completion: 08.10.10
Likely Completion : ---------(Proj. Mgr. : N.C.Ray, DGM), 21359

J-23

OVERALL STATUS AS ON DATE


Jan.16
Unit
Total vol.
Plan
Prog
72.1
0
T

Activity

Total

Submtd.

7
19
3
29

7
14
1
22

Appd/KFR

7
14
0
21

AAN

Comntd.

0
0
0
0

U/S

0
0
1
1

0
0
0
0

Jan.16
Cum. Prog.
Plan
Prog
Dismantling of Eqpt.
No.
62
62
Relocation of Eqpt.
No.
40
0
22
Jan.16
Total
Activity
Unit
Cum. Prog.
vol.
Plan
Prog
Dismantling of sheet
M2
30000
0
26250
Dismantling of Railway track
MT
200
0
200
Dismantling of Boundary wall
RM
490
0
Dismantling of Railway track completed on 09.07.11. Case handles in arbitration.
Activity

Case handles in arbitration.

Unit

Total vol.

M/s Sadani Enterprises has not applied 10 nos. Machine commissioned successfully by 26.03.13.
for further date extension to complete
the work.

Contract Price Rs. 34.15 Lakhs.


Contract signed on 11.04.11,
Contr. completion: 10.10.11
(Proj. Mgr. : N.C.Ray, DGM), 21359

J-26

Replacement of NB 1200 mm mixed gas


pipe line from mixing station to
normalizing furnace. Consultant- CET,
Agency : HSCL
Award value Rs. 1.712 Crs.
Date of award: 06.12.11.
Contr. completion: 05.11.12
(Proj. Mgr. H.L. Ghidole, AGM), 20416

J-27

Civil & structural works for construction of


overhead pipe and cable gallery in URM
complex (Pkg. 77-02A) at BSP, Bhilai
Consultant- MECON
Agency : M/S HSCL Nirman Bhawan Bhilai
Award value Rs. 6161786 Lakhs.
Date of award: 18.12.15.
Contr. completion: 18.01.16

M/s HSCL has not applied for further


date extension to complete the work.

Activity

Earth work
Concreting
Fabrication of Strs.
Erection of Strs.
Fabrication of Tech. Pipes
Erection of Tech. Pipes

Column strengthening of all


Structural fabrication & erection in
Activity
progress.
Earth work
8 T Bldg. strs. fabricated.
Concreting
3 T Bldg. strs. erected.
Fabrication of Strs.
Erection of Strs.

Unit

Total vol.

M3
M3
T
T
RM
RM

705
215
135
135
1660
1660

Jan.16
Plan

Cum. Prog.
Prog

0
0
0
0
0
0

245
108
72
63
839
839

42 columns completed by 09.09.13.


Unit

Total vol.

M3
M3
T
T

2300
282
165
165

Jan.16

Cum. Prog.

Plan

Prog

165
165

93
58

2300
282
93
58

Earth work started on 16.12.15 & completed on 23.12.15. Concreting


work started on 19.12.15 & completed on 30.12.15.
Fabrication work started on 20.12.15. Erection started on 25.12.15.

1/12/2016

Page : 35

K1
K2
K3

SPECIAL PROJECT UNIT


Installation of Steel Processing Unit at Hosangabad (M.P.)
Installation of Steel Processing Unit at Ujjain(MP)
Installation of Steel Processing Unit at Gwalior (MP)

L.
SN
L1

STAGE-I approved schemes other than 7.0 MT expansion


SCHEME / PACKAGE
Setting up of a 1.0 Mtpa Pellet Plant along with Generated Iron Ore
Fines (GF) / Slime Beneficiation Plant at Dalli Mines of BSP
(Consultant-CET) (PCC-TK- P.H.Sharma, DGM) 20516

L2

L3
L4

L5

L6
L7

L8

SAIL Board has decided that the SPUs will be established with Joint Venture.

NIT
01.08.14

TOD
20.10.14

PBOD
10.03.15

BIDDERS
Consortium of MECON Ltd.,
Bangalore

Installation of On-line Marking Facility for Bloom Caster Machine-5


of SMS-II (Consultant CET)
(PCC-TK- R K Panigrahi, DGM) 20168

14.03.15

15.04.15

03.08.15

Addition of Facilities at First Floor in Steel Club Sector-8 at Bhilai


(Consultant EDD) (PCC NTK- P K Sur, AM) 23207
Modification of F-type block (24 unit/block) into 2F type block (having
12 unit/block) along with other renovation work
(Consultant TED) (PCC NTK- P K Sur, AM) 23207
Building and Infrastructure (Pkg.-1) for Setting Up of Static Facility
for Environmentally sound Management of PCB at BSP, Bhilai
(Consultant CET) (PCC-TK- R K Panigrahi, DGM) 20168
Flooring of EHT Yards (MSDS-I, II, III, IV, V & VI)-PSD
(Consultant EDD) (PCC NTK- Md. Naushad Aalam, DM) 22660
Geotechnical investigation & survey work (Pkg-1) for installation of
ESP in Sinter dispatch route of SP-II
(Consultant CET) (PCC NTK- Md. Naushad Aalam, DM) 22660
Installation of ESPs as replacement of Multicyclones for all 4 Nos of
Sinter Machine Sinter PlantII
(Consultant- CET) (PCC-TK- P.H.Sharma, DGM) 20516

22.06.15

22.07.15

01.10.15

Consortium
of
Maco {L-1 Cost : Rs 4,39,57,641 (NOC)}, CETs estimate : Rs. 8.76 Crs. (NOC)}
Documents forwarded to Shop on 03.10.15 for obtaining Stage-II
Corporation India Limited,
approval. L-1 bidder has been requested to extend the offer validity up to
Kolkata and Green Project S.r.I,
31.01.16, reply awaited. Reminder sent to party for the same.
Italy
Amkay Construction Co. , Bhilai
Letter sent on 20.10.15 for obtaining Stage II approval.

04.08.15

15.09.15

30.10.15

Speciality Protection, Bhilai

(L-1 Price Rs. 2.16 Crs, Estimate Rs 2.25 Crs)


Letter sent on 07.12.15 for obtaining Stage-II approval.

26.06.15

13.08.15

24.11.15

HSCL, Bhilai

01.07.15

30.07.15

16.11.15

HSCL

18.11.15

09.12.15

09.12.15

C&C Consulting Firm,


Kolkata

(Landed cost 30.88 Crs, Estimate 30.95 Crs.)


Case sent to Shop (PSD) on 11.12.15 for obtaining Stage-II approval.
Reminder sent to Shop (PSD) on 05.01.16 for the same.
(L-1 Cost -Rs. 5,15,27,496.86, Estimate Rs. 6,39,29,896.80 )
Letter sent on 31.12.15 for obtaining Stage-II approval
(L-1 Cost -Rs. 4.20 Lakhs, Estimate Rs. 5.91 Lakh )
Letter sent on 08.01.16 for obtaining Stage-II approval.

14.10.14

05.12.14

15.09.15

GEA Process Engineering (India)


Pvt.

30.11.15

Unicon Engineers, Coimbatore

L9

Upgradation of Waste Gas ESPs of Sintering Plant-III


(Consultant CET) (PCC-TK- R K Panigrahi, DGM) 20168

09.03.15

06.05.15

L 10

Replacement of Electrical drives, Panels & Control Systems by


modern state of the art systems for Slab Caster -3
(Consultant EDD) (PCC-TK- R K Panigrahi, DGM) 20168

28.03.14

16.05.14

L 11

Relocation of Nitrogen Vessels (7 Nos.) and installation of New


Pressure Reducing and Metering Station (PRMS) Package-II
(Consultant MECON) (PCC-TK- R K Panigrahi, DGM) 20168

19.12.14

05.02.15

1. KCS Private Limited, Rourkela


2 Parker Hannifin India Pvt. Ltd., Kolkata
3 Sterling and Wilson Limited.
4 L & T Ltd.
5. Siemens Ltd.
6. Danieli India Ltd
1. Tuaman Engineering Limited, Kolkata
2. Linde India Limited,Kolkata
3. Blue Star Limited,Kolkata
4. Sanmathi Enterprises,Bhilai
5. Bhilai Techneeds, Bhilai & Mechast Engrs,
Bhilai
6. Otto Projects Pvt. Ltd, Kolkata

1/12/2016

Page : 36

STATUS AS ON DATE
(L-1 Cost - 556.02 Cr., Estimate - 732.08 Cr.)
Proposal sent to Corporate Office on 26.03.15 for Stage-II approval.
MECON has extended the validity of their offer up to 31.01.16 and has
also confirmed extension of validity of Bank Guarantee towards EMD.
A meeting held on 31.12.15 between SAIL/BSP and M/s MECON led
Consortium regarding restructuring of their consortim for the package
(M/s Moorgate Projects Pvt.Ltd. being referred as consortium partner in
place of M/s Stemcor India & M/s Stemcor DMCC), party to revert back.

M/s GEA has extended validity of price and offer till 15.02.16.
M/s GEA vide email dt 04.01.16, regretted to give further discount and
requested to consider their quaoted price as final and the same has been
forwarded to CET for submission of price evaluation report.
(L-1 Cost Rs. 5.57 Crs, Estimate Rs. 7.78 Crs.)
RA report along with price break-up received from M/s Mjunction on
03.12.15 and sent to CET on 04.12.15 for price evaluation.
TC held on 23.11 / 27.11.15 for opening of offer of single eliglible
bidder, recommendation under approval.

All the 5 eligible bidders (M/s Bhilai Techneeds was ineligible bidder) have submitted
their confirmation of original price bid on 01.12.15.
TC held on 04.12.15 and recommended for conducting RA, recommendation is under
approval.
All the techno-commercial eligible and acceptable parties have been asked to extend
their offer validity up to 29.02.16 and EMD BG up to 30.06.16, confirmation for the
same received from all the bidders.

SN
L 12

SCHEME / PACKAGE
Replacement of Wet Type LD Gas Holder (Cap. 40,000 M3) by Dry
Type LD Gas Holder (Cap. 60,000 M3) Package-I
(Consultant MECON) (PCC-TK- R K Panigrahi, DGM) 20168

NIT
19.12.14

Installation of Gas Mixing Station of COB#3 in CO&CCD


(Consultant- CET) (PCC TK A.C.Rathi, DGM I/c) 21751

24.02.15

26.03.15

L 14 Installation of Coal Dust injection system in BF No-4


(Consultant-CET) (PCC TK V Anil Kumar, AGM) 20206

15.07.15

18.08.15

L 15 Development and operation of 14 MTPA Iron ore Mine at Rowghat of


BSP (Consultant- M/s aXYKno Capital Services Ltd)
(PCC-TK- A.C. Rathi, DGM I/c) 21751

06.05.15

31.08.15

L 16 Installation of ESP in Sinter Dispatch Route of Sinter Plant II (Pkg.II) (Consultant-CET) (PCC TK V Anil Kumar, AGM) 20206

04.08.15

22.09.15

L 17 Stack emission control for 2 nos of vertical shaft kilns of RMP-II


(Consultant-CET) (PCC TK R K Panigrahi, DGM) 20168

01.10.15

17.11.15

22.10.15

21.12.15

22.06.15

13.08.15

L 13

L 18 Re-building of COB No.7&8 in CO&CCD


(Consultant-CET) (PCC TK V Anil Kumar, AGM) 20206
a.
Battery Proper (Pkg-1)

b.

Oven Machines (Pkg-2)

TOD
05.03.15

PBOD

BIDDERS
1. Beijing Shougang Construction Group Co China Stewarts & Lloyds of India, Kolkata.
2 Motherwell Bridge Ltd., UK Gillanders Arbuthnot & Co Ltd, Kolkata
3. Bengal Tools Limited
4.Lazarus and Associates Ltd, UK and Maco
Corporation (India) Pvt. Ltd. Kolkata
1. Otto Projects Pvt. Ltd., Kolkata
2. Graduate Agro & Mech.Engineers, Bhilai
3. Technovations, Bhilai
4. Consortium of Mechast Engineers, Durg and Forbes
Marshall Pvt. Ltd., Pune
5. Instrumentation Ltd., Kota
6. Consortium of Oriental Nicco Projects
Private Ltd., Ahmedabad and Oriental
Enterprise Pvt. Ltd., Vadodara

1.
2.
3.
4.
5.

Oriental Nicco Projects Pvt. Ltd., Kolkata


Danieli Corus India Pvt. Ltd., New Delhi
Kuttner GmbH & Co KG, Germany
Paul Wurth India Pvt. Ltd.
China First Metallurgical Construction India
Pvt. Ltd
6. CISDI Engineering Co Ltd, China
1. Jaiprakash Associate Ltd., Noida
2. Theriveni Valencha JV, Tamil nadu
3 Lanco Infratech Ltd, Gurgaon
4. ACB (India) Ltd, Gurgaon
1.
2.
3.
4.
5.

1/12/2016

STATUS AS ON DATE
Documents of one of the eligible bidder. i.e. of M/s Bengal Tools
received from MECON on 30.12.15.
Documents of M/s MICCO received from MECON on 04.01.16.

TBEC meeting held on 30.11. 15, 09.12. 15 & 15.12.15.


Recommendation of TBEC received on 22.12.15.

TER issued on 10.11.15.


TBEC held on 30.11.15.
CBEC held on 01.01.16.

Clarification received from all bidders and the same has been
forwarded to Mines & Consulant by 02.11.15.

GEA Proces Engg (India) Pvt Ltd, Thane


Thermax Ltd, Pune
Bhilai Techneeds, Bhilai
Macmet Engineering Limited, Kolkata
Consortium of Enviro Care Filtration & System &
Atmastco Pvt. Ltd.
6. Unicon Engineers, Coimbatore
7. Uniseven Engg. & Infrastructure Pvt. Ltd., Kolkata
8. BTL EPC Ltd, Kolkata
9. Evo Tech Pvt Ltd, Bhilai
1. Evo Tech Pvt. Ltd., Bhilai
2. Uniseven Engineering Pvt. Limited, Kolkata
3. GEA Process Eng. (India) Pvt. Limited, Thane
4. RD Pollution Controls Pvt. Ltd., Hyderabad
5. Global Enviro Air Systems Pvt. Ltd., Hyderabad
6. Clair Engineers Private Limited, Hyderabad
7. Span Filtration Systems Pvt. Ltd
8. Macmet Engineering Limited, Kolkata
9. Aswathi Industries Ltd., Mumbai

TER issued on 15.12.15.

1. Consortium of Paulwurth India Pvt. Ltd., New


Delhi along with M/s Paulwurth Italia SpA, Italy
and N.P.Construction, Bokaro
2. MECON Ltd., Ranchi
3. Bhilai Engineering Corporation Ltd., Bhilai
4. Consortium of Beekay Engineering Corporation,
Bhilai along with Sinosteel Equipment &
Engineering Co. Ltd., China
5. Larsen & Toubro Limited, Kolkata
1. Beekay Engg. Corpn., Bhilai - Gosa Fom, Serbia
2. Taiyuan Heavy Industry Co. Ltd. - Associated
Industrial Furnaces (P) Ltd.
3. Graduate Agro & Mechanical Engineers, Bhilai
4. Bhilai Engineering Corporation Ltd., Bhilai
5. Paulwurth Italia SpA - Paulwurth India Pvt. Ltd. Larsen & Toubro Ltd.

Technical Comments sent by CET to bidders on 08.01.16.


Technical discussions scheduled at CET, Ranchi during 14.0118.01.16.

Page : 37

Techno-commercial discussions held with bidders at BSP, Bhilai


by 05.01.16.

TC held on 09.01.16 for deliberating the representation of M/s


Beekay Engineering Corporation.
Copy of TC MOM sent to CET on 09.01.16 for their
recommendation.

SN
c.

SCHEME / PACKAGE
Replacement of By-Product Plant Equipment (Pkg-3)

NIT
22.07.15

TOD
05.10.15

PBOD

Supply of Design & Engineering Drawings, Providing Expert


Supervision, Performance Guarantee and Inspection of Refractories at
Suppliers premises (Pkg-4)
Enabling Works for COB#7 (Pkg-5)

22.07.15

01.08.15

22.12.15

22.06.15

01.08.15

L 19 Modification of End Forging Plant to produce Forged Junction Rails


at RSM (Consultant CET) (PCC TK P.H.Sharma, DGM) 20516
L 20 Raising of Perimeter wall at various locations of BSP
(ConsultantCED) (PCC NTK- Md. Naushad Aalam, DM) 22660
L 21 Route relay inter locking by Solid state Interlocking signaling system
for internal railway yard (Re-tendered)
(Consultant- RITES, Gurgaon) (PCC NTK- Satya Prakash, DM) 22738
L 22 Delinking of Sewerage Systems of Main Hospital, Hospital Sector
&Talpuri Areas from Hudco Network and Diverting it to Supela Pump
House at Sector- 6 in Bhilai Township.
(Consultant- EDD) (PCC-TK- P.H.Sharma, DGM) 20516

16.11.15

26.11.15

02.01.16

30.01.16

d.

e.

BIDDERS

STATUS AS ON DATE
Technical discussions held with bidders at CET, Ranchi during
02.11-07.11.15 and on 16.11.15.
Commercial discussion held with bidders during 14.11-20.11.15
and on 26.11.15.
Reminders have been given to bidders on 28.11.15, 03.12.15,
11.12.15, 14.12.15, 17.12.15, 22.12.15, 24.12.15 & 25.12.15 for
submitting pending commercial documents/ clarifications.
Issuance of TER awaited

1. Consortium of Beekay Engg. Corporation, Bhilai -Hutni


Projekt, Frydek-Mistek, Czech Republic
2. NCC Limited, Hyderabad
3. Nuberg Engineering Ltd., Noida
4. Oriental Nicco Projects Private Ltd., Kolkata
5. Beijing Shougang Construction Group - Stewart & Lloyds
of India Ltd.
6. MECON Ltd., Ranchi
7. Gillanders Arbuthnot & Co. Ltd., Kolkata - JSC Vukhin,
Russia
8. BTL EPC Ltd., Kolkata
9. Paul Wurth India Ltd.-DMT GmbH & Co. KG
10. Shriram EPC Ltd., Kolkata - Baosteel Engineering &
Technology Group, China
11. Consortium of Bhilai Techneeds, Bhilai, Shanxi Qiyuan
Chemical Engineering Design Co. Ltd., Taiyuan and China
Metallurgical Engineering & Project Corporation, Beijing.

CUI, Ukraine

{L-1 Price Rs. 52.97 Crs (NOC), Estimate Rs 40.62 Crs (NOC)}
Price negotiation scheduled on 12.01.16.

1. Rosy Enterprises Pvt. Ltd., Rourkela


2. West India Construction Company, Bhilai
3. HSCL, Bhilai
4. A.K.Dutta & Co. Pvt. Ltd., Jamshedpur
5. Consortium of Sanmathi Enterprises, Bhilai &
S.B.Construction (P) Ltd., Rourkela
6. N.P.Construction, Bokaro
7. Beekay Engineering Corporation, Bhilai

08.01.16

Revised price bids submitted by all the 5 techno-commercially


eligible bidders i.e M/s Beekay Engineering Corporation, M/s
WICC, M/s A.K.Dutta & Co. Pvt. Ltd., M/s N.P.Construction &
M/s HSCL on 06.01.16.
TC meeting held on 07.01.16 for conducting RA among above 5
techno-commercially eligible bidders.
Physical price bid opened on 08.01.16.

Hydraulico, Denmark

Tender uploaded on SAILs website on 02.01.16 and due date of


opening is 30.01.16.
TC held on 16.10.15 for cancellation of tender, approval received
on 27.10.15 and the tender has been cancelled.
TC recommendation approved on 19.10.15 to cancel the present
tender and reprocess the case with revised TS, Eligibility Criteria
and scope of work and the same has been informed to PHE-PSD &
EDD for necessary action.
Revised proposal sent by PHE Deptt. in Nov15 is under
examination of EDD.
CEOs recommendation for dropping the case has been sent to GM
(Projects), Corporate Office on 24.12.15, further reply awaited.

L 23 Replacement of Analogue Thyristor System with Digital DC Drive


System for DC Motors of Stands 1D to 12D Mechanisms of Merchant
Mill (Consultant- EDD) (PCC TK P.H.Sharma, DGM) 20516
L 24 Construction of retaining wall for active waste dump at Dalli Mech.
Mines. (Consultant- Mines) (PCC NTK- A.K.Agrawal, DM) 23219
L 25 Replacement of 6 nos. conventional lathes by 3 nos. 5 T CNC
lathes for MM & WRM rolls in RTS
(Consultant-CET) (PCC-TK- A.C. Rathi, DGM I/c) 21751
L 26 Up-Gradation of Sinter Machine-1 of Sintering Plant II
(Consultant CET) (PCC-TK V Anil Kumar, AGM ) 20206

Case is dropped on 18.12.15.


TC held on 30.10.15 and recommendation approved on 30.10.15
for cancellation of the tender. The same has been communicated to
PP&E on 31.10.15 for further process.
TC held on 01.10.15 & 20.10.15 to cancel the present tender,
recommendation approved on 24.10.15 and the same has been
communicated to Shop for further necessary action.
TC recommendation approved on 15.09.15 for dropping the
tender and the same has been communicated to Shop on 18.09.15
for further processing.
TC held on 01.04.15 for cancellation of subject tender, TC MOM
approved by ED I/c (Projects) on 08.04.15.

L 27 Repl. of Stands 6 & 8 with Housingless Stands in Merchant Mill


(Consultant CET) (PCC-TK A C Rathi, DGM I/c) 21751
L 28 Installation of Secondary Emission Control for three Converters in SMS-II
(Pkg-2) -Civil Works
(Consultant CET) (PCC NTK- R K Panigrahi, DGM) 20168

1/12/2016

Page : 38

SN

SCHEME / PACKAGE

M. MODERNISATION & EXPANSION OF BSP TO 7.0 MT


L 29

L 30

L 31

NIT

TOD

PBOD

BIDDERS

TC recommendation approved on 20.03.15 to cancel the subject


tender and re-tender the package after review of Eligibility criteria.
Revised TS and Eligibility criteria awaited.

Installation of Slab Dimension Measurement and Slab Positioning


System in Plate Mill
(Consultant-CET) (PCC TK A C Rathi, DGM I/c) 21751
Installation of Secondary Emission Control for 3 Converters in SMSII (Pkg. I) at BSP (Consultant-CET)
(PCC-TK- R K Panigrahi, DGM) 20168
Installation of Electric Motor driven turbo blower at P & B Station
(Consultant MECON) (PCC TK- R K Panigrahi, DGM) 20168

M1

Capacity Enhancement at MSDS- 4 & 5 (Pkg 70 A)


(Consultant-MECON) (PCC TK A C Rathi, DGM I/c) 21751

15.05.14

22.10.14

03.03.15

Sterling & Wilson, Kolkata

M2

Fire Station Building (Pkg. No. 138) (Retendered)


(Consultant-MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Duration 12 months

14.08.14

22.09.14

13.08.15

Amkay Construction Co., Durg


Balaji Enterprsies, Bhilai

M3

Construction of Mould & Segment Repair Shop (Pkg-129A)


(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Fire Protection System in Universal Rail Mill and Bar & Rod Mill
(Pkg No 126-02) (Consultant- MECON)
(PCC TK A.C.Rathi, DGM I/c) 21751
Procurement of Rail Road Shunting Locomotive 02 Nos.
(Pkg -098-II)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Duration 08 Months

10.03.15

10.04.15

08.09.15

HSCL,Bhilai

24.02.15

02.05.15

27.11.15

Sterling & Wilson

31.08.13

08.11.13

M4

M5

M6
i.

ii.
iii.

M7

STATUS AS ON DATE

Stage-I approved by SAIL Board on 03.04.07 at an indicative cost of Rs. 11262 Crs. and sanctioned Rs. 200 Crs. Towards Enabling / Preliminary works.

Board note sent on 04.07.15 for submission of fresh proposal for


the subject package based on revised TS and estimate within 2
months.
As per MOM held at SAIL Corporate Office on 04.07.15, proposal
is kept in abeyance for time being. Meanwhile, BSP may examine
the feasibility of interconnection of the air blast grids of PBS-1 &
PBS-2 with the help of Consultant.
{L-1 Cost Rs. 48.76 crs, Estimate Rs. 40.24 crs (NOC)}
Case sent to PP&E on 18.04.15 for obtaining Stage-II
approval.
Revised price after discount received from bidder on 08.09.15
and sent to MECON for re-evaluation. Offer validity has been
extended upto 15.01.16 & EMD-BG has been extended upto
29.02.16.
- {L-1 Cost Rs. 8.9 Crs, (LCNC) Estimate Rs. 10.97 Crs}
Case sent to PP&E on 15.09.15 for obtaining Stage-II approval.
Reminder sent to PP&E on 30.12.15 and on several dates for
obtaining Stage-II approval.
Offer validity including price extended up to 31.01.16 and PBG
to be extended shortly.
TC held on 22.12.15 to cancel the tender, minutes under signature.

{L-1 Price Rs 30.18 Crs, (NOC), Estimate Rs 22.13 Crs (NOC)}


TC held on 01.01.16 for conducting 2nd round of price negotiation
with M/s Sterling and Wilson, party to revert back.
1. TrackmobileLic, USA (Offer submitted by Lloyds
Reminder sent to MECON on 01.01.2016 to give
Engg. Corp., Kolkata)
comments/recommendation regarding financial eligibility and
2. Harbin Railway Bureau Industry General Corp.,
commercial suitability.
China.
3. ITK Ingenieria S.A., Spain.
4. Zephir spa (c/o M/s NovagonaIndia, Delhi)

Augmentation of SMS-II (Pkg.-038)


(Consultant-MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Modernization of Gas Cleaning Plant (Pkg.-038-03)
(Re-tendered) Duration 12 months

Duly cleared EOI alongwith comments for incorporation of


Financial Eligibility Criteria has been forwarded to Shop on
02.07.15.
MECON suggested BSP on 26.08.11 not to invest for this package.
Case is under process by Shop to drop the proposal.
TC recommendation approved on 30.03.15 to cancel the present
tender. Letter along with copy of approval forwarded to GM (SMS
II & CCP) on 31.03.15 for further processing the case.
TS issued by MECON on 07.02.15.
Cost estimate received from MECON on 01.04.15.

Combined blowing of Argon / Nitrogen in Converter


(Pkg.-038-05) (Re-tendered)
Modernization of BOF Automation (Pkg.-038-06)
(Re-tendered)
Duration 18 months
Procurement of Refractories and its Support Structure for Protection
lining of BOF & CCP Complex (Pkg. No.-124) (Consultant- MECON)
(PCC-TK- R K Panigrahi, DGM) 20168
1. Refractory bricks , castables and mortars - (06 items)

PO created on 22.07.15 to M/s SRU, Bokaro at a LCNC cost of


Rs. 18.61 Crs. and delivery period is 31.03.16.

1/12/2016

Page : 39

SN

SCHEME / PACKAGE
2. High Alumina Low Cement Gunning Castable (01 item)
Open Tender

NIT
07.05.15

TOD
05.06.15

3. SS Anchors 03 items
Open Tender

18.05.15

10.06.15

1. Luthra C.S. Engg. Works


2. Industrial Associates
3. Raghukul Marketing and Engg. Services
4. AMI Refractrahold
5. Jana & Co., Howrah
6. Ravi Engineering Works Bhilai
7. Bhilai Techneeds, Bhilai
8. R. K. Steel Industries, Bhilai
9. Arun Engineers and Fabricators,
10.Rajat Metals, Mumbai
11.Sunrise Machination LLP, Pune

Reminder sent to MECON and Shop on 01.01.16


comments/recommendation on parties offers and clarification.
Comments/recommendation received from Shop on 07.01.16.

M8

Mould & Segment Repair Shop Machines/Equipments (Pkg-129B)


(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168

09.05.15

13.07.15

TC held on 22.12.15 to cancel the tender, minutes under signature.

M 9

Procurement of Freight cum Passenger Elevators for BOF & CCP of


SMS-III (Pkg.-029C) (05 items)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168

05.06.15

28.08.15

M 10

Mobile firefighting equipments (Pkg. 098-3)


2. Towing Vehicle (PR No.-1200000892) (Re-tendered)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Laboratory Buildings and Laboratory Equipments (Pkg-090A)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Power Factor Compensation (Pkg-071B) (Consultant MECON)
(PCC TK A C Rathi, DGM I/c) 21751 Duration 16 months

20.02.15

09.09.15

1. Shiv Machine Tools, Chennai


2. MUV Multitech Pvt. Ltd., Chennai
3. Elite Engg. & General Works, Batala
4. Maco Corporation Pvt. Ltd., Kolkata
1.East Endia Elevators, Ahmedabad
2.ORBIS Elevators Co. Ltd., Ahmedabad
3. ECE Industries Ltd., Nagpur
4. Kone Elevator India Pvt. Ltd.Raipur
5. Omega Elevators, Ahmedabad
1. Tata Motors

M 11
M 12

M 13

Plant wide Network connectivity (Pkg.145)


(Consultant- MECON) (PCC TK A C Rathi, DGM I/c) 21751

M 14

Solid state Interlocking Signaling system (Pkg.-096)


(Consultant-MECON) (PCC-TK - A C Rathi, DGM I/c) 21751
Installation of New LT Substation - 50B and Replacement of existing
substation - 9B & 9H (Pkg.-118 R) (Re-tendered)
(Consultant-MECON) (PCC TK V Anil Kumar, AGM) 20206

M 15

PBOD

Bidders
1. Continental Refractories.
2. Sharadaa Ceramics.
3. Shreekant Ind..
4. Industrial Associates.
5. Refcom.
6. Dalmia Refractories.
7. TRL Krosaki.
8. National Refractories.
9. Champion Ceramics
10. IGL Refractories
11. Arvind

STATUS AS ON DATE
TAR issued by MECON on 02.01.16.

for

Comments received from Shop on 24.12.15 regarding clarifications


received from bidders.
Reminder
sent
to
MECON
on
15.01.16
for
comments/recommendation on parties offers and clarification.
TAR/recommendation received on 21.12.15 from MECON and sent
to Purchase on 21.12.15.
Commercial clarification/scrutiny is under process.
Note processed on 19.11.15 for uploading of NIT, approval received.
NIT to be uploaded.
MECON to issue revised TS after compiling the relevant data from
technological packages.
Final TS, Eligibility & Commercial Volume awaited from MECON.
Final TS awaited from MECON.
MECONs offer pertaining to preparation of SIP received on
24.10.14. Letter forwarded to PP&E on 24.10.14 for further needful.
Final TS, Eligibility & Commercial Volume received from Shop on
16.11.15.
Note processed for uploading of NIT, under approval.
Cost Estimate received from MECON on 04.01.16.
Note processed on 05.01.16 for formation of committee for
examining the initial estimate prepared by the Consultant, under
approval.

1/12/2016

Page : 40

Das könnte Ihnen auch gefallen