Instructions for Completing Implementation Costs

Click on the tab at the bottom marked "Implementation".

The spreadsheet has protection turned on without password protection. You can enter data in any unprotected
cell. The cursor will NOT move to protected cells.

Provide the name of the project.

Replace "FYxx" with the applicable fiscal year. For example, FYxx becomes FY11 or FY12.

Replace or delete the blue sample data.

Provide the IT costs and breakdown of full-time and part-time, permanent and project IT FTEs required to
implement this investment. IT FTEs should include staff on loan from other agencies. Do not include ongoing
maintenance costs.

If there are not enough rows in the IT FTE area, additional rows may be added. Rows cannot be deleted.

Copy the total from the yellow highlighted cell to "Investment Cost" in Section 4 of the IAR form

Instructions for Completing Maintenance Costs


1

Click on the tab at the bottom marked "Maintenance".

The spreadsheet has protection turned on without password protection. You can enter data in any unprotected
cell. The cursor will NOT move to protected cells.

Provide the name of the project.

Replace "FYxx" with the applicable fiscal year. For example, FYxx becomes FY11 or FY12.

Replace or delete the blue sample data.

Provide the IT costs and IT FTE breakdown for ongoing maintenance and support of this investment. Do not
include implementation costs listed in the Implementation spreadsheet.

If there are not enough rows in the IT FTE area, additional rows may be added. Rows cannot be deleted.

Copy the total from the yellow highlighted cell to "Maintenance Cost" in Section 4 of the IAR form.

Project Name: Place project name here.

Year 1
FYxx
# FTEs

Cost Breakdown (implementation)


Year 3
Year 2
FYxx
FYxx
(if needed)

Salaries &
Benefits

# FTEs

Salaries &
Benefits

# FTEs

Year 4
FYxx
(if needed)

Salaries &
Benefits

# FTEs

Totals

Salaries &
Benefits

IT FTEs - (For each job type, list the


number of staff and the total salary and
benefits)
Examples:
WMS Band 2
WMS Band 3 Project Manager

47.50

654,646

3.50

3,500,000

3.00

300,000

1.00

100,000

WMS Band 1 Quality Assurance

0.00

0.00

ITAS6

0.00

0.00

ITAS4

0.00
1.00

0
60,000

0.00
1.00

0
60,000

Other (admin Asst. 2)


Total IT FTEs

51.50

Total IT FTE Salary and Benefits

5.50
1,014,646

3,660,000

Purchased Services Contracts


Personal Services Contracts

Project Manager
Quality Assurance
IV&V
All others combined
Hardware Purchase or Upgrades
Hardware Maintenance
Software License Purchase or Upgrades

Software Maintenance
Hardware Lease or Finance (including
servers)
Indirect Costs
Training
Travel
Other Costs

Annual Total

4,674,646
-

1,014,646

3,660,000

4,674,646

Cost Breakdown (maintenance)


Year 1
FYxx
# FTEs

Year 2
FYxx

Salaries &
Benefits

# FTEs

Year 3
FYxx

Salaries &
Benefits

# FTEs

Year 4
FYxx

Salaries &
Benefits

# FTEs

Year 5
FYxx

Salaries &
Benefits

# FTEs

Totals

Salaries &
Benefits

IT FTEs - (For each job type, list the


number of staff and the total salary and
benefits)
Examples:
WMS Band 2
WMS Band 3 Project Manager
WMS Band 1 Quality Assurance
ITAS6
ITAS4
Other (admin Asst. 2)
Total IT FTEs

3.50

3,500,000

3.50

3,850,000

3.50

4,235,000

3.50

4,658,500

3.50

5,124,350

1.00
0.00

100,000
0

1.00
0.00

110,000
0

1.00
0.00

121,000
0

1.00
0.00

133,100
0

1.00
0.00

146,410
0

0.00
0.00
1.00

0
0
60,000

0.00
0.00
1.00

0
0
66,000

0.00
0.00
1.00

0
0
72,600

0.00
0.00
1.00

0
0
79,860

0.00
0.00
1.00

0
0
87,846

5.50

Total IT FTE Salary and Benefits


Purchased Services Contracts

5.50
3,660,000

5.50
4,026,000

5.50
4,428,600

5.50
4,871,460

5,358,606

Personal Services Contracts


Project Manager

Quality Assurance
IV&V
All others combined
Hardware Purchase or Upgrades
Hardware Maintenance
Software License Purchase or Upgrades
Software Maintenance
Hardware Lease or Finance (including
servers)
Indirect Costs
Training
Travel
Other Costs

Annual Total

22,344,666
-

3,660,000

4,026,000

4,428,600

4,871,460

5,358,606

Copy the total from the highlighted cell to "Maintenance Cost" in Section 4 of the IAR form

22,344,666