Beruflich Dokumente
Kultur Dokumente
18-1
Monitoring progress can be done by simply marking the individual activitys progress
and noting if you are meeting the time line. Non-critical activities can slip and become
critical so all paths must be monitored, not just the red line ones.
A secondary means of monitoring progress is to make a cumulative addition of all
progress payments to see if the cash flow is matching the projection or a standard S
curve. Funds are not expended in a straight-line method. The contractor is mobilizing
and ordering materials early in the project, and does not gain maximum momentum until
the middle third of the work. At the end of the project, most of the work is done, and the
billings are relatively less. If your project has an unbalanced cash flow, either early or
late, then you are in trouble. The contractor has taken more of your money, and has not
performed the work, or else is significantly behind schedule. (SEE S CURVE.)
Schedules are updated for each progress meeting when the General Contractor must make
a detailed review of the progress to date. Options for regaining lost time are discussed,
but the ultimate decision on means and methods rests with the GC. If you start directing
his efforts, then you have assumed direct responsibility for failure of the time line.
Sample CPM Calculations
The following table shows the logical relationships for six activities. The start dates
are based on a cumulative addition of the durations along the logic path. When two paths
join (B & D meet at E) the highest cumulative duration is used. The back pass
calculation is made following the logic path, but this time the smaller cumulative duration
governs. When the early and late dates are identical the activity is on the critical path.
The mathematical difference between late start and early start is the float time, which
indicates how many days the activity can be delayed without effecting the total project
duration.
Activity
Start
Predecessor
A
B
C
D
E
F
A
A
C
B,D
E
0
1
1
3
4
5
Finish
The critical path is A-C-D-E-F, and activity B has one day of float.
18-2
0
2
1
3
4
5
Float
The following activities are commonly used for a building project. If you enter these
activities into a CPM schedule program then you can assign durations and develop a
timeline for the project, which includes design, construction, inspections, and milestones.
ID
TASK
PREDECESSOR
DESIGN:
Program Definition
Schematic Design
Design Development
Construction Documents
Bid
Bid Evaluation
Award
Preconstruction Meeting
10
11
SITE WORK:
12
MOBILIZE
13
CLEARING SITE
12
14
SITE EARTHWORK
13
15
14
16
15
17
16
18
SITE LIGHTING
17
19
17
20
PARKING PAVEMENT
19
21
PARKING STRIPE
20
22
SIDEWALKS
19
23
LANDSCAPE
22
24
25
26
BUILDING:
SLAB-
27
13
28
FOUNDATION POUR
27
29
POUR SLAB
28
30
SHELL-
31
29
32
31
33
32
34
33
35
ROOF SHEATH
31
18-3
36
37
ROOFING
35
INTERIOR-
38
35
39
38
40
39
41
40
42
CEILING GRID
41
43
CEILING TILES
42
44
41
45
FINISH PAINT
41
46
45
47
FINAL CLEAN UP
46
48
49
MEP:
50
28
51
ROUGH IN ELECTRIC
38
52
ROUGH IN PLUMBING
38
53
ROUGH IN HVAC
38
54
55
54
56
38
57
42
58
42
59
45
38,51,52,53
60
45
61
45
62
43
63
TELE/DATA OPERATIONAL
59
64
65
60
60,61,62,64
66
67
INSPECTIONS:
68
FOUNDATION
27
69
SITE MEP
16
70
50
71
FRAMING
40
72
ROUGH IN MEP
54
73
INSULATION
40
74
54
75
43
76
FINAL ELECTRIC
60
77
FINAL PLUMBING
61
78
FINAL HVAC
63
18-4
79
80
ELEVATOR INSPECTION
81
82
CERTIFICATE OF OCCUPANCY
83
84
43,44
64
80,64
76,77,78,80
65
82,83
85
86
MILESTONES:
87
SLAB POURED
88
36
89
PERMANENT POWER ON
76
90
43
91
65
92
FLOORING DONE
46
93
46
94
93
95
82
96
TURNOVER TO CUSTOMER
29
95,59,82,84
18-5