Sie sind auf Seite 1von 26

COST BUDGET

CONSTRUCTION OF SAFARI VILLAS TYPE - B (GREY STRUCTURE)


BAHRIA TOWN GARDEN CITY
BUILT-UP FLOOR AREA = 5916 SFT

LABOR (A)
S.NO

DESCRIPTION

UNIT

QUANTITY

DIRECT UNIT
COST

DIRECT TOTAL
COST

INDIRECT
UNIT COST

MACHINERY (B)
INDIRECT
TOTAL COST

DIRECT &
INDIRECT TOTAL
COST

UNIT
COST

MATERIAL (C)

TOTAL COST

UNIT COST

RATE (Rs)

TOTAL COST

AMOUNT (Rs)

CONCRETE FRAME STRUCTURE WORKS


1)

EXCAVATION WORKS

1.1 Excavation in hard soil upto 1.5 m depth to obtain earth for
embankments or to clear building sites etc.
1.2 Earth Filling in area where required in 150 mm layers, borrow from
other site and fill according to requirement and as directed by the
engineer incharge.

COST OF EXCAVATION WORKS


COST PER SFT
2)

Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.

2.1b

Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.

2.2.1
2.2.2
2.2.3
2.2.4
2.2.5

3)

3.1
3.2
3.3
3.4
3.5

13,228.00

0.85

11,243.80

0.07

925.96

12,169.76

0.95

12,566.60

1.87

24,736.36

0.52%

Cft

12,338.00

1.15

14,188.70

0.09

1,110.42

15,299.12

2.80

34,546.40

4.04

49,845.52

1.05%

2,036.38
0.34

27,468.88
4.64

74,581.88
12.61

1.58%

RS

10.62

9,200.00

0.85

736.35

9,936.35

3.75

3,248.59

64.50

55,875.71

79.72

69,060.64

1.46%

Cft

644.63

10.62

6,845.97

0.85

547.94

7,393.91

3.75

2,417.36

64.50

41,578.64

79.72

51,389.90

1.09%

Raft and Column Footing ( 3,000 PSI )


Retaining Wall ( 3,000 PSI )
Columns ( 3,750 PSI )
Slabs ( 3,000 PSI )
Lintels & Beams ( 3,000 PSI )

Cft
Cft
Cft
Cft
Cft

2,703.76
574.00
2,644.23
1,732.89
7,654.88

8.85
8.85
8.85
8.85
8.85

23,928.28
5,079.90
23,401.44
15,336.08

0.90
0.90
0.90
0.90
0.90

2,433.38
516.60
2,379.81
1,559.60

26,361.66
5,596.50
25,781.25
16,895.68

7.10
7.10
7.10
7.10
7.10

19,196.70
4,075.40
18,774.03
12,303.52

104.76
113.84
102.76
102.76

283,245.90
65,344.16
271,721.07
178,071.78

121.61
16.85
130.69
119.61
119.61

328,804.25
75,016.06
316,276.35
207,270.97

6.95%

COST OF CONCRETE WORKS


COST PER SFT

RS

8,173.68
1.38

91,965.35
15.55

1,219.94
626.77
2,957.18

20,128.95
10,341.74
48,793.50

4,803.89
0.81

79,264.19
13.40

232.97
3,735.84
6,398.18
7,328.90

3,174.50
50,905.19
87,182.71
99,864.83

17,695.89
2.99

241,127.23
40.76

Providing and Placing reinforced cement concrete in different Grades


using crushed or broken stone graded as specified in specificatins.

Column Footing
Retaining Wall
Columns @ 5.454 KG/CFT
Slabs
Slab, Lintels & Beams

83,791.67
14.16

RS

STEEL
Cutting, Bending & Fixing of Steel as per drawing as directed by
engineer incharge.
Kg
Kg
Kg
Kg
Kg

6,099.68
3,133.86
14,785.91
24,019.45
110.76

3.10
3.10
3.10

18,909.01
9,714.97
45,836.32

0.20
0.20
0.20

74,460.30
12.59

RS
RS

60,015.60
10.14

0.40
0.40
0.40

2,439.87
1,253.54
5,914.36

895,837.26
151.43

55.00
55.00
55.00

9,607.77
1.62

335,482.40
172,362.30
813,225.05

1,047,818.17
177.12

58.70
58.70
58.70

1,321,069.75
223.30

358,051.22
183,957.58
867,932.92

1,409,941.72
238.33

1.59%
6.68%
4.38%

Raft & Column Footing


Retaining Wall
Columns
Slabs
Lintels & Beams

Sft
Sft
Sft
Sft
Sft
M2/M3

217.73
3,491.44
5,979.61
6,849.44
16,538.22
7.09

13.51
13.51
13.51
13.51

2,941.53
47,169.35
80,784.53
92,535.93

1.07
1.07
1.07
1.07
1.07

0.51
0.51
0.51
0.51
0.51

111.04
1,780.63
3,049.60
3,493.21

8.30
24.00
24.00
14.20

1,807.16
83,794.56
143,510.64
97,262.05

23.39
39.09
39.09
29.29

7.57%
3.89%
18.34%

29.79%

5,092.70
136,480.39
233,742.95
200,620.10

0.11%
0.00%
2.88%
4.94%
4.24%

575,936.14
97.35

12.17%

135.00
223,431.34
37.77

RS
RS

8,434.48
1.43

326,374.41
55.17

Termite Proofing in area where required with approved material from


main contractor, according to requirement and as directed by the

6)

11)
11.01
11.02
11.03
11.04
11.05
11.06

engineer incharge.

Sft

ANTI-TERMITE WORKS
COST PER SFT

RS

Water Proofing as specified


WATERPROOFING WORKS
COST PER SFT
OTHER WORKS
Overhead water tank concrete
Overhead water tank reinforcement
Overhead water tank formwork
PVC waterstop for OHWT
Manhole cover and insulation for OHWT
Underground watertank concrete

5,372.79

0.75

4,029.59
4,029.59
0.68

0.06

322.37
322.37
0.05

4,351.96
4,351.96
0.74

2.66

14,291.62
14,291.62
2.42

3.47

18,643.58
18,643.58
3.15

0.39%
0.39%

1,894.94

14.00

26,529.16
26,529.16
4.48

1.12

2,122.33
2,122.33
0.36

28,651.49
28,651.49
4.84

56.00

106,116.64
106,116.64
17.94

71.12

134,768.13
134,768.13
22.78

2.85%
2.85%

147.39
558.66
450.00
20.00
1.00
96.05

8.85
3.10
13.51
25.00
200.00
8.85

1,304.40
1,731.85
6,079.50
500.00
200.00
850.04

0.90
0.20
1.07
0.18
5.77
0.90

132.65
111.73
481.50
3.60
5.77
86.45

1,437.05
1,843.58
6,561.00
503.60
205.77
936.49

104.76
56.00
8.30
165.00
2,500.00
104.76

15,440.58
31,284.96
3,735.00
3,300.00
2,500.00
10,062.20

121.61
59.60
23.39
190.18
2,705.77
121.61

17,924.10
33,296.14
10,525.50
3,803.60
2,705.77
11,680.64

0.38%
0.70%
0.22%
0.08%
0.06%
0.25%

RS
Sft
RS
RS

Cft
Kg
Sft
Rft
Set
Cft

7.10
0.30
0.51
7.10

1,046.47
167.60
229.50
681.96

22.14%

FORMWORK
Providing, Fixing & Removal of formwork with good quality & smooth
surface of concrete after removal, complete in all respect or as
directed by the engineer incharge.

COST OF FORMWORK
COST PER SFT
7)

866.29

KG/M3

4.1
4.2
4.3
4.4
4.5

47,113.00
7.96

Cft

COST OF REINFORCEMENT WORKS


COST PER SFT
4)

25,432.50
4.30

RS

CONCRETE WORKS

2.1a

2.2

Cft

Kg
Sft
Rft

11.07
11.08
11.09
11.10

Underground watertank reinforcement


Underground watertank formwork
PVC waterstop for UGWT
Waterproofing for UGWT wall (with Bitumen)

11.11
11.14
11.15
11.17

Gully trap (2 Nos) & Manhole (1 No)


Boundary wall RCC
Boundary wall Lean Concrete
PCC (1:4:8) for walkway

Sft
Cft
Cft
Cft
Cft

COST OF OTHER WORKS


COST PER SFT

RS

COST OF CONCRETE FRAME STRUCTURE WORKS


COST PER SFT

325.00
432.00
28.00
140.00
73.50
210.00
92.00
184.92

3.10
13.51
25.00
28.00
15.00
8.85
8.85
10.62

RS

1,007.50
5,836.32
700.00
3,920.00
1,102.50
1,858.50
814.20
1,963.85
27,868.66
4.71

0.20
1.07
0.18
2.04
1.20
0.90
0.90
0.85

465,543.22
78.69

RS
RS

65.00
462.24
5.04
285.60
88.20
189.00
82.80
157.18
2,156.76
0.36

1,072.50
6,298.56
705.04
4,205.60
1,190.70
2,047.50
897.00
2,121.03
30,025.42
5.08

37,311.30
6.31

502,854.52
85.00

0.30
0.51
0.17
0.17
7.10
7.10
3.95

97.50
220.32
23.80
12.50
1,491.00
653.20
730.43
5,354.28
0.91

56.00
8.30
165.00
5.33
85.00
104.76
104.76
64.50

130,525.13
22.06

18,200.00
3,585.60
4,620.00
746.20
6,247.50
21,999.60
9,637.92
11,927.34
143,286.90
24.22

59.60
23.39
190.18
35.54
101.37
121.61
121.61
79.92

2,806,976.58
474.47

19,370.00
10,104.48
5,325.04
4,975.60
7,450.70
25,538.10
11,188.12
14,778.81
178,666.60
30.20

3,440,356.22
581.53

0.41%
0.21%
0.11%
0.11%
0.16%
0.54%
0.24%
0.31%
3.78%

72.69%

OTHER ASSOCIATED WORK FOR GREY


STRUCTURE
5)

BLOCK WORK
Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand
Mortar (1:4) In Super Structure , including form work, curing etc
complete in all respect or as directed by the engineer incharge.

8)

Plaster works
Applying 13mm thick cement and sand plaster (1:4) to be trowelled
smooth with steel trowel to brick or block wall,as Directed by the
engineer incharge.

BLOCKWORKS & PLASTERING WORKS


COST PER SFT
9)

10)

11)
11.12
11.13
11.16

EMBEDDED ITEMS FOR ELECTRICAL WORKS

Cft

4,053.55

13.43

54,439.18

1.07

4,337.30

58,776.48

0.20

810.71

50.33

204,015.17

65.03

263,602.36

5.57%

Sft

15,156.29

8.50

128,828.47

0.68

10,306.28

139,134.75

0.20

3,031.26

8.01

121,401.88

17.39

263,567.88

5.57%

14,643.58
2.48

197,911.23
33.45

527,170.24
89.11

11.14%

183,267.65
30.98

RS
RS

3,841.97
0.65

325,417.05
55.01

Sft

5,916.00

5.33

31,532.28

0.55

3,253.80

34,786.08

0.30

1,774.80

63.53

375,843.48

69.71

412,404.36

8.71%

EMBEDDED ITEMS FOR PLUMBING WORKS

Sft

5,916.00

5.07

29,994.12

0.53

3,135.48

33,129.60

0.27

1,597.32

44.50

263,262.00

50.37

297,988.92

6.30%

COST OF ELECTRICAL & PLUMBING WORKS


COST PER SFT

RS

61,526.40
10.40

6,389.28
1.08

67,915.68
11.48

710,393.28
120.08

15.01%

41,991.77

260.44
436.80
1,523.20
2,220.44
0.38

3,515.94
5,896.80
20,563.20
29,975.94
5.07

6,645.05
9,332.40
38,886.40
54,863.85
9.27

0.14%
0.20%
0.82%
1.16%

272,549.55
46.07

23,253.30
3.93

295,802.85
50.00

7,731.40
1.31

988,893.13
167.16

1,292,427.37
218.46

27.31%

465,543.22
78.69

37,311.30
6.31

502,854.52
85.00

130,525.13
22.06

2,806,976.58
474.47

3,440,356.22
581.53

72.69%

272,549.55
46.07

23,253.30
3.93

295,802.85
50.00

7,731.40
1.31

988,893.13
167.16

1,292,427.37
218.46

27.31%

5,916.00

5,916.00

5,916.00

5,916.00

5,916.00

5,916

738,093

60,565

798,657

138,257

3,795,870

4,732,784

124.76
124.76
15.60%

10.24
10.24
1.28%

135.00
135.00
16.88%

23.37
23.37
2.92%

641.63
641.63
80.20%

800.00
800.00

RS

OTHER WORKS
Plastering of Tank and Manholes
Boundary wall brickwork
Boundary wall Plastering

Sft
Cft
Sft

COST OF OTHER WORKS


COST PER SFT

RS

OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS


COST PER SFT

383.00
420.00
2,240.00

RS

RS
RS

COST OF CONCRETE FRAME STRUCTURE WORKS (A) :


COST PER SFT
OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS (B) :
COST PER SFT

Covered Area (Sft)


TOTAL COST (A+B) :
COST PER SFT
ADD: CONTINGENCIES FOR ANY OTHER COST
TOTAL BUDGETED COST PER SFT:
% OF BUDGETED COST :

8.50
13.00
8.50

3,255.50
5,460.00
19,040.00
27,755.50
4.69

DIRECT LABOUR
(A)

0.68
1.04
0.68

INDIRECT
LABOUR
(B)

TOTAL LABOUR
(A+B)

3,372.12
0.57

0.17
0.17
0.17

65.11
71.40
380.80
517.31
0.09

MACHINERY
(C)

639,105.48
108.03

8.00
8.01
8.01

3,064.00
3,364.20
17,942.40
24,370.60
4.12

MATERIAL
(D)

17.35
22.22
17.36

800.00

TOTAL AMOUNT
(A+B+C+D)

TOTAL CONTRACT COST :

73,808,016

6,057,984

79,866,000

13,825,692

379,588,308

473,280,000

TOTAL BUDGETED COST :

57,272,796

6,057,984

63,330,780

12,595,164

379,588,308

455,514,252

POSSIBLE COST SAVING :

16,535,220

16,535,220

1,230,528

17,765,748

100.00%

0.00%
100.00%

COST BUDGET

CONSTRUCTION OF SAFARI VILLAS TYPE - B (GREY STRUCTURE)


BAHRIA TOWN GARDEN CITY
BUILT-UP FLOOR AREA = 5916 SFT

S.NO

DESCRIPTION

UNIT

QUANTITY

LABOR (A)
DIRECT UNIT
COST

DIRECT TOTAL
COST

MACHINERY (B)

INDIRECT
UNIT COST

INDIRECT
TOTAL COST

DIRECT &
INDIRECT
TOTAL COST

UNIT
COST

RATE (Rs)

MATERIAL (C)

TOTAL COST

UNIT COST

AMOUNT (Rs)
%

TOTAL COST

CONCRETE FRAME STRUCTURE WORKS


1)

EXCAVATION WORKS

1.1 Excavation in hard soil upto 1.5 m depth to obtain earth for
embankments or to clear building sites etc.
1.2 Earth Filling in area where required in 150 mm layers, borrow from
other site and fill according to requirement and as directed by the
engineer incharge.

COST OF EXCAVATION WORKS


COST PER SFT
2)

Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.

2.1b

Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.

2.2.1
2.2.2
2.2.3
2.2.4
2.2.5

3)

3.1
3.2
3.3
3.4
3.5

13,228.00

0.85

11,243.80

0.07

925.96

12,169.76

0.95

12,566.60

1.87

24,736.36

0.52%

Cft

12,338.00

1.15

14,188.70

0.09

1,110.42

15,299.12

2.80

34,546.40

4.04

49,845.52

1.05%

2,036.38
0.34

27,468.88
4.64

74,581.88
12.61

1.58%

RS

10.62

9,200.00

0.85

736.35

9,936.35

3.75

3,248.59

64.50

55,875.71

79.72

69,060.64

1.46%

Cft

644.63

10.62

6,845.97

0.85

547.94

7,393.91

3.75

2,417.36

64.50

41,578.64

79.72

51,389.90

1.09%

2,703.76
574.00
2,644.23
1,732.89
7,654.88

8.85
8.85
8.85
8.85

23,928.28
5,079.90
23,401.44
15,336.08

0.71
0.71
0.71
0.71

1,919.67
407.54
1,877.40
1,230.35

25,847.95
5,487.44
25,278.84
16,566.43

7.08
7.08
7.08
7.08

19,142.62
4,063.92
18,721.15
12,268.86

104.76
113.84
102.76
102.76

283,245.90
65,344.16
271,721.07
178,071.78

121.40
130.48
119.40
119.40

328,236.46
74,895.52
315,721.06
206,907.07

6.94%

Slabs ( 3,000 PSI )


Lintels & Beams ( 3,000 PSI )

Cft
Cft
Cft
Cft
Cft

COST OF CONCRETE WORKS


COST PER SFT

RS
RS

6,719.25
1.14

90,510.92
15.30

1,219.94
626.77
2,957.18

16,835.12
8,649.45
40,809.11

4,803.89
0.81

66,293.68
11.21

217.73
3,491.44
5,979.61
6,849.44

2,939.36
47,134.44
80,724.74
92,467.44

16,538.22
2.80

223,265.98
37.74

Providing and Placing reinforced cement concrete in different Grades


using crushed or broken stone graded as specified in specificatins.
Raft and Column Footing ( 3,000 PSI )
Retaining Wall ( 3,000 PSI )
Columns ( 3,750 PSI )

STEEL
Cutting, Bending & Fixing of Steel as per drawing as directed by
engineer incharge.
Column Footing
Retaining Wall
Columns @ 5.454 KG/CFT
Slabs
Slab, Lintels & Beams

Kg
Kg
Kg
Kg
Kg

83,791.67
14.16

6,099.68
3,133.86
14,785.91
24,019.45
110.76

2.56
2.56
2.56

15,615.18
8,022.68
37,851.93

0.20
0.20
0.20

61,489.79
10.39

RS
RS

59,862.50
10.12

0.40
0.40
0.40

2,439.87
1,253.54
5,914.36

895,837.26
151.43

55.00
55.00
55.00

9,607.77
1.62

335,482.40
172,362.30
813,225.05

1,046,210.65
176.84

58.16
58.16
58.16

1,321,069.75
223.30

354,757.39
182,265.30
859,948.53

1,396,971.22
236.13

1.58%
6.67%
4.37%

22.11%

7.50%
3.85%
18.17%

29.52%

FORMWORK
Providing, Fixing & Removal of formwork with good quality & smooth
surface of concrete after removal, complete in all respect or as
directed by the engineer incharge.
Raft & Column Footing
Retaining Wall
Columns
Slabs
Lintels & Beams

COST OF FORMWORK
COST PER SFT
7)

866.29

KG/M3

4.1
4.2
4.3
4.4
4.5

47,113.00
7.96

Cft

COST OF REINFORCEMENT WORKS


COST PER SFT
4)

25,432.50
4.30

RS

CONCRETE WORKS

2.1a

2.2

Cft

Sft
Sft
Sft
Sft
Sft
M2/M3
RS

217.73
3,491.44
5,979.61
6,849.44
16,538.22
7.09

12.50
12.50
12.50
12.50

2,721.63
43,643.00
74,745.13
85,618.00

1.00
1.00
1.00
1.00

206,727.76
34.94

RS

0.20
0.20
0.20
0.20

43.55
698.29
1,195.92
1,369.89
3,307.65

7.80
16.80
9.80
9.80

6,615.30
1.12

1,698.29
58,656.19
58,600.18
67,124.51

21.50
30.50
23.50
23.50

186,079.17
31.45

4,681.20
106,488.92
140,520.84
160,961.84

0.10%
0.00%
2.25%
2.97%
3.40%

412,652.80
69.75

8.72%

Termite Proofing in area where required with approved material from


main contractor, according to requirement and as directed by the
engineer incharge.
ANTI-TERMITE WORKS
COST PER SFT

6)

11)
11.01
11.02
11.03
11.04
11.05
11.06
11.07
11.08
11.09
11.10
11.11
11.14
11.15
11.17

Water Proofing as specified


WATERPROOFING WORKS
COST PER SFT
OTHER WORKS
Overhead water tank concrete
Overhead water tank reinforcement
Overhead water tank formwork
PVC waterstop for OHWT
Manhole cover and insulation for OHWT
Underground watertank concrete
Underground watertank reinforcement
Underground watertank formwork
PVC waterstop for UGWT
Waterproofing for UGWT wall (with Bitumen)
Gully trap (2 Nos) & Manhole (1 No)
Boundary wall RCC
Boundary wall Lean Concrete
PCC (1:4:8) for walkway
COST OF OTHER WORKS
COST PER SFT
COST OF CONCRETE FRAME STRUCTURE WORKS
COST PER SFT

5,372.79

0.75

4,029.59
4,029.59
0.68

0.06

322.37
322.37
0.05

4,351.96
4,351.96
0.74

2.66

14,291.62
14,291.62
2.42

3.47

18,643.58
18,643.58
3.15

0.39%
0.39%

Sft
RS
RS

1,894.94

14.00

26,529.16
26,529.16
4.48

1.12

2,122.33
2,122.33
0.36

28,651.49
28,651.49
4.84

56.00

106,116.64
106,116.64
17.94

71.12

134,768.13
134,768.13
22.78

2.85%
2.85%

Cft
Kg
Sft
Rft
Set
Cft
Kg
Sft
Rft
Sft
Cft
Cft
Cft
Cft
RS

147.39
558.66
450.00
20.00
1.00
96.05
325.00
432.00
28.00
140.00
73.50
210.00
92.00
184.92

8.85
2.56
12.50
2.20
72.12
8.85
2.56
12.50
2.20
0.56
15.00
8.85
8.85
10.62

0.71
0.20
1.00
0.18
5.77
0.71
0.20
1.00
0.18
0.04
1.20
0.71
0.71
0.85

104.65
111.73
450.00
3.60
5.77
68.20
65.00
432.00
5.04
5.60
88.20
149.10
65.32
157.18
1,711.39
0.29

1,409.05
1,541.90
6,075.00
47.60
77.89
918.24
897.00
5,832.00
66.64
84.00
1,190.70
2,007.60
879.52
2,121.03
23,148.17
3.91

104.76
56.00
8.80
165.00
2,500.00
104.76
56.00
8.80
165.00
5.33
85.00
104.76
104.76
64.50

15,440.58
31,284.96
3,960.00
3,300.00
2,500.00
10,062.20
18,200.00
3,801.60
4,620.00
746.20
6,247.50
21,999.60
9,637.92
11,927.34
143,727.90
24.29

121.40
59.06
22.47
167.38
2,577.89
121.40
59.06
22.47
167.38
6.10
101.37
121.40
121.40
79.92

17,893.15
32,994.46
10,111.50
3,347.60
2,577.89
11,660.47
19,194.50
9,707.04
4,686.64
854.00
7,450.70
25,494.00
11,168.80
14,778.81
171,919.56
29.06

0.38%
0.70%
0.21%
0.07%
0.05%
0.25%
0.41%
0.21%
0.10%
0.02%
0.16%
0.54%
0.24%
0.31%
3.63%

RS

1,304.40
1,430.17
5,625.00
44.00
72.12
850.04
832.00
5,400.00
61.60
78.40
1,102.50
1,858.50
814.20
1,963.85
21,436.78
3.62

RS
RS

429,437.25
72.59

34,253.83
5.79

463,691.08
78.38

83.00

128,242.05
21.68

Sft
RS
RS

7.08
0.30
0.17
7.08
0.30
0.17
0.17
0.17
7.08
7.08
3.95

1,043.52
167.60
76.50
680.03
97.50
73.44
23.80
12.50
1,486.80
651.36
730.43
5,043.48
0.85

2,667,122.34
450.83

3,255,747.82
550.33

68.79%

OTHER ASSOCIATED WORK FOR GREY


STRUCTURE
5)

BLOCK WORK
Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand
Mortar (1:4) In Super Structure , including form work, curing etc
complete in all respect or as directed by the engineer incharge.

8)

Plaster works
Applying 13mm thick cement and sand plaster (1:4) to be trowelled
smooth with steel trowel to brick or block wall,as Directed by the
engineer incharge.

BLOCKWORKS & PLASTERING WORKS


COST PER SFT
9)

10)

11)
11.12
11.13
11.16

EMBEDDED ITEMS FOR ELECTRICAL WORKS

Cft

4,053.55

13.43

54,439.18

1.07

4,337.30

58,776.48

0.20

810.71

50.33

204,015.17

65.03

263,602.36

Sft

15,156.29

8.50

128,828.47

0.68

10,306.28

139,134.75

0.20

3,031.26

8.01

121,401.88

17.39

263,567.88

5.57%

14,643.58
2.48

197,911.23
33.45

527,170.24
89.11

11.14%

8.90%

183,267.65
30.98

RS
RS

3,841.97
0.65

325,417.05
55.01

5.57%

Sft

5,916.00

6.83

40,406.28

0.55

3,253.80

43,660.08

0.30

1,774.80

63.53

375,843.48

71.21

421,278.36

EMBEDDED ITEMS FOR PLUMBING WORKS

Sft

5,916.00

6.57

38,868.12

0.53

3,135.48

42,003.60

0.27

1,597.32

44.50

263,262.00

51.87

306,862.92

6.48%

COST OF ELECTRICAL & PLUMBING WORKS


COST PER SFT

RS
RS

6,389.28
1.08

85,663.68
14.48

728,141.28
123.08

15.39%

260.44
436.80
1,523.20
2,220.44
0.38

3,515.94
5,896.80
20,563.20
29,975.94
5.07

OTHER WORKS
Plastering of Tank and Manholes
Boundary wall brickwork
Boundary wall Plastering

79,274.40
13.40

RS

RS
RS

290,297.55
49.07

23,253.30
3.93

313,550.85
53.00

7,731.40
1.31

988,893.13
167.16

1,310,175.37
221.46

27.68%

52.00

429,437.25
72.59

34,253.83
5.79

463,691.08
78.38

83.00

128,242.05
21.68

2,667,122.34
450.83

3,255,747.82
550.33

68.79%

COST PER SFT


OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS
(B) :
COST PER SFT

290,297.55
49.07

23,253.30
3.93

313,550.85
53.00

52.00

7,731.40
1.31

988,893.13
167.16

1,310,175.37
221.46

27.68%

5,916.00

5,916.00

5,916.00

5,916.00

5,916.00

5,916

719,735
121.66
2.70
124.36
15.54%

57,507
9.72
0.36
10.08
1.26%

777,242
131.38
3.05
134.43
16.80%

135,973
22.98
1.99
24.97
3.12%

3,656,015
617.99
22.59
640.57
80.07%

4,565,923
771.79
28.21
800.00

COST OF OTHER WORKS


COST PER SFT
OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS
COST PER SFT
COST OF CONCRETE FRAME STRUCTURE WORKS (A) :

Covered Area (Sft)


TOTAL COST (A+B) :
COST PER SFT
ADD: CONTINGENCIES FOR ANY OTHER COST
TOTAL BUDGETED COST :
% OF BUDGETED COST :

8.50
13.00
8.50

INDIRECT
LABOUR
(B)

DIRECT LABOUR
(A)
TOTAL CONTRACT COST :
TOTAL BUDGETED COST :

POSSIBLE COST SAVING :

0.68
1.04
0.68

73,568,690
-

73,568,690

TOTAL LABOUR
(A+B)

5,960,892
-

5,960,892

79,529,581
-

79,529,581

0.17
0.17
0.17

65.11
71.40
380.80
517.31
0.09

639,105.48
108.03

3,255.50
5,460.00
19,040.00
27,755.50
4.69

Sft
Cft
Sft
RS

383.00
420.00
2,240.00

3,372.12
0.57

MACHINERY
(C)

8.00
8.01
8.01

3,064.00
3,364.20
17,942.40
24,370.60
4.12

MATERIAL
(D)

14,774,645
-

14,774,645

17.35
22.22
17.36

799.98

6,645.05
9,332.40
38,886.40
54,863.85
9.27

TOTAL AMOUNT
(A+B+C+D)

378,963,668
-

378,963,668

473,280,000
-

473,280,000

0.14%
0.20%
0.82%
1.16%

96.47%
3.53%
100.00%

COST BUDGET

CONSTRUCTION OF SAFARI VILLAS TYPE - B (GREY STRUCTURE)


BAHRIA TOWN GARDEN CITY
BUILT-UP FLOOR AREA = 5916 SFT

LABOR (A)
S.NO

DESCRIPTION

UNIT

QUANTITY

DIRECT UNIT
COST

INDIRECT
DIRECT TOTAL COST
UNIT COST

MACHINERY (B)
DIRECT &
INDIRECT TOTAL
INDIRECT TOTAL
COST
COST

UNIT
COST

MATERIAL (C)

TOTAL COST

UNIT COST

RATE (Rs)

TOTAL COST

AMOUNT (Rs)

CONCRETE FRAME STRUCTURE WORKS


1)

EXCAVATION WORKS

1.1 Excavation in hard soil upto 1.5 m depth to obtain earth for
embankments or to clear building sites etc.
1.2 Earth Filling in area where required in 150 mm layers, borrow from
other site and fill according to requirement and as directed by the
engineer incharge.

COST OF EXCAVATION WORKS


COST PER SFT
2)

Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.

2.1b

Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.

2.2.1
2.2.2
2.2.3
2.2.4
2.2.5

3)

3.1
3.2
3.3
3.4
3.5

13,228.00

Cft

12,338.00

6,349.44

0.07

925.96

7,275.40

0.95

12,566.60

1.50

19,842.00

0.44%

0.09

1,110.42

1,110.42

1.80

22,208.40

1.89

23,318.82

0.51%

2,036.38
0.34

8,385.82
1.42

43,160.82
7.30

0.95%

6,349.44
1.07

RS
RS

34,775.00
5.88

Cft

866.29

4.00

3,465.16

0.85

736.35

4,201.51

3.75

3,248.59

64.50

55,875.71

73.10

63,325.80

1.39%

Cft

644.63

4.00

2,578.52

0.85

547.94

3,126.46

3.75

2,417.36

64.50

41,578.64

73.10

47,122.45

1.03%

2,703.76
574.00
2,644.23
1,732.89
7,654.88

4.00
4.00
4.00
4.00
4.00

10,815.04
2,296.00
10,576.92
6,931.56

0.90
0.90
0.90
0.90
0.90

2,433.38
516.60
2,379.81
1,559.60

13,248.42
2,812.60
12,956.73
8,491.16

7.10
7.10
7.10
7.10
7.10

19,196.70
4,075.40
18,774.03
12,303.52

104.76
113.84
102.76
102.76

283,245.90
65,344.16
271,721.07
178,071.78

116.76
12.00
125.84
114.76
114.76

315,691.02
72,232.16
303,451.83
198,866.46

6.93%

Lintels & Beams ( 3,000 PSI )

Cft
Cft
Cft
Cft
Cft

COST OF CONCRETE WORKS


COST PER SFT

RS
RS

8,173.68
1.38

44,836.88
7.58

1,219.94
626.77
2,957.18

16,469.14
8,461.42
39,921.96

4,803.89
0.81

64,852.52
10.96

232.97
3,735.84
6,398.18
7,328.90

2,410.27
38,650.24
66,194.28
75,823.30

17,695.89
2.99

183,078.09
30.95

0.06

322.37
322.37
0.05

322.37
322.37
0.05

2.66

14,291.62
14,291.62
2.42

2.72

14,613.99
14,613.99
2.47

0.32%
0.32%

56.00

106,116.64
106,116.64
17.94

63.12

119,608.61
119,608.61
20.22

2.63%
2.63%

104.76
56.00
8.30
165.00
2,500.00
104.76
56.00
8.30
165.00
5.33
85.00
104.76
104.76
64.50

15,440.58
31,284.96
3,735.00
3,300.00
2,500.00
10,062.20
18,200.00
3,585.60
4,620.00
746.20
6,247.50
21,999.60
9,637.92
11,927.34
143,286.90
24.22

116.76
59.00
19.88
190.18
2,705.77
116.76
59.00
19.88
190.18
35.54
101.37
116.76
116.76
73.30

17,209.26
32,960.94
8,946.00
3,803.60
2,705.77
11,214.80
19,175.00
8,588.16
5,325.04
4,975.60
7,450.70
24,519.60
10,741.92
13,554.64
171,171.03
28.93

0.38%
0.72%
0.20%
0.08%
0.06%
0.25%
0.42%
0.19%
0.12%
0.11%
0.16%
0.54%
0.24%
0.30%
3.76%

Providing and Placing reinforced cement concrete in different Grades


using crushed or broken stone graded as specified in specificatins.
Raft and Column Footing ( 3,000 PSI )
Retaining Wall ( 3,000 PSI )
Columns ( 3,750 PSI )
Slabs ( 3,000 PSI )

STEEL
Cutting, Bending & Fixing of Steel as per drawing as directed by
engineer incharge.
Column Footing
Retaining Wall
Columns @ 5.454 KG/CFT
Slabs
Slab, Lintels & Beams

COST OF REINFORCEMENT WORKS


COST PER SFT

Kg
Kg
Kg
Kg
Kg
KG/M3
RS
RS

4)

FORMWORK
Providing, Fixing & Removal of formwork with good quality & smooth
surface of concrete after removal, complete in all respect or as
directed by the engineer incharge.

4.1
4.2
4.3
4.4
4.5

Raft & Column Footing


Retaining Wall
Columns
Slabs
Lintels & Beams

Sft
Sft
Sft
Sft
Sft

COST OF FORMWORK
COST PER SFT

M2/M3
RS
RS

7)

0.48

CONCRETE WORKS

2.1a

2.2

Cft

36,663.20
6.20

6,099.68
3,133.86
14,785.91
24,019.45
110.76

2.50
2.50
2.50

15,249.20
7,834.65
36,964.78

0.20
0.20
0.20

60,048.63
10.15

217.73
3,491.44
5,979.61
6,849.44
16,538.22
7.09

10.00
10.00
10.00
10.00

2,177.30
34,914.40
59,796.10
68,494.40

1.07
1.07
1.07
1.07
1.07

165,382.20
27.96

60,015.60
10.14

0.40
0.40
0.40

2,439.87
1,253.54
5,914.36

895,837.26
151.43

55.00
55.00
55.00

9,607.77
1.62

0.51
0.51
0.51
0.51
0.51

111.04
1,780.63
3,049.60
3,493.21

335,482.40
172,362.30
813,225.05

1,000,689.72
169.15

58.10
58.10
58.10

1,321,069.75
223.30

8.30
24.00
24.00
14.20

8,434.48
1.43

1,807.16
83,794.56
143,510.64
97,262.05

354,391.41
182,077.27
859,061.37

1,395,530.05
235.89

19.88
35.58
35.58
25.78

326,374.41
55.17

1.59%
6.66%
4.37%

21.97%

7.78%
4.00%

18.86%

30.64%

4,328.47
124,225.44
212,754.52
176,578.56

0.10%
0.00%
2.73%
4.67%
3.88%

517,886.99
87.54

11.37%

Termite Proofing in area where required with approved material from


main contractor, according to requirement and as directed by the
Sft
RS
RS

5,372.79

ANTI-TERMITE WORKS
COST PER SFT
Water Proofing as specified
WATERPROOFING WORKS
COST PER SFT

Sft
RS
RS

1,894.94

6.00

11,369.64
11,369.64
1.92

1.12

2,122.33
2,122.33
0.36

13,491.97
13,491.97
2.28

OTHER WORKS
Overhead water tank concrete
Overhead water tank reinforcement
Overhead water tank formwork
PVC waterstop for OHWT
Manhole cover and insulation for OHWT
Underground watertank concrete
Underground watertank reinforcement
Underground watertank formwork
PVC waterstop for UGWT
Waterproofing for UGWT wall (with Bitumen)
Gully trap (2 Nos) & Manhole (1 No)
Boundary wall RCC
Boundary wall Lean Concrete
PCC (1:4:8) for walkway
COST OF OTHER WORKS
COST PER SFT

Cft
Kg
Sft
Rft
Set
Cft
Kg
Sft
Rft
Sft
Cft
Cft
Cft
Cft
RS
RS

147.39
558.66
450.00
20.00
1.00
96.05
325.00
432.00
28.00
140.00
73.50
210.00
92.00
184.92

4.00
2.50
10.00
25.00
200.00
4.00
2.50
10.00
25.00
28.00
15.00
4.00
4.00
4.00

589.56
1,396.65
4,500.00
500.00
200.00
384.20
812.50
4,320.00
700.00
3,920.00
1,102.50
840.00
368.00
739.68
20,373.09
3.44

0.90
0.20
1.07
0.18
5.77
0.90
0.20
1.07
0.18
2.04
1.20
0.90
0.90
0.85

132.65
111.73
481.50
3.60
5.77
86.45
65.00
462.24
5.04
285.60
88.20
189.00
82.80
157.18
2,156.76
0.36

722.21
1,508.38
4,981.50
503.60
205.77
470.65
877.50
4,782.24
705.04
4,205.60
1,190.70
1,029.00
450.80
896.86
22,529.85
3.81

37,311.30
6.31

337,497.50
57.05

engineer incharge.

6)

11)
11.01
11.02
11.03
11.04
11.05
11.06
11.07
11.08
11.09
11.10
11.11
11.14
11.15
11.17

COST OF CONCRETE FRAME STRUCTURE WORKS


COST PER SFT

300,186.20
50.74

RS
RS

7.10
0.30
0.51
7.10
0.30
0.51
0.17
0.17
7.10
7.10
3.95

1,046.47
167.60
229.50
681.96
97.50
220.32
23.80
12.50
1,491.00
653.20
730.43
5,354.28
0.91

118,187.13
19.98

2,806,976.58
474.47

3,262,661.21
551.50

71.63%

OTHER ASSOCIATED WORK FOR GREY


STRUCTURE
5)

BLOCK WORK
Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand
Mortar (1:4) In Super Structure , including form work, curing etc
complete in all respect or as directed by the engineer incharge.

8)

9)
10)

11)
11.12
11.13
11.16

Plaster works
Applying 13mm thick cement and sand plaster (1:4) to be trowelled
smooth with steel trowel to brick or block wall,as Directed by the
engineer incharge.

Cft

4,053.55

13.43

54,439.18

1.07

4,337.30

58,776.48

0.20

810.71

50.33

204,015.17

65.03

263,602.36

Sft

15,156.29

8.50

128,828.47

0.68

10,306.28

139,134.75

0.20

3,031.26

8.01

121,401.88

17.39

263,567.88

5.79%

14,643.58
2.48

197,911.23
33.45

527,170.24
89.11

11.57%

9.05%

183,267.65
30.98

3,841.97
0.65

325,417.05
55.01

5.79%

BLOCKWORKS & PLASTERING WORKS


COST PER SFT

RS
RS

EMBEDDED ITEMS FOR ELECTRICAL WORKS

Sft

5,916.00

5.33

31,532.28

0.55

3,253.80

34,786.08

0.30

1,774.80

63.53

375,843.48

69.71

412,404.36

EMBEDDED ITEMS FOR PLUMBING WORKS

Sft

5,916.00

5.07

29,994.12

0.53

3,135.48

33,129.60

0.27

1,597.32

44.50

263,262.00

50.37

297,988.92

6.54%

COST OF ELECTRICAL & PLUMBING WORKS


COST PER SFT

RS
RS

6,389.28
1.08

67,915.68
11.48

710,393.28
120.08

15.60%

OTHER WORKS
Plastering of Tank and Manholes
Boundary wall brickwork
Boundary wall Plastering
COST OF OTHER WORKS
COST PER SFT

Sft
Cft
Sft
RS
RS

260.44
436.80
1,523.20
2,220.44
0.38

3,515.94
5,896.80
20,563.20
29,975.94
5.07

272,549.55
46.07

23,253.30
3.93

295,802.85
50.00

COST PER SFT

300,186.20
50.74

37,311.30
6.31

337,497.50
57.05

OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS


(B) :
COST PER SFT

272,549.55
46.07

23,253.30
3.93

295,802.85
50.00

5,916.00

5,916.00

5,916.00

5,916.00

5,916.00

5,916

572,736

60,565

633,300

125,919

3,795,870

4,555,089

96.81
96.81

10.24
10.24

107.05
107.05
13.90%

21.29
21.29
2.77%

641.63
641.63
83.33%

769.97
769.97

OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS


COST PER SFT

61,526.40
10.40

383.00
420.00
2,240.00

RS
RS

COST OF CONCRETE FRAME STRUCTURE WORKS (A) :

Covered Area (Sft)


TOTAL COST (A+B) :
COST PER SFT
ADD: CONTINGENCIES FOR ANY OTHER COST
TOTAL BUDGETED COST PER SFT:
% OF BUDGETED COST :

TOTAL BUDGETED COST :

8.50
13.00
8.50

3,255.50
5,460.00
19,040.00
27,755.50
4.69

0.68
1.04
0.68

12.57%

1.33%

DIRECT LABOUR
(A)

INDIRECT LABOUR
(B)

57,272,796

6,057,984

TOTAL LABOUR
(A+B)
63,330,780

3,372.12
0.57

0.17
0.17
0.17

65.11
71.40
380.80
517.31
0.09

639,105.48
108.03

8.00
8.01
8.01

3,064.00
3,364.20
17,942.40
24,370.60
4.12

7,731.40
1.31

988,893.13
167.16

83.00

118,187.13
19.98

2,806,976.58
474.47

52.00

7,731.40
1.31

988,893.13
167.16

MACHINERY
(C)
12,595,164

MATERIAL
(D)
379,588,308

17.35
22.22
17.36

551.50
218.47

769.97

6,645.05
9,332.40
38,886.40
54,863.85
9.27

0.15%
0.20%
0.85%
1.20%

1,292,427.37
218.46

28.37%

3,262,661.21
551.50

71.63%

1,292,427.37
218.46

28.37%

TOTAL AMOUNT
(A+B+C+D)
455,514,252

100.00%

0.00%
100.00%

BOQ Item-03
RATE ANALYSIS OF 400 x 200 x 200 MM Thick Block Masonry.

Providing and laying cement concrete Hollow block masonry walls of specified strength as per

specification, using machine made blocks (approved quality of fine and course aggregate) laid

cement sand mortar, in any shape, length or height, laid at specified levels, including cost of s

Wall ties as per drawing including racking out joints cutting, curing etc, complete in all respec

conforming to the requirements of drawings, specifications and to the entire satisfaction of th


S.No

DETAILS

Unit Rate per 100 SFT


Rate per unit

Qty

MATERIAL
Concete Blocks (16" X 8" X 8")
Including 10% Wastage.

123.75

Nos

10.84

CFT

Cement ( OPC ).

0.55

Sand
Wall Ties

Mortar Required for 100 SFT Block work

Rs.

29.00

P.No.

Bags

Rs.

350.00

P.Bag

3.20

Cft

Rs.

18.00

P.Cft

8.00

No

Rs.

35.00

P.No

Total

(A).

LABOUR.
Mason

2.0

No

Rs.

500.00

per day

Labour

3.0

No

Rs.

300.00

per day

Bahishti

2.0

No

Rs.

300.00

per day

Scaffolder

0.3

No

Rs.

350.00

per day

Total

(B).

Item Rates.
Composite Rate for 100 SFT

Total

Composite Rate for one SFT.

Submitted By.

Checked By.

(A+B).

BOQ Item-03

400 x 200 x 200 MM Thick Block Masonry.

w block masonry walls of specified strength as per

approved quality of fine and course aggregate) laid in 1:6

r height, laid at specified levels, including cost of scaffolding,

out joints cutting, curing etc, complete in all respects and

s, specifications and to the entire satisfaction of the Engineer


Unit Rate per 100 SFT
Amount
MATERIAL
Rs.

3,588.75

Rs.

192.50

Rs.

57.60

Rs.

280.00

Rs.

4,118.85

Rs.

41.19

Rs.

1,000.00

Rs.

900.00

Rs.

600.00

Rs.

105.00

Rs.

2,605.00

Rs.

26.05

Rs.

6,724.00

Rs.

67.24

LABOUR.

Approved By.

BOQ Item-2.1
RATE ANALYSIS OF 4000PSI CONCRETE

Providing and laying, straight or curved cast-in place designed mix reinforced structural cem
cylinder crushing strength 4000 psi for Beams and Slab, using O.P cement including vibrating

mechanical vibrator, leveling, compacting, curing all as per specifications and to the entire sat
Engineer.
S.No

DETAILS

Unit Rate per CUM.


Rate per unit

Qty
MATERIAL

a.

Concrete Delivered from IJM Concrete.

b.

Wastage of concrete

1.00

CFT

5.00%

%age

Rs.

61.40

P.CFT
P.CFT

Total

(A).

LABOR.
a.

Mason

0.06

Hour

Rs.

62.50

P. Hour

b.

Labor

0.20

Hour

Rs.

31.25

P. Hour

c.

Curing of Concrete

0.03

Hour

Rs.

31.25

P. Hour
Total

Composite Rate for one CUM.

Submitted By.

Checked By.

BOQ Item-2.1

ALYSIS OF 4000PSI CONCRETE

t-in place designed mix reinforced structural cement concrete of

ms and Slab, using O.P cement including vibrating through electro

uring all as per specifications and to the entire satisfaction of the


Unit Rate per CUM.
Amount
MATERIAL
Rs.

61.40

Rs.

3.07

Rs.

64.50

Rs.

3.54

Rs.

6.19

Rs.

0.88

Rs.

10.62

Rs.

75.12

LABOR.

Approved By.

BOQ Item-5.1
RATE ANALYSIS OF CONCRETE FOR COLUMNS

Providing and laying, straight or curved cast-in place designed mix reinforced structural cemen
using O.P cement including vibrating through electro mechanical vibrator, leveling, compacting, c
specifications and to the entire satisfaction of the Engineer.

S.No

DETAILS

Unit Rate per CUM.


Rate per unit

Qty
MATERIAL

a.

Concrete Delivered from IJM Concrete.

1.00

CFT

b.

Wastage of concrete

c.

Rs.

125.00

P.CFT

5.00%

%age

Curing of Concrete (Concure from Fosroc)

0.06

LTR

Rs.

35.00

P.LTR

d.

Nitobond SBR (Fosroc)

0.01

LTR

Rs.

172.00

P.LTR

e.

Conbextra GP (Fosroc)

0.01

KG

Rs.

62.00

P.KG

f.

Mortar

0.01

CFT

Rs.

113.27

P.CFT

P.CFT

Total

(A).

LABOR.
a.

Mason

0.03

Hour

Rs.

62.50

P. Hour

b.

Labor

0.20

Hour

Rs.

31.25

P. Hour

c.

Curing of Concrete

0.03

Hour

Rs.

31.25

P. Hour
Total

Composite Rate for one CFT.

Submitted By.

Checked By.

BOQ Item-5.1

YSIS OF CONCRETE FOR COLUMNS

-in place designed mix reinforced structural cement concrete Raft,


electro mechanical vibrator, leveling, compacting, curing all as per
the Engineer.

Unit Rate per CUM.


Amount
MATERIAL
Rs.

125.00

Rs.

6.25

Rs.

1.98

Rs.

2.44

Rs.

0.88

Rs.

1.13

Rs.

137.70

Rs.

1.77

Rs.

6.19

Rs.

0.88

Rs.

8.85

Rs.

146.55

LABOR.

Approved By.

BOQ Item-5.2~5.5
RATE ANALYSIS OF CONCRETE FOR OTHER STRUCTURE

S.No

DETAILS

Unit Rate per CUM.


Rate per unit

Qty
MATERIAL

a.

Concrete Delivered from IJM Concrete.

1.00

CFT

b.

Wastage of concrete

c.

Rs.

99.50

P.CFT

5.00%

%age

Curing of Concrete (Concure from Fosroc)

0.06

LTR

Rs.

35.00

P.LTR

d.

Nitobond SBR (Fosroc)

0.01

LTR

Rs.

172.00

P.LTR

e.

Conbextra GP (Fosroc)

0.01

KG

Rs.

62.00

P.KG

f.

Mortar

0.01

CFT

Rs.

113.27

P.CFT

P.CFT

Total

(A).

LABOR.
a.

Mason

0.03

Hour

Rs.

62.50

P. Hour

b.

Labor

0.20

Hour

Rs.

31.25

P. Hour

c.

Curing of Concrete

0.03

Hour

Rs.

31.25

P. Hour
Total

Composite Rate for one CUM.

Submitted By.

Checked By.

BOQ Item-5.2~5.5

OF CONCRETE FOR OTHER STRUCTURE

Unit Rate per CUM.


Amount
MATERIAL
Rs.

99.50

Rs.

4.98

Rs.

1.98

Rs.

2.44

Rs.

0.88

Rs.

1.13

Rs.

110.90

Rs.

1.77

Rs.

6.19

Rs.

0.88

Rs.

8.85

Rs.

119.75

LABOR.

Approved By.

BOQ Item-06
RATE ANALYSIS OF STEEL REINFORCEMENT

Providing fabricating and fixing in position grade 60 reinforcing bars of any size of any diameter with 60,000

strength including the cost of straightening cutting, wastage and such overlaps as are not shown on the drawin

Chairs, chairs tying in all kinds of reinforced concrete and in any position at any level or elevations or at any h

conforming to the requirement of drawings and specifications, complete in all respects. Waste, lappage and r
on contractor account (Item rate to cover the cost of steel also)
S.No

DETAILS

Unit Rate per M.TON


Rate per unit

Qty
MATERIAL

a.

Steel Bar from approved manufacturers. (Cut to length)

1.00

KG

Rs.

65.00

b.

Binding Wire (20 SWG)

0.08

KG

Rs.

90.00

d.

Wastage of Steel Bar & B.Wire

5.00%

%age
Total

(A

Total

(B

LABOR
a.

Steel Fixers (Including cutting, bending & Fixing)

0.020

Hour

87.5

b.

Helpers (Including cutting, bending & Fixing)

0.045

Hour

43.75

Total
Note:

Submitted By.

Checked By.

(A + B

BOQ Item-06

SIS OF STEEL REINFORCEMENT

nforcing bars of any size of any diameter with 60,000 psi per sq. inch yield

age and such overlaps as are not shown on the drawings in position on M.S.

d in any position at any level or elevations or at any height and any position

ations, complete in all respects. Waste, lappage and rolling margin shall be

el also)
Unit Rate per M.TON
Rate per unit

Amount

MATERIAL

Total

P.KG

Rs.

65.00

P.KG

Rs.

7.20

Rs.

3.61

(A). Rs.

75.81

LABOR

Total
Total

P. Hour

Rs.

1.75

P. Hour

Rs.

1.97

(B). Rs.

3.72

(A + B ). Rs.

79.53

Approved By.

BOQ Item-7.3
RATE ANALYSIS OF FORMWORK FOR COLUMNS

Providing, fixing and removing of plasform as per drawing& specification and as directed by the Engineer.

S.No

DETAILS

Unit Rate per SFT


Rate per unit

Qty
MATERIAL

a.

Plasform

1.00

SFT

Rs.

13.00

P.SFT

b.

Mold Oil @ 5 Sqm with 1 Litre

0.20

Ltr

Rs.

10.04

P.SFT

c.

Steel Nails

0.15

Kg

Rs.

8.83

P.SFT

d.

G.I. Sheets or Unfor seen Items etc.

0.03

SFT

Rs.

34.39

P.SFT

e.

Spacer Blocks (avg 5pcs/SQM)

5.00

Pcs

Rs.

0.08

P.Pcs

Total

(A).

LABOR.
a.

Carpenters

0.12

Hour

Rs.

43.75

P. Hour

b.

Helpers

0.30

Hour

Rs.

25.00

P. Hour

Total
Total

Submitted By.

Checked By.

= (B)

(A + B ).

BOQ Item-7.3

F FORMWORK FOR COLUMNS

ing& specification and as directed by the Engineer.


Unit Rate per SFT
Amount
MATERIAL
Rs.

13.00

Rs.

2.01

Rs.

1.32

Rs.

1.03

Rs.

0.42

Rs.

17.80

Rs.

5.03

Rs.

7.50

Rs.

12.50

Rs.

30.30

LABOR.

Approved By.

BOQ Item-7.1/7.2
RATE ANALYSIS OF FORMWORK FOR WALLS

Providing, fixing and removing of plasform as per drawing& specification and as directed by the Engineer.

S.No

DETAILS

Unit Rate per SFT


Rate per unit

Qty
MATERIAL

a.

Plasform

1.00

SFT

Rs.

6.00

P.SFT

b.

Mold Oil @ 5 Sqm with 1 Litre

0.20

Ltr

Rs.

10.04

P.SFT

c.

Steel Nails

0.15

Kg

Rs.

8.83

P.SFT

d.

G.I. Sheets or Unfor seen Items etc.

0.03

SFT

Rs.

34.39

P.SFT

e.

Spacer Blocks (avg 5pcs/SQM)

5.00

Pcs

Rs.

0.08

P.Pcs

Total

(A).

LABOR.
a.

Carpenters

0.12

Hour

Rs.

43.75

P. Hour

b.

Helpers

0.30

Hour

Rs.

25.00

P. Hour

Total
Total

Submitted By.

Checked By.

= (B)

(A + B ).

BOQ Item-7.1/7.2

OF FORMWORK FOR WALLS

ing& specification and as directed by the Engineer.


Unit Rate per SFT
Amount
MATERIAL
Rs.

6.00

Rs.

2.01

Rs.

1.32

Rs.

1.03

Rs.

0.42

Rs.

10.80

Rs.

5.03

Rs.

7.50

Rs.

12.50

Rs.

23.30

LABOR.

Approved By.

BOQ Item-7.4/7.5
RATE ANALYSIS OF FORMWORK FOR BEAMS AND SLABS

Providing, fixing and removing of plasform as per drawing& specification and as directed by the Engineer.

S.No

DETAILS

Unit Rate per SFT


Rate per unit

Qty
MATERIAL

a.

Plasform

1.00

SFT

Rs.

4.00

P.SFT

b.

Mold Oil @ 5 Sqm with 1 Litre

0.20

Ltr

Rs.

10.04

P.SFT

c.

Steel Nails

0.15

Kg

Rs.

8.83

P.SFT

d.

G.I. Sheets or Unfor seen Items etc.

0.03

SFT

Rs.

34.39

P.SFT

e.

Spacer Blocks (avg 5pcs/SQM)

5.00

Pcs

Rs.

0.08

P.Pcs

Total

(A).

LABOR.
a.

Carpenters

0.12

Hour

Rs.

43.75

P. Hour

b.

Helpers

0.30

Hour

Rs.

25.00

P. Hour

Total
Total

Submitted By.

Checked By.

= (B)

(A + B ).

BOQ Item-7.4/7.5

ORMWORK FOR BEAMS AND SLABS

ing& specification and as directed by the Engineer.


Unit Rate per SFT
Amount
MATERIAL
Rs.

4.00

Rs.

2.01

Rs.

1.32

Rs.

1.03

Rs.

0.42

Rs.

8.80

Rs.

5.03

Rs.

7.50

Rs.

12.50

Rs.

21.30

LABOR.

Approved By.

Basic Material Rates Supply By Employer


S.No

DETAILS

Rate

Remarks

MATERIAL
a.

Concrete (1:4:8)

Rs.

2,165.00

/ CUM

b.

Concrete (3750 PSI) for COLUMNS

Rs.

4,414.00

/ CUM

c.

Concrete (3000 PSI) for Other Structure

Rs.

3,514.00

/ CUM

d.

Steel G-60

Rs.

53,000.00

e.

/ M. Ton

SUMMARY OF BUDGETTED OFFICE EXPENSES OF "CMS"


SR #
1

DESCRIPTION
RENTAL OF STAFF HOUSE
a) MONTHLY RENTAL
b) MAINTENANCE FEES
c) ELECTRICITY
d) SUI GAS
e) CLEANER'S COST
f) DRINKING MINERAL WATER
g) FURNISHING
OFFICE STAFF SALARIES
MALAYSIAN
a) PROJECT DIRECTOR
b) FINANCE AND ACCOUNTS MANAGER
LOCAL STAFF
a) PROJECT MANAGER
b) CONSTRUCTION MANAGER
c) ADMIN/HR MANAGER
d) ELECTRICAL ENGINEER
e) MECHANICAL ENGINEER
f) CONTRACTS EXECUTIVE
g) PA/IT COORDINATOR
h) DOCUMENT CONTROLLER
j) OFFICE BOY
k) TIME-KEEPER
m) COOK
n) DRIVER

UNIT

QTY

MTH
MTH
MTH
MTH
MTH
MTH
LS

18
18
18
18
18
18

MTH
MTH

18
18

MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH

18
18
18
18
18
18
18
18
18
18
18
18

AIR TICKETS

TRIPS

12

PURCHASE OF SALOON CAR 1500CC

UNIT

FUEL AND MAINTENANCE

UNIT

18

MEDICAL ALLOWANCE

MTH

18

ENTERTAIMENTS/ FOOD & DRINKS

MTH

18

TOTAL :

PENSES OF "CMS"
RATE

AMOUNT (RS)

42,000
2,000
20,000
1,500
3,000
4,500

756,000
36,000
360,000
27,000
54,000
81,000
100,000

750,000
250,000

13,500,000
4,500,000

80,000
65,000
70,000
40,000
30,000
35,000
35,000
25,000
12,000
15,000
10,000
12,000

1,440,000
1,170,000
1,260,000
720,000
540,000
630,000
630,000
450,000
216,000
270,000
180,000
216,000

60,000

720,000

1,000,000

1,000,000

20,000

360,000

15,000

270,000

10,000

180,000
29,666,000

420,000.00

1,429,000

COMPUTATION OF BUDGETTED PROFIT

SR #
1

DESCRIPTION

UNIT

QTY

UNIT

100

ESTIMATED CONSTRUCTION COST :a)

SAFARI VILLA UNIT - B

MANAGEMENT FEE @ 10 %

LESS : OFFICE EXPENSES

LESS : PROPOSED PROJECT INCENTIVES

BUDGETTED PROFIT

MTH

DGETTED PROFIT
BUILT-UP
FLOOR AREA
(SFT)

BUDGETTED
COST/ SFT

5916

BASIC
SALARY/MTH
714,500

800

AMOUNT (RS)

473,280,000

10%

47,328,000

6.27%

(29,666,000)

0.91%

(4,287,002)

13,374,998
2.83%

COST BUDGET

CONSTRUCTION OF SAFARI VILLAS TYPE - B (GREY STRUCTURE)


BAHRIA TOWN GARDEN CITY
S.NO

DESCRIPTION

UNITS

BUILT-UP FLOOR AREA = 5916 SFT

QUANTITY

LABOR (A)
DIRECT UNIT
COST

1)

Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken stone
graded in foundation as specified.

2.1b

Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken stone
graded in foundation as specified.

2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
3)

3.1
3.2
3.3
3.4
3.5

4.1
4.2
4.3
4.4
4.5

MATERIAL (C)

MACHINERY (B)
UNIT COST

TOTAL COST

UNIT COST

RATE (Rs)

AMOUNT (Rs)

TOTAL COST

13,228.00

0.85

11,243.80

0.07

925.96

12,169.76

0.95

12,566.60

1.87

24,736.36

Cft

12,338.00

1.15

14,188.70

0.09

1,110.42

15,299.12

2.80

34,546.40

4.04

49,845.52

Cft

866.29

5.00

4,331.45

0.85

736.35

5,067.80

3.75

3,248.59

64.50

55,875.71

74.10

64,192.09

Cft

644.63

5.00

3,223.15

0.85

547.94

3,771.09

3.75

2,417.36

64.50

41,578.64

74.10

47,767.08

Cft
Cft
Cft
Cft
Cft

2,703.76
574.00
2,644.23
1,732.89
7,654.88

5.00

13,518.80

0.71

1,919.67

15,438.47

7.08

19,142.62

104.76

283,245.90

117.55

317,826.99

Kg
Kg
Kg
Kg
Kg

6,099.68

Providing and Placing reinforced cement concrete in different Grades using


crushed or broken stone graded as specified in specificatins.
Raft and Column Footing ( 3,000 PSI )
Retaining Wall ( 3,000 PSI )
Columns ( 3,750 PSI )
Slabs ( 3,000 PSI )
Lintels & Beams ( 3,000 PSI )

5.00

2,870.00

0.71

407.54

3,277.54

7.08

4,063.92

113.84

65,344.16

126.63

72,685.62

5.00

13,221.15

0.71

1,877.40

15,098.55

7.08

18,721.15

102.76

271,721.07

115.55

305,540.78

5.00

8,664.45

0.71

1,230.35

9,894.80

7.08

12,268.86

102.76

178,071.78

115.55

200,235.44

2.20

13,419.30

0.20

1,219.94

14,639.24

0.40

2,439.87

55.00

335,482.40

57.80

352,561.50

STEEL

Cutting, Bending & Fixing of Steel as per drawing as directed by engineer


incharge.
Column Footing
Retaining Wall

Columns @ 5.454 KG/CFT


Slabs
Slab, Lintels & Beams

3,133.86
-

2.20
###

14,785.91

2.20

217.73
3,491.44
5,979.61
6,849.44
16,538.22
7.09

10.00

24,019.45
110.76

6,894.49

0.20

626.77

32,529.00

0.20

2,177.30

1.00

7,521.26

2,957.18

0.40

1,253.54

35,486.18

0.40

2,395.03

0.20

5,914.36

55.00

172,362.30

55.00

57.80

181,137.11

813,225.05

57.80

1,698.29

19.00

854,625.60

FORMWORK
Providing, Fixing & Removal of formwork with good quality & smooth
surface of concrete after removal, complete in all respect or as directed by
the engineer incharge.
Raft & Column Footing
Retaining Wall
Columns
Slabs
Lintels & Beams

Sft
Sft
Sft
Sft
Sft
M2/M3

5)

DIRECT &
INDIRECT TOTAL
COST

Cft

KG/M3
4)

INDIRECT TOTAL
COST

CONCRETE WORKS

2.1a

2.2

INDIRECT
UNIT COST

EXCAVATION WORKS

1.1 Excavation in hard soil upto 1.5 m depth to obtain earth for embankments
or to clear building sites etc.
1.2 Earth Filling in area where required in 150 mm layers, borrow from other
site and fill according to requirement and as directed by the engineer
incharge.

2)

DIRECT TOTAL
COST

217.73

43.55

7.80
-

4,136.87

10.00

34,914.40

1.00

3,491.44

38,405.84

0.20

698.29

16.80

58,656.19

28.00

97,760.32

10.00

59,796.10

1.00

5,979.61

65,775.71

0.20

1,195.92

9.80

58,600.18

21.00

125,571.81

10.00

68,494.40

1.00

6,849.44

75,343.84

0.20

1,369.89

9.80

67,124.51

21.00

143,838.24

810.71

BLOCK WORK
Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand Mortar
(1:4) In Super Structure , including form work, curing etc complete in all
respect or as directed by the engineer incharge.

Cft

4,053.55

13.43

54,439.18

1.07

4,337.30

58,776.48

0.20

50.33

204,015.17

65.03

263,602.36

6)

Water Proofing as specified

Sft

1,894.94

14.00

26,529.16

1.12

2,122.33

28,651.49

56.00

106,116.64

71.12

134,768.13

7)

Termite Proofing in area where required with approved material from main
-

2.66

14,291.62

3.47

18,643.58

121,401.88

16.89

contractor, according to requirement and as directed by the engineer


incharge.
8)

9)
10)

11)
11.01
11.02
11.03
11.04
11.05
11.06
11.07
11.08
11.09
11.10
11.11
11.12
11.13
11.14
11.15
11.16
11.17

Sft

5,372.79

0.75

4,029.59

0.06

322.37

4,351.96

Plaster works
Applying 13mm thick cement and sand plaster (1:4) to be trowelled
smooth with steel trowel to brick or block wall,as Directed by the engineer
incharge.

Sft

15,156.29

8.00

121,250.32

0.68

10,306.28

131,556.60

COST OF CIVIL WORKS

RS

47,186.02

542,920.76

COST PER SFT

RS

7.98

91.77

EMBEDDED ITEMS FOR ELECTRICAL WORKS

Sft

5,916.00

6.83

40,406.28

0.55

3,253.80

43,660.08

0.30

1,774.80

63.53

375,843.48

71.21

421,278.36

EMBEDDED ITEMS FOR PLUMBING WORKS

Sft

5,916.00

6.57

38,868.12

0.53

0.27

1,597.32

44.50

263,262.00

51.87

306,862.92

COST OF ELECTRICAL & PLUMBING WORKS


COST PER SFT

RS
RS

OTHER WORKS
Overhead water tank concrete
Overhead water tank reinforcement
Overhead water tank formwork
PVC waterstop for OHWT
Manhole cover and insulation for OHWT
Underground watertank concrete
Underground watertank reinforcement
Underground watertank formwork
PVC waterstop for UGWT
Waterproofing for UGWT wall (with Bitumen)
Gully trap (2 Nos) & Manhole (1 No)
Plastering of Tank and Manholes
Boundary wall brickwork
Boundary wall RCC
Boundary wall Lean Concrete
Boundary wall Plastering
PCC (1:4:8) for walkway

Cft
Kg
Sft
Rft
Set
Cft
Kg
Sft
Rft
Sft
Cft
Sft
Cft
Cft
Cft
Sft
Cft

COST OF OTHER WORKS


COST PER SFT

RS
RS

COST FOR CIVIL, ELECTRICAL, PLUMBING & OTHER WORKS

Covered Area (Sft)

495,734.74
83.80

147.39
558.66
450.00
20.00
1.00
96.05
325.00
432.00
28.00
140.00
73.50
383.00
420.00
210.00
92.00
2,240.00
184.92

0.20

3,031.26

8.01

123,732.89

2,848,811.49

20.91

255,989.74
3,515,465.14

481.54

594.23

3,135.48

42,003.60

79,274.40

6,389.28

85,663.68

3,372.12

639,105.48

728,141.28

13.40

1.08

14.48

0.57

108.03

123.08

8.85

1,304.40

0.71

104.65

1,409.05

7.08

1,043.52

104.76

15,440.58

121.40

17,893.15

2.56

1,430.17

0.20

111.73

1,541.90

0.30

167.60

56.00

31,284.96

59.06

32,994.46

12.50

5,625.00

1.00

450.00

6,075.00

0.17

76.50

8.80

3,960.00

22.47

10,111.50

2.20

44.00

0.18

3.60

47.60

165.00

3,300.00

167.38

72.12

72.12

5.77

5.77

77.89

2,500.00

2,500.00

2,577.89

2,577.89

8.85

850.04

0.71

68.20

918.24

7.08

680.03

104.76

10,062.20

121.40

11,660.47

2.56

832.00

0.20

65.00

897.00

0.30

97.50

56.00

18,200.00

59.06

19,194.50

12.50

5,400.00

1.00

432.00

5,832.00

0.17

73.44

8.80

3,801.60

22.47

9,707.04

2.20

61.60

0.18

5.04

66.64

165.00

4,620.00

167.38

4,686.64

0.56

78.40

0.04

5.60

84.00

0.17

23.80

5.33

746.20

6.10

854.00

15.00

1,102.50

1.20

88.20

1,190.70

0.17

12.50

85.00

6,247.50

101.37

7,450.70

8.50

3,255.50

0.68

260.44

3,515.94

0.17

65.11

8.00

3,064.00

17.35

6,645.05

13.00

5,460.00

1.04

436.80

5,896.80

0.17

71.40

8.01

3,364.20

22.22

9,332.40

8.85

1,858.50

0.71

149.10

2,007.60

7.08

1,486.80

104.76

21,999.60

121.40

25,494.00

8.85

814.20

0.71

65.32

879.52

7.08

651.36

104.76

9,637.92

121.40

11,168.80

8.50

19,040.00

0.68

1,523.20

20,563.20

0.17

380.80

8.01

17,942.40

17.36

38,886.40

10.62

1,963.85

0.85

157.18

2,121.03

3.95

730.43

64.50

11,927.34

79.92

3,347.60

14,778.81

49,192.28

3,931.83

53,124.11

5,560.79

168,098.50

226,783.41

8.32

0.66

8.98

0.94

28.41

38.33

624,201.42

57,507.13

681,708.55

132,665.80

3,656,015.47

4,470,389.83

5,916.00

5,916.00

5,916.00

5,916.00

5,916.00

5,916.00

105.51

9.72

115.23
6.76
122.00
15.25%

22.42
1.32
23.74
2.97%

617.99
36.28
654.26
81.78%

755.64
44.36
800.00

CHECK

COST PER SFT


ADD: CONTINGENCIES FOR ANY OTHER COST
TOTAL BUDGETTED COST :

13.96%

1.29%

DIRECT LABOUR
(A)

INDIRECT LABOUR
(B)

TOTAL LABOUR
(A+B)

MAXIMUM COST OF CONSTRUCTION

71,973,480.00

5,750,713.00

78,091,200.00

BUDGETTED LABOUR COST

62,420,142.00

5,750,713.00

68,170,855.00

COST SAVING

9,553,338.00

9,920,345.00

MACHINERY
(C)
13,748,784.00

MATERIAL
(D)
378,961,212.00

800.00

TOTAL AMOUNT
(A+B+C+D)
473,280,000.00

755.64

Das könnte Ihnen auch gefallen