Beruflich Dokumente
Kultur Dokumente
LABOR (A)
S.NO
DESCRIPTION
UNIT
QUANTITY
DIRECT UNIT
COST
DIRECT TOTAL
COST
INDIRECT
UNIT COST
MACHINERY (B)
INDIRECT
TOTAL COST
DIRECT &
INDIRECT TOTAL
COST
UNIT
COST
MATERIAL (C)
TOTAL COST
UNIT COST
RATE (Rs)
TOTAL COST
AMOUNT (Rs)
EXCAVATION WORKS
1.1 Excavation in hard soil upto 1.5 m depth to obtain earth for
embankments or to clear building sites etc.
1.2 Earth Filling in area where required in 150 mm layers, borrow from
other site and fill according to requirement and as directed by the
engineer incharge.
Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.
2.1b
Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
3)
3.1
3.2
3.3
3.4
3.5
13,228.00
0.85
11,243.80
0.07
925.96
12,169.76
0.95
12,566.60
1.87
24,736.36
0.52%
Cft
12,338.00
1.15
14,188.70
0.09
1,110.42
15,299.12
2.80
34,546.40
4.04
49,845.52
1.05%
2,036.38
0.34
27,468.88
4.64
74,581.88
12.61
1.58%
RS
10.62
9,200.00
0.85
736.35
9,936.35
3.75
3,248.59
64.50
55,875.71
79.72
69,060.64
1.46%
Cft
644.63
10.62
6,845.97
0.85
547.94
7,393.91
3.75
2,417.36
64.50
41,578.64
79.72
51,389.90
1.09%
Cft
Cft
Cft
Cft
Cft
2,703.76
574.00
2,644.23
1,732.89
7,654.88
8.85
8.85
8.85
8.85
8.85
23,928.28
5,079.90
23,401.44
15,336.08
0.90
0.90
0.90
0.90
0.90
2,433.38
516.60
2,379.81
1,559.60
26,361.66
5,596.50
25,781.25
16,895.68
7.10
7.10
7.10
7.10
7.10
19,196.70
4,075.40
18,774.03
12,303.52
104.76
113.84
102.76
102.76
283,245.90
65,344.16
271,721.07
178,071.78
121.61
16.85
130.69
119.61
119.61
328,804.25
75,016.06
316,276.35
207,270.97
6.95%
RS
8,173.68
1.38
91,965.35
15.55
1,219.94
626.77
2,957.18
20,128.95
10,341.74
48,793.50
4,803.89
0.81
79,264.19
13.40
232.97
3,735.84
6,398.18
7,328.90
3,174.50
50,905.19
87,182.71
99,864.83
17,695.89
2.99
241,127.23
40.76
Column Footing
Retaining Wall
Columns @ 5.454 KG/CFT
Slabs
Slab, Lintels & Beams
83,791.67
14.16
RS
STEEL
Cutting, Bending & Fixing of Steel as per drawing as directed by
engineer incharge.
Kg
Kg
Kg
Kg
Kg
6,099.68
3,133.86
14,785.91
24,019.45
110.76
3.10
3.10
3.10
18,909.01
9,714.97
45,836.32
0.20
0.20
0.20
74,460.30
12.59
RS
RS
60,015.60
10.14
0.40
0.40
0.40
2,439.87
1,253.54
5,914.36
895,837.26
151.43
55.00
55.00
55.00
9,607.77
1.62
335,482.40
172,362.30
813,225.05
1,047,818.17
177.12
58.70
58.70
58.70
1,321,069.75
223.30
358,051.22
183,957.58
867,932.92
1,409,941.72
238.33
1.59%
6.68%
4.38%
Sft
Sft
Sft
Sft
Sft
M2/M3
217.73
3,491.44
5,979.61
6,849.44
16,538.22
7.09
13.51
13.51
13.51
13.51
2,941.53
47,169.35
80,784.53
92,535.93
1.07
1.07
1.07
1.07
1.07
0.51
0.51
0.51
0.51
0.51
111.04
1,780.63
3,049.60
3,493.21
8.30
24.00
24.00
14.20
1,807.16
83,794.56
143,510.64
97,262.05
23.39
39.09
39.09
29.29
7.57%
3.89%
18.34%
29.79%
5,092.70
136,480.39
233,742.95
200,620.10
0.11%
0.00%
2.88%
4.94%
4.24%
575,936.14
97.35
12.17%
135.00
223,431.34
37.77
RS
RS
8,434.48
1.43
326,374.41
55.17
6)
11)
11.01
11.02
11.03
11.04
11.05
11.06
engineer incharge.
Sft
ANTI-TERMITE WORKS
COST PER SFT
RS
5,372.79
0.75
4,029.59
4,029.59
0.68
0.06
322.37
322.37
0.05
4,351.96
4,351.96
0.74
2.66
14,291.62
14,291.62
2.42
3.47
18,643.58
18,643.58
3.15
0.39%
0.39%
1,894.94
14.00
26,529.16
26,529.16
4.48
1.12
2,122.33
2,122.33
0.36
28,651.49
28,651.49
4.84
56.00
106,116.64
106,116.64
17.94
71.12
134,768.13
134,768.13
22.78
2.85%
2.85%
147.39
558.66
450.00
20.00
1.00
96.05
8.85
3.10
13.51
25.00
200.00
8.85
1,304.40
1,731.85
6,079.50
500.00
200.00
850.04
0.90
0.20
1.07
0.18
5.77
0.90
132.65
111.73
481.50
3.60
5.77
86.45
1,437.05
1,843.58
6,561.00
503.60
205.77
936.49
104.76
56.00
8.30
165.00
2,500.00
104.76
15,440.58
31,284.96
3,735.00
3,300.00
2,500.00
10,062.20
121.61
59.60
23.39
190.18
2,705.77
121.61
17,924.10
33,296.14
10,525.50
3,803.60
2,705.77
11,680.64
0.38%
0.70%
0.22%
0.08%
0.06%
0.25%
RS
Sft
RS
RS
Cft
Kg
Sft
Rft
Set
Cft
7.10
0.30
0.51
7.10
1,046.47
167.60
229.50
681.96
22.14%
FORMWORK
Providing, Fixing & Removal of formwork with good quality & smooth
surface of concrete after removal, complete in all respect or as
directed by the engineer incharge.
COST OF FORMWORK
COST PER SFT
7)
866.29
KG/M3
4.1
4.2
4.3
4.4
4.5
47,113.00
7.96
Cft
25,432.50
4.30
RS
CONCRETE WORKS
2.1a
2.2
Cft
Kg
Sft
Rft
11.07
11.08
11.09
11.10
11.11
11.14
11.15
11.17
Sft
Cft
Cft
Cft
Cft
RS
325.00
432.00
28.00
140.00
73.50
210.00
92.00
184.92
3.10
13.51
25.00
28.00
15.00
8.85
8.85
10.62
RS
1,007.50
5,836.32
700.00
3,920.00
1,102.50
1,858.50
814.20
1,963.85
27,868.66
4.71
0.20
1.07
0.18
2.04
1.20
0.90
0.90
0.85
465,543.22
78.69
RS
RS
65.00
462.24
5.04
285.60
88.20
189.00
82.80
157.18
2,156.76
0.36
1,072.50
6,298.56
705.04
4,205.60
1,190.70
2,047.50
897.00
2,121.03
30,025.42
5.08
37,311.30
6.31
502,854.52
85.00
0.30
0.51
0.17
0.17
7.10
7.10
3.95
97.50
220.32
23.80
12.50
1,491.00
653.20
730.43
5,354.28
0.91
56.00
8.30
165.00
5.33
85.00
104.76
104.76
64.50
130,525.13
22.06
18,200.00
3,585.60
4,620.00
746.20
6,247.50
21,999.60
9,637.92
11,927.34
143,286.90
24.22
59.60
23.39
190.18
35.54
101.37
121.61
121.61
79.92
2,806,976.58
474.47
19,370.00
10,104.48
5,325.04
4,975.60
7,450.70
25,538.10
11,188.12
14,778.81
178,666.60
30.20
3,440,356.22
581.53
0.41%
0.21%
0.11%
0.11%
0.16%
0.54%
0.24%
0.31%
3.78%
72.69%
BLOCK WORK
Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand
Mortar (1:4) In Super Structure , including form work, curing etc
complete in all respect or as directed by the engineer incharge.
8)
Plaster works
Applying 13mm thick cement and sand plaster (1:4) to be trowelled
smooth with steel trowel to brick or block wall,as Directed by the
engineer incharge.
10)
11)
11.12
11.13
11.16
Cft
4,053.55
13.43
54,439.18
1.07
4,337.30
58,776.48
0.20
810.71
50.33
204,015.17
65.03
263,602.36
5.57%
Sft
15,156.29
8.50
128,828.47
0.68
10,306.28
139,134.75
0.20
3,031.26
8.01
121,401.88
17.39
263,567.88
5.57%
14,643.58
2.48
197,911.23
33.45
527,170.24
89.11
11.14%
183,267.65
30.98
RS
RS
3,841.97
0.65
325,417.05
55.01
Sft
5,916.00
5.33
31,532.28
0.55
3,253.80
34,786.08
0.30
1,774.80
63.53
375,843.48
69.71
412,404.36
8.71%
Sft
5,916.00
5.07
29,994.12
0.53
3,135.48
33,129.60
0.27
1,597.32
44.50
263,262.00
50.37
297,988.92
6.30%
RS
61,526.40
10.40
6,389.28
1.08
67,915.68
11.48
710,393.28
120.08
15.01%
41,991.77
260.44
436.80
1,523.20
2,220.44
0.38
3,515.94
5,896.80
20,563.20
29,975.94
5.07
6,645.05
9,332.40
38,886.40
54,863.85
9.27
0.14%
0.20%
0.82%
1.16%
272,549.55
46.07
23,253.30
3.93
295,802.85
50.00
7,731.40
1.31
988,893.13
167.16
1,292,427.37
218.46
27.31%
465,543.22
78.69
37,311.30
6.31
502,854.52
85.00
130,525.13
22.06
2,806,976.58
474.47
3,440,356.22
581.53
72.69%
272,549.55
46.07
23,253.30
3.93
295,802.85
50.00
7,731.40
1.31
988,893.13
167.16
1,292,427.37
218.46
27.31%
5,916.00
5,916.00
5,916.00
5,916.00
5,916.00
5,916
738,093
60,565
798,657
138,257
3,795,870
4,732,784
124.76
124.76
15.60%
10.24
10.24
1.28%
135.00
135.00
16.88%
23.37
23.37
2.92%
641.63
641.63
80.20%
800.00
800.00
RS
OTHER WORKS
Plastering of Tank and Manholes
Boundary wall brickwork
Boundary wall Plastering
Sft
Cft
Sft
RS
383.00
420.00
2,240.00
RS
RS
RS
8.50
13.00
8.50
3,255.50
5,460.00
19,040.00
27,755.50
4.69
DIRECT LABOUR
(A)
0.68
1.04
0.68
INDIRECT
LABOUR
(B)
TOTAL LABOUR
(A+B)
3,372.12
0.57
0.17
0.17
0.17
65.11
71.40
380.80
517.31
0.09
MACHINERY
(C)
639,105.48
108.03
8.00
8.01
8.01
3,064.00
3,364.20
17,942.40
24,370.60
4.12
MATERIAL
(D)
17.35
22.22
17.36
800.00
TOTAL AMOUNT
(A+B+C+D)
73,808,016
6,057,984
79,866,000
13,825,692
379,588,308
473,280,000
57,272,796
6,057,984
63,330,780
12,595,164
379,588,308
455,514,252
16,535,220
16,535,220
1,230,528
17,765,748
100.00%
0.00%
100.00%
COST BUDGET
S.NO
DESCRIPTION
UNIT
QUANTITY
LABOR (A)
DIRECT UNIT
COST
DIRECT TOTAL
COST
MACHINERY (B)
INDIRECT
UNIT COST
INDIRECT
TOTAL COST
DIRECT &
INDIRECT
TOTAL COST
UNIT
COST
RATE (Rs)
MATERIAL (C)
TOTAL COST
UNIT COST
AMOUNT (Rs)
%
TOTAL COST
EXCAVATION WORKS
1.1 Excavation in hard soil upto 1.5 m depth to obtain earth for
embankments or to clear building sites etc.
1.2 Earth Filling in area where required in 150 mm layers, borrow from
other site and fill according to requirement and as directed by the
engineer incharge.
Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.
2.1b
Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
3)
3.1
3.2
3.3
3.4
3.5
13,228.00
0.85
11,243.80
0.07
925.96
12,169.76
0.95
12,566.60
1.87
24,736.36
0.52%
Cft
12,338.00
1.15
14,188.70
0.09
1,110.42
15,299.12
2.80
34,546.40
4.04
49,845.52
1.05%
2,036.38
0.34
27,468.88
4.64
74,581.88
12.61
1.58%
RS
10.62
9,200.00
0.85
736.35
9,936.35
3.75
3,248.59
64.50
55,875.71
79.72
69,060.64
1.46%
Cft
644.63
10.62
6,845.97
0.85
547.94
7,393.91
3.75
2,417.36
64.50
41,578.64
79.72
51,389.90
1.09%
2,703.76
574.00
2,644.23
1,732.89
7,654.88
8.85
8.85
8.85
8.85
23,928.28
5,079.90
23,401.44
15,336.08
0.71
0.71
0.71
0.71
1,919.67
407.54
1,877.40
1,230.35
25,847.95
5,487.44
25,278.84
16,566.43
7.08
7.08
7.08
7.08
19,142.62
4,063.92
18,721.15
12,268.86
104.76
113.84
102.76
102.76
283,245.90
65,344.16
271,721.07
178,071.78
121.40
130.48
119.40
119.40
328,236.46
74,895.52
315,721.06
206,907.07
6.94%
Cft
Cft
Cft
Cft
Cft
RS
RS
6,719.25
1.14
90,510.92
15.30
1,219.94
626.77
2,957.18
16,835.12
8,649.45
40,809.11
4,803.89
0.81
66,293.68
11.21
217.73
3,491.44
5,979.61
6,849.44
2,939.36
47,134.44
80,724.74
92,467.44
16,538.22
2.80
223,265.98
37.74
STEEL
Cutting, Bending & Fixing of Steel as per drawing as directed by
engineer incharge.
Column Footing
Retaining Wall
Columns @ 5.454 KG/CFT
Slabs
Slab, Lintels & Beams
Kg
Kg
Kg
Kg
Kg
83,791.67
14.16
6,099.68
3,133.86
14,785.91
24,019.45
110.76
2.56
2.56
2.56
15,615.18
8,022.68
37,851.93
0.20
0.20
0.20
61,489.79
10.39
RS
RS
59,862.50
10.12
0.40
0.40
0.40
2,439.87
1,253.54
5,914.36
895,837.26
151.43
55.00
55.00
55.00
9,607.77
1.62
335,482.40
172,362.30
813,225.05
1,046,210.65
176.84
58.16
58.16
58.16
1,321,069.75
223.30
354,757.39
182,265.30
859,948.53
1,396,971.22
236.13
1.58%
6.67%
4.37%
22.11%
7.50%
3.85%
18.17%
29.52%
FORMWORK
Providing, Fixing & Removal of formwork with good quality & smooth
surface of concrete after removal, complete in all respect or as
directed by the engineer incharge.
Raft & Column Footing
Retaining Wall
Columns
Slabs
Lintels & Beams
COST OF FORMWORK
COST PER SFT
7)
866.29
KG/M3
4.1
4.2
4.3
4.4
4.5
47,113.00
7.96
Cft
25,432.50
4.30
RS
CONCRETE WORKS
2.1a
2.2
Cft
Sft
Sft
Sft
Sft
Sft
M2/M3
RS
217.73
3,491.44
5,979.61
6,849.44
16,538.22
7.09
12.50
12.50
12.50
12.50
2,721.63
43,643.00
74,745.13
85,618.00
1.00
1.00
1.00
1.00
206,727.76
34.94
RS
0.20
0.20
0.20
0.20
43.55
698.29
1,195.92
1,369.89
3,307.65
7.80
16.80
9.80
9.80
6,615.30
1.12
1,698.29
58,656.19
58,600.18
67,124.51
21.50
30.50
23.50
23.50
186,079.17
31.45
4,681.20
106,488.92
140,520.84
160,961.84
0.10%
0.00%
2.25%
2.97%
3.40%
412,652.80
69.75
8.72%
6)
11)
11.01
11.02
11.03
11.04
11.05
11.06
11.07
11.08
11.09
11.10
11.11
11.14
11.15
11.17
5,372.79
0.75
4,029.59
4,029.59
0.68
0.06
322.37
322.37
0.05
4,351.96
4,351.96
0.74
2.66
14,291.62
14,291.62
2.42
3.47
18,643.58
18,643.58
3.15
0.39%
0.39%
Sft
RS
RS
1,894.94
14.00
26,529.16
26,529.16
4.48
1.12
2,122.33
2,122.33
0.36
28,651.49
28,651.49
4.84
56.00
106,116.64
106,116.64
17.94
71.12
134,768.13
134,768.13
22.78
2.85%
2.85%
Cft
Kg
Sft
Rft
Set
Cft
Kg
Sft
Rft
Sft
Cft
Cft
Cft
Cft
RS
147.39
558.66
450.00
20.00
1.00
96.05
325.00
432.00
28.00
140.00
73.50
210.00
92.00
184.92
8.85
2.56
12.50
2.20
72.12
8.85
2.56
12.50
2.20
0.56
15.00
8.85
8.85
10.62
0.71
0.20
1.00
0.18
5.77
0.71
0.20
1.00
0.18
0.04
1.20
0.71
0.71
0.85
104.65
111.73
450.00
3.60
5.77
68.20
65.00
432.00
5.04
5.60
88.20
149.10
65.32
157.18
1,711.39
0.29
1,409.05
1,541.90
6,075.00
47.60
77.89
918.24
897.00
5,832.00
66.64
84.00
1,190.70
2,007.60
879.52
2,121.03
23,148.17
3.91
104.76
56.00
8.80
165.00
2,500.00
104.76
56.00
8.80
165.00
5.33
85.00
104.76
104.76
64.50
15,440.58
31,284.96
3,960.00
3,300.00
2,500.00
10,062.20
18,200.00
3,801.60
4,620.00
746.20
6,247.50
21,999.60
9,637.92
11,927.34
143,727.90
24.29
121.40
59.06
22.47
167.38
2,577.89
121.40
59.06
22.47
167.38
6.10
101.37
121.40
121.40
79.92
17,893.15
32,994.46
10,111.50
3,347.60
2,577.89
11,660.47
19,194.50
9,707.04
4,686.64
854.00
7,450.70
25,494.00
11,168.80
14,778.81
171,919.56
29.06
0.38%
0.70%
0.21%
0.07%
0.05%
0.25%
0.41%
0.21%
0.10%
0.02%
0.16%
0.54%
0.24%
0.31%
3.63%
RS
1,304.40
1,430.17
5,625.00
44.00
72.12
850.04
832.00
5,400.00
61.60
78.40
1,102.50
1,858.50
814.20
1,963.85
21,436.78
3.62
RS
RS
429,437.25
72.59
34,253.83
5.79
463,691.08
78.38
83.00
128,242.05
21.68
Sft
RS
RS
7.08
0.30
0.17
7.08
0.30
0.17
0.17
0.17
7.08
7.08
3.95
1,043.52
167.60
76.50
680.03
97.50
73.44
23.80
12.50
1,486.80
651.36
730.43
5,043.48
0.85
2,667,122.34
450.83
3,255,747.82
550.33
68.79%
BLOCK WORK
Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand
Mortar (1:4) In Super Structure , including form work, curing etc
complete in all respect or as directed by the engineer incharge.
8)
Plaster works
Applying 13mm thick cement and sand plaster (1:4) to be trowelled
smooth with steel trowel to brick or block wall,as Directed by the
engineer incharge.
10)
11)
11.12
11.13
11.16
Cft
4,053.55
13.43
54,439.18
1.07
4,337.30
58,776.48
0.20
810.71
50.33
204,015.17
65.03
263,602.36
Sft
15,156.29
8.50
128,828.47
0.68
10,306.28
139,134.75
0.20
3,031.26
8.01
121,401.88
17.39
263,567.88
5.57%
14,643.58
2.48
197,911.23
33.45
527,170.24
89.11
11.14%
8.90%
183,267.65
30.98
RS
RS
3,841.97
0.65
325,417.05
55.01
5.57%
Sft
5,916.00
6.83
40,406.28
0.55
3,253.80
43,660.08
0.30
1,774.80
63.53
375,843.48
71.21
421,278.36
Sft
5,916.00
6.57
38,868.12
0.53
3,135.48
42,003.60
0.27
1,597.32
44.50
263,262.00
51.87
306,862.92
6.48%
RS
RS
6,389.28
1.08
85,663.68
14.48
728,141.28
123.08
15.39%
260.44
436.80
1,523.20
2,220.44
0.38
3,515.94
5,896.80
20,563.20
29,975.94
5.07
OTHER WORKS
Plastering of Tank and Manholes
Boundary wall brickwork
Boundary wall Plastering
79,274.40
13.40
RS
RS
RS
290,297.55
49.07
23,253.30
3.93
313,550.85
53.00
7,731.40
1.31
988,893.13
167.16
1,310,175.37
221.46
27.68%
52.00
429,437.25
72.59
34,253.83
5.79
463,691.08
78.38
83.00
128,242.05
21.68
2,667,122.34
450.83
3,255,747.82
550.33
68.79%
290,297.55
49.07
23,253.30
3.93
313,550.85
53.00
52.00
7,731.40
1.31
988,893.13
167.16
1,310,175.37
221.46
27.68%
5,916.00
5,916.00
5,916.00
5,916.00
5,916.00
5,916
719,735
121.66
2.70
124.36
15.54%
57,507
9.72
0.36
10.08
1.26%
777,242
131.38
3.05
134.43
16.80%
135,973
22.98
1.99
24.97
3.12%
3,656,015
617.99
22.59
640.57
80.07%
4,565,923
771.79
28.21
800.00
8.50
13.00
8.50
INDIRECT
LABOUR
(B)
DIRECT LABOUR
(A)
TOTAL CONTRACT COST :
TOTAL BUDGETED COST :
0.68
1.04
0.68
73,568,690
-
73,568,690
TOTAL LABOUR
(A+B)
5,960,892
-
5,960,892
79,529,581
-
79,529,581
0.17
0.17
0.17
65.11
71.40
380.80
517.31
0.09
639,105.48
108.03
3,255.50
5,460.00
19,040.00
27,755.50
4.69
Sft
Cft
Sft
RS
383.00
420.00
2,240.00
3,372.12
0.57
MACHINERY
(C)
8.00
8.01
8.01
3,064.00
3,364.20
17,942.40
24,370.60
4.12
MATERIAL
(D)
14,774,645
-
14,774,645
17.35
22.22
17.36
799.98
6,645.05
9,332.40
38,886.40
54,863.85
9.27
TOTAL AMOUNT
(A+B+C+D)
378,963,668
-
378,963,668
473,280,000
-
473,280,000
0.14%
0.20%
0.82%
1.16%
96.47%
3.53%
100.00%
COST BUDGET
LABOR (A)
S.NO
DESCRIPTION
UNIT
QUANTITY
DIRECT UNIT
COST
INDIRECT
DIRECT TOTAL COST
UNIT COST
MACHINERY (B)
DIRECT &
INDIRECT TOTAL
INDIRECT TOTAL
COST
COST
UNIT
COST
MATERIAL (C)
TOTAL COST
UNIT COST
RATE (Rs)
TOTAL COST
AMOUNT (Rs)
EXCAVATION WORKS
1.1 Excavation in hard soil upto 1.5 m depth to obtain earth for
embankments or to clear building sites etc.
1.2 Earth Filling in area where required in 150 mm layers, borrow from
other site and fill according to requirement and as directed by the
engineer incharge.
Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.
2.1b
Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken
stone graded in foundation as specified.
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
3)
3.1
3.2
3.3
3.4
3.5
13,228.00
Cft
12,338.00
6,349.44
0.07
925.96
7,275.40
0.95
12,566.60
1.50
19,842.00
0.44%
0.09
1,110.42
1,110.42
1.80
22,208.40
1.89
23,318.82
0.51%
2,036.38
0.34
8,385.82
1.42
43,160.82
7.30
0.95%
6,349.44
1.07
RS
RS
34,775.00
5.88
Cft
866.29
4.00
3,465.16
0.85
736.35
4,201.51
3.75
3,248.59
64.50
55,875.71
73.10
63,325.80
1.39%
Cft
644.63
4.00
2,578.52
0.85
547.94
3,126.46
3.75
2,417.36
64.50
41,578.64
73.10
47,122.45
1.03%
2,703.76
574.00
2,644.23
1,732.89
7,654.88
4.00
4.00
4.00
4.00
4.00
10,815.04
2,296.00
10,576.92
6,931.56
0.90
0.90
0.90
0.90
0.90
2,433.38
516.60
2,379.81
1,559.60
13,248.42
2,812.60
12,956.73
8,491.16
7.10
7.10
7.10
7.10
7.10
19,196.70
4,075.40
18,774.03
12,303.52
104.76
113.84
102.76
102.76
283,245.90
65,344.16
271,721.07
178,071.78
116.76
12.00
125.84
114.76
114.76
315,691.02
72,232.16
303,451.83
198,866.46
6.93%
Cft
Cft
Cft
Cft
Cft
RS
RS
8,173.68
1.38
44,836.88
7.58
1,219.94
626.77
2,957.18
16,469.14
8,461.42
39,921.96
4,803.89
0.81
64,852.52
10.96
232.97
3,735.84
6,398.18
7,328.90
2,410.27
38,650.24
66,194.28
75,823.30
17,695.89
2.99
183,078.09
30.95
0.06
322.37
322.37
0.05
322.37
322.37
0.05
2.66
14,291.62
14,291.62
2.42
2.72
14,613.99
14,613.99
2.47
0.32%
0.32%
56.00
106,116.64
106,116.64
17.94
63.12
119,608.61
119,608.61
20.22
2.63%
2.63%
104.76
56.00
8.30
165.00
2,500.00
104.76
56.00
8.30
165.00
5.33
85.00
104.76
104.76
64.50
15,440.58
31,284.96
3,735.00
3,300.00
2,500.00
10,062.20
18,200.00
3,585.60
4,620.00
746.20
6,247.50
21,999.60
9,637.92
11,927.34
143,286.90
24.22
116.76
59.00
19.88
190.18
2,705.77
116.76
59.00
19.88
190.18
35.54
101.37
116.76
116.76
73.30
17,209.26
32,960.94
8,946.00
3,803.60
2,705.77
11,214.80
19,175.00
8,588.16
5,325.04
4,975.60
7,450.70
24,519.60
10,741.92
13,554.64
171,171.03
28.93
0.38%
0.72%
0.20%
0.08%
0.06%
0.25%
0.42%
0.19%
0.12%
0.11%
0.16%
0.54%
0.24%
0.30%
3.76%
STEEL
Cutting, Bending & Fixing of Steel as per drawing as directed by
engineer incharge.
Column Footing
Retaining Wall
Columns @ 5.454 KG/CFT
Slabs
Slab, Lintels & Beams
Kg
Kg
Kg
Kg
Kg
KG/M3
RS
RS
4)
FORMWORK
Providing, Fixing & Removal of formwork with good quality & smooth
surface of concrete after removal, complete in all respect or as
directed by the engineer incharge.
4.1
4.2
4.3
4.4
4.5
Sft
Sft
Sft
Sft
Sft
COST OF FORMWORK
COST PER SFT
M2/M3
RS
RS
7)
0.48
CONCRETE WORKS
2.1a
2.2
Cft
36,663.20
6.20
6,099.68
3,133.86
14,785.91
24,019.45
110.76
2.50
2.50
2.50
15,249.20
7,834.65
36,964.78
0.20
0.20
0.20
60,048.63
10.15
217.73
3,491.44
5,979.61
6,849.44
16,538.22
7.09
10.00
10.00
10.00
10.00
2,177.30
34,914.40
59,796.10
68,494.40
1.07
1.07
1.07
1.07
1.07
165,382.20
27.96
60,015.60
10.14
0.40
0.40
0.40
2,439.87
1,253.54
5,914.36
895,837.26
151.43
55.00
55.00
55.00
9,607.77
1.62
0.51
0.51
0.51
0.51
0.51
111.04
1,780.63
3,049.60
3,493.21
335,482.40
172,362.30
813,225.05
1,000,689.72
169.15
58.10
58.10
58.10
1,321,069.75
223.30
8.30
24.00
24.00
14.20
8,434.48
1.43
1,807.16
83,794.56
143,510.64
97,262.05
354,391.41
182,077.27
859,061.37
1,395,530.05
235.89
19.88
35.58
35.58
25.78
326,374.41
55.17
1.59%
6.66%
4.37%
21.97%
7.78%
4.00%
18.86%
30.64%
4,328.47
124,225.44
212,754.52
176,578.56
0.10%
0.00%
2.73%
4.67%
3.88%
517,886.99
87.54
11.37%
5,372.79
ANTI-TERMITE WORKS
COST PER SFT
Water Proofing as specified
WATERPROOFING WORKS
COST PER SFT
Sft
RS
RS
1,894.94
6.00
11,369.64
11,369.64
1.92
1.12
2,122.33
2,122.33
0.36
13,491.97
13,491.97
2.28
OTHER WORKS
Overhead water tank concrete
Overhead water tank reinforcement
Overhead water tank formwork
PVC waterstop for OHWT
Manhole cover and insulation for OHWT
Underground watertank concrete
Underground watertank reinforcement
Underground watertank formwork
PVC waterstop for UGWT
Waterproofing for UGWT wall (with Bitumen)
Gully trap (2 Nos) & Manhole (1 No)
Boundary wall RCC
Boundary wall Lean Concrete
PCC (1:4:8) for walkway
COST OF OTHER WORKS
COST PER SFT
Cft
Kg
Sft
Rft
Set
Cft
Kg
Sft
Rft
Sft
Cft
Cft
Cft
Cft
RS
RS
147.39
558.66
450.00
20.00
1.00
96.05
325.00
432.00
28.00
140.00
73.50
210.00
92.00
184.92
4.00
2.50
10.00
25.00
200.00
4.00
2.50
10.00
25.00
28.00
15.00
4.00
4.00
4.00
589.56
1,396.65
4,500.00
500.00
200.00
384.20
812.50
4,320.00
700.00
3,920.00
1,102.50
840.00
368.00
739.68
20,373.09
3.44
0.90
0.20
1.07
0.18
5.77
0.90
0.20
1.07
0.18
2.04
1.20
0.90
0.90
0.85
132.65
111.73
481.50
3.60
5.77
86.45
65.00
462.24
5.04
285.60
88.20
189.00
82.80
157.18
2,156.76
0.36
722.21
1,508.38
4,981.50
503.60
205.77
470.65
877.50
4,782.24
705.04
4,205.60
1,190.70
1,029.00
450.80
896.86
22,529.85
3.81
37,311.30
6.31
337,497.50
57.05
engineer incharge.
6)
11)
11.01
11.02
11.03
11.04
11.05
11.06
11.07
11.08
11.09
11.10
11.11
11.14
11.15
11.17
300,186.20
50.74
RS
RS
7.10
0.30
0.51
7.10
0.30
0.51
0.17
0.17
7.10
7.10
3.95
1,046.47
167.60
229.50
681.96
97.50
220.32
23.80
12.50
1,491.00
653.20
730.43
5,354.28
0.91
118,187.13
19.98
2,806,976.58
474.47
3,262,661.21
551.50
71.63%
BLOCK WORK
Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand
Mortar (1:4) In Super Structure , including form work, curing etc
complete in all respect or as directed by the engineer incharge.
8)
9)
10)
11)
11.12
11.13
11.16
Plaster works
Applying 13mm thick cement and sand plaster (1:4) to be trowelled
smooth with steel trowel to brick or block wall,as Directed by the
engineer incharge.
Cft
4,053.55
13.43
54,439.18
1.07
4,337.30
58,776.48
0.20
810.71
50.33
204,015.17
65.03
263,602.36
Sft
15,156.29
8.50
128,828.47
0.68
10,306.28
139,134.75
0.20
3,031.26
8.01
121,401.88
17.39
263,567.88
5.79%
14,643.58
2.48
197,911.23
33.45
527,170.24
89.11
11.57%
9.05%
183,267.65
30.98
3,841.97
0.65
325,417.05
55.01
5.79%
RS
RS
Sft
5,916.00
5.33
31,532.28
0.55
3,253.80
34,786.08
0.30
1,774.80
63.53
375,843.48
69.71
412,404.36
Sft
5,916.00
5.07
29,994.12
0.53
3,135.48
33,129.60
0.27
1,597.32
44.50
263,262.00
50.37
297,988.92
6.54%
RS
RS
6,389.28
1.08
67,915.68
11.48
710,393.28
120.08
15.60%
OTHER WORKS
Plastering of Tank and Manholes
Boundary wall brickwork
Boundary wall Plastering
COST OF OTHER WORKS
COST PER SFT
Sft
Cft
Sft
RS
RS
260.44
436.80
1,523.20
2,220.44
0.38
3,515.94
5,896.80
20,563.20
29,975.94
5.07
272,549.55
46.07
23,253.30
3.93
295,802.85
50.00
300,186.20
50.74
37,311.30
6.31
337,497.50
57.05
272,549.55
46.07
23,253.30
3.93
295,802.85
50.00
5,916.00
5,916.00
5,916.00
5,916.00
5,916.00
5,916
572,736
60,565
633,300
125,919
3,795,870
4,555,089
96.81
96.81
10.24
10.24
107.05
107.05
13.90%
21.29
21.29
2.77%
641.63
641.63
83.33%
769.97
769.97
61,526.40
10.40
383.00
420.00
2,240.00
RS
RS
8.50
13.00
8.50
3,255.50
5,460.00
19,040.00
27,755.50
4.69
0.68
1.04
0.68
12.57%
1.33%
DIRECT LABOUR
(A)
INDIRECT LABOUR
(B)
57,272,796
6,057,984
TOTAL LABOUR
(A+B)
63,330,780
3,372.12
0.57
0.17
0.17
0.17
65.11
71.40
380.80
517.31
0.09
639,105.48
108.03
8.00
8.01
8.01
3,064.00
3,364.20
17,942.40
24,370.60
4.12
7,731.40
1.31
988,893.13
167.16
83.00
118,187.13
19.98
2,806,976.58
474.47
52.00
7,731.40
1.31
988,893.13
167.16
MACHINERY
(C)
12,595,164
MATERIAL
(D)
379,588,308
17.35
22.22
17.36
551.50
218.47
769.97
6,645.05
9,332.40
38,886.40
54,863.85
9.27
0.15%
0.20%
0.85%
1.20%
1,292,427.37
218.46
28.37%
3,262,661.21
551.50
71.63%
1,292,427.37
218.46
28.37%
TOTAL AMOUNT
(A+B+C+D)
455,514,252
100.00%
0.00%
100.00%
BOQ Item-03
RATE ANALYSIS OF 400 x 200 x 200 MM Thick Block Masonry.
Providing and laying cement concrete Hollow block masonry walls of specified strength as per
specification, using machine made blocks (approved quality of fine and course aggregate) laid
cement sand mortar, in any shape, length or height, laid at specified levels, including cost of s
Wall ties as per drawing including racking out joints cutting, curing etc, complete in all respec
DETAILS
Qty
MATERIAL
Concete Blocks (16" X 8" X 8")
Including 10% Wastage.
123.75
Nos
10.84
CFT
Cement ( OPC ).
0.55
Sand
Wall Ties
Rs.
29.00
P.No.
Bags
Rs.
350.00
P.Bag
3.20
Cft
Rs.
18.00
P.Cft
8.00
No
Rs.
35.00
P.No
Total
(A).
LABOUR.
Mason
2.0
No
Rs.
500.00
per day
Labour
3.0
No
Rs.
300.00
per day
Bahishti
2.0
No
Rs.
300.00
per day
Scaffolder
0.3
No
Rs.
350.00
per day
Total
(B).
Item Rates.
Composite Rate for 100 SFT
Total
Submitted By.
Checked By.
(A+B).
BOQ Item-03
3,588.75
Rs.
192.50
Rs.
57.60
Rs.
280.00
Rs.
4,118.85
Rs.
41.19
Rs.
1,000.00
Rs.
900.00
Rs.
600.00
Rs.
105.00
Rs.
2,605.00
Rs.
26.05
Rs.
6,724.00
Rs.
67.24
LABOUR.
Approved By.
BOQ Item-2.1
RATE ANALYSIS OF 4000PSI CONCRETE
Providing and laying, straight or curved cast-in place designed mix reinforced structural cem
cylinder crushing strength 4000 psi for Beams and Slab, using O.P cement including vibrating
mechanical vibrator, leveling, compacting, curing all as per specifications and to the entire sat
Engineer.
S.No
DETAILS
Qty
MATERIAL
a.
b.
Wastage of concrete
1.00
CFT
5.00%
%age
Rs.
61.40
P.CFT
P.CFT
Total
(A).
LABOR.
a.
Mason
0.06
Hour
Rs.
62.50
P. Hour
b.
Labor
0.20
Hour
Rs.
31.25
P. Hour
c.
Curing of Concrete
0.03
Hour
Rs.
31.25
P. Hour
Total
Submitted By.
Checked By.
BOQ Item-2.1
61.40
Rs.
3.07
Rs.
64.50
Rs.
3.54
Rs.
6.19
Rs.
0.88
Rs.
10.62
Rs.
75.12
LABOR.
Approved By.
BOQ Item-5.1
RATE ANALYSIS OF CONCRETE FOR COLUMNS
Providing and laying, straight or curved cast-in place designed mix reinforced structural cemen
using O.P cement including vibrating through electro mechanical vibrator, leveling, compacting, c
specifications and to the entire satisfaction of the Engineer.
S.No
DETAILS
Qty
MATERIAL
a.
1.00
CFT
b.
Wastage of concrete
c.
Rs.
125.00
P.CFT
5.00%
%age
0.06
LTR
Rs.
35.00
P.LTR
d.
0.01
LTR
Rs.
172.00
P.LTR
e.
Conbextra GP (Fosroc)
0.01
KG
Rs.
62.00
P.KG
f.
Mortar
0.01
CFT
Rs.
113.27
P.CFT
P.CFT
Total
(A).
LABOR.
a.
Mason
0.03
Hour
Rs.
62.50
P. Hour
b.
Labor
0.20
Hour
Rs.
31.25
P. Hour
c.
Curing of Concrete
0.03
Hour
Rs.
31.25
P. Hour
Total
Submitted By.
Checked By.
BOQ Item-5.1
125.00
Rs.
6.25
Rs.
1.98
Rs.
2.44
Rs.
0.88
Rs.
1.13
Rs.
137.70
Rs.
1.77
Rs.
6.19
Rs.
0.88
Rs.
8.85
Rs.
146.55
LABOR.
Approved By.
BOQ Item-5.2~5.5
RATE ANALYSIS OF CONCRETE FOR OTHER STRUCTURE
S.No
DETAILS
Qty
MATERIAL
a.
1.00
CFT
b.
Wastage of concrete
c.
Rs.
99.50
P.CFT
5.00%
%age
0.06
LTR
Rs.
35.00
P.LTR
d.
0.01
LTR
Rs.
172.00
P.LTR
e.
Conbextra GP (Fosroc)
0.01
KG
Rs.
62.00
P.KG
f.
Mortar
0.01
CFT
Rs.
113.27
P.CFT
P.CFT
Total
(A).
LABOR.
a.
Mason
0.03
Hour
Rs.
62.50
P. Hour
b.
Labor
0.20
Hour
Rs.
31.25
P. Hour
c.
Curing of Concrete
0.03
Hour
Rs.
31.25
P. Hour
Total
Submitted By.
Checked By.
BOQ Item-5.2~5.5
99.50
Rs.
4.98
Rs.
1.98
Rs.
2.44
Rs.
0.88
Rs.
1.13
Rs.
110.90
Rs.
1.77
Rs.
6.19
Rs.
0.88
Rs.
8.85
Rs.
119.75
LABOR.
Approved By.
BOQ Item-06
RATE ANALYSIS OF STEEL REINFORCEMENT
Providing fabricating and fixing in position grade 60 reinforcing bars of any size of any diameter with 60,000
strength including the cost of straightening cutting, wastage and such overlaps as are not shown on the drawin
Chairs, chairs tying in all kinds of reinforced concrete and in any position at any level or elevations or at any h
conforming to the requirement of drawings and specifications, complete in all respects. Waste, lappage and r
on contractor account (Item rate to cover the cost of steel also)
S.No
DETAILS
Qty
MATERIAL
a.
1.00
KG
Rs.
65.00
b.
0.08
KG
Rs.
90.00
d.
5.00%
%age
Total
(A
Total
(B
LABOR
a.
0.020
Hour
87.5
b.
0.045
Hour
43.75
Total
Note:
Submitted By.
Checked By.
(A + B
BOQ Item-06
nforcing bars of any size of any diameter with 60,000 psi per sq. inch yield
age and such overlaps as are not shown on the drawings in position on M.S.
d in any position at any level or elevations or at any height and any position
ations, complete in all respects. Waste, lappage and rolling margin shall be
el also)
Unit Rate per M.TON
Rate per unit
Amount
MATERIAL
Total
P.KG
Rs.
65.00
P.KG
Rs.
7.20
Rs.
3.61
(A). Rs.
75.81
LABOR
Total
Total
P. Hour
Rs.
1.75
P. Hour
Rs.
1.97
(B). Rs.
3.72
(A + B ). Rs.
79.53
Approved By.
BOQ Item-7.3
RATE ANALYSIS OF FORMWORK FOR COLUMNS
Providing, fixing and removing of plasform as per drawing& specification and as directed by the Engineer.
S.No
DETAILS
Qty
MATERIAL
a.
Plasform
1.00
SFT
Rs.
13.00
P.SFT
b.
0.20
Ltr
Rs.
10.04
P.SFT
c.
Steel Nails
0.15
Kg
Rs.
8.83
P.SFT
d.
0.03
SFT
Rs.
34.39
P.SFT
e.
5.00
Pcs
Rs.
0.08
P.Pcs
Total
(A).
LABOR.
a.
Carpenters
0.12
Hour
Rs.
43.75
P. Hour
b.
Helpers
0.30
Hour
Rs.
25.00
P. Hour
Total
Total
Submitted By.
Checked By.
= (B)
(A + B ).
BOQ Item-7.3
13.00
Rs.
2.01
Rs.
1.32
Rs.
1.03
Rs.
0.42
Rs.
17.80
Rs.
5.03
Rs.
7.50
Rs.
12.50
Rs.
30.30
LABOR.
Approved By.
BOQ Item-7.1/7.2
RATE ANALYSIS OF FORMWORK FOR WALLS
Providing, fixing and removing of plasform as per drawing& specification and as directed by the Engineer.
S.No
DETAILS
Qty
MATERIAL
a.
Plasform
1.00
SFT
Rs.
6.00
P.SFT
b.
0.20
Ltr
Rs.
10.04
P.SFT
c.
Steel Nails
0.15
Kg
Rs.
8.83
P.SFT
d.
0.03
SFT
Rs.
34.39
P.SFT
e.
5.00
Pcs
Rs.
0.08
P.Pcs
Total
(A).
LABOR.
a.
Carpenters
0.12
Hour
Rs.
43.75
P. Hour
b.
Helpers
0.30
Hour
Rs.
25.00
P. Hour
Total
Total
Submitted By.
Checked By.
= (B)
(A + B ).
BOQ Item-7.1/7.2
6.00
Rs.
2.01
Rs.
1.32
Rs.
1.03
Rs.
0.42
Rs.
10.80
Rs.
5.03
Rs.
7.50
Rs.
12.50
Rs.
23.30
LABOR.
Approved By.
BOQ Item-7.4/7.5
RATE ANALYSIS OF FORMWORK FOR BEAMS AND SLABS
Providing, fixing and removing of plasform as per drawing& specification and as directed by the Engineer.
S.No
DETAILS
Qty
MATERIAL
a.
Plasform
1.00
SFT
Rs.
4.00
P.SFT
b.
0.20
Ltr
Rs.
10.04
P.SFT
c.
Steel Nails
0.15
Kg
Rs.
8.83
P.SFT
d.
0.03
SFT
Rs.
34.39
P.SFT
e.
5.00
Pcs
Rs.
0.08
P.Pcs
Total
(A).
LABOR.
a.
Carpenters
0.12
Hour
Rs.
43.75
P. Hour
b.
Helpers
0.30
Hour
Rs.
25.00
P. Hour
Total
Total
Submitted By.
Checked By.
= (B)
(A + B ).
BOQ Item-7.4/7.5
4.00
Rs.
2.01
Rs.
1.32
Rs.
1.03
Rs.
0.42
Rs.
8.80
Rs.
5.03
Rs.
7.50
Rs.
12.50
Rs.
21.30
LABOR.
Approved By.
DETAILS
Rate
Remarks
MATERIAL
a.
Concrete (1:4:8)
Rs.
2,165.00
/ CUM
b.
Rs.
4,414.00
/ CUM
c.
Rs.
3,514.00
/ CUM
d.
Steel G-60
Rs.
53,000.00
e.
/ M. Ton
DESCRIPTION
RENTAL OF STAFF HOUSE
a) MONTHLY RENTAL
b) MAINTENANCE FEES
c) ELECTRICITY
d) SUI GAS
e) CLEANER'S COST
f) DRINKING MINERAL WATER
g) FURNISHING
OFFICE STAFF SALARIES
MALAYSIAN
a) PROJECT DIRECTOR
b) FINANCE AND ACCOUNTS MANAGER
LOCAL STAFF
a) PROJECT MANAGER
b) CONSTRUCTION MANAGER
c) ADMIN/HR MANAGER
d) ELECTRICAL ENGINEER
e) MECHANICAL ENGINEER
f) CONTRACTS EXECUTIVE
g) PA/IT COORDINATOR
h) DOCUMENT CONTROLLER
j) OFFICE BOY
k) TIME-KEEPER
m) COOK
n) DRIVER
UNIT
QTY
MTH
MTH
MTH
MTH
MTH
MTH
LS
18
18
18
18
18
18
MTH
MTH
18
18
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
MTH
18
18
18
18
18
18
18
18
18
18
18
18
AIR TICKETS
TRIPS
12
UNIT
UNIT
18
MEDICAL ALLOWANCE
MTH
18
MTH
18
TOTAL :
PENSES OF "CMS"
RATE
AMOUNT (RS)
42,000
2,000
20,000
1,500
3,000
4,500
756,000
36,000
360,000
27,000
54,000
81,000
100,000
750,000
250,000
13,500,000
4,500,000
80,000
65,000
70,000
40,000
30,000
35,000
35,000
25,000
12,000
15,000
10,000
12,000
1,440,000
1,170,000
1,260,000
720,000
540,000
630,000
630,000
450,000
216,000
270,000
180,000
216,000
60,000
720,000
1,000,000
1,000,000
20,000
360,000
15,000
270,000
10,000
180,000
29,666,000
420,000.00
1,429,000
SR #
1
DESCRIPTION
UNIT
QTY
UNIT
100
MANAGEMENT FEE @ 10 %
BUDGETTED PROFIT
MTH
DGETTED PROFIT
BUILT-UP
FLOOR AREA
(SFT)
BUDGETTED
COST/ SFT
5916
BASIC
SALARY/MTH
714,500
800
AMOUNT (RS)
473,280,000
10%
47,328,000
6.27%
(29,666,000)
0.91%
(4,287,002)
13,374,998
2.83%
COST BUDGET
DESCRIPTION
UNITS
QUANTITY
LABOR (A)
DIRECT UNIT
COST
1)
Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken stone
graded in foundation as specified.
2.1b
Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken stone
graded in foundation as specified.
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
3)
3.1
3.2
3.3
3.4
3.5
4.1
4.2
4.3
4.4
4.5
MATERIAL (C)
MACHINERY (B)
UNIT COST
TOTAL COST
UNIT COST
RATE (Rs)
AMOUNT (Rs)
TOTAL COST
13,228.00
0.85
11,243.80
0.07
925.96
12,169.76
0.95
12,566.60
1.87
24,736.36
Cft
12,338.00
1.15
14,188.70
0.09
1,110.42
15,299.12
2.80
34,546.40
4.04
49,845.52
Cft
866.29
5.00
4,331.45
0.85
736.35
5,067.80
3.75
3,248.59
64.50
55,875.71
74.10
64,192.09
Cft
644.63
5.00
3,223.15
0.85
547.94
3,771.09
3.75
2,417.36
64.50
41,578.64
74.10
47,767.08
Cft
Cft
Cft
Cft
Cft
2,703.76
574.00
2,644.23
1,732.89
7,654.88
5.00
13,518.80
0.71
1,919.67
15,438.47
7.08
19,142.62
104.76
283,245.90
117.55
317,826.99
Kg
Kg
Kg
Kg
Kg
6,099.68
5.00
2,870.00
0.71
407.54
3,277.54
7.08
4,063.92
113.84
65,344.16
126.63
72,685.62
5.00
13,221.15
0.71
1,877.40
15,098.55
7.08
18,721.15
102.76
271,721.07
115.55
305,540.78
5.00
8,664.45
0.71
1,230.35
9,894.80
7.08
12,268.86
102.76
178,071.78
115.55
200,235.44
2.20
13,419.30
0.20
1,219.94
14,639.24
0.40
2,439.87
55.00
335,482.40
57.80
352,561.50
STEEL
3,133.86
-
2.20
###
14,785.91
2.20
217.73
3,491.44
5,979.61
6,849.44
16,538.22
7.09
10.00
24,019.45
110.76
6,894.49
0.20
626.77
32,529.00
0.20
2,177.30
1.00
7,521.26
2,957.18
0.40
1,253.54
35,486.18
0.40
2,395.03
0.20
5,914.36
55.00
172,362.30
55.00
57.80
181,137.11
813,225.05
57.80
1,698.29
19.00
854,625.60
FORMWORK
Providing, Fixing & Removal of formwork with good quality & smooth
surface of concrete after removal, complete in all respect or as directed by
the engineer incharge.
Raft & Column Footing
Retaining Wall
Columns
Slabs
Lintels & Beams
Sft
Sft
Sft
Sft
Sft
M2/M3
5)
DIRECT &
INDIRECT TOTAL
COST
Cft
KG/M3
4)
INDIRECT TOTAL
COST
CONCRETE WORKS
2.1a
2.2
INDIRECT
UNIT COST
EXCAVATION WORKS
1.1 Excavation in hard soil upto 1.5 m depth to obtain earth for embankments
or to clear building sites etc.
1.2 Earth Filling in area where required in 150 mm layers, borrow from other
site and fill according to requirement and as directed by the engineer
incharge.
2)
DIRECT TOTAL
COST
217.73
43.55
7.80
-
4,136.87
10.00
34,914.40
1.00
3,491.44
38,405.84
0.20
698.29
16.80
58,656.19
28.00
97,760.32
10.00
59,796.10
1.00
5,979.61
65,775.71
0.20
1,195.92
9.80
58,600.18
21.00
125,571.81
10.00
68,494.40
1.00
6,849.44
75,343.84
0.20
1,369.89
9.80
67,124.51
21.00
143,838.24
810.71
BLOCK WORK
Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand Mortar
(1:4) In Super Structure , including form work, curing etc complete in all
respect or as directed by the engineer incharge.
Cft
4,053.55
13.43
54,439.18
1.07
4,337.30
58,776.48
0.20
50.33
204,015.17
65.03
263,602.36
6)
Sft
1,894.94
14.00
26,529.16
1.12
2,122.33
28,651.49
56.00
106,116.64
71.12
134,768.13
7)
Termite Proofing in area where required with approved material from main
-
2.66
14,291.62
3.47
18,643.58
121,401.88
16.89
9)
10)
11)
11.01
11.02
11.03
11.04
11.05
11.06
11.07
11.08
11.09
11.10
11.11
11.12
11.13
11.14
11.15
11.16
11.17
Sft
5,372.79
0.75
4,029.59
0.06
322.37
4,351.96
Plaster works
Applying 13mm thick cement and sand plaster (1:4) to be trowelled
smooth with steel trowel to brick or block wall,as Directed by the engineer
incharge.
Sft
15,156.29
8.00
121,250.32
0.68
10,306.28
131,556.60
RS
47,186.02
542,920.76
RS
7.98
91.77
Sft
5,916.00
6.83
40,406.28
0.55
3,253.80
43,660.08
0.30
1,774.80
63.53
375,843.48
71.21
421,278.36
Sft
5,916.00
6.57
38,868.12
0.53
0.27
1,597.32
44.50
263,262.00
51.87
306,862.92
RS
RS
OTHER WORKS
Overhead water tank concrete
Overhead water tank reinforcement
Overhead water tank formwork
PVC waterstop for OHWT
Manhole cover and insulation for OHWT
Underground watertank concrete
Underground watertank reinforcement
Underground watertank formwork
PVC waterstop for UGWT
Waterproofing for UGWT wall (with Bitumen)
Gully trap (2 Nos) & Manhole (1 No)
Plastering of Tank and Manholes
Boundary wall brickwork
Boundary wall RCC
Boundary wall Lean Concrete
Boundary wall Plastering
PCC (1:4:8) for walkway
Cft
Kg
Sft
Rft
Set
Cft
Kg
Sft
Rft
Sft
Cft
Sft
Cft
Cft
Cft
Sft
Cft
RS
RS
495,734.74
83.80
147.39
558.66
450.00
20.00
1.00
96.05
325.00
432.00
28.00
140.00
73.50
383.00
420.00
210.00
92.00
2,240.00
184.92
0.20
3,031.26
8.01
123,732.89
2,848,811.49
20.91
255,989.74
3,515,465.14
481.54
594.23
3,135.48
42,003.60
79,274.40
6,389.28
85,663.68
3,372.12
639,105.48
728,141.28
13.40
1.08
14.48
0.57
108.03
123.08
8.85
1,304.40
0.71
104.65
1,409.05
7.08
1,043.52
104.76
15,440.58
121.40
17,893.15
2.56
1,430.17
0.20
111.73
1,541.90
0.30
167.60
56.00
31,284.96
59.06
32,994.46
12.50
5,625.00
1.00
450.00
6,075.00
0.17
76.50
8.80
3,960.00
22.47
10,111.50
2.20
44.00
0.18
3.60
47.60
165.00
3,300.00
167.38
72.12
72.12
5.77
5.77
77.89
2,500.00
2,500.00
2,577.89
2,577.89
8.85
850.04
0.71
68.20
918.24
7.08
680.03
104.76
10,062.20
121.40
11,660.47
2.56
832.00
0.20
65.00
897.00
0.30
97.50
56.00
18,200.00
59.06
19,194.50
12.50
5,400.00
1.00
432.00
5,832.00
0.17
73.44
8.80
3,801.60
22.47
9,707.04
2.20
61.60
0.18
5.04
66.64
165.00
4,620.00
167.38
4,686.64
0.56
78.40
0.04
5.60
84.00
0.17
23.80
5.33
746.20
6.10
854.00
15.00
1,102.50
1.20
88.20
1,190.70
0.17
12.50
85.00
6,247.50
101.37
7,450.70
8.50
3,255.50
0.68
260.44
3,515.94
0.17
65.11
8.00
3,064.00
17.35
6,645.05
13.00
5,460.00
1.04
436.80
5,896.80
0.17
71.40
8.01
3,364.20
22.22
9,332.40
8.85
1,858.50
0.71
149.10
2,007.60
7.08
1,486.80
104.76
21,999.60
121.40
25,494.00
8.85
814.20
0.71
65.32
879.52
7.08
651.36
104.76
9,637.92
121.40
11,168.80
8.50
19,040.00
0.68
1,523.20
20,563.20
0.17
380.80
8.01
17,942.40
17.36
38,886.40
10.62
1,963.85
0.85
157.18
2,121.03
3.95
730.43
64.50
11,927.34
79.92
3,347.60
14,778.81
49,192.28
3,931.83
53,124.11
5,560.79
168,098.50
226,783.41
8.32
0.66
8.98
0.94
28.41
38.33
624,201.42
57,507.13
681,708.55
132,665.80
3,656,015.47
4,470,389.83
5,916.00
5,916.00
5,916.00
5,916.00
5,916.00
5,916.00
105.51
9.72
115.23
6.76
122.00
15.25%
22.42
1.32
23.74
2.97%
617.99
36.28
654.26
81.78%
755.64
44.36
800.00
CHECK
13.96%
1.29%
DIRECT LABOUR
(A)
INDIRECT LABOUR
(B)
TOTAL LABOUR
(A+B)
71,973,480.00
5,750,713.00
78,091,200.00
62,420,142.00
5,750,713.00
68,170,855.00
COST SAVING
9,553,338.00
9,920,345.00
MACHINERY
(C)
13,748,784.00
MATERIAL
(D)
378,961,212.00
800.00
TOTAL AMOUNT
(A+B+C+D)
473,280,000.00
755.64