Beruflich Dokumente
Kultur Dokumente
PORTAL CULVERT
INSTALLATION MANUAL
P.I.P.E.S
CONCRETE
PIPE AND
PORTAL CULVERT
INSTALLATION
MANUAL
(Reprinted April 2009)
Published by:
ISBN 0-620-13661-8
Page 1
April 2009
2003
Page 1
PREFACE
Concrete is possibly the most widely accepted
material for stormwater pipes, culverts, sewer
lines and many other applications.
CONTENTS
1.
Introduction
1.1.
1.2.
1.3.
1.4.
1.5.
1.6.
2.
p3
General
Scope
Selection of Product Strength
Study of Product Specifications
Installation Conditions
Pre-construction Activities
7.
Ordering,Receipt and
Acceptance of Product
8.
Surveying
9.
Excavation
General
5.1.
5.2.
5.3.
5.4.
5.5.
Page 2
Page 2
Safety
Trench Widths and Depth
De-watering
Preparing Trench Bottom
p18
General
Precast Base Slabs
Cast-in-Place Bases
Placing of Culverts
Joint Sealing
Backfilling
p20
9.1. General
9.2. Final Backfilling
9.3. Special Technique for Backfilling Culverts
5.
p16
Lowering of Pipe
Line and Grade
Jointing
Curves
Culvert Bases
8.1.
8.2.
8.3.
8.4.
8.5.
p5
p14
Purpose of Bedding
Bedding Material
Types of Bedding
Placement of Bedding
Pipe Laying
7.1.
7.2.
7.3.
7.4.
p4
4.
Bedding
6.1.
6.2.
6.3.
6.4.
3.
6.
p10
p22
p23
p24
2003
April 2009
13.
13.INTRODUCTION
INTRODUCTION
SANS
SANS1200
1200LB
LB Civil
CivilEngineering
EngineeringConstruction:
Construction:
Bedding
Bedding(Pipes).
(Pipes).
1.1
1.1 GENERAL
GENERAL
SANS
SANS1200
1200LD
LD Civil
CivilEngineering
EngineeringConstruction:
Construction:
Sewers.
Sewers.
1.1.1
1.1.1The
The interdependent
interdependentrelationship
relationship between
between design
design
and
andinstallation
installationrequires
requiresinstallation
installationpractices
practicesthat
that
ensure
ensure satisfactory
satisfactory hydraulic
hydraulic and
and structural
structural
performance
performanceofofthe
thecomplete
completepipe
pipeororculvert
culvertline.
line.
SANS
SANS1200
1200LE
LE Civil
CivilEngineering
EngineeringConstruction:
Construction:
Stormwater
StormwaterDrainage.
Drainage.
SANS
SANS10120
10120
Code
CodeofofPractice
PracticeforforUse
Usewith
with
Standardised
StandardisedSpecifications
Specificationsforfor
Civil
CivilEngineering
EngineeringConstruction
Construction
and
andContract
ContractDocuments.
Documents.
1.1.2
1.1.2The
Theengineering
engineeringdesign
designofofany
anyproject,
project,described
describedinin
the
thespecifications
specificationsand
anddrawings,
drawings,must
mustbebeproperly
properly
executed
executedduring
duringconstruction.
construction. The
TheClerk
ClerkofofWorks,
Works,
1.3 SELECTION
SELECTIONOF
OFPRODUCT
PRODUCTSTRENGTH
STRENGTH
asas a a representative
representative ofof the
the Engineer,
Engineer, shares
shares 1.3
responsibility
responsibilitywith
withthe
theContractor
Contractorforforensuring
ensuringthat
that
1.3.1Once
Oncethe
thesize
sizeofofproduct
producthas
hasbeen
beendetermined,
determined,the
the
the
thepipe
pipeororportal
portalculvert
culvertisisinstalled
installedininaccordance
accordance 1.3.1
selection
selectionofofproduct
productstrength
strengthhas
hassix
sixlogical
logicalsteps:
steps:
with
withthe
thecontract
contractdocuments.
documents. Proper
Properinspection
inspection
calculate
calculatedeadloads;
deadloads;
requires
requires careful
careful attention
attention toto site
site operation,
operation, but
but
calculate
internal
calculate
internalpressure;
pressure;
should
shouldnot
notduplicate
duplicatethe
thedetailed
detailedinspection
inspectionand
and
calculate
calculatelive
liveloads;
loads;
testing
testingcarried
carriedout
outbybythe
thepipe
pipemanufacturer.
manufacturer.
choose
choosebedding
beddingfactor;
factor;
choose
choosesafety
safetyfactor;
factor;
Supervisory
Supervisorypersonnel
personneldirectly
directlyassociated
associatedwith
withthe
the
select
selectrequired
requiredproduct
productclass.
class.
installation
installationshould
shouldhave
havea abasic
basicunderstanding
understandingofof
design
designprinciples
principlessosothat
thatthe
theextent
extentand
andlimitations
limitations
1.3.2It Itisisimportant
importanttotonote
notethat
thatthere
thereare
arealways
alwaysa a
ofofthe
theproject
projectspecification
specificationand
anddrawings
drawingscan
canbebe 1.3.2
numberofofoptions,
options,which
whichneed
needtotobebeconsidered
consideredinin
number
interpreted
interpretedcorrectly.
correctly.
ordertotofind
findthe
theoptimum
optimumsolution.
solution. Generally
Generallyit itisis
order
more
economic
to
use
a
high
strength
pipewith
witha a
more
economic
to
use
a
high
strength
pipe
1.1.3
1.1.3This
ThisManual
Manualcannot,
cannot,and
andshould
shouldnot,
not,bebeused
usedasasa a
low
class
bedding.
low
class
bedding.
textbook,
textbook,nor
norcan
canit itrelieve
relievethe
theDesigner
Designerand
andthe
the
Contractor
Contractorofofthe
theneed
needforformaking
makinga athorough
thoroughstudy
study
1.3.3Reference
Reference toto the
the Concrete
Concrete Pipe
Pipe Handbook,
Handbook,
ofofthe
thetheoretical
theoreticaland
andpractical
practicalproblems
problemsthat
thatoccur
occur 1.3.3
published byby the
the Concrete
Concrete Pipe
Pipe Association
Association ofof
published
ininpractice.
practice.
SouthernAfrica,
Africa,will
willbebeofofassistance
assistancewith
withmost
mostofof
Southern
theproblems
problemsthat
thatcan
canoccur
occurwith
withpipe
pipeselection.
selection.
the
When
Wheninindoubt,
doubt,advice
adviceshould
shouldbebesought
soughtfrom
froma a
Alternatively, Designers
Designers and
and Contractors
Contractors should
should
Alternatively,
reputable
reputablemanufacturer.
manufacturer.
consulta aconcrete
concretepipe
pipemanufacturer.
manufacturer.
consult
1.2
1.2 SCOPE
SCOPE
1.4 STUDY
STUDYOF
OFPROJECT
PROJECTSPECIFICATION
SPECIFICATION
1.4
1.2.1
1.2.1This
This Manual
Manual describes
describes proven
proven methods
methods for
for
1.4.1The
The drawings
drawings that
that are
are either
either supplied
supplied byby the
the
installation
installationofofprecast
precastconcrete
concretepipes
pipesand
andportal
portal 1.4.1
Engineer
or
from
part
of
the
contract
documents
Engineer
or
from
part
of
the
contract
documents
culverts.
culverts.
shouldbebestudied
studiedthoroughly
thoroughlyforforallallsalient
salientfeatures.
features.
should
1.2.2
1.2.2The
The selection,
selection, manufacture
manufacture and
and installation
installation ofof
1.4.2Make
Makea anote
noteofofthe
thelocations,
locations,numbers
numbersand
andtypes
typesofof
precast
precastconcrete
concretepipes
pipesand
andculverts
culvertsare
arecovered
coveredbyby 1.4.2
appurtenant structures
structures and
and fittings
fittings such
such asas
allall appurtenant
the
thefollowing:
following:
manholes,junctions,
junctions,tees,
tees,valves
valves(sluice,
(sluice,airairand
and
manholes,
scour)
and
bends.
scour)
and
bends.
SANS
SANS10102
10102
The
TheSelection
SelectionofofPipes
Pipesfor
forBuried
Buried
Pipelines
PipelinesParts,
Parts,I, I,II.II.
SANS
SANS676
676
Reinforced
ReinforcedConcrete
ConcretePressure
Pressure
Pipes.
Pipes.
SANS
SANS677
677
Concrete
ConcreteNon-Pressure
Non-PressurePipes
Pipes
SANS
SANS986
986
Precast
PrecastReinforced
ReinforcedConcrete
Concrete
Culverts.
Culverts.
SANS
SANS974
974
Rubber
RubberJoint
JointRings
Rings(Non(NonCellular).
Cellular).
SANS
SANS1200
1200DB
DB Civil
CivilEngineering
EngineeringConstruction:
Construction:
Earthworks
Earthworks(Pipe
(PipeTrenches).
Trenches).
SANS
SANS1200
1200L L
2003
2003
April 2009
Civil
CivilEngineering
EngineeringConstruction:
Construction:
Low
LowPressure
PressurePipelines.
Pipelines.
1.4.3Using
Usingthe
theinformation
informationavailable
availableononthe
thedrawings,
drawings,
1.4.3
determine:
determine:
heightofoffillfillabove
abovethe
theproduct;
product;
height
anysuperimposed
superimposedororlive
liveloads;
loads;
any
typeofofinstallation
installation(i.e.
(i.e.trench,
trench,embankment,
embankment,
type
etc.);
etc.);
whetherthere
thereare
areany
anyspecial
specialconditions.
conditions.
whether
1.4.4Determine
Determinefrom
fromthe
thedocuments
documentsthe
theclass
classofofbedding
bedding
1.4.4
andtype
typeofofbedding
beddingmaterials
materialsspecified.
specified.
and
1.4.5The
Theinformation
informationgleaned
gleanedininthe
theparagraphs
paragraphsabove
above
1.4.5
shouldbebeused
usedtotocheck
checkthe
thespecified
specifiedstrength
strength
should
classofofthe
thepipes
pipesororculverts.
culverts. This
Thiskind
kindofofcheck
check
class
may seem
seem superfluous,
superfluous, but
but could
could prevent
prevent the
the
may
productfrom
fromsustaining
sustainingloads
loadsininexcess
excessofofthose
those
product
Pipe
Pipe& &Portal
PortalCulvert
CulvertInstallation
InstallationManual
Manual
Page
Page3 3
Page 3
INSTALLATION CONDITIONS
2.
2.1
1.6
PRE-CONSTRUCTION ACTIVITIES
2003
April 2009
2.3
DISTRIBUTION
3.
Portals
3.1
CONCRETE PRODUCTS
Trench
SITE ACCESS
April 2009
Excavated
Spoil
Fig. 2 Distributing Culverts Along Trench
3.3.4 If possible, double handling should be avoided.
However, where the site conditions do not permit
storing of products as described in 3.3.2 and 3.3.3
above, a storage yard away from the laying site will
have to be established. The product may then be
received at the storage yard and transported to the
laying site when required.
3.3.5 The Contractor must ensure that he has all the
necessary equipment to carry out any double
handling as efficiently as possible. It is essential
that a good road links the yard to the site so that the
products are transported as smoothly as possible
and damage eliminated.
Page 5
Page 5
3.4
STORAGE AREA
ACCEPTANCE OF PRODUCT
OFFLOADING OF PIPES
2003
April 2009
3.7
OFFLOADING OF CULVERTS
Correct
Incorrect
Malpractices
Correct
Correct Practice
Incorrect
STACKING OF PIPES
2003
April 2009
No. of layers
150 - 225
300 375
450 600
675 900
Above 900
6
4
3
2
1
Page 7
Page 7
STACKING OF CULVERTS
Large R S H Porta
4.
SURVEYING
4.1
PRELIMINARY WORK
4.1.1
Large Portal
2003
April 2009
road/rail crossings;
4.1.2
4.1.6
4.1.3
4.1.7
Up to 300
375 450
525 675
750 900
1 050
1 200
1 350
1 500
1 800
900
1 100
1 300
1 700
1 900
2 100
2 400
2 600
2 900
4.2
4.2.1
4.2.2
4.2.3
2900 = 1,11
2 750
4.1.4
4.3
4.3.1
2003
April 2009
CENTRE LINES
LEVELS
The levels are transferred from the level reference
pegs to the trench floor by using a dumpy level
and staff.
Control points are then established along the trench
bottom.
4.3.2
Page 9
Page 9
5.
EXCAVATION
5.1
GENERAL
5.1.1
5.1.2
Batter Board
Grade
String
Grade
Stake
Grade Rod
Registering
Grade of Trench
Grade Rod
Registering
Grade of Invert
5.1.4
5.1.5
Page 10
Page 10
5.2
5.2.1
SAFETY
Persons responsible for excavation must adhere
to the law. The statutory precautions stated in
Section D.16 of Chapter V from the Factories,
Machinery and Building Act 1941, as amended,
must be taken. When ground conditions vary from
place to place, the appropriate safety measures
must be taken.
2003
April 2009
5.2.2
5.2.3
5.2.5
5.3.1
5.3.2
5.3.3
5.3.4
5.3.5
5.3
Walers
Sheathing
CLOSE
SHEATHING
CLOSE
SHEATHING
ONE HALF
TRENCH
DEPTH
EXCAVATED
MATERIAL
TRENCH DEPTH
ORIGINAL
GROUND LINE
5.2.4
NOTE:
CLAYS, SILTS, LOAMS OR
NON-HOMOGENOUS SOILS
REQUIRE SHORING AND BRACING
THE PRESENCE OF GROUND
WATER REQUIRES SPECIAL
TREATMENT
2003
April 2009
Page 11
Page 11
5.4
5.4.1
DEWATERING
EXCAVATED
MATERIAL
Header Pipe
Pump
Gate Valve
Pump
Sump
SUMP SYSTEM
Discharge
Page 12
Page 12
2003
April 2009
5.4.4
5.4.5
5.5.4
5.5.5
These
a) Sludge pump (Centrifugal Type).
pumps are normally self-priming and can
pump very dirty water. Very little supervision
is required once the pump has been started.
b) Diaphragm pump. Very reliable if properly
maintained and can pump very dirty water,
but with a slower pumping rate than a
centrifugal type pump. Very little supervision
is required once the pump has been started.
5.4.7
5.5
5.5.1
5.5.2
6.
BEDDING
6.1
PURPOSE OF BEDDING
6.1.1
6.1.2
6.2
BEDDING MATERIAL
6.2.1
6.2.2
6.2.3
6.2.4
2003
April 2009
Page 13
Page 13
6.2.6
6.2.7
6.2.8
6.3
TYPES OF BEDDING
6.3.1
6.3.2
Apparatus
An open-ended cylinder of length
Cylinder.
approximately 250 mm and nominal internal
diameter 150 mm.
A metal rammer of mass
Rammer.
approximately 1 kg and having a striking face of
diameter approximately 38 mm.
Rule. A steel rule graduate in millimetres.
Procedure
Obtain a representative sample of the material as
follows:
CORRECT
INCORRECT
INCORRECT
Fig. 18 Uniform and Non Uniform Support
6.3.3
Bedding Class A
The pipe is normally supported on saddles or
other suitable supports, spaced so that there are
two supports per pipe. A soft-board strip must be
placed between the pipe and the saddle. Once
the line and grade have been fully checked, the
concrete bedding is cast around the pipe as
2003
April 2009
D
Compacted
Selected Fill
Blanket
300 mm
Bedding Cradle
of compacted
granular material
a) Trench
1:25 D min.
D
Compacted
Selected Fill
Blanket
300 mm
Compacted
granular
material
D/
20 Mpa
Concrete
D/ Max 300 mm
Min. i)100 mm in soil
ii) 50 mm in rock
1:25 D min.
120
20 Mpa
Concrete
b) Embankment
a) Trench
D/ limits
as for trench
Bedding Class C
The same comments apply to Class C bedding
as to Class B.
Bedding Cradle
of compacted
granular material
for trench)
Compacted
Selected Fill
Blanket
b) Embankment
6.3.4
Bedding Class AR
The introduction of 0,4% steel reinforcement will
increase the bedding factor significantly.
6.3.5
Bedding Class B
A granular bedding material should be thoroughly
compacted under the pipe and around the sides
of the pipe.
2003
April 2009
D/
Bedding Cradle
of compacted
selected granular
material
300 mm
6
a) Trench
1:25 D min.
90
20 Mpa
Concrete
D/ limits
8
as for trench
b) Embankment
Bedding Class D
Little or no care is exercised either to shape the
trench bottom to fit the lower part of the pipe
Page 15
Page 15
6.4.2
3. Fill Blanket
2. Second placement
of selected granular
material
1. Initial mound of
selected granular
material
6.4.3
6.4.4
6.4.5
4. Normal Backfill
PLACING OF BEDDING
a) Correct
Allmost impossible
to compact
under pipe
Well compacted
flat surface
6.4.6
6.4.7
Page 16
Page 16
a) Incorrect
Fig. 22 Construction of Bedding
6.4.9
2003
April 2009
7.
PIPE LAYING
7.1
LOWERING PIPE
7.1.1
7.1.2
7.1.3
7.1.4
7.1.5
7.1.6
7.2
7.2.1
7.2.2
7.2.3
7.2.4
7.2.5
7.3
JOINTING
7.3.1
7.3.2
7.3.3
7.3.4
i)
ii)
iii)
2003
April 2009
Page 17
Page 17
v)
7.3.6
ii)
7.3.7
7.3.8
iv)
Pipe
Internal
diameter
(mm)
Permissible
angular
deflection
(degrees)
Minimum radius
of curves (m)
for pipes
2,44 long
100
150
225
300
375
450
525
600
675
750
825
900
1 050
1 200
1 350
1 500
And laternal
6,5
4,5
3,0
2,0
2,0
1,5
1,25
1
0,75
0,50
21,5
31,0
46,5
56,0
70,0
93,0
112,0
140,0
186,0
-
2003
April 2009
7.4
CURVES
7.4.1
Curves
in
a
pipeline
are
normally
accommodated at manholes. However, it is
possible for curves of large radius to be
accommodated by means of deviating the
rubber ring -jointed pipes from the centre line.
7.4.2
7.4.3
8.
CULVERT BASES
8.1
GENERAL
8.1.1
8.1.2
8.2
8.2.1
8.2.2
8.3
8.3.1
CAST-IN-PLACE BASES
The founding preparation for cast-in-place slabs
is the same as for precast base slabs.
A layer of binding should be cast on this before
placing the steel reinforcement. This prevents
the soil or debris from coming into contact with it.
8.3.2
8.3.3
8.3.4
8.3.5
8.3.7
8.3.8
2003
April 2009
Page 19
Page 19
8.4
8.4.1
8.4.2
PLACING
8.4.3
8.4.4
8.4.5
8.4.6
8.4.7
8.4.8
8.5
8.5.1
8.5.2
8.5.3
10 MM GAP
DISTRIBUTION OF
CULVERTS ON SITE
MORTAR PAD IN
GROOVE
BIDIM WRAPPED
NO FUSS CONCRETE
FOR DRAINAGE
STAGGERED JOINTS
Page 20
Page 20
2003
April 2009
9.
BACKFILLING
9.1
GENERAL
9.1.1
When fixed into the joint after the portals have
been placed, it is essential that the size of joint
gap be consistent so as to accept the sealant. In
both in-stances the jointing material must be
firmly attached to withstand external water
pressure.
8.5.4
FLUSH JOINT
NO SEALING
9.2
9.2.1
9.2.2
9.2.3
9.2.4
9.2.5
10 - 20 MM
BIDIM SEALANT
WATER BAR
9.3
SEALANT APPLIED
AFTER INSTALLATION
9.3.1
2003
April 2009
Page 21
Page 21
9.3.3
9.3.4
10.
SPECIAL CONDITIONS
SUPPORT
H/
3
9.3.7
9.3.8
9.3.9
ii)
iii)
2003
April 2009
iii)
iv)
v)
vi)
11.
FIELD TESTING
ii)
iii)
iv)
not
2003
April 2009
Page 23
Page 23
12.
SPECIAL APPLICATIONS
Page 24
Page 24
2003
April 2009
(021)
(011)
(011)
(011)
(011)
386
827
670
357
914
1923
3517
7600
7600
8500
website: www.cmapipes.co.za