Beruflich Dokumente
Kultur Dokumente
INSTRUCTIONS
For FieldAssembly and Installation
ITABLE
OF CONTENTS
Page Number
Section
INTRODUCTION ........................................
1
BEFORE STARTING INSTALLATION ......................
.3
ASSEMBLY OF INDIVIDUAL POLE-UNITS. ................. . 4
Section
Page Number
IINTRODUCTION
General
The following instructions are for field assembly (erection) and installation
of S&CLine-Rupters. See Figure 1.
The S&C Line-Rupter employs an in-series circuitbreaking interrupter anda circuit-making and isolating
disconnect, makingit especiallysuited for line and cable
switching; specifically, load splitting (parallel or loop
switching), load dropping, andline and cable dropping.
Line-Rupter is capable of closing,carrying,and
interrupting load currents and parallel
loopor
currents,
as well as line- and cable-charging current.
Line-Rupters utilize the time-provenreliability of the
S&C Circuit-Switcher's brain and in-series interrupter,
combinedinacompact,economical,minimummaintenance switching package. Line-Rupter
interrupters are economically tailored for specific applications
by employing the precise number of interrupting gaps
required.
Each pole-unit of the S&C Line-Rupter includes a
brainwhichprovidesbuilt-inpositivesequence
control . . . and a fully enclosed stored-energy source
dedicated solely to operation of the interrupter which
Mounting of Line-Rupters
S&C Line-Rupters are intended for upright mounting
on S&C Mounting Pedestals or, alternately,for upright
mounting on the user's steel pedestals or supporting
structures which must meet specific static deflection
limits shown in an S&C data sheet.
The weight of the bus plus any associated ice load
exerts a vertical force on upright-mounted Line-Rupter
terminalpads. This vertical force mustnotexceed
400 pounds on either terminal pad.
'1991
INSTRUCTION SHEET
S&C
COMPANY
ELECTRIC
Page4 Chicago
S&C ELECTRIC CANADA LTD. Toronto
7521500
1 of 17
December 16,1991
S&C Line-Rupters
Outdoor Transmission (115 kv through 230 kv)
INTRODUCTION - Continued
752400
Page 2 of 17
December 16,199l
13
4-r
I.__
KV
..- -..-mounted
-r -.--- -,
------- ---~:-III~IIS:
mnnuallv
aaerated.
and
on S&C
...-..--...
GVIIIIIIL---,
IL alllperv:rr
nommal, d-n*
---I--I
1~s~~ucm0N SHEET
S&C ELECTRIC COMPANY l Chicago
S&C ELECTRIC CANADA LTD. l Toronto
IBEFORE
STARTING INSTALLATION
Gas-Pressure Indicator
An S&C erection drawing will be found in a waterresistant envelope attached to the interrupter
container on one of the threeLine-Rupter pole-units. Study
the erection drawing carefully and check the bill of
material to be sureall parts areat hand.
TheLine-Ruptershipmentshouldincludethe
following items, as shown in Figure 2:
1. Three pole-units, each mounted on a skid, with the
live partsattacheddirectlytotheinsulatormounting flanges;
2. Insulators, shippedin separate crates;
3. Miscellaneousoperating-mechanismcomponents
including a temporary adapter for hand operation
of the individual pole-units;
pipe;
4. Interphase and vertical operating
5. An S&C ManualGearedOperatingHandle
(if
specified) or an S&C Switch 0perator"Type LS-2
(if specified, in place of a manual geared operating
handle);
6. S&C Mounting Pedestals(if specified).
Interrupter Target
Line-Rupters are usually shipped with the interrupters
in the open position. Therefore, the interrupter target,
located onthe side of each brain housing (see
Figure S),
will appear yellow. During the step-by-step instructions
which follow, the disconnect blades will be moved to
the fully open position. This will close the interrupter
and charge and latch the stored-energy sourcewithin
the brain, and the target
will appear gray (normal).
INSTRUCTION SHEET
S&C ELECTRIC COMPANY Chicago
S&C ELECTRIC CANADA LTD. Toronto
752m500
Page 3 of 17
December 16,1991
S&C Line-Rupters
Outdoor Transmission (115 kv through 230 kv)
Disconnect
/-Interrupter
Pressure-relief device
h-tsulator hardware
Interrupter target
752400
Page 4 of 17
December 16,199l
INSTRUCTION SHEET
S&C ELECTRIC COMPANY l Chicago
S&C ELECTRIC CANADA LTD. l Toronto
Step 5
Unbolt and remove the jaw-contact assembly and
terminal adapter, as a unit, from the front insulator
support. See Figure 4.
Step 6
Assemble the insulator stacks (with rain shields, where
applicable) directly on their insulator supports, using
the galvanized hardware specified in Figure 7. Note that
the supports for the stationary insulator stacks each
have eight mounting holes. Be sure to orient these stacks
correctly so that the holes in the insulator caps are
positioned as shown in Figure 7.
w Temporary
hand-operation
Chicago
l Toronto
Page5of 17
December 16,199l
S&C Line-Rupters
Outdoor Transmission (115 kv through 230 kv)
. Jaw-contact
assembly
Terminal adapter
Front insulator
Figure 4. Using the temporary hand-operation aaapter to operate ,,,r pl~:-lw, I ll,C ups,, pvrmllvll.
752-500
Page 6 of 17
December 16,199l
INSTRUCTION SHEET
S&C ELECTRIC COMPANY. Chlcago
S&C ELECTRIC CANADA LTD. l Toronto
q
-
h -13X2%
positioning bolt 1
Brain mounting
flange
Wonbrainshaft Looset~o,~L~z~~~,
IL5 ue,o,t!
Pressure-relief device
Gas-pressure indicator
Page 7 of 17
December 16,199l
S&C Line-Rupters
Outdoor Transmission (115 kv through 230 kv)
(a) Loosen the four locking nuts and adjust the leveling
screws located under the stationary insulator
support. See Figure 7. (The leveling screws are
threaded into the insulator-support flange.) To
avoid changing the effective height of the insulator
stack, do not use more than three of thefour leveling
Step 9
Adjust for the necessary centerline distance and the
stack alignment, as described in Step 8, as follows:
Within % inch
of dimension
shown on erec-
Insulator stacks
*insulator cap
-- - - - -e
lockwashers
Rotating insulator
stack must be
perpendicular to
base. Use shims
here if required.
See Step 7
Locking nuts
Figure 7. Critical dimension and alignment to be attained using snlms ana leveung screws.
752400
Page 8 of 17
December 18,199l
INSTRUCTION
SHEET
S&C ELECTRIC COMPANY l Chicago
S&C ELECTRIC CANADA LTD. l Toronto
See Figure 8. Be sure to place the brain-andinterrupter assembly on the same pole-unit from
which it was removed.
(c) Install the cap screws (with lo&washers) finger
tight at both ends of the brain-and-interrupter
assembly. See Figure 8. Make sure that alignment
is such that the cap screws enter freely. If necessary,
reposition the rear stationary insulator stack using
the leveling screws. Also, if necessary, loosen the
cap screws at the rotating-insulator support. Then,
with the pole-unit drive lever against its stop bolt
as described in (a) above, torque to final tightness,
5/a- 11X1%"
hex-head galvanized
steel cap screws
and lockwashers
A
C
\\
..
Figure 8. Lifting brain-and-interrupter assembly into place. Inset shows jaw-contact assembly and terminal adapter being
placed.
Page 9 of 17
December 16,1991
S&C Line-Rupters
Outdoor Transmission (115 kv through 230 kv)
step 12
Remove, from the adjustment-holding device under the
brain, the Yz-13x2s positioning bolt installed in
Step 3. (A visible gap between mating parts is normal
when the bolt is removed.)
Do not attempt to operate the Line-Rupter pole-unit
before removing the positioning bolt.
to the pole-unit base and unbolt the base from the skid.
Raise the pole-unit to its mounting position as shown
on the erection drawing. Make sure that the rigging
does not stress the interrupter or the brain. Furthermore, extreme care should be exercised to prevent the
lifting slings or fall lines from interfering with the
interrupter target, the gas-pressure indicator, or the
pressure-relief device during erection, and to prevent
contact with other objects during lifting.
Step 13
Mount the jaw-contact assembly and terminal adapter
as a unit on the front insulator stack using the
galvanized hardware specified in Figure 8. Align the
jaw-contact assembly with the blade by shifting the
terminal adapter as required. See Figure 8. (Optimum
alignment of the jaw-contact assembly with the blade
may require adjustment of the front-insulator-support
leveling screws. This final adjustment should be made
only after the pole-unit has been mounted in place and
bolted to the pedestals or structure.)
step 15
Bolt the Line-Rupter pole-unit in place using %-inch
galvanized bolts, flat washers, lo&washers, and nuts
(furnished only if so specified on order). See Figure 9.
The pole-unit base should be shimmed as required if
the mounting surface is sufficiently irregular to distort
the base.
Step 14
With the temporary hand-operation adapter, operate
the pole-unit to the closed position. Attach lifting slings
Step 16
Make a final check of the Line-Rupter pole-unit for
adjustment and alignment of the blade with the jaw-
arm at the top of the brain should rest against its open
stop, and the pole-unit drive lever should rest against
its stop bolt, in a positive-toggle condition. See Figure 11. Both stops have been carefully adjusted at the
factory to provide the travel necessary to achieve full
closure of the interrupter and positive latching of the
stored-energy source within the brain. Do not attempt
Current-carrying
tongue contacts
r/+
Circuit-closing
jaw contacts
Current-carrying
7 Circuit-closing
tongue contact
Figure 10. Tongue-contact and jaw-contact assemblies shown In partially closed and tully closea positions.
Page 11 of 17
December 16,199l
S&C Line-Rupters
Outdoor Transmission (115 kv through 230 kv)
Step 20
After the pole-unit has been checked and adjusted as
described above, place the disconnect blade in the open
position (make sure that the pole-unit drive lever is
against its stop, in a positive-toggle condition). Then
remove the temporary hand-operation adapter.
step 21
If the outboard bearing assembly is furnished for
separate mounting, install it on the structure in the
position shown on the erection drawing.
Ball-joint shaft
Rotating-yoke
lock nut
\
Blade crank-arm
Rotating-yoke
\ coupling pin
Open stop -
Ball-joint-shaft
INSTRUCTION SHEET
ELECTRIC
S&C
ELECTRIC
S&C
COMPANY
Page Chicago
CANADA LTD. Toronto
752-500
13 of 17
December 16,1991
S&C Line-Rupters
Outdoor Transmission (115 kv through 230 kv)
Interphase-shaft
Interphase-shaft drive
lever clamp (removed)
Interphase shaft has been
lifted into saddle! of
drive lever
Pole-unlt drtve lever ctamp
is replaced and clamp bolts
anrl nipTr:-- --, ----...
IS
7521500
Page 14 of 17
December 16,199l
INSTRUCTION SHEET
S&C ELECTRIC COMPANY l Chicago
S&C ELECTRIC CANADA LTD. l Toronto
q
.
Step 23
Attach a universal coupling to the hex shaft extending
below the outboard bearing assembly.
Note: If more than one section of vertical pipe is
required, the upper section(s) with associated coupling(s), guide bearing(s), and thrust bearing(s) should
be installed first, in accordance with the directions
shown on the erection drawing.
If an S&C Switch Operator-Type LS-2 is to be used,
install it as directed in S&C Instruction
Sheet 753-500, furnished with the switch operator.
If an S&C Manual Geared Operating Handle is to
be used, install it as directed in S&C Instruction
Sheet 719530, furnished with the operating handle.
Key interlock
(Catalog Number Suffix I-L)
OPEN position
Indicator
Step 24
Make certain that all coupling clamp bolts for the
vertical operating pipe are securely tightened. Then
tighten the piercing set screws for the vertical
operating-pipe couplings and for the manual geared
operating handle, piercing the pipe, and continue
turning until a firm resistance is felt.
Step 26
Attach one end of the grounding strap to the lowest
vertical operating-pipe section with the U-bolt connector furnished. Then connect the other end of the
grounding strap to a suitable earth ground. (S&C
Mounting Pedestals include, for this purpose, a tab
welded to the pedestal adjacent to the handle location,
and a separate grounding connection near the base
of the pedestal for the users earth ground.)
Auxiliary switch
I-.. m* .
(r;atalog Numoer bun
- lx -Q)
Output shaft and
flexible coupling
Padlocking
provision
Terminal block (included
with optional auxiliary switch)
Conduit-entrance plate
Page 15 of 17
December 16,199l
S&C Line-Rupters
Outdoor Transmission (115 kv through 230 kv)
I
to achieve an equal stance when fully open. If, for
this reason, adjustment is required, loosen the balljoint-shaft locking nut. Turn the shaft (which is an
eccentric) to achieve a satisfactory blade position.
See Figure 11. Retighten the locking nut. Note that
it is not necessary to loosen the socket-head screw
(in the blade crank-arm) to make the above
adjustment. It is not a lock screw.
Repositioning the ball-joint shaft will affect the
depth of blade penetration into the jaw contact
during completion of the closing stroke. The
difference in penetration will range from very slight
(at lower voltage ratings) to significant (at the higher
voltage ratings).
If the adjustment described above is performed,
recheck for proper blade penetration and readjust
if necessary (as in Step 19).
0 With the disconnect blades in the fully open position,
the pole-unit drive lever on each Line-Rupter base
Contact (closed)
Roller
Inner gear
Adjacent spring
I
(b) Rotate the cam to advance or retard engagement
with its roller.
(c) Lower (or raise) the
cam makingsure that the teeth
are in mesh with the inner gear.
Step 30
Connect high-voltage conductors to their
Line-Rupter terminal pads.
~~
Step 31
Remove the containerfrom eachinterrupter as follows:
Remove anddiscardthe
Yi""16 zinc-plated
serrated hex nuts which run the length of the
container.
Remove anddiscardthe
YLif-l6X7/S" and two
%"-16X1" zinc-plated hex-head cap screws and
flat washers which attach
the upper container-half
to thecoupling end castingof the interrupter.Also
remove and discard the three3/S"-l6X%" and two
%"-16X1" zinc-platedhex-head cap crews and
flat washers which attach the upper container-half
to theindicator end castingof the interrupter.
Pry the cor.tainer-halves apart with a screwdriver.
The upper container-half cannow be removed and
discarded-slotted holes
are provided so that a
ropeor
lifting sling can be attachedandthe
container-half more conveniently lowered to the
ground.
Now remove and discard the3/8"-16X7/g" hex-head
cap screw and flat washerwhich attach the lower
container-half to the coupling end casting of the
interrupter,andthe
3/""16X?/"hex-head
cap
screwand flat washerwhichattachthe
lower
container-half to the indicator end casting of the
interrupter. Then discard this container-half.
Finally, remove and discard the foam-core inner
liner wrapped aroundthe iuterrupter.
Now remove the shield forthe pressure-relief device.
step 32
Please completeand mail the Line-Rupter registration
card! The information requested on this card is vital
toensurepromptnotification
in the event field
modifications are needed.
INSTRUCTION SHEET
S&C ELECTRIC
17COMPANY
Page Chicago
S&C ELECTRIC
LTD.CANADA
Toronto
respective
752-500
of 17
December 16,1991