Beruflich Dokumente
Kultur Dokumente
ECE 472S
Engineering Economic Analysis & Entrepreneurship
R. Vander Kraats
Week 1 - 1
Introduction
Each engineering project should be evaluated along two
dimensions:
Is it economically viable?
Private sector/regulated utilities
Will it make a profit?
Will it increase the wealth of the shareholders?
Public sector
Are the benefits of the project to society greater
than the costs to society (i.e., the taxpayer)?
Week 1 - 2
Introduction
Each technically acceptable alternative presents a
different set of economic consequences.
Consider all of the costs and all of the benefits over the
life cycle of the project.
The best engineering design is of little value to the
company if it cant be sold to management.
Engineering Economics
techniques to assist engineers in presenting the
economics of technical alternatives
techniques to evaluate projects involving long-term
investments in capital equipment from a financial point
of view
maximize a joint achievement function
performance objectives and costs
$$$ MONEY
presenting the economics of technical alternatives
Week 1 - 3
Week 1 - 4
Week 1 - 5
Week 1 - 6
$X
1
2
3
4
5
6
1 000
1 050
1 100
1 250
2 000
10 000
Week 1 - 7
Week 1 - 8
Alternative A
10 000
+ 7 000
+ 5 000
+ 3 000
+ 1 000
Alternative B
10 000
+ 1 000
+ 3 000
+ 5 000
+ 7 000
Week 1 - 9
$5 000
(+)
$3 000
$1 000
(-)
Alternative A
$10 000
$5 000
$7 000
$3 000
(+)
$1 000
0
(-)
Alternative B
$10 000
Week 1 - 10
$6 000
(+)
$2 000
3
0
2
$2 000
()
$6 000
Difference between alternatives
(A B)
+ cash flows benefits of choosing Alternative A
cash flows things given up when choosing Alternative A
A dollar at some future time has less
value than a dollar today.
Week 1 - 11
(+)
()
$200
$200
Alternative C
$450
$300
$200
$200
$100
(+)
()
Alternative D
$450
$200
(+)
()
3
0
4
$100
Week 1 - 12
2015-2016
Fee schedule
Week 1 - 13
Benefits
Time
1
Costs
Week 1 - 14
Cost Terminology
Compare engineering project alternatives on the basis of an
economic measure of effectiveness.
Which costs should be considered?
Life Cycle Costs
Week 1 - 15
Cost Terminology
To fairly compare alternatives, one must consider all the
costs over the life of each alternative.
Often there is a trade-off between First Cost and Operating
& Maintenance costs.
Which time period does one use for the length of the life
cycle?
functional life
economic life
Example: A solid-state telephone switch may be functionally
useful for 10 years. But due to technological
improvements, it may only have an economic life
of 6 years.
Economic Life < Functional Life
Always use the estimated economically useful life for
engineering analysis.
Week 1 - 16
Net
Salvage
Value
0
Operating and
Maintenance Costs
First
Costs
Week 1 - 17
Depreciation
40 000
$40 000
$10 000
5
10 000
$6 000
5
Week 1 - 18
Historical Costs
Cost Terminology
Past Costs Historical costs that have occurred
Sunk Costs Past Costs that are unrecoverable
Example: The salvage value for the server was estimated to
be $10 000 at the end of 5 years. However, at that
time, it turned out to be worth only $2 000.
Original Depreciation Charge
Should have been
40 000
40 000
10 000
$6 000
5
2 000
$7 600
5
Annual difference
= $1 600
This extra $1 600 was not recovered when the service was
sold. It can no longer be recovered and therefore is lost.
Sunk Cost = 5 1 600 = $8 000
Week 1 - 19
Surplus Datasets
A telephone company has 1 000 obsolete datasets that cost
$800 each when new. These datasets can be upgraded to the
current release level for $300 each and then sold for $650
each. The other alternative is to sell them as is to a local
electronics hobby store for $100 each. What would your
decision be?
Week 1 - 20
Surplus Datasets
Alternative A
Alternative B
A-B
Benefits
550K
Costs
1 000 300=300K
300K
100K
250K
350K
Week 1 - 21
COST TERMINOLOGY
Future Costs
future costs must be estimated over the project planning
period
estimates of future costs are uncertain and subject to error
uncertainty introduces risk into the project
assume for now future costs are known with certainty
Opportunity Costs
the cost of foregoing the opportunity to earn a return on
investment funds
Cost of Capital
the cost of obtaining funds for financing engineering
projects
MARR minimum attractive rate of return
Sources of Capital
bonds (DEBT FINANCING)
shares (EQUITY FINANCING)
what is the optimal debt ratio?
risk-return relationship
Week 1 - 22
kE
35.0%
30.0%
25.0%
20.0%
kD
15.0%
10.0%
5.0%
0.0%
0.00
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
0.55
0.60
0.65
0.70
0.75
0.80
0.85
Debt Ratio
k = D kD + E kE
V
V
Week 1 - 23