Sie sind auf Seite 1von 65

Project Report

PROJECT COST ESTIMATING - BLDG 6851


Submitted by: Group 1

BLDG 6851 Project Cost Estimating

DEPARTMENT OF BUILDING, CIVIL & ENVIRONMENTAL ENGINEERING

Project Report

ACKNOWLEDGEMENT

We would like to convey our special thanks to Dr. Mona Metwally Abouhamad, for giving us
the opportunity in working on this project with her excellent guidance and her valuable
advices regarding the project that helped us to complete this project.

BLDG 6851 Project Cost Estimating

Project Report

TABLE OF CONTENTS
TABLE OF CONTENTS.............................................................................................................................
LIST OF FIGURES.....................................................................................................................................
LIST OF TABLES.......................................................................................................................................
Summary.....................................................................................................................................................
1. WBS........................................................................................................................................................
1.1. Introduction to WBS.............................................................................................................................
1.2. Methodology........................................................................................................................................
1.3. Developing WBS..................................................................................................................................
2.Introduction to the Given project............................................................................................................
3.Package 1................................................................................................................................................
4.Package 2................................................................................................................................................
5.Package 3................................................................................................................................................
6. Conclusion.............................................................................................................................................
7. Abbreviations.........................................................................................................................................
8. References.............................................................................................................................................

BLDG 6851 Project Cost Estimating

Project Report

LIST OF FIGURES
Figure 1: General Requirements WBS.......................................................................................................
Figure 2: Site Work WBS..........................................................................................................................
Figure 3: Concrete WBS............................................................................................................................
Figure 4: Metal WBS................................................................................................................................
Figure 5: Wood and Plastics WBS............................................................................................................
Figure 6: Thermal and Moisture Protection WBS......................................................................................
Figure 7: Doors and Windows WBS..........................................................................................................
Figure 8: Finishes WBS.............................................................................................................................
Figure 9: Specialties WBS........................................................................................................................
Figure 10: Furnishing WBS.......................................................................................................................
Figure 11: Conveying Systems WBS.........................................................................................................
Figure 12: Mechanical Works WBS..........................................................................................................
Figure 13: Parking Level 1- Building A.....................................................................................................
Figure 14: Parking Level 1- Building B.....................................................................................................
Figure 15: S.O.G. Sections........................................................................................................................
Figure 16: Concrete Column Reinforcing Type.........................................................................................
Figure 17: Concrete Wall Reinforcing Zones.............................................................................................
Figure 18: Concrete Ramp Section............................................................................................................
Figure 19: U.S. standard Size to Metric Bar size.......................................................................................
Figure : Metric Mass Conversion..............................................................................................................
Figure : Weight versus length relationships for different angles................................................................
Figure : Plan of Ground level slab Building A........................................................................................
Figure 23: Plan of ground level slab Building B.....................................................................................
Figure 24: Plan of office 2nd floor Building A.........................................................................................
Figure 25: Plan of office 2nd floor slab Building A..................................................................................
Figure 26: Plan of office 2nd floor Building B.........................................................................................
Figure 27: Plan of office 2nd floor slab Building B..................................................................................
Figure 28: Plan of 3rd and 4th floor Building A......................................................................................
Figure 29: Plan of 3rd and 4th floor slab Building A...............................................................................
Figure 30: Plan of 3rd and 4th floor Building B......................................................................................
Figure 31: Plan of 3rd and 4th floor slab Building B...............................................................................

BLDG 6851 Project Cost Estimating

Project Report

LIST OF TABLES
Table 1 - Quantity take-ff and pricing for Foundation Concrete................................
Table 2 - Quantity take-ff and pricing for Foundation Reinforcement........................
Table 3 - Quantity take-ff and pricing for S.O.G. Concrete (Parking Level 1Building A & B).........................................................................................................
Table 4 - Quantity take-ff and pricing for S.O.G. reinforcement (Parking Level 1Building A & B).........................................................................................................
Table 5 - Quantity take-ff and pricing for Column Concrete (Parking Level 1Building A & B).........................................................................................................
Table 6 - Quantity take-ff and pricing for Column Reinforcement (Parking Level 1Building A & B).........................................................................................................
Table 7 - Quantity take-ff and pricing for Wall Concrete (Parking Level 1- Building
A & B).......................................................................................................................
Table 8 - Quantity take-ff and pricing for Wall Reinforcement (Parking Level 1Building A & B).........................................................................................................
Table 9 - Quantity take-ff and pricing for Ramp Concrete.........................................
Table 10-Quantity take-ff and pricing for Wall Reinforcement..................................
Table 11 - Quantity take-off and pricing for Reinforcement Ground level slab
Building A...............................................................................................................
Table 12 -Quantity take-off and pricing for Concrete Ground level slab Building
A...............................................................................................................................
Table 13 - Quantity take-off and pricing for Reinforcement for different sections
on G.L.Bldg-A............................................................................................................
Table 14 - Quantity take-off and pricing for Concrete for different sections on
G.L.Bldg-A.................................................................................................................
Table 15 - Quantity take-off and pricing for Reinforcement for different sections
on G.L.Bldg-B............................................................................................................
Table 16 - Quantity take-off and pricing for Concrete for different sections on
G.L.Bldg-B.................................................................................................................
Table 17 - Quantity take-off and pricing for Reinforcement for different sections
on G.L.Bldg-A............................................................................................................
Table 18 - Quantity take-off and pricing for Concrete for different sections on
Ground level slab bldg.B
.................................................................................................................................
Table 19 - Quantity take-off and pricing for Reinforcement of Piers and Piers Caps
of Ground level slab Building A & B..........................................................................
Table 20 - Quantity take-off and pricing for Concrete of Piers and Piers Caps of
Ground level slab bldg. A &
B
.34
Table 21 - Quantity take-off and pricing for Reinforcement Second Floor Building
A...............................................................................................................................
Table 22 - Quantity take-off and pricing for Concrete Second Floor Building A......
Table 23 - Quantity take-off and pricing for Reinforcement Second Floor Building
A...............................................................................................................................
Table 24 - Quantity take-off and pricing for Concrete Second Floor Building A......

BLDG 6851 Project Cost Estimating

Project Report
Table 25 - Quantity take-off and pricing for Reinforcement Second Floor Building
A...............................................................................................................................
Table 26 - Quantity take-off and pricing for Concrete Second Floor Building A......
Table 27 - Quantity take-off and pricing for Reinforcement Second Floor Building
B...............................................................................................................................
Table 28 - Quantity take-off and pricing for Concrete Second Floor Building B......
Table 29 - Quantity take-off and pricing for Reinforcement Third Floor Building A
.................................................................................................................................
Table 30 - Quantity take-off and pricing for Reinforcement Fourth Floor Building
B...............................................................................................................................
Table 31 - Quantity take-off and pricing for Concrete Third Floor Building B..........
Table 32 - Quantity take-off and pricing for Concrete Fourth Floor Building A........
Table 33 - Quantity take-off and pricing for Reinforcement Third Floor Building A
.................................................................................................................................
Table 34 - Quantity take-off and pricing for Reinforcement Fourth Floor Building
A...............................................................................................................................
Table 35- Quantity take-off and pricing for Concrete Third Floor Building A...........
Table 36 - Quantity take-off and pricing for Concrete Fourth Floor Building A........
Table 37 - Quantity take-off and pricing for Reinforcement Third Floor Building B
.................................................................................................................................
Table 38 - Quantity take-off and pricing for Reinforcement Fourth Floor Building
B...............................................................................................................................
Table 39 - Quantity take-off and pricing for Concrete Third Floor Building B..........
Table 40- Quantity take-off and pricing for Concrete Fourth Floor Building B.........
Table 41 - Quantity take-off and pricing for Reinforcement Third Floor Building B
.................................................................................................................................
Table 42 - Quantity take-off and pricing for Reinforcement Fourth Floor Building
B...............................................................................................................................
Table 43- Quantity take-off and pricing for Concrete Third Floor Building B...........
Table 44 - Quantity take-off and pricing for Concrete Fourth Floor Building B........
Table 45 - Quantity take-off and pricing for Concrete Roof Level Building A & B.....
Table 46 - Quantity take-off and pricing for Reinforcement Roof Level Building A
& B...........................................................................................................................
Table 47 - Final Summary Sheet Per Package No. 1..................................................
Table 78 - Final Summary Sheet Per Package No. 2..................................................
Table 79 - Final Summary Sheet Per Package No. 3..................................................
Table 50 - Final Summary Sheet For Project..............................................................

BLDG 6851 Project Cost Estimating

Project Report

SUMMARY

Nowadays Architecture, Engineering and Construction Industry are very demanding in


accurate cost estimation, scheduling and project management construction processes. These
Industries are dynamic places, where numerous contractors, subcontractors, trades people and
labourers come together to carry out tasks and complete the project.
Efficient management and execution of these activities using the available resources are
usually difficult and frequently problematic. This leads to wastage of time, money and
resources. Therefore, in this project report the first focus is concentrated on Development of
detailed Work Breakdown Structure, then we are going to introduce the given case study
Four storey office buildingand how we assigned a scope of work, calculation of Quantity
take-off, Cost estimation, Complete Bid Estimate and Profit estimation.
Our Submittal consists of :

One electronic copy (PDF file of the whole project)

BLDG 6851 Project Cost Estimating

Project Report

1.

WORK BREAKDOWN STRUCTURE

1.1.
Introduction
A work Breakdown Structure (commonly known as WBS), is a hierarchical breakdown of a
project into simpler tasks or deliverables.
The Work Breakdown Structure (WBS) identifies the projects tasks and provides a
framework for organizing and managing the work. The importance of the WBS derives from
that it is the cornerstone for most of the project phases for example as, but not limited to:
Project Planning
Execution
Project Controls
Project reporting
Cost estimation
Scheduling

BLDG 6851 Project Cost Estimating

Project Report
Therefore, the planning and development of the WBS should be done carefully as its structure
and codes integrate all the project components (Scope, Schedule and Cost). The WBS is
necessary to achieve all the technical objectives of the work described.
A work Breakdown Structure (commonly known as WBS), is a hierarchical breakdown of a
project into simpler tasks or deliverables.
A WBS can be created by breaking down a project into major divisions, based on their
disciplines or the actual work area/phase of the project. These divisions can further be subdivided into more categories, and can therefore be monitored/controlled accordingly. The
level of detail mainly depends on the purpose the WBS is being established for.
1.2.
Methodology
For our case study, the Work Breakdown Structure was carried out depending on its
functions. MasterFormat was used to identify levels of functions subject to the project size,
complexity and organization are more logical to breakdown to cost centers (packages) which
can be measurable and controllable by its functions.
First, the WBS was done according to the owners point of view and the contractor expanded
the WBS on the execution part to show the project components and sequence of the works.
Code accounts were given to each level of the WBS to make it easy to track the changes
happening specially to the cost centers.
We found that considering the scope of this project, it would be relatively convenient to
divide the work according to their discipline. We assumed that each work package would be
assigned to one contractor. Breaking down the work according to their disciplines would
prevent clashes and disputes amongst various contractors working on the same project.
In order to create our coding system we initially considered the master format which is
widely used throughout the industry however we decided to develop our own codes based on
general knowledge because it is simpler to describe. Typically, each specific component of
the building would have a very specific code which would be assigned based on factors such
as category, location and type of work involved.
MasterFormat is the specifications-writing standard for most commercial building design and
construction projects in North America and its numbers and titles are internationally
structured. It is a product of the Construction specifications Institute (CSI) and Constructions
Specification Canada.
We established the WBS based on the work-package assigned to each building component.
Each building component was divided in common work-packages such as Civil, Electrical,
Mechanical and Architectural.
1.3.
Developing WBS
Development of a WBS requires a thorough understanding of the project scope of work.
Experience in building is key to establishing a functional WBS. The WBS and the hierarchy
of work packages of which it is composed are used to determine the status of a project and to
manage the project from a time, cost, and quality perspective. Mentally, building a WBS
structures the work that must be physically accomplished to realize the project and its end
objective.
BLDG 6851 Project Cost Estimating

Project Report
In establishing the WBS, the following guidelines need to be considered:
Work packages must be clearly distinguishable from other work packages.
Each work package must have a unique starting and ending date.
Each work package should have its own unique budget.
Work packages should be small enough that precise measurement of work progress
is possible.
Planning can be thought of as the definition and sequencing of the work packages within a
given project. Namely: Planning =Work Breakdown+ Work Sequencing.
Planning leads to a refinement of the scope of work as established in the contract documents.
A good plan reduces uncertainty and improves efficiency. The WBS also assists in
determining the level of planning required.
In construction, the various aspects of the work that contribute to breakdown of the project
into packages relate to:
Methods used to place work.
Skills needed for the work.
Craft workers involved.
Critical resources (e.g., cranes, crews, etc )
The definition of work packages can be facilitated by using categories which help in
establishing a level of uniqueness. For this example, the following four categories have been
defined:
Location or area within the project (e.g., foundationpile cap).
Material type (e.g., concrete, steel, ).
Method of installation (e.g., excavation).
Types of resources required (e.g., labor and equipment needed).

BLDG 6851 Project Cost Estimating

10

Project Report

OWNERSS WBS

BLDG 6851 Project Cost Estimating

11

Project Report
CONTRACTORS WBS

BLDG 6851 Project Cost Estimating

12

Project Report

WBS BY DELIVERABLES

Figure 1: General Requirements WBS

BLDG 6851 Project Cost Estimating

13

Project Report

Figure 2: Site Work WBS

Figure 3: Concrete WBS

Figure 4: Metals WBS

BLDG 6851 Project Cost Estimating

14

Project Report

Figure 5: Wood & Plastics WBS

Figure 6: Thermal & Moisture Protection WBS

BLDG 6851 Project Cost Estimating

15

Project Report

Figure 7: Doors & Windows WBS

Figure 8: Finishes WBS

Figure 9: Specialties WBS

BLDG 6851 Project Cost Estimating

16

Project Report

Figure 10: Furnishing WBS

Figure 11: Conveying Systems WBS

Figure 12: Mechanical Works WBS

BLDG 6851 Project Cost Estimating

17

Project Report

2.

INTRODUCTION TO THE GIVEN CASE STUDY

Name of the Project: Four storey Office building


Procedure of work:
Our group has learnt provided project documents and met to elaborate the scope of work.
Athorough understanding of items included in the scope of work was developed by studying
the project drawings and specifications. After having clarified the scope of work, the scope
was divided into three work packages and allocated among six group members.
Scope of Work: The scope of work was given by the Professor to entirely cover the following
items:
Foundation Work
Concrete
Reinforcement
Roof
Steel
The work is divided in three categories and allocated to six estimators,
1. Package 1 (Substructure Foundations) estimated by Tamara Gavrilenko, Abdulnaser
Alamari and Yvonne Ocheoha, Amandeep Singh and Badwal-Kuldip Singh.

Foundation piles

Foundation concrete and reinforcement

Colums concrete and reinforcement

Slab on grade concrete and reinforcement

Exterior and Internal Walls on the Parkade floor concrete and reinforcement

2. Package 2 (Super structure(from Ground to Fourth floors)) estimated by Tamara


Gavrilenko, Abdulnaser Alamari and Yvonne Ocheoha, Amandeep Singh and BadwalKuldip Singh.

Beams

Walls
Slabs
Stairs

BLDG 6851 Project Cost Estimating

18

Project Report
Columns
Drop Panles
Pier caps etc.
3. Package 3 (Super Structure Penthousem,Roof and Ceiling) estimated by Shaik
Sirajuddin.

After having a clear understanding of scope of work each sub-group started the quantities
takeoff. Quantities were taken off from drawings using Metric units system. During the
quantity survey stage, the group had several progress and coordination meetings in order to
exchange proposals and to ensure that all work packages are following the same structured
method. After the quantity takeoff stage was completed, we began to assign prices to it.
The pricing was done by using RS Means 2015 for Building Construction Costs Estimation.
By using RS Means pricing method, every assigned estimator per package selected the
appropriate RS Means lines of material unit price according to the requirements of the project
specifications.
The cost of wastage is collectively assume to be 5 % of the total price. The final bid price was
calculated by applying 10% contingency to the total final price to account for material price
escalation, labor wage increase, inflation rates and construction risk.
Note:
Most of the figures in the project are extracted from the given project drawing sheets.
Pricing is calculated for all the material items using RS Means Building
Construction Cost data 2015

BLDG 6851 Project Cost Estimating

19

Project Report

1.PACKAGE 1: SUB STRUCTURE (FOUNDATION AND PARKING FLOOR )


Estimated by: Tamara Gavrilenko, Abdulnaser Alamari and Yvonne Ocheoha, Amandeep
Singh and Badwal-Kuldip Singh
1.1.
INTRODUCTION
The following work items are estimated under super structure

1.1.1. Tasks Performed and Assumptions.


The quantity take off of each work item are calculated using the dimensions shown on
the given drawings.
First centre line perimeter length is calculated for each of wall from given floor plan
(See Figure 13 & 14). Width and height are calculated from drawings. Quntities are
derived depending on the work items by multiplying the dimensions (length, width,
height and number).
Openings are deducted from the quantites (where it applies) to get the Net value.
Following conversion factors are used
1 m = 3.28 ft
1 m = 10.76 S.F.
1 m = 1.31 CY
1 kg = 0.0011 ton
1 kg = 2.2 lb
Each Unit Price is multiplied with Quantities takeoff to get the cost of material.
The Total Including Overhead & Profit column add 10% to the bare material cost.

BLDG 6851 Project Cost Estimating

20

Project Report

1.2.

FOUNDATION
1.2.1. FOUNDATION- BUILDING A & B
03 31 13.35 FOUNDATION CONCRETE

CSI CODE
03 31 13 35 03
50
03 31 13 35 02
00
03 31 13 35 02
00

MATERIAL
DESCRIPTI
ON
Concrete
footing(Pil
es)
Concrete
PC
Concrete
toppings

AIR
ENT.

QUANTITY

UNI
T

MATERIAL
PRICE PER
UNIT, $

TOTAL
COST, $

TOTAL
INCL. O/P,
$

6.5

3696.408

142.66

551356.2
173

606491.83
9

6.5

1085.1237
75

136.71

6.5

155.24621

136.71

155400.5
758
22232.80
973
728989.
6028

170940.63
34
24456.090
71
801888.5
631

Table 1: Quantity take-ff and pricing for Foundation Concrete


03 21 11.60 FOUNDATION REINFORCEMENT
CSI CODE
03 21 11 60
05 00
03 21 11 60
05 50
03 21
05
03 21
05
03 21
05
03 21
05
03 21
05

11
50
11
50
11
00
11
00
11
50

60
60
60
60
60

MATERIA
L
DESCRIPT
ION
Rebars
20M
Rebars
25M for
Piles
Rebars
25M
Rebars
30M
Stirrup
15M
Stirrup
20M
Stirrup
25M

No

LENGTH
,m

QUANTITY

UNI
T

MATERIAL
PRICE PER
UNIT, $

TOTAL
COST, $

9.88

5328.234
6

kg

0.97

5168.3875
62

218
0

139444.3
54

kg

0.97

135261.02
34

61.06

kg

0.97

57.42

kg

0.97

4.2696

kg

0.97

9.88

kg

0.97

50.49

kg

0.97

39485.187
73
43923.953
9
59517.688
45
29234.115
32
45048.790
68
357639.14
7

40706.37
91
45282.42
67
61358.44
17
30138.26
322
46442.05
225

BLDG 6851 Project Cost Estimating

21

IN

Project Report
Table 2: Quantity take-ff and pricing for Foundation Reinforcement

1.3.

PARKING LEVEL 1- BUILDING A & B

Figure 13: Parking Level 1- Building A

BLDG 6851 Project Cost Estimating

22

Project Report

Figure 14: Parking Level 1- Building B

1.3.1. SLABE ON GRADE

Figure 14: S.O.G. Sections

BLDG 6851 Project Cost Estimating

23

Project Report
03 31 13.35 S.O.G. CONCRETE
CSI CODE
03 31
02
03 31
02

13 35
20
13 35
20

MATERIAL
DESCRIPTION

QUANTITY

MATERIAL PRICE
PER UNIT, $

TOTAL
COST, $

TOTAL
INCL. O/P,
$

106638.51 117302.363
22
4
5865.4504 6451.99553
m
136.71
89
8
112503.9 123754.35
627
9
Table3 : Quantity take-ff and pricing for S.O.G. Concrete (Parking Level 1- Building A & B)
Concrete Slab-ongrade
S.O.G. Elevator's
area

780.0344
688
42.90432
66

UNI
T

136.71

03 21 11.60 S.O.G. REINFORCEMENT


MATERIAL
DESCRIPTION

CSI CODE
03 21
06
03 21
06
03 21
06
03 21
06

11
00
11
00
11
00
11
00

LENGT
H, m

QUANTITY

325.8
35
171.0
93

28295.43
948
5757.095
282

UNI
T

MATERIAL PRICE
PER UNIT, $

TOTAL
COST, $

27446.57
629
5584.382
60
Rebars 15M
Kg
0.97
423
1557.926
60
Rebars 25M
34.1
1606.11
Kg
0.97
7
102.4911
60
Stirrup
67.3
105.661
Kg
0.97
10M@200
7
34691.37
659
Table4 : Quantity take-ff and pricing for S.O.G. reinforcement (Parking Level 1- Building A & B)
60

Rebars 10M

Kg

0.97

TOTAL
INCL. O/P,
$

30191.233
92
6142.8206
66
1713.7193
7
112.74028
7
38160.51
425

1.3.2. COLUMNS
03 31 13 35 COLUMN CONCRETE (PARKING LEVEL 1-BUILDINGS A and B)
CSI CODE
03 31
04
03 31
04

13 35
11
13 35
11

MATERIAL
DESCRIPTION

QUANTIT
Y

UNI
T

MATERIAL PRICE
PER UNIT, $

TOTAL
COST, $

TOTAL
INCL. O/P,
$

6964.1759 7660.5935
3
23
5175.2452 5692.7698
34.1348
m
151.612
98
27
12139.42
13353.36
123
335
Table 5: Quantity take-ff and pricing for Column Concrete (Parking Level 1- Building A & B)
Concrete Column
with GDP-530 mm
Concrete Column
with GDP-630 mm

45.9342

BLDG 6851 Project Cost Estimating

151.612

24

Project Report

Figure 15: Concrete Column Reinforcing Type

03 21 11.60 COLUMN REINFORCEMENT (PARKING LEVEL 1-BUILDINGS A and B)


CSI CODE
03 21
02
03 21
02
03 21
02
03 21
02
03 21
02
03 21
02
03 21
02
03 21
02
03 21
02

11
00
11
00
11
00
11
50
11
50
11
50
11
50
11
50
11
00

60
60
60
60
60
60
60

MATERIAL
DESCRIPTION
Rebars 20M
(TYPE 7)
Rebars 20M
(TYPE 8)
Rebars 20M
(TOTAL)
Rebars 25M
(TYPE 1)
Rebars 25M
(TYPE 2)
Rebars 25M
(TYPE 4)
Rebars 25M
(TYPE 5)
Rebars 25M
(TOTAL)

LENG
TH, m

QUANTIT
Y

UNIT

MATERIAL
PRICE PER
UNIT, $

TOTAL
COST, $

32.2

75.831

kg

0.97

73.55607

80.

48.3

113.7465

kg

0.97

121

80.5

189.5775

kg

0.97

110.33410
5
183.8901
75

96.6

1516.62

kg

0.97

483

24013.15

kg

0.97

386.4

86952.88

kg

0.97

161

2527.7

kg

0.97

1127

kg

161

256

2451.869

269

0.97

1.3.3. WALLS
03 31 13.35 WALL CONCRETE

BLDG 6851 Project Cost Estimating

20

23292.755
5
84344.293
6

111560.0
395
5751.9143
60
Stirrup 10M
8.46
kg
0.97
93
229239.7
737
Table 6: Quantity take-ff and pricing for Column Reinforcement (Parking Level 1- Building A & B)
60

115010.3
5
5929.808
653

1471.1214

T
I
O

25

927

12

632

25

Project Report

CSI CODE
03
04
03
04

MATERIAL
DESCRIPTION

AIR
ENT.

QUANTITY

UNI
T

489.9354
25

MATERIAL
PRICE PER
UNIT, $

TOTAL
COST, $

76469.121
13
11934.415
8
76.46345
m
148.08
28
88403.53
641
Table 7 : Quantity take-ff and pricing for Wall Concrete (Parking Level 1- Building A & B)

31 13 35
00
31 13 35
00

Concrete
Foundation Wall
Concrete Shear
Wall

148.08

TO
INCL

8411
2
1312

9724
0

Figure 16: Concrete Wall Reinforcing Zones

03 21 11.60 WALL REINFORCEMENT


CSI CODE

MATERIAL
DESCRIPTION

BLDG 6851 Project Cost Estimating

LENGT
H, m

QUANTITY

UNI
T

MATERIAL
PRICE PER
UNIT, $

TOTAL
COST, $

26

IN

Project Report
03 21
07
03 21
07

11 60
00
11 60
50

Rebars 15M

1509.4
73

Rebars 25M

7.96

42526.87
731
1109.126
5

kg

0.97

kg

0.97

kg

0.97

kg

0.97

41251.07
099
1075.852
705

1108.290
475
330.4327
504

Zone 3 (# of
zones 2)
03 21 11 60
07 50
03 21 11 60
07 00

Rebars 25M

3.98

Stirrup 15M

3.98

1142.567
5
340.6523
2

Zone 4 (# of
zones 2)
03 21 11 60
07 50

Rebars 25M

3.98

724.555

kg

0.97

702.8183
5

03 21 11 60
07 00

Stirrup 15M

3.98

329.9512

kg

0.97

320.0526
64

Rebars 25M

8.95

167.205

kg

0.97

Stirrup 15M

8.95

24.15183
333

kg

0.97

162.1888
5
23.42727
833

Rebars 10M

8.95

11.147

kg

0.97

10.81259

Stirrup 10M

8.95

15.66153
5

kg

0.97

15.19168
895

Rebars 25M

19.9

668.82

kg

0.97

648.7554

Stirrup 15M

19.9

178.352

kg

0.97

173.0014
4

Rebars 15M

14.28

44.588

kg

0.97

43.25036

Stirrup 15M

14.28

44.14212

kg

0.97

42.81785
64

Rebars 15M

14.28

133.764

kg

0.97

Stirrup 15M

14.28

131.5346

kg

0.97

129.7510
8
127.5885
62

Rebars 15M

8.95

66.882

kg

0.97

64.87554

Stirrup 15M

8.95

47.56053
333

kg

0.97

46.13371
733

8.95

11.147

kg

0.97

10.81259

Zone 9 (# of
zones 2)
03 21 11 60
07 50
03 21 11 60
07 00
03 21 11 60
07 00
03 21 11 60
07 00

Zone 10 (# of
zones 6)
03 21 11 60
07 50
03 21 11 60
07 00

Zone 14 (# of
zones 1)
03 21 11 60
07 00
03 21 11 60
07 00

Zone 15 (# of
zones 3)
03 21 11 60
07 00
03 21 11 60
07 00

Zone 16 (# of
zones 2)
03 21
07
03 21
07

11 60
00
11 60
00

TOTAL
03 21 11 60
07 00

Rebars 10M

BLDG 6851 Project Cost Estimating

27

Project Report
03 21
07
03 21
07
03 21
07
03 21
07

11
00
11
50
11
00
11
00

60
60
60
60

Rebars 15M

1546.9
83

42772.11
131

kg

0.97

Rebars 25M

44.77

3812.274

kg

0.97

Stirrup 10M

8.95

kg

0.97

Stirrup 15M

74.32

kg

0.97

15.66153
5
1096.344
607

41488.94
797
3697.905
78
15.19168
895
1063.454
268
46276.31
23

Table 8: Quantity take-ff and pricing for Wall Reinforcement (Parking Level 1- Building A & B)

BLDG 6851 Project Cost Estimating

28

Project Report
1.3.4. RAMP

Figure 17: Concrete Ramp Section


03 31 13. 35 RAMP CONCRETE
CSI CODE
03 31 13 35
04 00

MATERIAL
DESCRIPTION
Concrete
Ramp

QUANTIT
Y

UNI
T

MATERIAL PRICE
PER UNIT, $

471.582

148.08

TOTAL
COST, $

69831.862
56
69831.862
56

TOTAL
O/P

76815.

76815
2

Table 9: Quantity take-ff and pricing for Ramp Concrete


03 21 11.60 RAMP REINFORCEMENT
CSI CODE
03 21 11 60
06 00

MATERIAL
DESCRIPTION
Rebars 10M

LENGT
H, m

QUANTI
TY

UNIT

MATERIAL
PRICE PER
UNIT, $

63.9

1371.08
1

kg

0.97

TOTAL
COST, $

1329.9485
7
1329.948
57

Table 10: Quantity take-ff and pricing for Wall Reinforcement

BLDG 6851 Project Cost Estimating

29

TO
INCL

1462

1462
2

Project Report

2. PACKAGE 2: SUPER STRUCTURE


Estimated by: Tamara Gavrilenko, Abdulnaser Alamari and Yvonne Ocheoha, Amandeep
Singh and Badwal-Kuldip Singh.
2.1.
INTRODUCTION:
In this case study, the super structure contains :
Beams
Walls
Slabs
Stairs
Columns
Drop Panles
Pier caps etc.
The quantites are calculated according to each section. The volume of concrete for each slab
is calculated separately depending upon their level and phases; A and B. From slab
reinforcement details, the thickness and other details of ground slab of both faces differs from
other slab on upper levels. So thats why we calculated the volume of concrete,
reinforcement saperately. Walls, beams and other deails which are above ground level slab on
both phases are counted saperately in different excel sheets. After that slabs of level 2 on both
faces took into consideration and their volume of concrete for each slab of both faces and
other sections which are above the slabs are counted saperately. Slabs and upper sections of
level 3 and 4 of both faces contain same details and that is why we took same values of
volume of concrete as well as of reinforcement. At the end, we just summarised whole values
of each floor and from there, we calculated the price for this super structure.

2.2. Assumptions
While calculating the price of different bars having different diameter, to make our
calculations simple, we assumed that there is a provision of Plain Steel Reinforcement
Bars and in this assumption, we got same price for whole bars irrespective of their
postion, whether those bars were in footing, slab or in walls.
Reference from
RS means 2015

Size of Bars

Material Price /ton

03 21 11.60 0100

Beams and Girders #3 to # 7

970

03 21 11.60 0150

#8 to #18

970

03 21 11.60 02 00

Columns #3 to #7

970

03 21 11.60 02 50

#8 to # 18

970

03 21 11.60.04 00

Slabs #3 to #7

03 21 11.60.05 00

Footings#4 to # 7

970

03 21 11.60 55 00

#8 to # 18

970

BLDG 6851 Project Cost Estimating

970

30

Project Report

We converted bars having U.S. standard Size to Metric Bar size from the following table of
conversion: (PURPOSES AND TYPES OF REINFORCING STEEL, n.d.)

Figure 18: U.S. standard Size to Metric Bar size

To make our calculatiuons more simple, we converted Price /Ton to Price/Kg because from
our references(metric mass conversions (canada wide reinforcement steel co ltd, n.d.)) we got
Diameter versus Weight relationships in terms of Kg/m.

Figure 19: Metric Mass Conversion

BLDG 6851 Project Cost Estimating

31

Project Report

We got weight versus length relationships for different angles from following tables
(canadian codes, n.d.):

Figure 20: Weight versus length relationships for different angles (canadian codes, s.d.)

BLDG 6851 Project Cost Estimating

32

Project Report

Heavy weight Concrete Ready Mix: From our RS means, we assumed that we will
use Heavy weight Concrete Ready Mix for this superstructure and we got price for
different strength of concrete in terms of Cubic Yards. But we had already calculated
our values in terms of cubic meter. So to get rid of complex conversions, instead of
converting volume of concrete into Cubic yards, we converted units of price in terms
of Price/m3.
References from RS means 2015

Strength in psi

Price/C.Y

R033105-20.0020
R033105-20.0100
R033105-20.0150
R033105-20.0200
R033105-20.0300
R033105-20.0350
R033105-20.0400
R033105-20.0411

2000
2500
3000
3500
4000
4500
5000
6000

97
99.50
102
104
107
110
113
116

Moreover we had some values lying in between standars values so we did interpolation as
well as conversion of units and at the end did multiplication with volume of concrete to get
the price in terms of cubic meter.
CSI Code
R033105-20.0350
R033105-20.0350
R033105-20.0411
R033105-20.0400

Type
Beams
Slabs
Columns
Walls

BLDG 6851 Project Cost Estimating

Strength in psi
4300
4300
6000
5160

Price/cubic meter
142.22
142.22
151.612
148.31

33

Project Report

2.3. Ground Level Slab


2.3.1.

Ground Level Slab Building A

Figure 21: Plan of Ground level slab Building A

CSI CODE

Ground Level Slab Building A Reinforcement


Bar
Length, m
Weight kg
Price per unit, $
size

Total price,
$

03 21 11 60 04
15 m
8218.963
12903.77191
0.97
12516.65875
00
03 21 11 60 04
20 m
7832.2
18444.831
0.97
17891.48607
00
03 21 11 60 04
25 m
629
2468.825
0.97
2394.76025
00
Table 11: Quantity take-off and pricing for Reinforcement Ground level slab Building A

Ground Level Slab Building A Concrete


Area of
Area of
Thicknes
Volume of
CSI CODE
slab, mm
slab m
sm
Conc. m
03 31 05 20
32461320
3246.132
0.25
811.533
04 11
00
Table 12: Quantity take-off and pricing for Concrete Ground level slab Building A

BLDG 6851 Project Cost Estimating

Price
per m
142.22

34

Tot
price
11541
233

Project Report

2.3.1.1. Calculations for different sections of ground level slab building - A

Reinforcement
Weight, kg

Price per kg

Total price,
$
3820.98049
2

CSI CODE

Bar Size

Length, m

03 21 11 60
04 00

10 M

5018.032033

3939.1551
46

0.97

03 21 11 60
04 00

15 M

11723.54933

18405.972
46

0.97

03 21 11 60
04 00

25 M

3863.5514
45

15164.439
42

0.97

17853.7932
8
14709.5062
4

03 21 11 60
04 00

30 M

345.24

1897.0938

0.97

1840.18098
6

03 21 11 60
04 00

Angle

27.0263

486.4734

0.97

471.879198

Concrete Volume
CSI CODE

Types

Volume of conc. m

Price
per m

03 31 05 20
Beams
43.75858
142.22
03 50
03 31 05 20
Walls
133.0910608
148.31
04 00
03 31 05 20
Columns
17.03617625
151.612
04 11
03 31 05 20
Sections in slab +
139.2921375
142.22
03 50
drop panels
Table 13: Quantity take-off and pricing for Reinforcement for different sections on
Ground level slab Building A
Table 14: Quantity take-off and pricing for Concrete for different sections on
Ground level slab Building A

BLDG 6851 Project Cost Estimating

35

Total price,
$
6223.34524
8
19738.7352
2
2582.88875
4

19810.1278

Project Report

2.3.2. Ground Level Slab Building B

Figure 22: Plan of ground level slab Building B

Ground Level Slab Building B Reinforcement


CSI CODE
03 21 11 60
04 00
03 21
04
03 21
04

11 60
00
11 60
00

Bar Size

Length, m

Weight kg

Price per kg

Total price
$

15 M

7229.3

11350.001

0.97

11009.50

20 M

7798.2

18364.761

0.97

17813.82

25 M

481

1887.925

0.97

1831.29

Table 15: Quantity take-off and pricing for Reinforcement


Ground level slab Building B

BLDG 6851 Project Cost Estimating

36

Project Report
Ground Level Slab Building B Concrete
CSI CODE

Area of
slab mm

Area of
slab m

Thicknes
sm

Volume of
Conc. m

Price
per m

Total
price

03 31 05 20
03 50

239120263
0

2391.2026
3

0.25

597.8006575

142.22

85019.21

Table 16: Quantity take-off and pricing forConcrete


Ground level slab Building B

2.3.2.1. Calculations for different sections of ground level slab building - B


Reinforcement
CSI CODE

Bar
Size

Length m

Weight kg

Price per kg

Total price
$

03 21 11 60
04 00

10 M

4440.462467

3485.763036

0.97

3381.19014
5

03 21 11 60
04 00

15 M

15927.99623

25006.95409

0.97

24256.7454
7

03 21 11 60
04 00

25 M

11365.52412

44609.68217

0.97

03 21 11 60
04 00

30 M

345.24

1897.0938

0.97

43271.3917
1840.18098
6

03 21 11 60
Angl
24.63808122
485.3702
0.97
470.809094
04 00
e
Table 17: Quantity take-off and pricing for Reinforecement for different sections on
Ground level slab Building A
Concrete Volume
CSI CODE
03 31
03
03 31
04
03 31
04

05 20
50
05 20
00
05 20
11

03 31 05 20
03 50

Type

Volume of conc.
m

Price per m

Total price

Beams

48.44683

142.22

6890.108163

Walls

351.63252

148.31

52150.61904

Columns

15.0793675

151.612

2286.213065

Sections
in slab +
drop
panels

111.4008475

142.22

15843.42853

Table 18: Quantity take-off and pricing for Concrete for different sections on
Ground level slab Building B

BLDG 6851 Project Cost Estimating

37

Project Report

2.3.3. Calculations of Pier and Pier Caps of ground level slab building - A & B
Reinforcement
CSI CODE

Bar Size

Length, m

Weight, kg

Price per
kg

Total
price, $

03 21 11 60
56.5486677
10 M
44.3907042
0.97
43.05
04 00
6
03 21 11 60
20 M
1446.6
3406.743
0.97
3304.54
04 00
03 21 11 60
25 M
327.84
1286.772
0.97
1248.16
04 00
03 21 11 60
30 M
533.52
2931.6924
0.97
2843.74
04 00
Table 19: Quantity take-off and pricing for Reinforcement of Piers and Piers Caps of Ground level
slab Building A & B

Concrete Volume
CSI CODE

Volume of conc. m

Price per unit m

Total price

03 31 05 20
116.3547253
142.22
16547.297
03 50
Table 20: Quantity take-off and pricing for Concrete of Piers and Piers Caps of Ground level slab
Building A & B

BLDG 6851 Project Cost Estimating

38

Project Report

2.4.

Second Floor

2.4.1.

Second Floor Building A

Figure 23: Plan of office 2nd floor Building A

Office 2nd Floor Building A Reinforcement


Bar Size

Weight kg

Price per kg

Total price $

10 M

1379.532833

0.97

1338.146848

15 M

22525.38341

0.97

21849.62191

25 M

8306.6432

0.97

8057.443904

angle
281.16
0.97
272.7252
Table 21: Quantity take-off and pricing for Reinforcement Second Floor Building A

Office 2nd Floor Building A Concrete


CSI CODE
03 31
03
03 31
04
03 31
03
03 31
04

Type

Volume of conc.
m

Price per m

05 20
Beams
5.5476
142.22
50
05 20
walls
67.96184
148.31
00
05 20
slab+
203.2943
142.22
50
droppanels
05 20
Columns
10.95
151.612
11
Table 22: Quantity take-off and pricing for Concrete Second Floor Building A

BLDG 6851 Project Cost Estimating

Total price
788.979672
10079.4204
9
28912.5153
5
1660.1514

39

Project Report

2.4.2. Second Floor Slab of Buillding A

Figure 24: Plan of office 2nd floor slab Building A

Office 2nd Floor Slab A Reinforcement


Lengt
Total price
Weight kg
Price per kg
hm
$
03 21 11 60
7586.9
11554.1661
15 M
11911.5115
0.97
04 00
5
6
03 21 11 60
5243.6
11978.3318
20 M
12348.79575
0.97
04 00
5
8
03 21 11 60
3306.3
12588.1010
25 M
12977.42375
0.97
04 00
5
4
Table 23: Quantity take-off and pricing for Reinforcement Second Floor Building A
CSI CODE

Bar
Size

Office 2nd Floor Slab A Concrete

CSI CODE
03 31 05 20
03 50

Area of
slab mm
2446980000

Area of
slab
m
2446.9

Thicknes

Volume of

Price

sm

Conc. m

per m

0.25
611.745
142.22
8
Table 24: Quantity take-off and pricing for Concrete Second Floor Building A

BLDG 6851 Project Cost Estimating

Total price

87002.3739

40

Project Report

2.4.3. Second Floor Building B

Figure 25: Plan of office 2nd floor Building B

Office 2nd Floor Building B Reinforcement


Bar Type

Weight kg

Price per kg

Total price $

10 M

622.6358333

0.97

603.96

15 M

22494.08808

0.97

21819.27

25 M

7733.0432

0.97

7501.05

angle

281.16

0.97

272.7252

Table 25: Quantity take-off and pricing for Reinforcement Second Floor Building A

BLDG 6851 Project Cost Estimating

41

Project Report

Office 2nd Floor Building B Concrete


CSI CODE
03 31 05 20 03
50
03 31 05 20 04
00
03 31 05 20 04
11
03 31 05 20 04
11

Type

Volume of
conc. m3

Price per
m3

Total
price $

Beams

5.5476

142.22

788.98

walls

67.96184

148.31

10079.42

columns

10.95

151.612

1660.15

Slabs

189.2718

142.22

26918.24

Table 26: Quantity take-off and pricing for Concrete Second Floor Building A

2.4.4. Second floor slab of Building B

Figure 26: Plan of office 2nd floor slab Building B

Office 2nd Floor Slab B Reinforcement

CSI CODE

Bar Size

Length

Weight kg

Price per
kg

Total price $

03 21 11 60 04
00

15 M

7586.95

11911.515

0.97

11554.16616

BLDG 6851 Project Cost Estimating

42

Project Report
03 21 11 60 04
00
03 21 11 60 04
00

20 M

5243.65

12348.795

0.97

11978.33188

25 M

3306.35

12977.423

0.97

12588.10104

Table 27: Quantity take-off and pricing for Reinforcement Second Floor Building B
Office 2nd Floor Slab B Concrete

CSI CODE

Area of
slab
mm

Area of
slab m

Thickne
ss m

Volume of
Conc. m

Price
per m

Total
price

03 31 05 20
03 50

24469800
00

2446.98

0.25

611.745

142.22

87002.373
9

Table 28: Quantity take-off and pricing for Concrete Second Floor Building B

1.1. 3rd and 4th Floor


1.1.1. 3rd and 4th Floor Building A

Figure 27: Plan of 3rd and 4th floor Building A

3rd floor Building A Reinforcement


Bar Type

Weight kg

BLDG 6851 Project Cost Estimating

Price per kg

Total price $

43

Project Report

10 M

1379.532833

0.97

1338.15

15 M

22525.38341

0.97

21849.62

25 M

8306.6432

0.97

8057.44

angle

281.16

0.97

272.73

Table 29: Quantity take-off and pricing for Reinforcement Third Floor Building A

4th floor Building A Reinforcement


Bar Type

Weight kg

Price per kg

Total price $

10 M

1379.532833

0.97

1338.15

15 M

22525.38341

0.97

21849.62

25 M

8306.6432

0.97

8057.44

angle

281.16

0.97

272.73

Table 30: Quantity take-off and pricing for Reinforcement Fourth Floor Building B

3rd floor Building A Concrete


CSI CODE

Type

Volume of
conc. m3

Price per m3

Total
price $

03 31 05 20 03
50

Beams

5.5476

142.22

788.98

03 31 05 20 04
00

walls

67.96184

148.31

10079.42

03 31 05 20 03
50

slab+
droppanels

203.2943

142.22

28912.52

03 31 05 20 04
11

Columns

10.95

151.612

1660.15

Table 31: Quantity take-off and pricing for Concrete Third Floor Building B
4th floor Building A Concrete
CSI CODE
03 31 05 20
03 50

Type

Volume of
conc. m3

Price per m3

Total
price $

Beams

5.5476

142.22

788.98

BLDG 6851 Project Cost Estimating

44

Project Report
03
04
03
03
03
04

31 05 20
00
31 05 20
50
31 05 20
11

walls

67.96184

148.31

10079.42

slab+ droppanels

203.2943

142.22

28912.52

Columns

10.95

151.612

1660.15

Table 32: Quantity take-off and pricing for Concrete Fourth Floor Building A

1.1.2. 3rd and 4th floor slab of Building A

Figure 28: Plan of 3rd and 4th floor slab Building A

Reinforcement (3rd floor slab A)


CSI CODE

Bar
Size

Length

BLDG 6851 Project Cost Estimating

Weight kg

Price per kg

Total price
$

45

Project Report
03 21 11 60
04 00

15 M

6727.95

10562.8815

0.97

10245.9950
6

03 21 11 60
04 00

20 M

4560.65

10740.33075

0.97

10418.1208
3

03 21 11 60
04 00

25 M

3306.35

12977.42375

0.97

12588.1010
4

Table 33: Quantity take-off and pricing for Reinforcement Third Floor Building A

Reinforcement (4th floor slab A)


CSI CODE
03 21 11 60 04
00
03 21 11 60 04
00
03 21 11 60 04
00

Bar
Size

Length

Weight kg

Price per kg

15 M

6727.95

10562.8815

0.97

20 M

4560.65

10740.33075

0.97

25 M

3306.35

12977.42375

0.97

Total price
$
10245.99506
10418.12083
12588.10104

Table 34: Quantity take-off and pricing for Reinforcement Fourth Floor Building A

Concrete (3rd floor slab A)


CSI CODE

Area of
slab mm

Area of
slab m

Thickne
ss m

Volume of
Conc. m

Price
per m

Total
price

03 31 05 20
03 50

24469800
00

2446.98

0.25

611.745

142.22

87002.3
7

Table 35: Quantity take-off and pricing for Concrete Third Floor Building A

Concrete (4th floor slab A)


CSI CODE

Area of
slab mm

Area of
slab m

BLDG 6851 Project Cost Estimating

Thickn
ess m

Volume of
Conc. m

Price
per m

Total
price

46

Project Report
03 31 05 20
03 50

24469800
00

2446.98

0.25

611.745

87002.3
7

142.22

Table 36: Quantity take-off and pricing for Concrete Fourth Floor Building A

1.1.3. 3rd and 4th Floor Building B

3rd floor Building B Reinforcement


Bar Type

Weight kg

Price per kg

Total price
$

10 M

622.6358333

0.97

603.96

15 M

22494.08808

0.97

21819.27

25 M

7733.0432

0.97

7501.05

angle

281.16

0.97

272.73

rd

th

Figure 29: Plan of 3 and 4 floor Building B

Table 37: Quantity take-off and pricing for Reinforcement Third Floor Building B

4th floor Building B Reinforcement


Bar Type

Weight kg

Price per kg

Total price
$

10 M

622.6358333

0.97

603.96

BLDG 6851 Project Cost Estimating

47

Project Report

15 M

22494.08808

0.97

21819.27

25 M

7733.0432

0.97

7501.05

angle

281.16

0.97

272.73

Table 38: Quantity take-off and pricing for Reinforcement Fourth Floor Building B

3rd floor Building B Concrete


CSI CODE

Type

Volume of
conc. m

Price per
m

Total
price $

03 31 05 20 03
50

Beams

5.5476

142.22

788.98

03 31 05 20 04
00

walls

67.96184

148.31

10079.42

03 31 05 20 04
11

columns

10.95

142.22

1557.31

03 31 05 20 03
50

Slabs

189.2718

151.612

28695.88

Table 39: Quantity take-off and pricing for Concrete Third Floor Building B

4th floor Building B Concrete


Type

Volume of
conc. m

Price per
m

Total
price $

20 03

Beams

5.5476

142.22

788.98

20 04

walls

67.96184

148.31

10079.42

20 04

columns

10.95

142.22

1557.31

20 03

Slabs

189.2718

151.612

28695.88

CSI CODE
03 31 05
50
03 31 05
00
03 31 05
11
03 31 05
50

Table 40: Quantity take-off and pricing for Concrete Fourth Floor Building B

1.1.4. 3rd and 4th Floor Slab of Building B

BLDG 6851 Project Cost Estimating

48

Project Report

Figure 30: Plan of 3rd and 4th floor slab Building B

Reinforcement (3rd floor slab B)


CSI CODE

Bar Size

Length

Weight kg

Price per kg

Total price
$

03 21 11 60
04 00

15 M

6727.95

10562.8815

0.97

10245.9950
6

03 21 11 60
04 00

20 M

4560.65

10740.33075

0.97

10418.1208
3

03 21 11 60
04 00

25 M

3306.35

12977.42375

0.97

12588.1010
4

Table 41: Quantity take-off and pricing for Reinforcement Third Floor Building B

Reinforcement (4th floor slab B)


CSI CODE

Bar Size

Length

Weight kg

Price per kg

Total price $

03 21 11 60 04
00

15 M

6727.95

10562.8815

0.97

10245.99506

BLDG 6851 Project Cost Estimating

49

Project Report
03 21 11 60 04
00
03 21 11 60 04
00

20 M

4560.65

10740.33075

0.97

10418.12083

25 M

3306.35

12977.42375

0.97

12588.10104

Table 42: Quantity take-off and pricing for Reinforcement Fourth Floor Building B

Concrete (3rd floor slab B)


CSI CODE

Area of
slab mm

Area of
slab m

Thickne
ss m

Volume of
Conc. m

Price
per
m

Total
price $

03 31 05 20 03
50

244698000
0

2446.98

0.25

611.745

142.22

87002.3
7

Table 43: Quantity take-off and pricing for Concrete Third Floor Building B

Concrete (4th floor slab B)


CSI CODE

Area of
slab mm

Area of
slab m

Thickne
ss m

Volume of
Conc. m

Price
per m

Total
price $

03 31 05 20 03
50

24469800
00

2446.98

0.25

611.745

142.2
2

87002.
37

Table 44: Quantity take-off and pricing for Concrete Fourth Floor Building B

3.PACKAGE 3: SUPER STRUCTURE ROOF AND CEILING


Estimated by: Shaik Sirajuddin

BLDG 6851 Project Cost Estimating

50

Project Report
3.1. INTRODUCTION
The roof is the uppermost part of the building.The charecteristics of the roof depends upon
the purpose of the building that it covers.The elements for the design of the roof is :
1)The material
2)The construction
3)The durability
The supporting structure of roof usually consists of rigid material and they are beams. So, the
tasks performed are with respect to these considerations.
2.4.5. Tasks Performed
There are various tasks performed with regards to the roof of building a and building b
calculations:
1)Calculation of the roof concrete volume:The volume of concrete for the roof is calculated
by taking the length,breadth and depth of the roof into consideration for the given values.
2) Calculation of the drop panel concrete volume
3) Calculation of the beam(B20,B25) concrete volume
4)Calculation of the roof reinforcement
5)Calculation of MAT roof reinforcement.
2.4.6. Assumptions
There are no major assumptons made with respect to roof calculations.Values are taken
as per the diagram.
CALCULATION FOR THE BAR 1-15M RUNNING OVER THE ROOF OF BUILDING A
AND BULDING B.
GIVEN 1-15M AROUND PERIMETER.
THE CONCRETE OF ROOF IS 30 Mpa.
THE PERIMETER OF THE ROOF IS 223.3M. FROM THE GIVEN VALUES.
LAP LENTH IS 223.3/12=18.96=19(APPX)
GIVEN 510MM IS THE LAP THE 19*0.510=9.66M
IT IS TOP AND BOTTOM THE IT IS TWICE=2*9.66=19.38M

CONCRETE OF ROOF BUILDING A and B

BLDG 6851 Project Cost Estimating

51

Project Report
CSI
CODE

073300
073300

MATERIAL
DESCRIPTION

QUANTITY

CONCRETE OF ROOF
FOR BUILDING A
CONCRETE OF ROOF
FOR BUILDING B

689.47
678.77

UNIT

MATERIAL
PRICE PER
UNIT, $

142.22

142.22

TOTAL COST, $

98056.56
96523.66

Table 45: Quantity take-off and pricing for Concrete Roof Level Building A & B

REINFORCEMENT OF ROOF BUILDING A and B


CSI CODE

073332
073332

MATERIAL
DESCRIPTION
Reinforcement
OF ROOF FOR
BUILDING A
REINFORCEMEN
T OF ROOF FOR
BUILDING B

QUANTIT
Y

UNIT

MATERIAL
PRICE PER
UNIT, $

21099

KG

0.90

22336

KG

0.90

TOTAL COST, $

18989.2
20102.4

Table 46: Quantity take-off and pricing for Reinforcement Roof Level Building A & B

7. CONCLUSION
BLDG 6851 Project Cost Estimating

52

Project Report
COMMENTS ON FINAL SUMMARY SHEET
CSI Master Format is strictly followed in making Final Summary Sheet.
All the work in which Concrete and concrete related items are covered under
Concrete Work division No 3.
All the work related to Openings (i.e. Doors. Windows, etc.) are covered under
division No 8.
A. Wastage 3.75% REINFORCEMENT
B. Wastage 7.5% Concrete
Profit (10%)
Tax (15%)
Insluation (1.9) %
SUMMARY OF COST OF THE WORK PACKAGES

BLDG 6851 Project Cost Estimating

53

Project Report

CSI CODE
03 31 13
03 31 13
03 50
03 31 13
02 00
03 31 13
02 00
03 31 13
02 00
03 31 13
02 20
03 31 13
04 00

35
35
35
35
35
35
35

FINAL SUMMARY COST SHEET PER PACKAGE No 1


MATERIAL PRICE PER
MATERIAL DESCRIPTION
QUANTITY
UNIT
UNIT, $
CONCRETE

TOTAL COST,
$

Concrete footing(Piles)

3696.408

142.66

527329.5653

1085.123775

149.16

161857.0623

155.24621

143.21

22232.80973

780.0344688

136.71

106638.5122

42.9043266

136.71

5865.450489

471.582

148.08

69831.86256

489.935425

156.08

76469.12113

Concrete Shear Wall

76.46345

156.08

11934.41528

Concrete Shear Wall

1040.80748

148.31

154362.1574

80.069

151.612

12139.42123

Concrete PC
Concrete toppings
Concrete Slab-on-grade
Slab-on-grade elevator's area
Concrete Ramp
CONCRETE FOR WALL

03 31
04
03 31
04
03 31
04

13 35
00
13 35
00
13 35
00

Concrete Foundation Wall

CONCRETE SLAB FOR COLUMN in


parking leavel
03 31 13 35
04 11
Totall
CSI CODE
03 21 11 60

Concrete Column

7918.574135
REINFORCEMENT

1136520.956

MATERIAL DESCRIPTION

QUANTITY

UNIT

MATERIAL PRICE PER


UNIT, $

TOTAL COST,
$

FOUNDATION REINFORCEMENT
Rebars 20M

5328.2346

Kg

0.97

5168.387562

BLDG 6851 Project Cost Estimating

54

Project Report

03
03
03
03
03
03

05
21
05
21
05
21
05
21
05
21
05
21
05

00
11
00
11
00
11
00
11
00
11
00
11
00

60
60
60
60
60
60

Rebars 25M for Piles

139444.354

Kg

0.97

135261.0234

Rebars 25M

40706.3791

Kg

0.97

39485.18773

Rebars 30M

45282.4267

Kg

0.97

43923.9539

Stirrup 15M

61358.4417

Kg

0.97

59517.68845

Stirrup 20M

30138.26322

Kg

0.97

29234.11532

Stirrup 25M

46442.05225

Kg

0.97

45048.79068

Rebars 20M (TYPE 7)

75.831

Kg

0.97

73.55607

Rebars 20M (TYPE 8)

113.7465

Kg

0.97

110.334105

Rebars 20M (TOTAL)

189.5775

Kg

0.97

183.890175

Rebars 25M (TYPE 1)

1516.62

Kg

0.97

1471.1214

Rebars 25M (TYPE 2)

24013.15

Kg

0.97

23292.7555

Rebars 25M (TYPE 4)

86952.88

Kg

0.97

84344.2936

Rebars 25M (TYPE 5)

2527.7

Kg

0.97

2451.869

Rebars 25M (TOTAL)

115010.35

Kg

0.97

111560.0395

Stirrup 10M

5929.808653

Kg

0.97

5751.914393

WALL REINFORCEMENT
Rebars 15M

42526.87731

Kg

0.97

41251.07099

COLUMN REINFORCEMENT
03 21 11 60
02 00
4 21 11 60
02 00
5 21 11 60
02 00
6 21 11 60
02 50
7 21 11 60
02 50
8 21 11 60
02 50
9 21 11 60
02 50
10 21 11 60
02 50
11 21 11 60
02 00
03 21 11 60

BLDG 6851 Project Cost Estimating

55

Project Report
07 00
03 21 11 60
07 50

Rebars 25M

1109.1265

Kg

0.97

1075.852705

Rebars 25M

1142.5675

Kg

0.97

1108.290475

Stirrup 15M

340.65232

Kg

0.97

330.4327504

Kg

0.97

Zone 3 (# of zones 2)
03
07
03
07

21 11 60
50
21 11 60
00

Zone 4 (# of zones 2)
03 21
07
03 21
07

11 60
50
11 60
00

03 21
07
03 21
07
03 21
07
03 21
07

11
50
11
00
11
00
11
00

Rebars 25M

724.555

Kg

0.97

702.81835

Stirrup 15M

329.9512

Kg

0.97

320.052664

Kg

0.97

Zone 9 (# of zones 2)
60
60
60
60

Rebars 25M

167.205

Kg

0.97

162.18885

Stirrup 15M

24.15183333

Kg

0.97

23.42727833

Rebars 10M

11.147

Kg

0.97

10.81259

Stirrup 10M

15.661535

Kg

0.97

15.19168895

Rebars 25M

668.82

Kg

0.97

648.7554

Stirrup 15M

178.352

Kg

0.97

173.00144

Kg

0.97

Zone 10 (# of zones 6)
03 21
07
03 21
07

11 60
50
11 60
00

03 21
07
03 21
07

11 60
00
11 60
00

Zone 14 (# of zones 1)

03 21 11 60

Rebars 15M

44.588

Kg

0.97

43.25036

Stirrup 15M

44.14212

Kg

0.97

42.8178564

133.764

Kg

0.97
0.97

129.75108

Zone 15 (# of zones 3)
Rebars 15M

BLDG 6851 Project Cost Estimating

56

Project Report
07 00
24 21 11 60
07 00

Stirrup 15M

131.5346

Kg

0.97

127.588562

Rebars 15M

66.882

Kg

0.97

64.87554

Stirrup 15M

47.56053333

Kg

0.97

46.13371733

Rebars 10M

11.147

Kg

0.97

10.81259

Rebars 15M

42772.11131

Kg

0.97

41488.94797

Rebars 25M

3812.274

Kg

0.97

3697.90578

Stirrup 10M

15.661535

Kg

0.97

15.19168895

Stirrup 15M

1096.344607

Kg

0.97

1063.454268

Rebars 10M

28295.43948

Kg

0.97

27446.57629

Rebars 15M

4482.255282

Kg

0.97

4347.787623

Rebars 15M

1606.11

Kg

0.97

1557.9267

Stirrup 10M@200

105.661

Kg

0.97

102.49117

3350.393219

Kg

0.97

3249.881423

1371.081

kg

0.97

1329.94857

Zone 16 (# of zones 2)
26 21
07
27 21
07
29 21
07
30 21
07
31 21
07
32 21
07
33 21
07

11
00
11
00
11
00
11
00
11
50
11
00
11
00

60
60
60
60
60
60
60

SLAB ON GRADE REINFORCEMENT


03 21 11 60
06 00
03 21 11 60
06 00
0321 11 60
06 00
03 21 11 60
06 00

ELEVATED SLABS ON GRADE


REINFORCEMNT
03 21 11 60
04 00

Rebars 15M
RAMP REINFORCEMENT

03 21 11 06
00

Rebars 10M

BLDG 6851 Project Cost Estimating

57

Project Report

Totall

717466.157
1

739655.8321

Table 47:
Summary
Package No.

Final
Sheet Per
1

FINAL SUMMARY COST SHEET PER PACKAGE No 2


REINFORCEMENT
CSI CODE
03 21
02
03 21
05
03 21
02
03 21
02
03 21
05
03 21
02

11
00
11
00
11
00
11
50
11
50
11
00

60
60
60
60
60
60

Weight
kg
12096.282
05
268799.66
29
107875.24
95
191401.24
53

Price per
kg

30 M

6725.88

0.97

angle

2658.8036

0.97

TOTAL

589557.1
234

Bar Size
10 M
15 M
20 M
25 M

0.97
0.97
0.97
0.97

Total
price $
11733.393
59
260735.67
3
104638.99
2
185659.20
79

Total Incld. O/P,


$

6524.1036

7176.51396

2579.0394
92
571870.4
097

12906.73295
286809.2403
115102.8912
204225.1287

2836.943441
629057.4506

CONCRETE VOLUME
CSI CODE
03 31 05 20
03 50
03 31 05 20
04 00
03 31 05 20
03 50
03 31 05 20
04Estimating
11
BLDG 6851 Project Cost

Total
price $
4733.8780
BEAMS
33.2856
142.22
32
60476.522
WALLS
407.77104
148.31
94
6508.1949
925595.48
slab+ droppanels
142.22
43
47
214.17026
32470.782
COLUMNS
151.612
91
84
58
7163.421
1023276.
TOTAL
852
669
1595147.
TOTAL BARE COST OF PACKAGE 2
078
Type

Volume
m3

Price per
m3

Total Incld. O/P,


$
5207.265835
66524.17524
1018155.033
35717.86112
1125604.335
1754661.786

Project Report

Table 48: Final Summary Sheet Per Package No. 2

FINAL SUMMARY COST SHEET PER PACKAGE No 3


CSI
CODE

MATERIAL
DESCRIPTION

CONCRETE OF
ROOF FOR
BUILDING A
CONCRETE OF
07330
ROOF FOR
0
BUILDING B
Reinforcement OF
07333
ROOF FOR
2
BUILDING A
REINFORCEMENT
BLDG 6851 Project
Cost Estimating
07333
OF ROOF FOR
2
BUILDING B
07330
0

QUANTITY

689.47
678.77
21099
22336

UNI
T

MATERIAL
PRICE PER
UNIT, $

142.22

142.22

KG

0.90

KG

0.90

TOTAL BARE COST OF PACKAGE


3

TOTAL COST, $

Total Incld.
O/P, $

98056.56

107862.216

96523.66

106176.026

18989.2

20888.12

20102.4

22112.64

2233671.82

2257039.00
2

59

Project Report

Table 49: Final Summary Sheet Per Package No. 3

03 31 13 35 04 11

FINAL SUMMARY SHEET FOR PROJECT


MATERIAL PRICE PER
MATERIAL DESCRIPTION
QUANTITY UNIT
UNIT, $
CONCRETE
Concrete footing(Piles)
3696.408
m
142.66
1085.12377
Concrete PC
m
149.16
5
Concrete toppings
155.24621
m
143.21
780.034468
Concrete Slab-on-grade
m
136.71
8
Elevated slabs
42.9043266
m
136.71
Concrete Ramp
471.582
m
148.08
CONCRETE FOR WALL
Concrete Foundation Wall
489.935425
m
156.08
Concrete Shear Wall
484.23449
148.08
Concrete Shear Wall
CONCRETE SLAB FOR COLUMN
Concrete Column
231.681
m
151.612

03 31 13 35 02 20

CONCRETE FOR SLAB


Concrete for slab

CSI CODE
03 31 13 35 03 50
03 31 13 35 02 00
03 31 13 35 02 00
03 31 13 35 02 20
03 31 13 35 02 20
03 31 13 35 04 00
03 31 13 35 04 00
03 31 13 35 04 00
03 31 13 35 04 00

BLDG 6851 Project Cost Estimating

7861.85494

142.22
60

TOTAL COST,
$

Total o&p
cost

527329.5653

606429.0001

161857.0623

186135.6216

22232.80973

25567.73119

106638.5122

122634.2891

5865.450489
69831.86256

6745.268063
80306.64194

76469.12113
71705.44328

87939.4893
82461.25977

35125.61977

40394.46274

1118113.01

1285829.961

Project Report

03 31 13 35 02 20

3
47.7056
15346.7102
4

Concerete for beam


TOTAL CONCRETE COST

142.22

6784.690432

7802.393997

2201953.147

2532246.119

REINFORCEMENT/Bar Size
03 21 11 60 02 00

#10 M

03 21 11 60 05 00

#15 M

03 21 11 60 02 00

#20 M

03 21 11 60 02 50

#25 M

03 21 11 60 05 50
03 21 11 60 02 00

#30 M
#angle
Total REINFORCEMENT COST

47851.8892
6
446884.414
9
145532.525
676389.028
6
52008.3067
2658.8036
1371324.96
8

kg

0.97

46416.33258

53378.78246

kg

0.97

433477.8825

498499.5649

kg

0.97

141166.5493

162341.5317

kg

0.97

656097.3578

754511.9614

kg
kg

0.97
0.97

50448.0575
2579.039492

58015.26612
2965.895416

1330185.219

1529713.002

Final Cost

3532138.366

A. Wastage 3.75%
REINFORCEMENT

49881.94572

B. Wastage 7.5% Concrete

165146.486

Profit (10%)

353213.8366

Tax (15%)

529820.7549

Insluation (1.9) %

67110.62896
Final Cost

Table 50: Final Summary Sheet For Project

BLDG 6851 Project Cost Estimating

61

4697312.018

4061959.12
1
57364.2375
7
189918.458
9
406195.912
1
609293.868
2
77177.2233
5401908.82
1

Project Report

BLDG 6851 Project Cost Estimating

62

Project Report

7. ABBREVIATIONS

CY------------------------------------ Cubic yard


mm----------------------------------- Millimeter
m-------------------------------------- Meter
m -------------------------------------Square meter
m------------------------------------- Cubic meter
Kg------------------------------------- Kilogram
Kg/m---------------------------------- Kilogram per meter
No------------------------------------- Number

BLDG 6851 Project Cost Estimating

63

Project Report

8. REFERENCES

canada wide reinforcement steel co ltd. (n.d.). Retrieved from


http://www.cwrebar.com/cgi-bin/cwrebarDisplay.cgi?proc=metric
canadian codes. (n.d.). Retrieved from
http://www.webcivil.com/readequal2L.aspx/
Moselhi, O. (1997). Cost Estimation in Project Management. In O. Moselhi.
Montreal.
Munns, A K and Bjermi, B F. (1996). The role of project management in achieving
project success. International Journal of Project Management , 81-87.
Pratt, D. J. (2011). Fundamentals of Construction Estimating. In D. J. Pratt,
Fundamentals of Construction Estimating (p. 482). New York.
PURPOSES AND TYPES OF REINFORCING STEEL. (n.d.). Retrieved from
http://www.tpub.com/steelworker2/76.htm
Rundell, R. (2006). 1-2-3 Revit: BIM and cost estimating. Building design, AIA,.

BLDG 6851 Project Cost Estimating

64

Project Report

BLDG 6851 Project Cost Estimating

65

Das könnte Ihnen auch gefallen