GreaterBaltimoreCommitteeTransportationSummit
May9,2014
Overview
BackgroundofMarylandsP3FrameworkandProcess
ExistingP3s:Seagirt MarineTerminalandI95TravelPlazas
PurpleLineP3
DevelopingMDsP3LegalandRegulatoryFramework
2010P3Law
(Chapters640and641of2010)
JointLegislativeandExecutiveCommissiononOversightofP3s(2011)
2013P3Law(Chapter5of2013)
(signedonApril9th;effectiveJuly1st )
ExecutiveOrderestablishingP3SubCabinet
(Summer2013)
MDOTRegulations:COMAR11.01.17
(Summer/Fall2013)
3
MarylandsP3Law:Definition
Methodfordeliveringpublicinfrastructureassetsusingalongterm,performance
basedagreementbetweenaReportingAgencyandaPrivateEntity.
Appropriaterisksandbenefitscanbeallocatedinacosteffectivemanner
betweenthecontractualpartners.
PrivateEntityperformsfunctionsnormallyundertakenbythegovernment,but
ReportingAgencyremainsultimatelyaccountableforthepublicinfrastructure
assetanditspublicfunction.
Statemayretainownershipinthepublicinfrastructureassetandtheprivate
entitymaybegivenadditionaldecisionmakingrightsindetermininghowthe
assetisfinanced,developed,constructed,operatedandmaintainedoverits
lifecycle.
Doesnotincludeanassetsaleorashorttermoperatingspacelease.
MarylandsP3Law:Details
Createspredictable,transparent,andstreamlinedapproach,incorporatingbest
practicesandlessonslearnedfromotherstates,whileaddressingtheneedsof
Marylanders
Allowsagenciestoconsiderunsolicitedproposalsforpotentialcompetitive
solicitations
Outlineskeyrequirementsforcompetitivesolicitationprocesses
ExemptsP3sfromstateprocurement(DivisionIIofStateProcurementArticle)
Requiresthatreportingagenciespromulgateregulationsforthedevelopment,
solicitation,evaluation,award,anddeliveryoffutureP3projects
RequiresthatBPWdesignateanypotentialP3,ensuringthatfutureP3projects
receivethehighestlevelofscrutinyBEFOREtheStateseeksproposalsfrompotential
partners
OutlineskeytermsandprovisionsthatshouldbepartofaP3Agreement
5
RegulatoryProcesstoAdvanceTransportationP3Concepts
Receiveinternallygenerated
P3concept
Receiveunsolicitedproposal
P3concept
Highlevelscreening
Initialscreeningofappropriateness,viability,andeffectivenessasaP3
Detailedlevelscreening
Morecomprehensivescreening,includingrelevantanalysesandduediligence
Presolicitationdevelopment
Completerelevanttasksrequiredforthedevelopmentofapresolicitationreport
Secretarysrecommendationtosubmitapresolicitationreport
6
ExistingP3s:SeagirtTerminal
KeyTerms
In2010,MPAenteredintoa50yearDBFOMwithPortsAmerica
ChesapeakeforredevelopmentofSeagirt.
$105millionprojecttoconstructdeepberthandcranescompletedin
2012,twoyearsaheadofschedule.
$140millionupfrontpayment,reinvestedinshovelready
transportationprojectsalongI95andtheChesapeakeBayBridge.
Annualpaymentof$3.2million,grownatinflationstartinginYr 5.
OngoingAchievements
2010
2013
ExistingP3s:I95TravelPlazas
In2012,MDTAenteredintoa35yearDBFOMwithAreasUSAfor
redevelopmentofthetwotravelplazasonI95.
AreasUSAiscurrentlyinvesting$56millionforreconstructionof
theMarylandHouseandChesapeakeHousetravelplazas.
AreasUSAwilloperateandmaintainthetravelplazasthrough
2047,whiletheMDTAretainsownershipandoversightofthe
plazas.
Statewillreceiveapproximately$400millioninestimatedrevenue
paymentsfromAreasUSAovera35yearperiod.
January2014MDHouseRibbonCutting
ChesapeakeHouseUnderConstruction
OperationsofbothtravelplazastransferredtoAreasUSAin
September2012.
P3projectwillsupport400constructionand575operationaljobs.
MarylandHousereopenedtothepublicinJanuary2014,
ChesapeakeHouseisscheduledtoreopeninSummer2014.
PurpleLineP3
Proposed16+milelightraillineextendingfromBethesdainMontgomeryCountytoNewCarrolltonin
PrinceGeorge'sCounty,enhancingconnectionsintheWashingtonDCmetroarea.
DeterminingP3PotentialforthePurpleLine
Preliminaryanalysesandindustryoutreachduring2011 2013,includingvalueformoneyanalysisin
2012.Conductseriesofinternalprojectdeliveryworkshopsinwinter2012/2013.
ReleaseofRequestforInformation(RFI)totheP3marketinApril2013;responsesreceivedMay8,2013
IndustryForumonMay15,2013
CompleteP3screeningprocessandanalysesinJuly2013
IssuepresolicitationreportforaDBFOMP3approachonAugust5,2013
SolicitationapproachapprovedbyBPWonNovember6,2013
10
KeyReasonsforUsingaDBFOMP3
Operationalfactors
ThePurpleLineisanaturalstandaloneassetandtheP3approachwillalsoincreasethe
likelihoodofconsistentlyexcellent,highlyresponsiveservice.
Risktransferefficiencies
P3willintegratevariousprojectelementsintoasingleagreementthatclearlyoutlines
theoptimalallocationofprojectriskbetweenthepublicandprivatepartners.
Wholelifecycleplanningandcostoptimization
P3willprovidegreaterincentivetomakeinvestmentdecisionsthatareoptimizedover
thelifeoftheasset.
Schedulediscipline
P3agreementstructurefocusedonassetavailabilitywillprovidestrongincentivesfor
theconcessionairetomaintainscheduledisciplineduringassetdelivery.
Enhancedopportunitiesforinnovation
P3willprovidetheprivatesectorwithopportunitiesandincentivestopropose
enhancementstotheassetdesignanddeliveryapproachthatcouldbenefitlongterm
operatingandmaintenanceperformance.
Potentialfinancialvalue
Duetotheoperationalbenefits,risktransferefficiencies,lifecycleplanning,scheduling
discipline,andinnovationopportunitiesoftheP3approach,thereispotentialforlong
termfinancialsavingsrelativetoatraditionalprojectdeliveryapproach.
11
KeyPurpleLineSolicitationMilestones
BoardofPublicWorksApprovesMDOT/MTA PurpleLineP3Proposal
November 6,2013
RequestforQualificationsIssued
November8,2013
StatementsofQualificationsSubmittedbyProposers
December11,2013
ShortlistofQualifiedProposersDetermined
January8,2014
DraftRequestforProposalsIssuedtoShortlistedProposers
January2014
Recommendationfor$900MillionFFGAforPurpleLine
March5, 2014
RecordofDecision
March19,2014
Summer2014
FinalProposalsDue
Fall2014
SelectedProposerAnnouncedandP3AgreementFinalized
Winter2015
FinalP3AgreementSubmittedtoComptroller,Treasurer,Budget
Committees,Dept.Legislative ServicesforReviewandComment
Winter2015
FinalP3AgreementRecommendedtoBPW
Winter2015
FinancialClose
Spring2015
12
ContactInformation
Foradditionalinformation:
JodieMisiak
AssistantDirector,InnovativeFinance
MarylandDepartmentofTransportation
(410)8651050