Beruflich Dokumente
Kultur Dokumente
Procedural Guideline:
Guideline
Overhead Design
CEM7097
1 CHECK that this printed document is the most recent version before you use it.
● The online version of this document is the current version.
19 OCTOBER 2007
ISSUE 3
CE-IN-CONFIDENCE
UNCONTROLLED COPY IF PRINTED
MANUAL – OVERHEAD DESIGN
CE-IN-CONFIDENCE CEM7097
CONTENTS PAGE
1 PURPOSE ................................................................................................................................. 3
2 KEY TERMS AND DEFINITIONS............................................................................................... 3
3 ACTIONS AND RESPONSIBILITIES .......................................................................................... 4
3.1 GENERAL...............................................................................................................................................4
3.2 RESPONSIBILITIES................................................................................................................................4
3.3 METHODS OF SUPPLY ..........................................................................................................................5
3.4 METHODS OF CONSTRUCTION AND MATERIALS ................................................................................6
3.5 OVERHEAD DESIGN AND CONSTRUCTION REQUIREMENTS..............................................................7
ATTACHMENT A – LOAD TYPE AND VALUES........................................................................................30
ATTACHMENT B - LOAD DENSITY VALUES FOR ASSESSMENT OF MAXIMUM DEMAND ..................32
ATTACHMENT C - CONDUCTOR INFORMATION ...................................................................................33
4 REFERENCES.........................................................................................................................35
5 REVISIONS .............................................................................................................................37
CE-IN-CONFIDENCE CEM7097
1 PURPOSE
This document outlines the basic requirements for the design of all overhead distribution power lines within
the franchise area covered by Country Energy so as to ensure a standardised network.
Country Energy’s objective is to provide a safe, reliable, efficient and economical electricity distribution
system. To achieve this objective, the overhead network shall be designed in accordance with the
requirements of all Country Energy policy documents, including this document, and all the design and
construction standards, specifications, Acts and Regulations referenced herein or issued by Country Energy.
The design process may introduce risk to Country Energy unless the process is controlled and due
consideration given to OHS issues during the design phase. Design control seeks to eliminate risks
emanating from the design process through the implementation of procedures that identify and account for
risk in design activities such as the construction and use of plant, equipment, facilities and processes.
These design requirements apply to new works associated with customer connections (i.e. Contestable
Works) and augmentation or refurbishment required by the Network owner.
For information relating to subtransmission lines requirements, refer to Country Energy’s Subtransmission
Line Projects Group. A specific Design Information Package (DIP) will be provided for each subtransmission
project.
CE-IN-CONFIDENCE CEM7097
Detailed design of electricity reticulation systems depends on assessed maximum demands, building and
street layouts, street lighting requirements and other local factors. The design information and parameters
specified in this Network Standard provide for minimum acceptable standards. Any deviations from this
specification must be submitted to Country Energy’s Planning and Customer Connection Manager for the
region in which the project is proposed for approval before they are implemented.
Where new developments take place in overhead reticulated areas, Country Energy will determine the extent
of undergrounding of existing overhead mains that may be necessary. For new subdivisions, dedicated
roadway sites for future substations and cable easements for future use may also be required by Country
Energy. For underground supply requirements refer to Country Energy document CEM7098 – Underground
Design.
Street lighting design may form part of the low voltage system design in new developments and must conform
to the requirements of both the street lighting customer and Country Energy. Approval of the street lighting
customer for the applicable street lighting charges must be obtained first before construction work
commences. Refer also to Country Energy document CEM7107 – Distribution Overhead Mains – Lighting.
This document should be read in conjunction with the Electrical Standards and Network Standards listed in
Section 4 – References.
3.2 Responsibilities
During the course of supply negotiations the ASP shall provide all information to allow Country Energy to
determine the most appropriate method of supply (as described in Clause 3.3). Accredited Designers should
be aware of and advise on the possibility of any demand management opportunities and options that may be
available when considering new or additional load application. Country Energy’s relevant Regional Planning
and Customer Connection Manager will prepare and provide design information sufficient to enable design
and construction drawings to be completed.
Overhead designs must be prepared by an Accredited Designer. The ASP is responsible for the design, supply
of some materials and construction of the electricity reticulation system (including substations) to supply the
new development as detailed in Country Energy’s design information. The ASP is also responsible for
providing local authorities and the RTA (as appropriate) with copies of the proposed construction plans at
least 40 days before work is to commence and must comply with any special requirements of these
authorities. These special requirements, along with any services that are in close proximity of the new
development, must be indicated on the construction plan. In addition, where other authorities such as the
State Rail Authority or Waterways Authority have jurisdiction over land or water impacted by development,
special additional conditions may apply. As these may vary from time to time, current applicable conditions
must be checked at the time of the development/construction.
Accredited Designers should always be mindful of the need for safe work practices and the minimisation of
operational interference between power systems and cabled telecommunication systems.
CE-IN-CONFIDENCE CEM7097
The ASP is also required to carry out an environmental review at the design stage of the project in accordance
with the Environmental Planning and Assessment Act 1979 (EP & A Act). It is a requirement that the ASP
considers all Environmental Planning Instruments (EPIs). Applicable EPIs in most cases will include Local
Environment Plans (LEPs), Regional Environmental Plans (REPs) and State Environmental Planning Policies
(SEPPs). An Environmental Impact Assessment (EIA), including bushfire protection measures as outlined in
the Planning for Bushfire Protection 2001 guidelines, must consider not only the construction itself but also
the ongoing operation and maintenance of the assets.
Where easements are required, it will be the responsibility of the ASP to arrange for such easements in favour
of Country Energy and in accordance with the relevant information contained in this or other documents
issued by Country Energy.
Accredited Designers (Level 3 ASP’s) are responsible for arranging where necessary the identification and/or
survey and the pegging of boundaries so as to allow plant and equipment to be correctly installed and to
simplify auditing on completion of the installation.
Level 1 and/or Level 2 ASP’s are responsible for “Non Electrical Work” such as tree clearing, excavation,
restoration, landscaping and any construction that supports the electrical work.
It is important to note that it is the responsibility of an ASP to report any Network component associated with
or being considered in a project that may be in an unsafe or dangerous condition to Country Energy’s local
Area Co-ordinator for assessment and remedial action.
Certain non-electrical work, including work within close working distance of the existing electrical network,
must be undertaken in accordance with Country Energy’s Electrical Safety Rules subject to specific
accreditation requirements.
The customer (end user) is responsible for supplying and installing the portion of service mains from the
street alignment to the customer’s terminals in accordance with the NSW Service and Installation Rules.
The decision as to the most appropriate method of supply will be made by Country Energy’s relevant Regional
Planning and Customer Connection Manager as part of the supply negotiation phase. This initial step in the
process of establishing an electricity supply involves exchange of details pertaining to the development
between the developer, customer and Country Energy. The options for electricity supply are:
3.3.1 Service from the existing low voltage reticulation system – nominally 400/230V
This may provide for the connection of services (overhead or underground) rated up to 400 amps. Overhead
services should be restricted to a rating of 275A or 4-core 150mm2 LVABC.
This method of supply is limited by the available capacity of the existing reticulation system and the
associated distribution substations.
CE-IN-CONFIDENCE CEM7097
A list of all distribution substation types and their approximate ratings is provided in Clause 3.5.10.
Where supply is taken direct from a customer’s substation, the customer’s main switchboard shall, wherever
practicable, be located immediately adjacent to the substation. If the customer’s main switchboard cannot be
located immediately adjacent to the substation, the proposed location must be approved by Country Energy’s
local Customer Service Planning Section before the design proceeds.
Urban network is defined as that part of a network that is not a rural network.
In urban areas where overhead construction is specified for high voltage reticulation the small delta
construction shall be used and for low voltage reticulation, low voltage aerial bundled cables shall be used as
the standard construction. In rural areas Country Energy shall stipulate the type of construction to be used
and material types as may be appropriate in identified bushfire-prone areas.
Where overhead construction is specified for high voltage reticulation (eg rural networks) the construction
shall be either of the open wire construction type or covered conductor type. Country Energy shall be the
determining authority as to which type is the most appropriate and may also stipulate material types to be
used in identified bushfire-prone areas.
In general, it is expected that high voltage lines in rural areas shall utilise the standard delta configuration.
The general guidelines for the form of construction for each project shall be determined by Country Energy’s
relevant Regional Planning and Customer Connection Manager and shall be in accordance with the prevailing
19 October 2007 – Issue 3
Approved By: Group Manager Standards and Demand Management
Page 6 of 37
CE-IN-CONFIDENCE UNCONTROLLED COPY IF PRINTED
MANUAL – OVERHEAD DESIGN
CE-IN-CONFIDENCE CEM7097
policy of the time. The final interpretation and decision as to the type of construction to be used shall be as
stated in Country Energy’s design information package issued for the project.
It is NOT anticipated that flat construction be used for high voltage lines except in a dual circuit mid-pole
situation.
The use of high voltage raiser brackets to retrofit existing low voltage overhead lines is NOT a standard
construction.
The gas switch is the standard switch to be used on the Country Energy distribution network.
Where an ASP has reason to prepare a design that varies with the requirements stipulated in the Country
Energy Construction Manual, the designer must seek permission from the Manager Planning and Customer
Connection for the region in which the project is proposed before proceeding with the variation.
Extension of the low voltage mains is by overhead reticulation unless it is an extension off an existing
underground network. Country Energy may agree to the undergrounding of the low voltage reticulation if
requested by the ASP or if it is a stipulation of subdivision approval by the local council.
3.4.1 Materials
Materials to be used for all overhead construction works are to be new and equivalent or superior in terms of
total lifetime performance as those issued and used by Country Energy and assessed for compliance with the
appropriate Country Energy specification. Where materials are intended to be supplied that are not sourced
directly from Country Energy or do not meet Country Energy’s specifications and are not included in Country
Energy’s Approved Materials Inventory list; these shall be indicated for assessment during the design-
checking phase, i.e. the design shall be assessed for compliance with this standard on the basis that
materials and equipment to be used are of equivalence to that which would be used and supplied by Country
Energy.
Where materials are sourced from other than Country Energy, evidence of compliance with Country Energy’s
specifications or manufacturer’s certificate of equivalence to that supplied to Country Energy shall be
required.
Designers intending to use alternate materials are advised to discuss this situation with Country Energy’s
Standards Group for evaluation of the alternatives proposed before making such decisions. There will be a
charge for these services based on the fees established by the Independent Pricing and Regulatory Tribunal.
CE-IN-CONFIDENCE CEM7097
“It is a requirement that all proposed work must have an appropriate impact assessment carried out in
accordance with the Environmental Planning and Assessment Act 1979 (EPA Act) and in accordance with
Country Energy Procedural Guideline CEPG2016 – Environmental Impact Assessment.
For part 5 assessments under the EPA Act refer to Country Energy documents CEPG2295 Environmental
Procedures Supplementary Notes, CEFD6024 – Environmental Impact Assessment form and CEFD6470
Consultant checklist for preparation of REF for further details”.
The clearing of vegetation to enable the construction of a new power line should be carried out in accordance
with document CEPG2010 – Vegetation Clearing Guidelines for New Power Lines.
Should it be necessary for vegetation to be removed near existing overhead power lines then this work should
be carried out in accordance with document CEPG2021 – Removing Vegetation Near Overhead Powerlines.
3.5.3 Easements
Where an overhead power line, (either existing or new), other than a dedicated connection asset on the
connecting customer’s property, are not or cannot be constructed within a public road reserve, then an
easement will generally be required. Such easements shall be provided in favour of Country Energy.
Easement widths required will generally be in accordance with the Industry Guidelines (ISSC20) and are
reproduced in the Country Energy document CEPG8046 – Easement Requirements.
Where easements are required in association with new customer connections that are funded by the
customer, all costs associated with obtaining these easements shall be borne by the customer, some of those
costs being:
• Survey costs
• Consultation costs (eg Crown Land)
• Land valuation expenses
• Compensation payments
• Legal expenses, etc.
Where easements are required in association with Network-funded projects (eg augmentation of shared
assets) the costs associated with obtaining those easements shall be borne by the Network owner.
Where projects involve both shared and dedicated assets, the costs shall be apportioned between the
customer and Country Energy Networks, based on:
• New versus existing assets
• Works initiated by ‘the proponent’
CE-IN-CONFIDENCE CEM7097
Once constructed, Network assets are generally transferred to the Networks owner and need to be added to
various asset databases, maps, plans, GIS etc.
For these reasons, it is essential that certain minimum information is included on the construction plans with
a reasonable level of standard symbology to allow:
• An ASP to construct those assets
• Network personnel to update their asset records system
All design and construction plans shall use the standard symbols and be in the format nominated in draft
document CEM7001 – Construction Drawing Standard Symbology. All network project design and
construction plans are to be identified with a unique project number. Reference is made to previous Clause
3.2 as to the responsibilities of an ASP in the provision of the necessary information on the construction plan
as well as providing information to the appropriate authorities.
On completion of the construction of a new line, the following ‘as built’ information is to be recorded/updated
on the construction plan:
• As constructed line/pole schedule
• Final as constructed route plan
• Final height of the lowest conductor above ground at the nominated design maximum operating
temperature along the route of the line
• Conductor stringing tensions and tables
Alternatively, a separate design information sheet, or a copy of the design information as provided
from an approved software package displaying the same unique project number as the project
drawing, can be provided. This design information should include conductor stringing details such
as the design tension, initial sags, the final sags and the minimum ground clearance at the
nominated design operating temperature. Also required is the conductor final tension at 5°C with no
wind in addition to the conductor tension under the wind/ice loading condition if applicable to the
installation location.
• Line profile for rural extensions, where terrain profile varies by >5% at any point in a span and the
ruling span exceeds 100 metres, or terrain profile is >10% in addition to the provision of property
schedules. Alternatively, a designer may opt to retain a separate profile that can be produced if and
as required by Country Energy for audit purposes. Recommended scale for route profiles are 1:2500
horizontal and 1:250 vertical.
• Pole foundation details if they vary from the minimum prescribed in Clause 3.5.9.1 of this document.
• Other assets attached to Country Energy’s poles.
CE-IN-CONFIDENCE CEM7097
The demand for an individual development shall be assessed in accordance with Australian Standard
Publication AS3000, based on appropriate diversity factors being applied to a submitted list of maximum
demands for all items of equipment. These factors should be used in conjunction with discussions with the
ASP to ensure there are no mitigating circumstances that would negate or reduce their use.
Where either actual surveyed load data for upgrade work or assessed maximum demands are not provided
for new designs, then recommended After Diversity Maximum Demands (ADMD’s) may be used.
Recommended ADMD’s in accordance with the requirements of Country Energy’s document CEPG8003 –
Subtransmission and Distribution Network Planning Criteria and Guidelines are provided in Attachment A.
Where the ADMD in conjunction with the utilisation factor as provided in Attachment A is used to assess the
transformer capacity required for a project, then a common sense/realistic approach should be adopted.
There will be occasions, mainly in rural situations, where it may be necessary to differentiate between the
various listed ADMD’s to suit a particular project. One project may, due to the type of housing, be assessed at
7.0kVA/dwelling whereas another project may be assessed at 4.0kVA/dwelling for sizing transformers.
In the case of industrial, commercial and multi occupant developments, if a full list of connected loads is not
initially available, Country Energy will nominate a load density value in VA per square metre for floor area used
as provided in Attachment B.
It is also essential that the assessed maximum demand appropriately incorporates any definitive plans that
the customer has for expanding or augmenting the development in the foreseeable future.
The following design criteria for the initial electrical loading on low voltage distributors must be satisfied:
• The designed maximum load on any LV distributor must not exceed 75% of the distributor’s nominal
rating, unless otherwise nominated by Country Energy. This provides a reasonable margin for load
growth and paralleling requirements. Distributors are nominally rated in accordance with the
ambient temperature, the temperature rating of the style of construction and type of conductor and
associated cross-sectional area of materials used.
• The load to be connected to a distribution centre must be balanced across the LV distributors and
their respective phases, unless agreed otherwise.
The ultimate voltage level to be maintained at the Point of Supply should be not less than 226 volts and not
greater than 253 volts, in accordance with Country Energy’s documents CEPG8003 – Subtransmission and
Distribution Network Planning Criteria and Guidelines and CEK8026 – Electricity Supply Standard.
The designed maximum voltage drop, as determined by “LVDROP” in a low voltage distributor must not
exceed 9V at the extremities. “LVDROP” is a design package used by Country Energy to assess the affect of
new developments connecting to its LV network and is based on established engineering principles as outline
in Section 4 of publication AS/NZS 3008.1.1.
The voltage drop in the service mains must not exceed 1% at full load.
The maximum three phase volt drop constants for distributor and service must be calculated and supplied
with the design details.
19 October 2007 – Issue 3
Approved By: Group Manager Standards and Demand Management
Page 10 of 37
CE-IN-CONFIDENCE UNCONTROLLED COPY IF PRINTED
MANUAL – OVERHEAD DESIGN
CE-IN-CONFIDENCE CEM7097
Voltage drops shall be determined using ‘LVDROP” software (Version 5.48 or later) and the load information,
provided in Attachment A & B and conductor impedance values as provided in Attachment C. Voltage drops
submitted with the design will be checked by Country Energy using the same methodology and information.
Alternate supply to LV distributors must be provided from adjacent distribution centres wherever practicable.
Each distributor will normally require two alternate points of supply to allow low voltage paralleling under
maximum demand conditions.
Every opportunity must be taken to establish loop feeds where loop roadways exist (i.e. interconnection
between distributors from the same distribution centre or between different branches of the same
distributor). Extension of distributors beyond that necessary to provide a paralleling path will not normally be
required unless nominated otherwise by Country Energy’s relevant Regional Planning and Customer
Connection Manager.
High Voltage
During the course of supply negotiations Country Energy’s relevant Regional Planning and Customer
Connection Manager will determine the minimum level of high voltage reliability required and provide this
information as part of its design information. In doing so, Country Energy will take into account the level of
reliability of the existing network, type of existing construction (i.e. overhead or underground), permissible
number of ‘Tee off connections’ allowed, permissible number of substations on a radial supply (both on a
temporary and permanent basis), future load growth and any other network requirements. All costs
associated with levels of reliability in excess Country Energy requirements shall be met by the customer.
The installation and connection of all service mains shall only be carried out by suitably accredited and
authorised Level 2 Service Providers in accordance with the NSW Service and Installation Rules.
In urban areas, under no conditions are new service mains to be erected so as to cross over the boundary of
any property other than that property for which the service is intended.
Standard overhead services acceptable for connection to Country Energy’s LV network are those provided in
Table 3.5.7.3.
CE-IN-CONFIDENCE CEM7097
Where the clearances stipulated in the following Table 3.5.6.6 and those stipulated in documents
CEM7106.25, CEM7106.26 and CEM7106.27 exceed those provided in publication ENA C(b)1-2006 then the
values stipulated by Country Energy shall take precedence.
The maximum conductor operating temperature that apply to the design clearances shown in Table 3.5.6.6
are provided in Clause 3.5.6.7.
Insulated conductor
without earthed screen,
bare conductor or
covered conductor:
Table 3.5.6.6 – Clearance from Ground for Overhead Lines other than Insulated Service Lines
Notes:
1 For the purpose of this clause, the term ‘ground’ includes any unroofed elevated area accessible to
plant or vehicles.
2 Ground clearance over the carriageway of road includes a distance of up to 4 metres on either side
of formed surface.
3 Where the usage of land is such that vehicles of unusual height are likely to pass under an overhead
line, the clearances given in this clause may need to be increased.
4 In special circumstances Country Energy’s relevant Regional Planning and Customer Connection
Manager may approve that the design ground clearance be reduced to that provided in ENA C(b)1-
2006.
CE-IN-CONFIDENCE CEM7097
Design
Maximum
Nominal Voltage Conductor Type Situation/Location
Operating
Temperature
Low Voltage All conductors All locations 65° C
11kV, 22kV & 33kV SC/GZ Where permitted 50° C
Minor Rural distribution
ACSR or AAAC 65° C
backbone lines
11kV, 22kV & 33kV
Town mains and Major rural
AAAC 75° C
distribution backbone lines
Table 3.5.6.7
The general principles for the use of bare overhead conductors on Country Energy’s Distribution networks are:
a Low voltage – restricted usage only, i.e. LVABC should be used wherever possible. Approval required
from Country Energy’s relevant Regional Planning and Customer Connection Manager before
installation of bare conductor.
Low voltage spreaders are to be attached to all three or four wire bare LV approved installations
where:
• The span is less than 45 metres and
• is adjacent to overhanging trees and/or
• will be in line with trees that require regular lopping.
• conductor clashing due to stringing terrain is possible.
• The span is greater than 45 metres (one spreader mid span for up to 90 metre spans)
• The span is greater than 90 metres (two spreaders, one at each third of the span)
Construction plans are to show the number and location of LV spreaders that are to be installed in
the project.
b 11kV, 22kV and 33kV – standard bare conductors should be used except in the following
circumstances:
• where the area is identified as bushfire prone in accordance with Country Energy document
CEK8022 – Network Bush Fire Risk Management Plan OR
• where substantial tree cover does or will exist OR
• where proximity of trees will or do present a problem OR
CE-IN-CONFIDENCE CEM7097
• where proposed ongoing tree trimming requirements will be cost and/or environmentally
prohibitive OR
• where there are restrictions on the removal/trimming of trees due to heritage listing or
trees being of significant value to the community OR
• where approved projects dictate that alternative arrangements are necessary
AND
• the use of alternative conductors is the most economical and environmentally acceptable
solution after all other alternatives have been exhausted.
Stranding/
Country Energy Country Energy
Wire Diameter/ Code name
Catalogue No Specification No.
Conductor type
Table 3.5.7.1
* Note: Installation of 3/2.75 SC/GZ, galvanised steel conductor is not generally encouraged and will require
the approval of the relevant Regional Planning and Customer Connection Manager prior to construction. The
installation of 3/2.75 SC/GZ will NOT be permitted within 50km of the coastline, or tidal waterways, or within
a 10km radius of an existing or planned zone substation in accordance with Country Energy document
CEK8003 – Subtransmission and Distribution Network Planning Criteria and Guidelines.
Country Energy
Description CE Specification No.
Catalogue No
600460 19/2.00 SC/GZ CES5104.43
600490 19/2.75 SC/GZ CES5104.45
Table 3.5.7.2
LVABC is the standard overhead cable to be used throughout the Country Energy LV networks.
CE-IN-CONFIDENCE CEM7097
Country Energy
Description CE Specification No.
Catalogue No
0.6/1kV 2-Core 25mm2 XLPE
445680 CES5102.05
Stranded Aluminium LVABC
0.6/1kV 4-Core 25mm2 XLPE
445710 CES5102.07
Stranded Aluminium LVABC
0.6/1kV 2-Core 95mm2 XLPE
447330 CES5102.21
Stranded Aluminium LVABC
0.6/1kV 4-Core 95mm2 XLPE
447420 CES5102.23
Stranded Aluminium LVABC
0.6/1kV 4-Core 150mm2 XLPE
447360 CES5102.31
Stranded Aluminium LVABC
Table 3.5.7.3
Country Energy
Description CE Specification No.
Catalogue No
11kV 3-Core 50mm2 stranded
Aluminium (7/5.00 AAAC) XLPE
447300 CES5102.43
insulated, non-metallic screened,
HDPE sheathed
11kV 3-Core 150mm2 stranded
Aluminium (19/3.65 AAAC) XLPE
447310 CES5102.47
insulated, non-metallic screened,
HDPE sheathed
Table 3.5.7.4
CE-IN-CONFIDENCE CEM7097
Table 3.5.7.5
High Voltage CCT is an insulated unscreened conductor and does not require an earthing system to maintain
its integrity. However, the system requires Current Limiting Arcing Horn & Discharge Connector (CLAH/DC) to
divert surge energy, resulting from lightning strikes, to earth.
The CLAH/DC units are to be installed at intervals of not more than 400 metres giving a protection zone of
200 metres either side of the unit installation. Surge diverters are to be provided on substations and at
underground to overhead interfaces.
CE-IN-CONFIDENCE CEM7097
For overhead line design it is usual to use a tension at a reference temperature with no transverse wind for
design purposes. This reference tension is the long term average tension in the conductor/cable and is the
recommended design tension listed in the following tables. The reference temperature normally used
throughout Australia is 15°C.
When calculating maximum sags for new conductors, allowances shall be made for conductor creep and for
minor errors in construction, by allowing for an extra 5 or 10˚C in conductor tension calculations. For
example, if a conductor is to be strung at 6,000 N at 15˚C, then the final design should be based on
assuming conductor tension is 6,000 N at 5˚C for aluminium conductors and 10°C for steel conductors. This
additional creep allowance does not have to be applied to existing conductors which are being diverted or
reconstructed.
In the initial design process, unless indicated otherwise in the design brief, or the actual temperatures in
accordance with the definitions provided in ENA C(b)1 – 2006 are available, the following conditions may be
used.
• For uplift conditions in Coastal and Western regions – 5˚C and in Tablelands and Ranges – 10˚C.
• The serviceability limit states for sustained load conditions in South, Mid and North Coastal regions
15˚C and Far South Coastal and other regions 10˚C.
Unless otherwise indicated in the design brief, the minimum operating temperature shall be taken as 5˚C.
The maximum operating temperature shall be as per Clause 3.5.6.7 of this document. For inter-circuit
clearances, the upper circuit shall be assumed to be at maximum operating temperature while the lower
circuit is at minimum operating temperature. When this requirement imposes the need for increased pole
heights or reduced span lengths, then the design shall be discussed with Country Energy’s representative.
Country Energy’s representative may under some conditions permit the design to be based on the assumption
that the lower circuit will be operating at the sustained load condition temperature. The need for pole
changes would then be reviewed. Unless otherwise indicated in the design brief, for blowout calculations, the
conductor is assumed to be at 50˚C and under wind loads specified in ENA C(b)1-2006.
For overhead lines constructed along streets in urban areas, span lengths are normally restricted to less than
100 metres for HV only and less than 50 metres for dual circuit HV and LV or LV only. In these cases, high
tensions provide little or no additional benefits. For urban areas, the recommended design tensions for
Country Energy’s overhead distribution networks are provided in Table 3.5.8.1, for which stringing tables are
included in the Overhead Construction Manual.
CE-IN-CONFIDENCE CEM7097
LV ABC
4% 4% 4% 7%
Refer Note 1
Table 3.5.8.1
Note 1:
General rules for installation of Low Voltage Aerial Bundled Cable (LVABC) as listed in Clause 3.5.7.3 are:
• In span tension joints are not permitted for new installations.
• Maximum everyday final tensions shall not exceed the values indicated in Australia/New Zealand
Standard AS/NZS3560.1:2000 LESS 2.5% and are as follows:
For lines constructed in non-urban or rural areas, the base case horizontal design tensions should not exceed
those permitted in ENA C(b)1-2006. For example, where a base case horizontal tension of 15% of CBL is
permitted for AAAC/1120 conductor, lines shall be designed to be erected at no more than 15% plus the
appropriate incremental increase that may be allowed for static stress and dynamic stress considerations.
CE-IN-CONFIDENCE CEM7097
For rural areas, the recommended maximum design tensions for Country Energy’s overhead distribution
networks are provided in Table 3.5.8.2. In regions where overhead lines may be subject to snow/ice loading,
special conditions as described in ENA C(b)1-200 Clause 3.4.2 shall apply.
Table 3.5.8.2
3.5.9 Poles
Overhead power poles and their foundations should be designed in accordance with publication ENA C(b)1-
2006, taking into consideration the following requirements:
Country Energy has a preference for not concreting pole footings. Alternatives to be considered are:
• Use a heavier pole (kN strength rating) to increase the circumference and soil-bearing area
• Increase setting depth
• Utilise specified backfill such as ‘crusher dust’.
Where pole foundations must be concreted, then the concrete is to stop 450mm below ground line to
facilitate future pole inspections.
Where pole stays are required, then the following should be taken into account:
Ground stays are generally preferred to overhead stays due to cost and ongoing maintenance of additional
stay pole.
Where access permits, ground stays are generally preferred to sidewalk stays.
CE-IN-CONFIDENCE CEM7097
Ground stays should be avoided in stock (e.g. cattle and horse) paddocks due to the fact that stock rubbing
against stay wire can cause system operation problems. When alternate locations are not possible a stay
guard rail shall be used as shown in Country Energy’s Overhead Construction Manual drawing, CEM7103.16.
In urban areas, line routes should be selected so as to negate or reduce the need for road crossing (service)
poles and new or replacement poles should have a clearance of 1 metre from face of kerb to face of pole,
wherever practical. Poles for low voltage construction should generally be positioned every second property
boundary so as to eliminate service encroachments on neighbouring properties. Footpath allocations may
also vary between Local Government areas. Some poles (eg streetlight poles, road crossing poles etc) will
ideally be placed near the property alignment.
Elsewhere, roadside poles should have setbacks as outlined in the ‘Pole Setback Zones’, Section B6 of
AS1158, Part 1.3; 1997 ‘Vehicular Traffic (Category V) Lighting – Guide to Design, Installation, Operation and
Maintenance’.
Poles in rural areas should not be installed too close to fences. Apart from the electrical hazard arising from
step and touch potentials, pole and line inspectors require an area around poles to allow for routine
inspection. A minimum separation of 1.5m between fence and pole is recommended.
CE-IN-CONFIDENCE CEM7097
b Concrete Poles – Concrete poles may be used in “special” or “frequented” locations where common
multiple earth neutral (CMEN) earthing requirements can be achieved. All concrete poles in these
locations must be bonded to the LV neutral conductor or to a special CMEN conductor to ensure that
they are touch safe. Concrete poles are NOT to be used in these locations where the separately
earthed system is used as they will not meet touch potential safety requirements. Concrete poles
can be used in “remote” locations, where the requirement for positive protection operation can be
me, regardless of the method of earthing. Refer to document ENA C(b)1-2006 for definition of
“locations”.
For specification details for Pre-stressed Concrete Poles, refer to Section CEM7102.05, and for Spun
concrete Poles, refer to Section CEM7102.06 of the Overhead Construction Manual.
Sections of the South Western Region of Country Energy have established HV feeders where the
installation of concrete poles is considered standard construction. A list of zone substation locations
from which these HV feeders emanate are provided as follows:
• Narrandera • Hanwood
• Kywong • Tharbogang
• Yanco • Beelbangera
• Leeton • Griffith
• Coleambally • Warrawidgee
• Darlington Point • Carathool
• Ringwood Rd • Hay
• Egansford • Hillston
• Whitton • Ivanhoe
• Murrami • Wigelli
• Yenda • Cudgel
For further information on these locations contact the Manager Planning and Customer Connections
– South Western Region at Country Energy Albury office.
c Steel Poles – steel poles may be used in “remote” locations where the requirement for positive
primary protection operation can be met, regardless of the method of earthing. Refer to document
ENA C(b) 1-2006 for definition of “locations”.
Steel poles shall not be used in seaside or estuarine areas known to be subject to salt pollution or in
soils which are known to be chemically aggressive.
For specification details of Steel Poles, refer to Section CEM7102.08 of the Overhead Construction
Manual.
When considering the use of conductive poles, the designer shall ensure that the insulation co-ordination of
the structure is compatible with the existing network.
CE-IN-CONFIDENCE CEM7097
Supplementary fittings, in addition to the normal standard fittings, will be required as indicated in the
following situations.
• Aerial inspection markers in accordance with EC guide for poles either side of any line crossing.
• Aircraft warning markers fitted to overhead lines in proximity of authorised landing sites and marking
of overhead cable for low level flying in accordance with Australian Standard AS 3891.
• Sighters/bird diverters fitted to overhead conductors in the vicinity of known wildlife corridors to
improve visibility of conductors.
• LV spacers to each span of bare overhead low voltage conductor in accordance with Clause 3.5.7.1.
Where a substation requires that a 200kVA or larger transformer be installed and the substation is shared by
two or more customers, then Maximum Demand Indicators (MDIs) are to be installed on the structure.
Distribution Transformer Fusing shall be in accordance with Country Energy’s document CEPG5099 –
Distribution Transformer Fusing.
Where a pole mounted substation is to be upgraded and the new transformer is of similar weight and physical
size to that which is to be replaced and the pole has been inspected and found to be in a sound condition by
Country Energy, then the substation pole will not need to be replaced.
Only standard size transformers, listed as follows, are acceptable for connection to the network system.
CE-IN-CONFIDENCE CEM7097
Standard Pole-Mounted Distribution Transformer – Refer to Country Energy’s Standard Construction Manual, Sections 7104-22 and 7104-23 for
further details.
CE-IN-CONFIDENCE CEM7097
3.5.11 Earthing
The design and construction of all earthing systems forming part of the works to be vested in Country Energy
shall comply with Country Energy’s Construction Standard for Distribution System Earthing Document –
CEM7109.
All substations are required to have an accompanying electrode type earthing system suitable for its purpose.
The earthing electrodes for pole-mounted substations are generally installed in a dedicated roadway or
easement surrounding the pole base (if shared transformer on private property).
Special earthing designs and segregation limits may be required in situations relating to swimming pools,
communication centres, petrol and liquid fuel centres etc. For the principles of earthing, reference can be
made to the Electricity Council of NSW document, EC5 ‘Guide to Protective Earthing’ and attention is drawn to
the Energy Networks Association of Australia/Telstra document ‘Earth Mat Rise Code’.
Where concrete poles are to be installed in “special” or “frequented” locations, a common multiple earth
neutral (CMEN) system is required and ALL the concrete poles must be bonded to the LV neutral conductor or
to a special CMEN conductor to ensure that they are touch safe.
Conductive poles are NOT to be installed in “special” or “frequented” locations where the separately earthed
system is used as they will not meet touch potential safety requirements.
In locations where staff may be required to operate pole mounted equipment, the earthing should comply with
the ENA document C(b)1-2006 clause 11.1.4, to the levels recommended for “Frequented” Locations.
a 11kV/22kV Feeders
Reclosing will be provided at the source substation and initiated by all protection other than sensitive earth
fault. Automatic reclose timing and automatic reclose attempts shall be in accordance with Country Energy
document – CEK8002.
Back up protection will be provided by one of several options. This protection will improve limitations in the
design of the feeder configuration as follows:
19 October 2007 – Issue 3
Approved By: Group Manager Standards and Demand Management
Page 24 of 37
CE-IN-CONFIDENCE UNCONTROLLED COPY IF PRINTED
MANUAL – OVERHEAD DESIGN
CE-IN-CONFIDENCE CEM7097
• A minimum conductor size will be nominated by Country Energy for a particular feeder depending on
fault levels, protective clearing times and load capacity. This also applies to any underground cable
connected and to the cable sheath.
• A maximum feeder impedance will be specified by Country Energy to ensure minimum fault levels at
feeder extremities are adequately detected by protection including back-up protection. All designs
must account for these aspects and will be checked for compliance.
b Line Reclosers
Pole-mounted line reclosers will be used in overhead distribution feeders where nominated by Country Energy.
Line reclosers will be of a type complying with Country Energy’s specification and will provide protection,
reclosing and remote control (SCADA) facilities.
Line Sectionalisers and line fuses may occasionally be used on 11kV and 22kV feeders but their use is kept
to a minimum.
All 400/230V overhead bare conductor or aerial bundled conductor (ABC) networks are to be protected by
current limiting HRC fuses at the distribution substation.
Fuse types and application are to be in accordance with Country Energy’s Fuse Standard document –
CEPG5099. The fuse size to be used will be nominated by Country Energy’s Planning and Customer
Connection Manager for the region in which the installation is to be carried out and in accordance with the
above documents.
The maximum rating fuse to be used on an overhead low voltage network or distributor is 400A and all fuses
shall be fast characteristic as defined in CEPG5099. Small rating distributor fuses shall be used in small
transformer installations as defined in CEPG5099.
There are limitations on the use of ABC conductors for protection reasons. The maximum impedance of LV
network to the extremity of the ABC conductor is defined in Table 3.5.12.2 and associated notes.
CE-IN-CONFIDENCE CEM7097
Table 3.5.12.2
CE-IN-CONFIDENCE CEM7097
Failure performance of the installation is very adversely affected by seemingly minor departures from
construction standards affecting clearances or configuration.
The basic insulation coordination principles as outlined in Australian Standard AS1824.1 and the guidelines
as set out in AS1824.2 should be applied to all overhead lines and associated equipment. It is important that
all material and equipment installed on the network comply with the appropriate Country Energy Specification.
CE-IN-CONFIDENCE CEM7097
Note: Low voltage (230/400V) aerial crossings of electrified tracks are NOT permitted.
The Regional Office of Country Energy for the region in which the Waterways crossing is to be located will
prepare and submit the application on behalf of the ASP to the Waterways Authority.
The height of TransGrid conductors should indicate the time, the day, month and year and the ambient
temperature at which the measurement was taken with appropriate notation of any wind condition present at
the time.
The maximum height of Country Energy lines shown on the profile shall be the minimum designed operating
temperature of the line.
Country Energy’s Office for the Region in which the undercrossing occurs will assist with the submission of the
approval application when the ASP has provided the information previously outlined.
Glide path dimensions are provided in Civil Aviation Authority Publication CAAP92-1(1), 1998.
Fitment of aircraft warning marker balls to conductors of lines located near aircraft landing fields may be
required, refer to Clause 3.5.9. Designers should increase the wind loading on conductors accordingly.
CE-IN-CONFIDENCE CEM7097
It is a requirement that all designs comply with the true spirit and intent of the aforementioned guidelines.
CE-IN-CONFIDENCE CEM7097
Standard
Customer Utilisation Factor
Region Load Type ADMD Deviation
for Transformer Sizing
Ratio
Units and Relocatable No. of Utilisation
All 3.0kVA/dwelling 1.0
Homes Customers Multiplier
Prestige Units, Integrated
3.5kVA/dwelling 1.0 1 2.0
Housing
Rural Estates 7.0kVA/lot 1.0 2 1.60
Rural domestic 5.0kVA/dwelling 1.0 3 1.47
Light Industrial Estates** 30.0kVA/lot** 0 4 1.40
Pumps and Motors Actual Rating 0
5 1.36
Coast Residential* 4.0kVAlot* 1.0
Prestige Housing, Canal
Coast Estates, Village 5kVA/lot 1.0 10 1.25
Residential
Prestige Residential – no
Inland 7.5kVA/lot*** 1.0
reticulated gas***
20 1.10
Residential – no
Inland 6.0kVA/lot 1.0
reticulated gas
Residential – reticulated
Inland 4kVA 1.0
gas
30 1
Prestige Residential
Inland 5.5kVA 1.0
reticulated gas
In addition to the previous load information, when calculating voltage drops using “LVDROP” (version 5.48 or
later) software, the following parameters should also be used.
Transformer: LOIMP
Voltage:
Source = 240V
Nominal = 230V
Confidence Factors for Overhead Systems:
Voltage Drop = 3.00
Conductor Loading = 2.00
Transformer sizing use Utilisation Factor Table above.
Method Statistical
POA All Point of Application factors are to be calculated
Load Power Factor: Use 0.9 if not known
Node 3 phase total load: Use unbalanced multiplier of 1.
Node single phase: Use twice (2x) the distance as per the software instructions.
CE-IN-CONFIDENCE CEM7097
SIZING OF TRANSFORMERS:
Where customer loads are not assessed using AS3000 and the tabulated ADMD values are used, then the
utilisation multiplier must be used in assessing the transformer capacity for the required number of
customers.
As a general rule, the transformer size obtained using this method should be in the order of 50% of the value
that would be obtained using the total load current shown in the LVDROP program.
CE-IN-CONFIDENCE CEM7097
Range Average
Type of Development
VA/m2 VA/m2
Offices Not air conditioned 40-60 50
Air conditioned – cooling only 70-100 85
Reverse Cycle 60-90 75
Electrical reheat open areas 80-120 100
Electrical reheat zonal or package units 90-130 110
Variable volume 60-80 70
Car Parking Open air 0-10 5
Ventilated 10-20 15
Warehousing Unventilated 5-15 10
Ventilated 10-20 15
Shops Not air conditioned 40-100 70
Air conditioned 60-140 100
Shopping Centres (assumed air 60-140 100
Not air conditioned public areas
conditioned shops)
Air conditioned public areas 80-160 120
Industrial Light 10-20 15
If ventilated add 10-20 15
If air conditioned add (see note) 30-50 40
Theatres, halls, etc Ventilated 50-70 60
Air conditioned 80-120 100
Hotels, taverns, restaurants 60-100 80
Note: Medium and heavy industrial areas require full details of connected load before an assessment of
demand can be made. Only uniformly distributed loads such as lighting and air conditioning can be
assessed using this area usage method.
CE-IN-CONFIDENCE CEM7097
CE-IN-CONFIDENCE CEM7097
CE-IN-CONFIDENCE CEM7097
4 REFERENCES
CECG1000 – Safety, Health and Environmental Management
CEFD6024 – Environmental Assessment
CEK8003 – Subtransmission and Distribution Network Planning Criteria and Guidelines
CEK8042 – Distribution Apparatus Node Number Plates and Operational Number Labelling
CEK8046 – Easement Requirements
CEM7001 – Construction Drawing Standard Symbology
CEM7011 – Standard Overhead Conductor Current Rating Guide
CEM7063 – Information Security Sensitivity Handling
CEM7098 – Construction Standard Manual – Underground Design
CEM7099 – Standard Overhead Construction Manual
CEP2010 – Vegetation Clearing Guidelines for New Power Lines
CEPG1096 – Information Security Sensitivity Labelling and Handling
CEPG2016 – Environmental Impact Assessment
CEPG2021 – Removing Vegetation near Overhead Powerlines
CEPG2162 – Policy Document Management
CEPG5099 – Distribution Transformer Fusing
CEPG5124 – Full Length Preservative Treated Hardwood Poles
CEPG8002 – Protection Guidelines
CEPG8008 – Vegetation Management Plan
CEPG8019 – Capital Contributions
CEPG8022 – Bush Fire Risk Management Plan
CEPG8040 – Corporate Purchasing
EP10 01 00 05 SP – Rail Infrastructure Corporation Requirements for Electric Aerials Crossing RIC
Infrastructure
ENA C(b)1-2006 – Energy Networks Association Publication ‘Guidelines for Design and Maintenance of
Overhead Distribution and Transmission Lines’
CE-IN-CONFIDENCE CEM7097
CE-IN-CONFIDENCE CEM7097
5 REVISIONS
This document shall be reviewed in accordance with Country Energy policy document CEPG2162 – Policy
Document Management, as a minimum requirement.