Beruflich Dokumente
Kultur Dokumente
Vedanta - Jharsuguda
14
138-02-043
Group 431/432 G
DE-060300
Process
14.1.1
Revision: 0
Date: 29.09.2006
Page 1 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
CONTROL PHILOSOPHY
05.10.2006
1 (2)
Rev. 00
132-01-083 UB
P+I Diagram
168-01-063 UB
The process is described in order to the material flow whereas the control philosophy is written
in order to the signal flow, which is counter current to the material flow.
This Process Group 431 G collects pitch fumes from the following other Groups:
An air heater (431 G 050) is used to keep the waste gas, collected from the paste cooler (431
J 200), above water dew point temperature to prevent condensation of evaporated cooling
water. To achieve the aforesaid, the complete pitch fume dry scrubbing system shall be
preheated to operation temperature before starting of anode production and sucking off pitch
fumes. The envisaged operating temperature, measured in the stack [431 G 135-TIR], has to
be varied from about 25C (winter) to about 65C (summer) with the actual ambient
temperature and humidity. The best operating temperature has to be found out during
commissioning. It is most important that at all points of high humidity like the duct work
downstream the hot air dilution chamber (431 G 055), the reactor (431 G 100), filter (431
G120), fan (431 G 135) and the stack the gas temperature is always at minimum 5C higher
as the water dew point in order to prevent clogging of ducts, the reactor fluid bed bottom and
of the filter bags.
As soon as the operating conditions (waste gas temperature, fluid bed height) are reached,
anode production may start while then pitch fumes are set free from hot anode paste. Because
all equipment for anode paste handling is covered or hooded the pitch fumes are collected and
sucked through a pipe work into the settling chamber (431 G 060), where a part of the anode
paste particles and pitch fume droplets, coming with the fumes, are separated.
From the settling chamber the fumes are sucked through a duct and a throttle flap (431 G
080), which is opened pneumatically and is closed by counter weight. If high temperature is
measured in certain ducts [431 G 055-TAHH; 431 G 060-TAHH; 431 G 080-TAHH] this Group
is shut down automatically and the throttle flap (431 G 080) closes.
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
2 (2)
Rev. 00
Fresh adsorbent from the fresh adsorbent bin (431 F 450) is reclaimed by a rotary lock with
variable speed drive (431 G 010). Continuous discharge of fresh adsorbent is maintained by
an aeration unit (431 G 006), which is pulsing compressed air into the bin bottom. The two
hand-operated butterfly valves (431 G 020 / 025) and a bulker bag (431 G 030) are used to
calibrate the feed rate of the rotary lock.
The fresh absorbent is fed via an fresh adsorbent divider (431 G 013) to the suction points of
pitch fumes from the mixer unit (431 J 100), the vibrating feeder (431 K 005), behind the hot
air dilution chamber and to the main gas duct where pitch fume loaded waste gases are
intensively mixed with the injected adsorbent while gas and adsorbent are transferred into the
fluid bed reactor (431 G 100).
In the reactor the mixture of waste gas and adsorbent passes through perforated plates at a
velocity required to form a uniform fluid bed on top of the plates.
A multiple adsorption of condensed hydrocarbons takes place in the main raw gas duct, the
reactor hoppers, fluid bed and on the filter bag surface of the bag filter (431 G 120).
To achieve a maximum removal of the condensed and solid pitch particles from the waste gas
stream, the requested height of the fluid bed is automatically build up and maintained by
means of a control unit, which is measuring the differential pressure across the fluid bed and
so regulates the fluid bed height by starting and stopping the rotary locks (431 G 200 / 205),
which are discharging the reactor hoppers. The bag filter (431 G 120) above the fluid bed
recovers the dust from the gas flow drawn by a Fan (431 G 135).
Loaded adsorbent enriched with condensed pitch fumes will be periodically discharged from
the fluid bed by means of two rotary locks (431 G 200 / 205) and subsequently transferred by
screw conveyors (431 G 220 / 225) into the bin for "Loaded Adsorbent (431 G 300).
After the anode production has been stopped, only the fresh adsorbent feed (rotary lock 431 G
010) is shut off, while the rest of the Group (fan 431 G 135, dust collector 431 G 120, air
heater 431 G 050 is kept running and kept warm, being ready for the next start of anode
production. The rest of the discharge system for loaded adsorbent (screw conveyors 431 G
220 and 431 G 225) are kept running, the rotary locks (431 G 200 / 205) are still enabled to
run on request and the knife gates (431 G 210 / 215) are kept closed.
If the pitch fume dry scrubber system has to be shut down totally because of a longer stand
still, the fan (431 G 135), the dust collector cleaning system (431 G 120), the rotary locks (431
G 010 and 431 G 200 and 431 G 205) are shut off instantly, the knife gates (431 G 210 and
431 G 215) will open and a part of the fluid bed will be removed from the reactor. The screw
conveyors (431 G 220 and 431 G 225) will transfer the loaded adsorbent into the bin for
"Loaded Adsorbent (431 G 300) for storage. After run empty of the loaded adsorbent is
terminated, all equipment still running is shut off and the knife gate (431 065) opens to allow
the slurry of pitch condensates and anode paste fines to run down into the pitch barrel (431 G
075) located underneath the settling chamber (431 G 060). It is most important that the door
for removing the pitch barrel is closed tightly to prevent cold fresh air from coming in the
housing when the knife gate is open.
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 3 of 53
138-02-043
Group 431/432 G
DE-060300
Make sure the total flow rate through the scrubber is about 52,000 m3/h. Flow rate
shall never be less than 46,500 m3/h respectively 17.0 m/s in each hole of the
perforated plates of the reactor. If flow rate is getting too low there is a high risk of a
fluid bed break down. Loaded adsorbent contains pitchy matters.
When cleaning a pitch fume ducts the hot air dilution chamber, the main settling
chamber, the reactor, the filter and the fan, rotary locks, bins, the pitch barrel and
screw conveyors protect skin and eyes against dust and condensed pitch fumes. The
use of a mask with particle filter, gloves and further protective clothing is mandatory!
Note: Pitch dust and fumes are irritating (burning) the skin and if breathed
could cause cancer.
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
The airflow through both scrubber compartments should be equal to attain same
scrubbing conditions in each compartment. If in doubt please check the flow by a
portable flow meter. If required adjust the baffle at the Y-duct downstream the reactor
inlet.
Check regularly the time between two discharges of the fluid bed. If this interval is
shorter as normal this is a sign of too much adsorbent fed to the scrubber. In this case
check first the speed of the rotary lock (431/432 G 010). The normal speed has been
fixed and listed during commissioning. Readjust the speed to the listed set point or
make a calibration if required.
If the discharge interval is still too short then calibrate the rotary lock by feeding into
the bulker bag. If calibration shows that the feed rate is not too high then check the
clearance between rotary vanes and the housing of the rotary lock (431/432 G 010)
and adjust it because rotary lock was not gas tight.
If there is no material flow anymore detected by the flow detectors [431/432 G 025FAL] then please check the following:
- is the rotor of the rotary lock running?
is the fresh adsorbent bin empty?.
is the chute between rotary lock and fresh adsorbent bin clogged because the
aeration is not working or is a foreign body in the chute.
is the bin outlet plugged?
In case of High-High reactor bed level [431/432 G 100-PDSHH] check following:
are rotors of the rotary locks (431/432 G 200 /205) running?
is a chute clogged between reactor and rotary locks?
is a chute clogged between rotary locks and screw conveyor (431/432 G 220)?
are rotary locks (431/432 G 200/205) and chutes upstream air tight to ambient?
Check pitch fume ductwork regularly for deposits of pitch condensate and dust. Clean
duct segments as soon as deposits are more than 15mm thick.
Check main settling chamber (431/432 G 060) regularly for deposits of pitch
condensate and dust. Clean chamber as soon as deposits are more than 15mm thick.
Change barrel for pitchy matters (431/432 G 075) regularly.
Check hot air dilution chamber (431/432 G 055) regularly for deposits of pitch
condensate and dust. Clean chamber as soon as deposits are more than 30mm thick.
Check insulation of pitch fume pipe work, main settling chamber (431/432 G 060), hot
air dilution chamber (431/432 G 055), reactor (431/432 G 100), Filter (431/432 G
115/120), fan (431/432 G 135) and stack. If insulation is not tightly fixed to the
equipment, insulation is missing completely or partly, insulation cladding is bent then
condensation of water, plugging of pitch fume/dust and probably corrosion in this area
may occur. If insulation of a whole branch has been removed while the system is
running condensed water may clog this part and likely the filter bags.
Revision: 0
Date: 29.09.2006
Page 5 of 53
14.2
Process Control
14.2.1
138-02-043
Group 431/432 G
DE-060300
(work copies)
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 7 of 53
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
1 (25)
Rev. 00
Control Philosophy
of
Process Group 431-G
Pitch Fume Treatment Reference:
Process Flow Sheet
132-01-083 UB
P+I Diagram
168-01-063 UB
2
2.1
2.2
2.3
2.3.1
2.3.2
2.3.3
2.3.4
2.4
2.4.1
2.4.2
2.4.3
2.4.4
2.4.5
2.5
2.6
2.6.1
2.6.2
2.6.3
2.6.4
2.6.5
2.7
2.8
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
1
2 (25)
Rev. 00
An air heater (431 G 050) is used to keep the waste gas, collected from the paste cooler (431
J 200), above water dew point temperature to prevent condensation of evaporated cooling
water. To achieve the aforesaid, the complete pitch fume dry scrubbing system shall be
preheated to operation temperature before starting of anode production and sucking off pitch
fumes. The envisaged operating temperature, measured in the stack [431 G 135-TIR], has to
be varied from about 25C (winter) to about 65C (summer) with the actual ambient
temperature and humidity. The best operating temperature has to be found out during
commissioning. It is most important that at all points of high humidity like the duct work
downstream the hot air dilution chamber (431 G 055), the reactor (431 G 100), filter (431
G120), fan (431 G 135) and the stack the gas temperature is always at minimum 5C higher
as the water dew point in order to prevent clogging of ducts, the reactor fluid bed bottom and
of the filter bags.
As soon as the operating conditions (waste gas temperature, fluid bed height) are reached,
anode production may start while then pitch fumes are set free from hot anode paste. Because
all equipment for anode paste handling is covered or hooded the pitch fumes are collected and
sucked through a pipe work into the settling chamber (431 G 060), where a part of the anode
paste particles and pitch fume droplets, coming with the fumes, are separated.
From the settling chamber the fumes are sucked through a duct and a throttle flap (431 G
080), which is opened pneumatically and is closed by counter weight. If high temperature is
measured in certain ducts [431 G 055-TAHH; 431 G 060-TAHH; 431 G 080-TAHH] this Group
is shut down automatically and the throttle flap (431 G 080) closes.
Fresh adsorbent from the fresh adsorbent bin (431 F 450) is reclaimed by a rotary lock with
variable speed drive (431 G 010). Continuous discharge of fresh adsorbent is maintained by
an aeration unit (431 G 006), which is pulsing compressed air into the bin bottom. The two
hand-operated butterfly valves (431 G 020 / 025) and a bulker bag (431 G 030) are used to
calibrate the feed rate of the rotary lock.
The fresh absorbent is fed via an fresh adsorbent divider (431 G 013) to the suction points of
pitch fumes from the mixer unit (431 J 100), the vibrating feeder (431 K 005), behind the hot
air dilution chamber and to the main gas duct where pitch fume loaded waste gases are
intensively mixed with the injected adsorbent while gas and adsorbent are transferred into the
fluid bed reactor (431 G 100).
In the reactor the mixture of waste gas and adsorbent passes through perforated plates at a
velocity required to form a uniform fluid bed on top of the plates.
Outokumpu Technology GmbH
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
3 (25)
Rev. 00
A multiple adsorption of condensed hydrocarbons takes place in the main raw gas duct, the
reactor hoppers, fluid bed and on the filter bag surface of the bag filter (431 G 120).
To achieve a maximum removal of the condensed and solid pitch particles from the waste gas
stream, the requested height of the fluid bed is automatically build up and maintained by
means of a control unit, which is measuring the differential pressure across the fluid bed and
so regulates the fluid bed height by starting and stopping the rotary locks (431 G 200 / 205),
which are discharging the reactor hoppers. The bag filter (431 G 120) above the fluid bed
recovers the dust from the gas flow drawn by a Fan (431 G 135).
Loaded adsorbent enriched with condensed pitch fumes will be periodically discharged from
the fluid bed by means of two rotary locks (431 G 200 / 205) and subsequently transferred by
screw conveyors (431 G 220 / 225) into the bin for "Loaded Adsorbent (431 G 300).
After the anode production has been stopped, only the fresh adsorbent feed (rotary lock 431 G
010) is shut off, while the rest of the Group (fan 431 G 135, dust collector 431 G 120, air
heater 431 G 050 is kept running and kept warm, being ready for the next start of anode
production. The rest of the discharge system for loaded adsorbent (screw conveyors 431 G
220 and 431 G 225) are kept running, the rotary locks (431 G 200 / 205) are still enabled to
run on request and the knife gates (431 G 210 / 215) are kept closed.
If the pitch fume dry scrubber system has to be shut down totally because of a longer stand
still, the fan (431 G 135), the dust collector cleaning system (431 G 120), the rotary locks (431
G 010 and 431 G 200 and 431 G 205) are shut off instantly, the knife gates (431 G 210 and
431 G 215) will open and a part of the fluid bed will be removed from the reactor. The screw
conveyors (431 G 220 and 431 G 225) will transfer the loaded adsorbent into the bin for
"Loaded Adsorbent (431 G 300) for storage. After run empty of the loaded adsorbent is
terminated, all equipment still running is shut off and the knife gate (431 065) opens to allow
the slurry of pitch condensates and anode paste fines to run down into the pitch barrel (431 G
075) located underneath the settling chamber (431 G 060). It is most important that the door
for removing the pitch barrel is closed tightly to prevent cold fresh air from coming in the
housing when the knife gate is open.
2
2.1
2.2
The exchange of control signals is described in the following chapters and especially under 2.8
below.
CONTROL PHILOSOPHY
05.10.2006
4 (25)
Rev. 00
Selections
2.3.1
2.3.2
2.3.3
2.3.4
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
5 (25)
Rev. 00
Group Start
2.4.1
2.4.2
Start Preconditions
CONTROL PHILOSOPHY
05.10.2006
6 (25)
Rev. 00
New Setpoint
Previous Setpoint
Standard Setpoint
(Setpoint SP 1)
Low Speed: The speed of the rotary lock can be varied between 20 % and 100 %
corresponding to a feed rate between 0.5 and 2.5 tons/hour. This feed rate can be varied
any time but requires the shift leaders password.
On SCADA the operator has the choice to select one of three options, New setpoint,
Previous setpoint and Standard setpoint all overriding the actual setpoint. The Standard
Setpoint has to be found out during commissioning.
High Speed: The speed of the rotary lock can be varied between 20 % and 100 %
corresponding to a feed rate between 0.5 and 2.5 tons/hour. This feed rate can be varied
any time but requires the shift leaders password.
On SCADA the operator has the choice to select one of three options, New setpoint,
Previous setpoint and Standard setpoint) all overriding the actual setpoint. The
Standard Setpoint has to be found out during commissioning.
(Setpoint SP 2)
The fluid bed height is controlled by the differential pressure (431 G 100-PDY) across the bed.
The fluid bed height (expressed as differential pressure) setpoints can be varied any time
but require the shift leaders password.
On SCADA the operator has the choice to select one of three options, New setpoint,
Previous setpoint and Standard setpoint (first approach for Standard Setpoint is 50%)
all overriding the actual setpoint.
Low-Low Level [431 G 100-PDAL] {setpoint 9.5mbar}:
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
7 (25)
Rev. 00
If the differential pressure is below this value for more than 15 seconds an alarm is
initiated and the rotary lock (431 G 010) is switched to high speed (high feed rate) if it
is not already running at high speed.
Low Level [431 G 100-PDSL] { setpoint 10mbar}:
If the pressure has reached low level [431 G 100-PDSL] or is above this value for
more than 15 seconds the rotary lock is switched to low speed.
If the pressure has reached or is below low level [431 G 100-PDSL] (coming from high
or high-high fluid bed level) for more than 5 seconds after the rotary locks (431 G 200 /
205) were running to reduce the fluid bed height, the rotary locks are shut off.
High Level [431 G 100-PDSH] { setpoint 12mbar}: If the pressure has reached high level
[431 G 100-PDSH] (coming from low fluid bed level):
rotary locks (431 G 200 / 205) are both started to discharge loaded adsorbent from the
fluid bed in order to reduce the fluid bed height.
The rotary locks are running until low level [431 G 100-PDSL] is detected since more
than 5 seconds.
rotary lock (431 G 010) is restarted automatically, if the rotary lock has been stopped
previously by high-high pressure [431 G 100-PDAHH].
High-High Level [431 G 100-PDSHH] { setpoint 12.5mbar}: If the pressure has reached
high-high level [431 G 100-PDSHH] (coming from high fluid bed level):
rotary lock (431 G 010) is shut off
rotary locks (431 G 200 / 205) are both started (if they have not been already started
by high level see 2-3 above -) to discharge loaded adsorbent from the fluid bed in
order to reduce the fluid bed height.
The rotary locks are running until low level [431 G 100-PDSL] is reached and are then
stopped.
-
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
8 (25)
Rev. 00
2.4.3.4 Air Heater 431 G 050 (Hot Air Flow Rate) (Setpoint SP 4)
If Auto Flow (SE 4-1) is selected the operator may set the hot air flow rate at any time in
a range of 2000m3/hour to 4500m3/hour. Setting [431 G 050-FC] and display [431 G 050FIR] of the actual flow rate is on SCADA. On SCADA the operator has the choice to select
one of three options, New setpoint, Previous setpoint and Standard setpoint ( first
approach 4000m3/hour) all overriding the actual setpoint but this requires the shift
leaders password.
The hot air flow rate [431 G 050-FIR] is continuously measured in the duct between the air
heater and the hot air dilution chamber (431 G 055).
The flow is controlled by a PID-software-controller generated in the PLC program of this
Group (431 PLC 15). The controller opens and closes the throttle flap (with servo-drive
operating time between open and closed position shall be 60-80 seconds) of the air
heater to attain the set flow rate within a range of +/-50m3/hour.
If Manual Flow (SE 4-2) is selected the operator may set the hot air flow rate manually at
any time in a range of 50% to 100% (equal to about 2250m3/hour to 4500m3/hour).
Setting [431 G 050-ZC] and display [431 G 050-FIR] of the actual flow rate is on SCADA.
On SCADA the operator has the choice to select one of three options, New setpoint,
Previous setpoint and Standard setpoint ( first approach is 89 % (equal to about
4000m3/hour) all overriding the actual setpoint.
The hot air flow rate [431 G 050-FIR] is continuously measured in the duct between the air
heater and the hot air dilution chamber (431 G 055).
The flow is controlled by the operator by typing a flap opening percentage between 50%
and 100%. The servo drive opens / closes the throttle flap (with servo-drive operating
time between open and closed position shall be 60-80 seconds) until the set position is
reached. The positions (%) for 2000 m3/hour and 4500 m3/hour have to be found out
during commissioning.
2.4.4
The operator has to start this Group always in the following sequence:
Step 1: Select SE 2-1 on SCADA and click START on SCADA (Start sequence 2.4.4.1
commences)
Step 2: This step requires Step 1 to be finished: Select then SE 2-2 on SCADA and click
START on SCADA (Start sequence 2.4.4.2 commences)
2.4.4.1 Heat-Up (Selection SE 2-1)
The operator is enabling Step 1 (selection SE 2-1) of this Group 431 G to start and to run the
selected equipment. To initiate the start he is using the SCADA system on the Operator
Station in the Central Control Room.
Signal from Group 431 C (Main Dust Treatment) is required (Group is running in CENTRAL
mode and is not in Group Start (START) or any Group Stop sequence (RESTOP or
FASTOP)).
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
9 (25)
Rev. 00
The horn starts to sound permanently for 15 seconds prior to start of the first equipment,
then it sounds intermittently until the last drive is running.
Screw conveyor (431 G 225) starts.
Screw conveyor (431 G 220) starts.
Aeration unit (431 G 105) is enabled.
Delay of 60 seconds to run empty the screw conveyors.
Knife gate (431 G 210) is closing until limit switch [431 G 210-ZL] is actuated.
Knife gate (431 G 215) is closing until limit switch [431 G 215-ZL] is actuated.
Throttle flap (431 G 130) is closing until limit switch [431 G 130-ZL] is actuated.
Knife gate (431 G 065) is closing until limit switch [431 G 065-ZL] is actuated.
Aeration unit (431 G 105) is disabled.
Fluid-bed height control loop (431 G 100-PDY; rotary locks 431 G 200 / 205; aeration unit
431 G 110) is enabled
Bag pulsing control loop (431 G 120-PDY; bag filter jet cleaning unit 431 G 120) is
enabled
Throttle flap (431 G 080) is opening until limit switch [431 G 080-ZH] is actuated.
Fan (431 G 135) starts, if
throttle flap (431 G 130) is closed [limit switch 431 G 130-ZL is actuated]
throttle flap (431 G 080) is open [limit switch 431 G 080-ZH is actuated].
knife gate (431 G 210) is closed [limit switch 431 G 210-ZL is actuated]
knife gate (431 G 215) is closed [limit switch 431 G 215-ZL is actuated]
Delay of 30 seconds for fan impeller run-up.
Throttle flap (431 G 130) is opening until limit switch [431 G 130-ZH] is actuated.
Air heater fan (431 G 050) starts if:
throttle flap (431 G 130) is open [limit switch 431 G 130-ZH is actuated]
throttle flap (431 G 080) is open [limit switch 431 G 080-ZH is actuated].
knife gate (431 G 210) is closed [limit switch 431 G 210-ZL is actuated]
knife gate (431 G 215) is closed [limit switch 431 G 215-ZL is actuated]
knife gate (431 G 065) is closed [limit switch 431 G 065-ZL is actuated]
Delay of 20 seconds for fan impeller run-up.
If SE 4-1 Auto Flow is selected, hot air flow control loop (431 G 050-FY; throttle flap 431
G 050) is enabled
If SE 4-2 Manual Flow is selected, jump to step 15.
Delay of 90 seconds for automatic throttle flap adjustment.
Hot Air Temperature control loop (431 G 050-TY; electric heater unit 431 G 050-E1) is
enabled.
Delay of 2 hours for heating up ducts, reactor, bag filter, fan and stack to temperature of
minimum 5C above the water dew point. During this delay time on SCADA the following
message is displayed: HEAT-UP.
It is possible to shorten the heat-up time by selecting SE 2-2 Feed Adsorbent on SCADA.
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
10 (25)
Rev. 00
This override should only be used if this Group has been shut down for a very
Note:
short time and only if the operator is sure the ducts, reactor, bag filter, fan and stack is hot
(5C above water dew point).
Now this Group is running in heat-up mode.
2.4.5
The horn starts to sound permanently for 15 seconds prior to start of the rotary, then it
sounds intermittently until the drive is running.
Aeration Unit of fresh Adsorbent Divider (431 G 013) is enable
Rotary lock (431 G 010) starts and runs at high speed (high feed rate), if low fluid bed level
[431 G 100-PDSL] or if no high fluid bed level1 [431 G 100-PDSH1 is detected.
Rotary lock (431 G 010) starts and runs at low speed, if fluid bed level2 [431 G 100PDSH2] or fluid bed level high [431 G 100-PDAH] is detected.
Rotary lock (431 G 010) does not start if fluid bed level high-high [431 G 100-PDAHH] is
detected.
This releases the signal Fume Scrubber on Service.
Now this Group is running in Normal Operation.
2.5
Normal Operation
Both Heat-Up operation (selection SE-2-1) and Feed Adsorbent operation (SE 2-2) is
Normal Operation because the only difference is the rotary lock (431 G 010), which is
running or is not running.
2.5.1
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
11 (25)
Rev. 00
If the rotary lock (431 G 010) runs and if after a delay of 20 seconds the flow switch [431 G
025-FAL] is not detecting fresh adsorbent flowing through the feed chute into the main
waste gas duct, the blasting time of the aeration unit is extended to 4 seconds as long as
the flow is interrupted or too low.
2.5.2
Rotary Lock 431 G 010 If the rotary lock is not tripped this Group is in normal operation.
Low Speed : The speed of the rotary lock can be varied between 20 % and 100 %
corresponding to a feed rate between 0.5 and 2.5 tons/hour. This feed rate can be varied
any time but requires the shift leaders password.
On SCADA the operator has the choice to select one of three options, New setpoint,
Previous setpoint and Standard setpoint all overriding the actual setpoint. The Standard
Setpoint has to be found out during commissioning.
High Speed: The speed of the rotary lock can be varied between 20 % and 100 %
corresponding to a feed rate between 0.5 and 2.5 tons/hour. This feed rate can be varied
any time but requires the shift leaders password.
On SCADA the operator has the choice to select one of three options, New setpoint,
Previous setpoint and Standard setpoint) all overriding the actual setpoint. The
Standard Setpoint has to be found out during commissioning.
Note:
In the past it turned out that the feed rate at high speed should be
approximately double of the rate fed at low speed. The best speed for both low- and high
speed has to be found out during commissioning.
2.5.3
Aeration Unit 431 G 013 for Fresh Adsorbent Divider 431 G 013
The aeration unit is equipped with a solenoid valve to open and close the compressed air
supply to the fresh adsorbent divider (431 G 013). If the rotary lock (431 G 010) runs, air
blast starts.
2.5.4
Air Heater Unit 431 G 050 Hot Air Temperature If the air heater unit is not tripped (fan, throttle flap, heater) this Group is in normal
operation
The hot air temperature may be changed at any time in a range of 4C to 200C but
requires the shift leaders password.
In case CENTRAL (SE 1-1) is selected setting [431 G 050-TC1] and display [431 G
050-TIR] of the actual temperature is on SCADA. On SCADA the operator has the
choice to select one of three options, New setpoint, Previous setpoint and
Standard setpoint ( first approach 115C) all overriding the actual setpoint.
In case LOCAL (SE 1-2) is selected setting is on the Local Operator Panel [431 G
050-LOP1] and display of the actual temperature is on SCADA [431 G 050-TIR] and is
locally [431 G 050-TI] but no shift leader password is required for changing the setting
in this operation mode.
The hot air temperature [remote 431 G 050-TIR (4 20 mA) and locally 431 G 050-TI] is
continuously measured in the duct between the air heater and the hot air dilution chamber
(431 G 055).
Air outlet temperature control is by the air heater unit using the 4 20 mA signal [431 G
050-TY] as control input. The outlet air temperature shall be kept within a range of +/- 1C
at all operation conditions (VEDANTA to check with supplier how temperature control
works in detail).
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
12 (25)
Rev. 00
2.5.5
Air Heater 431 G 050 -Hot Air Flow Rate If Auto Flow (SE 4-1) is selected, the operator may set the hot air flow rate at any time in
a range of 2000m3/hour to 4500m3/hour. Setting [431 G 050-FC] and display [431 G 050FIR] of the actual flow rate is on SCADA. On SCADA the operator has the choice to select
one of three options, New set point, Previous set point and Standard set point ( first
approach 4000m3/hour) all overriding the actual set point.
The hot air flow rate [431 G 050-FIR] is continuously measured in the duct between the air
heater and the hot air dilution chamber (431 G 055).
The flow is controlled by a PID-software-controller generated in the PLC program of this
Group (431 PLC 15). The controller opens and closes the throttle flap (with servo-drive
operating time between open and closed position shall be 60-80 seconds) of the air
heater to attain the set flow rate within a range of +/-50m3/hour.
If Manual Flow (SE 4-2) is selected the operator may set the hot air flow rate manually at
any time in a range of 2000m3/hour to 4500m3/hour. Setting [431 G 050-ZC] and display
[431 G 050-FIR] of the actual flow rate is on SCADA. On SCADA the operator has the
choice to select one of three options, New setpoint, Previous setpoint and Standard
setpoint ( first approach 4000m3/hour) all overriding the actual setpoint.
The hot air flow rate [431 G 050-FIR] is continuously measured in the duct between the air
heater and the hot air dilution chamber (431 G 055).
The flow is controlled by the operator by typing a flap opening percentage between 50%
and 100%. The servo drive opens / closes the throttle flap (with servo-drive operating
time between open and closed position shall be 60-80 seconds) until the set position is
reached. The positions (%) for 2000 m3/hour and 4500 m3/hour have to be found out
during commissioning.
2.5.6
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
13 (25)
Rev. 00
2.5.7
2.5.8
2.5.9
The fluid bed height (expressed as differential pressure) set points can be varied any time
but require the shift leaders password.
On SCADA the operator has the choice to select one of three options, New setpoint,
Previous setpoint and Standard setpoint all overriding the actual setpoint.
Low-Low Level [431 G 100-PDAL] {set point 9.5mbar}:
If the differential pressure is below this value for more than 15 seconds an alarm is
initiated and the rotary lock (431 G 010) is switched to high speed (high feed rate) if it
is not already running at high speed.
Low Level [431 G 100-PDSL] { set point 10mbar}:
If the pressure has reached low level [431 G 100-PDSL] or is above this value for
more than 15 seconds the feeding rotary lock is switched to low speed.
If the pressure has reached or is below low level [431 G 100-PDSL] (coming from high
or high-high fluid bed level) for more than 10 seconds after the fluid bed discharging
rotary locks (431 G 200 / 205) were running to reduce the fluid bed height, the rotary
locks are shut off.
High Level [431 G 100-PDSH] { set point 12mbar}: If the pressure has reached high level
[431 G 100-PDSH] (coming from low fluid bed level) for more than 5 seconds:
rotary locks (431 G 200 / 205) are both started to discharge loaded adsorbent from the
fluid bed in order to reduce the fluid bed height.
The rotary locks are running until low level [431 G 100-PDSL] is detected since more
than 10 seconds.
rotary lock (431 G 010) is restarted automatically, if the rotary lock has been stopped
previously by high-high pressure [431 G 100-PDAHH].
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
14 (25)
Rev. 00
2.5.11
2.5.12
2.5.13
2.5.14
2.5.15
2.5.16
2.5.17
2.5.18
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
15 (25)
Rev. 00
2.5.19
2.5.20
If this Group is running under Feed Adsorbent selection the operator may stop feeding of
fresh adsorbent any time. For this purpose he shuts down the rotary lock (431 G 010) by
clicking SE 2-1 - Heat-Up on SCADA From now this Group is running under Heat-Up
selection and is ready to be restarted for Feed Adsorbent operation.
Note:
The operator should be aware that if he selects Heat-UP and anode paste
production is running in Group 431 H that Group stops after a delay of 60 minutes by a
RESTOP automatically.
2.6
2.6.1
The operator stops this Group using the RESTOP push button on SCADA.
Aeration unit (431 G 006) cycle is disabled and solenoid [431 G 006-ZY1] closes.
Rotary lock (431 G 010) stops
Aeration unit (431 G 013) is disabled and solenoid [431 G 013-ZY1] closes.
Air heater unit (431 G 050) gets a STOP signal.
Rotary locks (431 G 200 / 205) stop, if they are running.
Aeration unit (431 G 110) cycle is disabled and solenoid [431 F 110-ZY1] closes.
Fan (431 G 135) stops.
Throttle flap (431 G 080) closes until limit switch [431 G 080-ZL] is activated.
Knife gate (431 G 210) opens until limit switch [431 G 210-ZH] is activated.
Knife gate (431 G 215) opens until limit switch [431 G 215-ZH] is activated.
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
2.6.2
16 (25)
Rev. 00
Knife gate (431 G 065) opens until limit switch [431 G 065-ZH] is activated.
Bag cleaning unit (431 G 120) is disabled.
Aeration unit (431 G 105) cycle is enabled.
The aeration unit is equipped with a solenoid valve to open and close the compressed air
supply to the reactor discharge chutes according to a time interval, which is pre-set in the
PLC (431 PLC 15). If the knife gate (431 G 210) is open, an air blast is generated every 10
seconds for a duration of 1 second. The pre-set intervals are checked and if necessary
readjusted during commissioning.
Delay of 10 minutes (run-empty time for screw conveyors)
Screw conveyor (431 G 220) stops.
Screw conveyor (431 G 225) stops.
Aeration unit (431 G 105) cycle is disabled.
The whole Group is stopped.
After a shut down of the Group or of a part of the Group all actual setpoints of this Group are
memorized as Actual Set Point.
2.6.2.1 Group 431 C Main Dust Treatment
Because a mayor part of equipment of this Group 431 G is connected to the Main Dust
Treatment it is essential that Group 431 C is running in CENTRAL control mode and is
not in a START or STOP sequence.
If this Group is running under selection SE-2-2 Feed Adsorbent and if Group 431 C is not
running anymore in CENTRAL mode because it has been stopped by a Normal Shut
Down (RESTOP), by a Fast Shut Down (FASTOP) or is tripped through a fault, shut down
of the rotary locks (431 G 200 / 205) and the screw conveyors (431 G 220 / 225) is
initiated and knife gates (431 G 210 / 215) do not open.
Rotary lock (431 G 010) is not shut down instantly, if the Group 431 C is shut
Note:
down or trips. The rotary lock is still feeding fresh adsorbent to the system until high-high
fluid bed level [431 G 100-PDAHH] stops the rotary lock.
2.6.3
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
17 (25)
Rev. 00
cause an alarm
VFD-unit is shut down
cause an alarm
pertinent VFD-unit is shut off
[431 G 010-SAL] The rotary lock is equipped with a proximity type low-speed detector
measuring the frequency of a target rotating with the rotor. If the frequency of the rotor is too
low or the switch fails
-
cause an alarm
equipment trips
alarm is generated
VFD-unit stops the motor automatically
solenoid of the aeration unit [431 G 006-Y1] closes
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
18 (25)
Rev. 00
causes an alarm
rotary lock (431 G 010) is shut off so that this group is running again in Heat-Up
selection.
2.6.4.3 Air heater 431 G 050 -VEDANTA to check with Supplier A collective fault signal initiated by the air heater package (resistance heating unit; fan; throttle
flap) [431 G 050-LOP1]
-
causes an alarm
Normal Shut Down is initiated automatically as described above (see 2.6.1).
[431 G 050-ZL / ZH] The throttle flap is equipped with two limit switches, incorporated in a
control box fitted to the drive unit. If a limit switch fails this
-
causes an alarm
causes an alarm
Normal Shut Down is initiated automatically as described
The maximum time required between start and stop of the actuator drive, which is tilting the
throttle flap, shall not be more than 90 seconds. If after 90 seconds the motor has not been
stopped automatically because the target position has not been reached
-
an alarm is initiated
Normal Shut Down is initiated automatically as described above (see 2.6.1).
[431 G 050-FAL] {set point ???? ask supplier - m3/hour} The flow rate of hot air is continuously
measured in the duct between the Air Heater and the Hot Air Dilution Chamber (431 G 055). If
the flow rate is below the set point
-
[431 G 050-FAH] {set point 4500 m3/hour} The flow rate of hot air is continuously measured in
the duct between the Air Heater and the Hot Air Dilution Chamber (431 G 055). If the flow rate
is above the set point
-
[431 G 050-TAL] {set point 80C} The temperature of hot air is continuously measured in the
duct between the Air Heater and the Hot Air Dilution Chamber (431 G 055). If the temperature
is below the set point
-
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
19 (25)
Rev. 00
[431 G 050-TAH] {set point 180C} The temperature of hot air is continuously measured in the
duct between the Air Heater and the Hot Air Dilution Chamber (431 G 055). If the temperature
is above the set point
-
[431 G 050-PAH] {set point 5mbar}The pressure in the duct between the Air Heater and the
Hot Air Dilution Chamber (431 G 055) is continuously measured. If the pressure is above the
set point
-
causes an alarm
Fast Shut Down is initiated automatically as described above (see 2.6.3)
[431 G 055-TAHH] {set point 200C} The temperature of waste gas is continuously measured
in the duct between the Hot Air Dilution Chamber (431 G 055) and the Settling Chamber (431
G 060). If the temperature is above the set point
-
causes an alarm
Fast Shut Down is initiated automatically as described above (see 2.6.3)
Note: In case of high temperature or high-high temperature it is likely there is a fire in the duct
especially if welders are working in the field. The operator has to decide to open the pertinent
water valves of the sprinkler system in order to flood the pitch fume main duct and the hot air
dilution chamber.
2.6.4.5 Settling Chamber 431 G 060
[431 G 060-TAH] {set point 210C} The temperature of waste gas is continuously measured in
the duct between the Mixer (431 J 100) and the Settling Chamber (431 G 060). If the
temperature is above the set point
-
causes an alarm
Fast Shut Down is initiated automatically as described above (see 2.6.3)
[431 G 060-TAHH] {set point 210C} The temperature of waste gas is continuously measured
in the duct between the Mixer (431 J 100) and the Settling Chamber (431 G 060). If the
temperature is above the set point
-
causes an alarm
Fast Shut Down is initiated automatically as described above (see 2.6.3)
Note: In case of high temperature or high-high temperature it is likely there is a fire in the duct
especially if welders are working in the field. The operator has to decide to open the pertinent
water valves of the sprinkler system in order to flood the pitch fume main duct and the hot air
dilution chamber.
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
20 (25)
Rev. 00
2.6.4.6 Throttle Flap 431 G 080 pneumatic [431 G 080-ZH / ZL]: The flap is equipped with two proximity type limit switches. If one of the
switches fails
-
causes an alarm
equipment trips
The maximum time required by the pneumatic drive for tilting the flap blade from one limit
switch to the other one shall not be more than 10 seconds. If after 10 seconds the limit switch
is not reached
-
causes an alarm
equipment trips
an alarm is generated
Normal Shut Down of this Group (see 2.6.1 above), which is initiated automatically.
[431 G 080-TAH] {set point 210C} The temperature of waste gas is continuously measured in
the duct between the Settling Chamber (431 G 060) and the reactor (431 G100). If the
temperature is above the set point
-
causes an alarm
Fast Shut Down is initiated automatically as described above (see 2.6.3).
[431 G 080-TAHH] {set point 210C} The temperature of waste gas is continuously measured
in the duct between the Settling Chamber (431 G 060) and the reactor (431 G100). If the
temperature is above the set point
-
causes an alarm
Fast Shut Down is initiated automatically as described above (see 2.6.3).
Note: In case of high temperature or high-high temperature it is likely there is a fire in the duct
especially if welders are working in the field. The operator has to decide to open the pertinent
water valves of the sprinkler system in order to flood the pitch fume main duct and the hot air
dilution chamber.
2.6.4.7 Reactor 431 G 100
[431 G 100-PDALL] {< 9.5mbar} If low-low differential pressure is detected across the reactor
filter bed and if SE 2-2 Feed Adsorbent is selected and if this signal [431 G 100-PDALL] is
valid for more than 15 minutes or if the measuring unit fails for more than 5 seconds
-
cause an alarm
Group is switched to Heat-Up mode automatically.
[431 G 100-PDAHH] {> 12.5mbar} If high-high differential pressure is detected across the
reactor fluid bed and this signal is valid for more than 10 minutes or if the switch fails for more
than 5 seconds
-
cause an alarm
Group is switched to Heat-Up mode automatically.
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
21 (25)
Rev. 00
an alarm is generated
Normal Shut Down (see 2.6.1 above) will be initiated automatically.
[431 G 120-PDAL] {< 2.5mbar} If low differential pressure is detected across the filter bags or
if the measuring unit fails for more than 5 seconds
-
cause an alarm
Normal Shut Down of this Group (see 2.6.1 above), which is initiated automatically.
NOTE: During Start or Restart of this Group there is an override of this function of 20 seconds
to allow the fan to run up.
[431 G 120-PDAH] {> 13mbar} If high differential pressure is detected across the filter bags or
if the measuring unit fails for more than 5 seconds
-
cause an alarm
[431 G 120-PDAHH] {> 15mbar} If high-high differential pressure is detected across the filter
bags or if the measuring unit fails for more than 5 seconds
-
cause an alarm
Normal Shut Down of this Group (see 2.6.1 above), which is initiated automatically.
[431 G 120-PAL] {< 6 bar} If low pressure is detected for more than 15 seconds in the
compressed air service line to the pneumatic service unit (431 G 120-PSU) or if the switch fails
for more than 5 seconds
-
cause an alarm
Normal Shut Down of this Group (see 2.6.1 above), which is initiated automatically.
2.6.4.9 Throttle Flap 431 G 130 pneumatic [431 G 130-ZH / ZL] The flap is equipped with two proximity type limit switches. If one of the
switches fails
-
causes an alarm
equipment trips
The maximum time required by the pneumatic drive for tilting the flap blade from one limit
switch to the other one shall not be more than 10 seconds. If after 10 seconds the limit switch
is not reached
-
causes an alarm
equipment trips
an alarm is generated
Normal Shut Down of this Group (see 2.6.1 above), which is initiated automatically.
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
22 (25)
Rev. 00
cause an alarm
equipment trips
[431 G 135-SAL] The fan is equipped with a proximity type low-speed switch measuring the
frequency of a target rotating with the impeller shaft. If the frequency of the rotor is too low or
the switch fails
-
cause an alarm
equipment trips
[431 G 135-VAH] The fan is equipped with a vibration switch. If vibration is too high
-
fan trips
an alarm is generated
fan (431 G 135) is shut down instantly.
This initiates a Normal Shut Down of this Group (see 2.6.1 above).
cause an alarm
equipment trips
[431 G 200M1] If there is a fault detected in the electric motor or in the MCC of this motor
-
cause an alarm
equipment trips
an alarm is generated
cause an alarm
equipment trips
[431 G 205M1] If there is a fault detected in the electric motor or in the MCC of this motor
-
cause an alarm
equipment trips
an alarm is generated
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
23 (25)
Rev. 00
cause an alarm
equipment trips
[431 G 220M1] If there is a fault detected in the electric motor or in the MCC of this motor
-
cause an alarm
equipment trips
an alarm is generated
rotary locks (431 G 200 / 205) are shut off.
cause an alarm
equipment trips
[431 G 220M1] If there is a fault detected in the electric motor or in the MCC of this motor
-
cause an alarm
equipment trips
an alarm is generated
rotary locks (431 G 200 / 205) and the screw conveyor (431 G 200) are shut off.
cause an alarm
rotary locks (431 G 200 / 205) are shut off automatically
screw conveyors (431 G 200 / 205) are shut off automatically
or if the Group is just running empty after the Normal Shut Down has been initiated
-
[431 G 300-LAHH] The bin is equipped with a level probe. If the level measurement fails
-
cause an alarm
rotary locks (431 G 200 / 205) are shut off automatically
screw conveyors (431 G 200 / 205) are shut off automatically
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
24 (25)
Rev. 00
or if the Group is just running empty after the Normal Shut Down has been initiated
-
2.6.5
cause an alarm
rotary locks (431 G 200 / 205)
screw conveyors (431 G 220 / 225) are shut off automatically
or if the Group is just running empty after the Normal Shut Down has been initiated
-
2.7
2.7.1
2.7.2
2.7.3
Safety Note: If there is not enough negative pressure in the pitch fume ducts hot air
could be blown out to ambient and could injure people.
CONTROL PHILOSOPHY
05.10.2006
Vedanta Alumina Ltd.
Jharsuguda Green Anode Plant
Client ref.: VJ/SML/PO/032/1
OTK ref.:
DE-060300
Doc. No.:
133-50-071
2.8
Rev. 00
Signal Exchange with Sub-Groups of this Group and Other Process Groups
Signal
Description
Sort of Signal
25 (25)
14.3
Main Equipment
14.3.1
14.3.2
14.3.3
14.3.4
14.3.5
14.3.6
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
14.3.7
138-02-043
Group 431/432 G
DE-060300
Manufacturer:
7408 mm
4354 mm
6 mm dia
17 m/s minimum
19.5 m/s maximum
Fluid bed:
average height
150 mm approx.
2800 kg approx.
Revision: 0
Date: 29.09.2006
Page 9 of 53
138-02-043
Group 431/432 G
DE-060300
Manufacturer:
Technical data
Filter type:
IFJN 80/5-3 BX
Operating pressure:
- 80 hPa
700 m2
Filter sleeves:
Nominal diameter
Nominal length
Material
Total number
Number in 1 row
Rows
Division of supporting cages
160 mm
3375 mm
PE-V 610
400 pieces
16
25
1 x 2250mm; 1 x 1125
Cleaning cycle:
120 s
Cycle time:
12 s
Pulse time:
0.05 s
80 Nm3 /h
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
14.3.7.2 Drawings
Revision: 0
Date: 29.09.2006
Page 11 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 13 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 15 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 17 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 19 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 21 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 23 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 25 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 27 of 53
138-02-043
Group 431/432 G
DE-060300
Electrical Equipment
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 29 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 31 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 33 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 35 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 37 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 39 of 53
138-02-043
Group 431/432 G
DE-060300
14.3.7.5 Maintenance
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 41 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 43 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 45 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 47 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 49 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
14.3.7.6 Safety
Revision: 0
Date: 29.09.2006
Page 51 of 53
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
file: 138-02-043_14_0.doc, Codeword: Vedanta
138-02-043
Group 431/432 G
DE-060300
Revision: 0
Date: 29.09.2006
Page 53 of 53